You are on page 1of 4

DISTRIBUTION

Kenyan case study: billing, metering


and revenue protection insights
by Shahid Mohammed, Kenya Power and Lighting Company

This paper gives an overview of the operational situation as it existed at Westwood Power Company (WPC) in June 2006 when the management
service contractor took charge of the company, and the acttions taken to improve the situation.

Prior to June 2006, the company operated in problems to a detailed and concise program Bank for assistance, and this resulted in a
an environment characterized by a prolonged of distribution substation maintenance as management services contract to manage
and severe draught which led to load well as upgrade of overloaded circuits and the company for a period of two years with
shedding and power rationing throughout transformers. These efforts included: effect from July 2006 under a performance
the country because a big percentage contract with yearly targets to be achieved
• Investigating cost effective strategies
of the company's source of power was in employing alternative loss reduction by the management contractor covering
hydro based. This substantially eroded the initiatives. parameters such as system efficiency,
company's revenue base, leading to financial revenue collection, power quality, and
• Tracking revenue through maintaining a
losses. The financial constraints experienced dedicated commercial cycle policy for quality of customer services. In an effort to
by the company at the time meant that vital meter reading. turn around the company, the management
system reinforcement projects had to be contractor focused on cost effective loss
• Assessing the critical key steps in dealing
severely curtailed, and this in effect resulted with our overall revenue management reduction initiatives, a dedicated commercial
into high system losses. The quality of supply to on a large scale. cycle policy, as well as improvement of the
customers also deteriorated to a point where process of revenue management as detailed
• Looking at plans for adoption new
the number of customer supply interruption billing technologies to help with revenue below.
incidences stood at about 13 000 incidences management dispositions. Cost effective loss reduction initiatives
per month by June 2006, a very high figure
These efforts resulted into a reduction of
compared to the corporate target of 6 000 As at June 2006, the system losses at WPC
customer supply interruption incidences
incidences per month at the time. Due to stood at 19,63%, while the tariff allowed for
from a high of 13 000 in June 2006 to
the prevailing difficulties experienced by losses of 15% meaning that the company
6 000 per month by June 2007. A daily
the company at the time, management was absorbing a direct loss of 4,63%. A study
monitoring of the connectivity progress was
lost focus and effort applied was basically was carried out separating the commercial
also introduced and this effort resulted into
geared towards fire fighting. increased revenue by connecting 120 000 losses from the technical losses, and the
new customers for the financial year ended following figures give an indication of these
In the area of connectivity, there existed a
June 2007, against a target of 120 000. loses (see Table 1 and 2).
very huge backlog of some 27 000 new
customers who were waiting to be connected With money still a constraint at the time, In order to address the challenge of reducing
to the grid, a situation that was quite alarming cost effective ways of billing and revenue this figure, the new management came
to the management of Westwood. This collection were employed which included up with separate initiatives for commercial
frustrated efforts to increase revenue base, smaller and manageable meter reading loss reduction and technical loss reduction.
and coupled with the slowness of the itineraries, and more accurate billing by use Given the limited financial resources and
economy at the time, meant that customers of hand-held sets. long lead times for procurement restricting
tended to use less electricity, while many While the company surpassed its yearly major projects at the time, the following cost
were tempted to steal electricity, thus further targets on reducing system losses and effective measures were employed:
eroding the company's revenue base. In the days receivables of collection through
Commercial loss reduction initiatives
process, losses increased while bad debts employing cost effective measures, it is
also increased, as more and more customers also considering introducing new billing and This included the following activities:
were unable to settle their bills. metering technologies including automatic
Global sweep
meter reading (AMR) and prepayment
The new management refocused employees
metering. It is believed this will help the The use of this term refers to the audit/
of the company using the available resources
company further combat fraud and inspection of all energy meters and their
at the time, through cost effective measures
electricity theft and improve on revenue associated installations. The initiative was
to improve on revenue security, while pursuing
collection. branded "Global Sweep" for emphasis
a culture change amongst the operational
purposes so as to rally support amongst the
staff from the "fire fighting" mode of handling The government negotiated with the World
involved staff. This operation was segmented
into ordinary supplies with low to medium
Technical losses Commercial losses Total consumption on the one hand, and large
Transmission 4,00% - 5,22% power supplies on the other for purposes
of creating a more focused approach,
Distribution 10,63% 5,00% 14,41
more so because large power supplies
Total 14,63% 5,00% 19,63%
accounted for 63% of revenue collected by
Table 1: Losses as at June 2006. the company.

energize - December 2007 - Page 10


DISTRIBUTION

Technical losses Commercial losses Total

Transmission 4,2% - 4,2%

Distribution 9,09% 4,6% 13,69%

Total 13,29% 4,60% 17,89%

Table 2: Losses as at June 2007.

For ordinary supplies, the aim was to weed emerging causes of commercial losses, for
out cases of meter tampering cases that example the disconnection of the neutral. This
were happening through the breaking of initiative was quite successful as a number of
meter body seals, bypassing of meters, partial cases were unearthed where the company
bypasses and disconnected neutral wires, was losing a substantial amount of units.
direct connections at the pole in informal
Technical loss reduction initiatives
settlements, and inaccurate and obsolete
electro-mechanical meters. The prevailing financial constraints at the
time, as well as the long lead times in
As for large power supplies, the aim was
procurement, constrained the ability for quick
to eliminate cases of incorrect metering
gains in this area, leaving management with
arrangements/wiring, data mismatch
no option but to resort to cost effective and
between current transformers (CTs) and
quick ways for reaping low hanging fruits.
meters, faulty and saturated CTs, CT shorting
A study was done which indicated that
and bypassing of CTs, and inaccurate
40 - 11 kV feeders were significantly overloaded
and obsolete electro-mechanical meters.
and required a total of approximately
The challenges faced included shortage
500 km of re-conductoring from 75 mm2 ACSR
of inspection staff, tools and transport.
conductor size to 150 mm2 size. The study
Corrective action included the raising of
also revealed that about 2000 distribution
backdated debt which was billed to the
transformers were either overloaded or had
customer responsible for the defective meter
overload/overextended circuits that required
to aid in the recovery of lost revenue.
to be relieved through introduction of new
Empowering the installation inspection relieving transformers and the splitting of
process network circuits so as to share the loads.

It was realized that although the company Improved operational practices


had technical personnel in the field of
By end of June 2006, it was realized that a
revenue protection (routine inspection), their
number of distribution operations were not
effectiveness was hampered due to lack of
being carried out in a professional manner,
tools, testing equipment and the requisite
and this included activities such as the wiring
training in the use of these equipment
of transformer substations, the jointing of
in order to measure losses and detect
conductors and transformer fuse grading,
electricity fraud. Therefore, procurement of
amongst others. The challenge was to
modern testing equipment and tools was
change the way operations were undertaken
undertaken towards this end, which resulted in
at the time, and to inculcate a culture of
the acquisition of the Zera Portable Standard
doing work to internationally acceptable
and Power Analyzer, amongst others. The
standards. To this end, emphasis was put
Zera equipment was especially useful in
on the correct way of doing the distribution
detecting bad wiring of large power metering
transformer substation circuit wiring, use of line
arrangements, and also testing the accuracy
taps on joints previously done with binding
of meters.
wire, carrying out of proper fuse grading,
Following the acquisition of this equipment, an balancing of transformer circuits and phases
aggressive campaign to train technical staff with unbalanced loads, replacement of faulty
was undertaken. The aim of this training was capacitors and faulty automatic voltage
to empower the staff with the knowledge and regulators in the distribution network so as to
skills of operating the testing equipment and achieve voltage improvement, and prompt
tools; as well as to show them how to correctly and regular cutting/trimming of tree branches
wire large power supplies and detect other along power line routes.

Achievement as at
Item Description Set target
June 2007
1. Meter reading coverage 98% 98%

2. Meter reading quality errors <3% 2%

3. Average time to read (days) 3 2

Table 3: Meter reading targets.

energize - December 2007 - Page 11


DISTRIBUTION

Achievement as at • An effective quality control team was


Item Description Set target
June 2007 established to coordinate the various
functions so as to ensure the process
Average period for resolution
1. 3 2 progressed to completion.
of anomalies (days)
The targets set for resolution of anomalies are
Table 4: Target for anomalies resolution.
given in Table 4.

System reinforcement reading calendar (meter reading The company's revenue collection process
calendar is a schedule of dates which was unimpressive, with a debt age of
System studies undertaken during this time
operate on a batch process for releasing two months, which translated to 60 days
period revealed that large portions of
the itineraries 3 days before the planned of receivables. Therefore, there was an
the distribution network were contributing reading dates. This calendar was updated urgent need to implement strategies for
substantially to technical losses due to at the beginning of every year and was improvement, and the following actions
the use of under-sized conductors, over- used as a complete year planner for
were adopted:
extended feeder lines, transformers with meter reading).
over-extended low voltage networks that • Automatic generation of service orders
• The calendar was based on the concept
resulted into poor voltage profiles and (S/O) after credit period of 21 days.
that each month had at least 20 working
hence pronounced losses, and over-loaded days (Monday to Friday) excluding all the • Printing or loading of generated service
transformers. An exercise was initiated national holidays. orders into hand-held sets and prompt
aimed at re-conductoring under sized MV action of the same.
• The itineraries were sent to reading
feeder lines to 150 mm2 ACSR conductor, centers that were specially created for • Prompt update of the service orders in
establishing new distribution transformer ease of management of readings, taking the billing system to enable change of
substations where low voltage lines were in to consideration the geographical status.
over-extended, and relieving of over- spread of customers. • Follow up on S/O if payment is not received
loaded distribution transformers through after 30 days of disconnection.
• The itineraries were uploaded into
the creation of additional transformer hand-held sets and assigned to meter • Introduction of defined zonal teams
substations with added potential of readers. with supervisors as their heads so as to
increasing connectivity. create a clear line of command and
The meter reading targets set are shown in accountability per team.
Dedicated commercial cycle policy Table 3.
The handling of customer accounts was
(DCCP)
Initially, there were big itineraries that posed segmented as shown in Table 5.
The dedicated commercial cycle policy reading problems and that resulted in very
The revenue collection targets set are shown
constitutes a set of principles that guide long cycles. This was solved by splitting these
in Table 6.
the processes of meter reading, billing and itineraries into smaller ones that could be
revenue collection by defining the various read within a day. In order to eliminate meter The following actions were taken:
targets for bench marking with internationally reading errors, the use of hand-held sets was
• Provision of tools: motorcycles, radios,
accepted practices for general customer introduced.
mobile telephones and pole teams (to
service improvement.
Billing principles handle difficult disconnections).
Metel reading principles • Levying of reconnection charges/
The following principles were adhered to:
fees to act as a deterrent to would be
• Meter reading was seen as the most
• Prompt billing of downloaded readings defaulters.
important of these processes as it is the
within a day. • Use of deposit to offset customer debt
starting point of the commercial cycle.
The following were done to improve this • Prompt resolution of all billing after two months, and release of a
activity. anomalies. demand note to customer in form of a
• Prompt dispatch of bills on the same day final account statement.
• Meters were grouped in itineraries for
of billing. A service level agreement with • Sending of a reminder demand note
ease of reading. Out of 900 000 plus
the Postal Corporation of Westwood was to the customer after 14 days. The debt
customers, there were 5064 itineraries
worked out such that bills for Nairobi were would thereafter be followed up for
spread over the country.
delivered the same day and those destined payment by debt collectors. Where the
• The releasing of itineraries for meter for upcountry areas were delivered to the debt collectors failed, such cases were
reading was managed by the meter mail boxes within two days. passed onto contracted private debt
collectors (PDC).
• Where the PDC were unable to collect,
Item Supply type Team handling
such cases were passed on to the legal
Revenue collection unit: comprised a supervisor
1. Ordinary (consumption <7000 UPM) department.
and revenue collection clerks
Large power unit, which comprised a supervisor (an Process improvement on revenue
2. Large power (cons. >7000 UPM)
engineer) and large power technicians
Corporate accounts: GOK, parastatals, Corporate account section: comprised a supervisor management on a large scale
3.
embassies and local authorities and customer service officers.
It was realized the vastness of some business
Table 5: Customer accounts segmentation.
areas was hampering focus on revenue
Item Description Set target
Achievement as collection. This was resolved through creation
at June 2007 of smaller and more manageable field
1. Collection as percentage of monthly billing 98% 99%
teams (zonal teams with a supervisor per
2. No. of days receivables 55 42 team), which brought about clear line of
Table 6: Revenue collection targets. command and accountability in each

energize - December 2007 - Page 12


DISTRIBUTION
team. Due to the existence of unscrupulous Metering technology solutions number about 4000 but constitute 63%
customers who were bent on locking their of the billing/revenue, hence the need
Upgrading of meters
premises or illegally reconnecting supplies to focus on this group of customers.
once disconnected, it was felt that a fresh The metering for these supplies evolved Therefore, by introducing AMR for these
approach was needed to counter these from single phase electro-mechanical customers, the company would be able
bad practices. This was achieved through the meters to single phase electronic meters, to effectively control 63% of its business
creation of support teams otherwise known which were introduced in 2001. The through constant monitoring of the supplies.
as "pole teams" whose job was to disconnect metering for three-phase supplies also Due diligence has already been done, and
such difficult cases at the terminal pole, a evolved from eletro-mechanical meters implementation is expected to commence
move that led to the efficient disconnection with a separate maximum demand in December 2007.
of all cases. indicator for CT metered supplies, to Prepayment
Segmentation of the customers according to tri-vector meters (which though eletro-
WPC faces meter reading and revenue
consumption and type of uses was undertaken mechanical in nature, combined all the
collection challenges in slums (informal
to also increase the efficiency of revenue parameters for large power supplies in
settlements) e.g. Kibera, which is the
management. Credit extension facility was also one unit), to finally three-phase electronic
largest of its kind in East and Central
introduced for purposes of allowing customers meters, which were introduced in 1998.
Africa. It is intended that prepayment
with huge debts to pay them in manageable
Comparison between electro-mechanical metering be introduced for these informal
monthly installments over a period of time.
and electronic meters settlements, and to gradually spread the
A number of reconnection fees were also
usage to other single-phase customers.
introduced to act as a deterrent to customers Electromechanical meters were plagued by
The type of metering to be used will be
who were perennial defaulters. These were: accuracy and tampering problems, and for
the prepayment split metering that offers
• 354 Kenyan Shillings for cut out cases where a maximum demand indicator deterrence to tampering. Towards this end,
reconnection was being used, their resetting became an there is already an electrification scheme
• 3300 Kenyan Shillings for pole issue as this was an insecure area which could in the Kibera slum that uses load limiters
reconnection be tampered with by unscrupulous customers installed at the poles to limit the customers'
• 12 000 Kenyan Shillings for service line or employees of a utility. consumption. Upon implementation of
reconnection prepayment metering, these load limiters
Consequently, electronic meters were
All these measures served to increase will be replaced with prepayment meters.
introduced, and these offered better
awareness on the customer's side, thereby Other than inspecting these prepayment
accuracy, together with a wide range
encouraging prompt payment without meters, there will be no need of regular
of functionality that are especially useful
disconnection. reading and disconnection, as this will
for large power (current transformer
be automatic, which will further improve
Billing technology solutions metered) supplies. In the area of fraud
on revenue management. When fully
prevention, electronic meters were found
The company's billing system has evolved operational, it is envisaged that the
over time from "ME29", which operated up to to be less susceptible to tampering/
prepayment metering will cover about
1995; then to "Custima", which operated until interference, and could record reversed
960 000 customers.
early 1997 (these were both batch based energy. The single phase electronic meter
records consumption correctly when Acknowledgement
billing systems); to finally a modern customer
relationship management (CRM) system connections are reversed, and can also This paper was presented at the Terrapin
known as Integrated Customer Services (ICS). detect disonnection of neutral fraud. In Billing and Metering World Africa 2007
ICS was started in 1997, and the system was the next consignment of single-phase Conference in Johannesburg, and is
further upgraded (named CMS) in April 2007. meters, the electronic meters will be able published with permission. v
As by July 2007, it was handling about 936 to record correctly even when the neutral
582 customers with limitless capacity. is disconnected i.e. the meters able to
operate on a single (live) wire only are to
The 2007 ICS upgrade was aimed at:
be procured.
• Increasing the processing speed through
converting of the billing system from the Future initiatives
former "bill based" (where each query
In line with the current global trends of
was accessing the entire number of bills
best practices in utilities, and so as to
since inception of ICS i.e. 33-million bills)
further improve on revenue management
to the current "balanced based" one,
which has lower memory requirements, dispositions, the company plans to introduce
as the old bills are closed, and it is only automatic meter reading (AMR) and
the balance that is carried forward. prepayments meters.
• Reducing the storage requirements which AMR
had risen from 65 GB to 320 GB. At the
current rate of connections, 12-million bills AMR is fast becoming a best practice in
are added every year, hence the need utility management worldwide. It is a natural
to have a system that enables archiving progression in the evolution of metering
of old bills once they are closed. technology. In WPC, large power customers

energize - December 2007 - Page 14

You might also like