You are on page 1of 40

ABSTRACT OF COST

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Structure : Boiler Building (12mx15m)
BILL OF QUANTITIES- SECURITY & BOILER BUILDING
Item Amount
Description Unit Quantity Rate (NRs) Remarks
No. (NRs)
1 Foundation Works
MECHANICAL EARTHWORK: Excavation in foundations in all types of soils
for foundation, trenches, footing, pits etc to the required depth including
dewatering by manual or mechanical means etc (including supporting and
1.1 butressing for shallow excavation work) as per specifiations with all m3 40.40 80.00 3,232.00
contractor's own machinary and equipments and disposing off the
surplus/unusable earth to outside the constuction premises etc all complete
as per drawings and specifications.

STONE SOLING AT FOUNDATION: Supplying and placing of 150mm of dry


1.2 stone soling with sand filling at foundation and ground flooring of the building m3 31.63 6,200.00 196,118.40
and lower tie beam as per specification and instruction of Enigneer.

PCC - M10/40 :Providing and placing machine mixed cement concrete Grade
1.3 M10/40 for foundation PCC including compaction, curing, testing and lead m3 3.33 14,350.00 47,785.50
30m. etc. all complete as per specification and drawing.

EARTHWORK BACKFILL :Backfilling in foundation, floors and sides of


foundation with approved gravel materials/soil in layer not exceeding 15cm
1.4 thick (compacted thickness) including purchasing and transportation of soil, m3 120.95 400.00 48,380.00
spreading in required line and level, sprinkling water, ramming, compacting
with mechanical rammers, testing etc all complete as per drawing and
specification.
2 Masonry Works
BRICKWORK: Good quality local brick Brickwork in 1:4 (cement:sand)
mortar in perfect line level finish including wetting the bricks, racking the m3 22.64 15,500.00 350,889.00
joints, scaffolding and curing the work for at least 7 days all complete as per
specification and instruction of Engineer.

Abstract of Cost
Page 1
Security Boiler Bldg.
ABSTRACT OF COST
Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur
Location : Janakpur
Structure : Boiler Building (12mx15m)
BILL OF QUANTITIES- SECURITY & BOILER BUILDING
Item Amount
Description Unit Quantity Rate (NRs) Remarks
No. (NRs)
3 Concrete Works

M20/20 CONCRETE: Providing and laying in position machine mixed and


machine vibrated design mix cement concrete M25 grade for reinforced
cement concrete work(Footing and Column Pedestal) using OPC 53 grade
3.1 cement with 20 mm graded machine crushed stone aggregate of approved m3 15.14 19,000.00 287,641.38
quality in various locations and heights including transportation of concrete to
site of placing, compaction, finished to required line and level, protection and
curing etc all complete as per drawings and specifications.

GROUTING CONCRETE LEVELLING COURSE: Providing and laying in


position High compressive non shrink grouting for levelling course of steel
3.2 m3 0.23 87,500.00 19,700.63
column base (maximum 75 mm thk.) finished to required line and level,
protection and curing etc all complete as per drawings and specifications.

REINFORCEMENT: Providing and fixing in position Fe 500 TMT steel


reinforcement of various diameter confirming to relevant IS code in RCC
works including straightening, cutting, bending, binding with 20 SWG
annealed wire for tying the reinforcement bars at each junctions (binding wire
shall not be measured separately) including all waste and cut pieces,
3.3 kg 1373.73 135.00 185,453.88
provision for adequate number of spacers, chairs, providing and placing
cement mortar (1:1) cover blocks to keep the bars in intended position at all
levels all complets as per drawings, specifications and instructions of the
Engineer. (The item shall include the installation of the anchhor bolts in line
and level (Client Provided).

FORMWORK/SHUTTERING: Providing and laying, centering and shuttering


with approved materials for all kinds RCC works including all necessary mild
steel propping,scaffolding, staging, supporting, etc. all complete net as per
3.4 m2 104.48 1,190.00 124,331.68
drawings, specifications and instructions of the engineer, all complete. a)
19mm thick waterproof Ply Wood or steel Form Work for plain slab,column,
Beams, foundations, etc

Abstract of Cost
Page 2
Security Boiler Bldg.
ABSTRACT OF COST
Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur
Location : Janakpur
Structure : Boiler Building (12mx15m)
BILL OF QUANTITIES- SECURITY & BOILER BUILDING
Item Amount
Description Unit Quantity Rate (NRs) Remarks
No. (NRs)
4 Flooring
SUB BASE PCC (1:3:6): Providing and laying 75 mm or thicker concrete (1
cement: 3 sand:3 aggregates) on the floor including chipping, cleaning and
4.1 m2 100.00 920.00 92,000.00
wetting the surface and curing the works as per drawings, specifications and
instruction of A/E
500 GAUGE PLASTIC FELT : Supplying, laying of 500 MM GAUGE
4.2 PLASTIC FELT over the prepared sub base PCC with welded joings as per m2 80.00 150.00 12,000.00
drawings, specifications and instruction of A/E.
VITRIFIED TILE FLOORING: Providing and laying non-slip 300x300x8mm
fully vitrified tiles of approved colour, shade, and pattern. To be laid on
4.3 minimum 25mm thick cement screed (1 cement : 4 sand) and jointed with m2 100.00 2,200.00 220,000.00
grouting epoxy matched to the shade of the tile. All as per drawings,
specifications and instruction of A/E.
Total of Item No. 1 To 6 1,587,532.46

Abstract of Cost
Page 3
Security Boiler Bldg.
DETAILED MEASUREMENT SHEET

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m
1 Foundation Works

MECHANICAL EARTHWORK: Excavation in foundations in all types


of soils for foundation, trenches, footing, pits etc to the required depth
including dewatering by manual or mechanical means etc (including
1.1 supporting and butressing for shallow excavation work) as per m3
specifiations with all contractor's own machinary and equipments and
disposing off the surplus/unusable earth to outside the constuction
premises etc all complete as per drawings and specifications.

i) Footing
Footing 1 4 2.200 1.700 2.000 29.92
iii) Lower Tie Beam
Grid 1-1,2-2 2 7.400 0.400 1.000 5.92
Grid A-A,B-B 2 5.700 0.400 1.000 4.56
Total: 40.40
GRAVELLY MIXED SOIL PACKING BELOW FOOTING: Providing,
laying, spreading, watering, levelling and full compaction (90%) of 200
1.2 mm thick gravelly mixed soil subbase grading material as per table m3
12.1 of standard specification(DoR Specification) and instruction of
Engineer.
Footing
Footing 1 4 2.200 1.700 0.300 4.49
Total: 4.49
STONE SOLING AT FOUNDATION: Supplying and placing of 150mm
of dry stone soling with sand filling at foundation and ground flooring
1.3 m3
of the building and lower tie beam as per specification and instruction
of Enigneer.
i) Footing
Footing 1 4 2.200 1.700 0.300 4.49
iii) Lower Tie Beam
Grid 1-1,2-2 2 7.400 0.400 0.300 1.78
Grid A-A,B-B 2 5.700 0.400 0.300 1.37
Ground Floor Flooring 1 10.000 8.000 0.300 24.00
Total: 31.63

Measurement Sheet Page 4 Main Building Block


DETAILED MEASUREMENT SHEET

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m
PCC - M10/40 :Providing and placing machine mixed cement concrete
Grade M10/40 for foundation PCC including compaction, curing,
1.4 m3
testing and lead 30m. etc. all complete as per specification and
drawing.
i) Footing
Footing 1 4 2.200 1.700 0.100 1.50
iii) Lower Tie Beam
Grid 1-1,2-2 2 7.400 0.400 0.100 0.59
Grid A-A,B-B 2 5.700 0.400 0.100 0.46
maSONRY BAND 1 26.200 0.400 0.075 0.79

Total: 3.33

EARTHWORK BACKFILL :Backfilling in foundation, floors and sides


of foundation with approved gravel materials/soil in layer not exceeding
15cm thick (compacted thickness) including purchasing and
1.5 m3
transportation of soil, spreading in required line and level, sprinkling
water, ramming, compacting with mechanical rammers, testing etc all
complete as per drawing and specification.

0.95
Upto Plinth 1 10.000 8.000 1.500 120.00
Total: 120.95
2 Masonry Works

BRICKWORK: Good quality local brick Brickwork in 1:4


(cement:sand) mortar in perfect line level finish including wetting the
2.1 m3
bricks, racking the joints, scaffolding and curing the work for at least 7
days all complete as per specification and instruction of Engineer.

Grid 1-1,2-2 2 9.000 0.350 2.000 12.60


Grid A-A,B-B 2 7.170 0.350 2.000 10.04
Total: 22.64
3 Concrete Works

Measurement Sheet Page 5 Main Building Block


DETAILED MEASUREMENT SHEET

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m

M20/20 CONCRETE: Providing and laying in position machine mixed


and machine vibrated design mix cement concrete M25 grade for
reinforced cement concrete work(Footing and Column Pedestal) using
OPC 53 grade cement with 20 mm graded machine crushed stone
3.1 m3
aggregate of approved quality in various locations and heights
including transportation of concrete to site of placing, compaction,
finished to required line and level, protection and curing etc all
complete as per drawings and specifications.

Pedestal
P1 2 0.330 0.600 3.30 1.31
P2 2 0.850 0.650 3.30 3.65

Footing
Footing 1 4 2.154 0.20 1.72 Trapezoidal
4 2.500 2.000 0.20 4.00 Uniform
Lower Tie Beam/Upper Tie beam
Grid 1-1,2-2 4 9.00 0.23 0.30 2.48
Grid A-A,B-B 4 7.17 0.23 0.30 1.98
Total: 15.14
GROUTING CONCRETE LEVELLING COURSE: Providing and laying
in position High compressive non shrink grouting for levelling course of
3.2 steel column base (maximum 75 mm thk.) finished to required line and m3
level, protection and curing etc all complete as per drawings and
specifications.
P1 2 0.330 0.600 0.15 0.06
P2 2 0.850 0.650 0.15 0.17
Total: 0.23

Measurement Sheet Page 6 Main Building Block


DETAILED MEASUREMENT SHEET

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m

REINFORCEMENT: Providing and fixing in position Fe 500 TMT steel


reinforcement of various diameter confirming to relevant IS code in
RCC works including straightening, cutting, bending, binding with 20
SWG annealed wire for tying the reinforcement bars at each junctions
(binding wire shall not be measured separately) including all waste and
3.3 cut pieces, provision for adequate number of spacers, chairs, providing kg
and placing cement mortar (1:1) cover blocks to keep the bars in
intended position at all levels all complets as per drawings,
specifications and instructions of the Engineer. (The item shall
include the installation of the anchhor bolts in line and level
(Client Provided).

Footing
12.00 mm 4 43.500 0.888 154.48
Pedestal
Main Bar
P1 20.00 mm 16 4.300 2.500 172.00
16.00 mm 16 4.300 1.600 110.08
Stirrups
Rectangular 8.00 mm 172 1.900 0.400 130.72
Single Legged 0.6 8.00 mm 172 0.750 0.400 51.60
Single legger 0.33 8.00 mm 172 0.480 0.400 33.02
Lower Tie Beam
Main Bar 16.00 mm 4 32.340 1.600 206.98
8.00 mm 1 228.536 0.400 91.41
Upper Tie Beam
Main Bar 16.00 mm 4 32.340 1.600 206.98
8.00 mm 1 228.536 0.400 91.41
Projected Part 8.00 mm 3 32.340 0.400 38.81
8.00 mm 216 1.000 0.400 86.24
1,373.73

Measurement Sheet Page 7 Main Building Block


DETAILED MEASUREMENT SHEET

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m

FORMWORK/SHUTTERING: Providing and laying, centering and


shuttering with approved materials for all kinds RCC works including all
necessary mild steel propping,scaffolding, staging, supporting, etc. all
3.4 m2
complete net as per drawings, specifications and instructions of the
engineer, all complete. a) 19mm thick waterproof Ply Wood or steel
Form Work for plain slab,column, Beams, foundations, etc

i) Footing
Footing 1 4 7.800 0.400 12.48
Pedestal
P1 2 1.860 3.300 12.28
P2 2 3.000 3.300 19.80
Footing
Footing 1 4 7.800 0.200 6.24
Lower Tie Beam/Upper Tie beam
Grid 1-1,2-2 4 9.000 0.830 29.88
Grid A-A,B-B 4 7.170 0.830 23.80
Total: 104.48
4 Flooring
SUB BASE PCC (1:3:6): Providing and laying 75 mm or thicker
concrete (1 cement: 3 sand:3 aggregates) on the floor including
4.1 m2
chipping, cleaning and wetting the surface and curing the works as per
drawings, specifications and instruction of A/E
Ground Floor 1 100.000 100.00
Total: 100.00

500 GAUGE PLASTIC FELT : Supplying, laying of 500 MM GAUGE


4.2 PLASTIC FELT over the prepared sub base PCC with welded joings m2
as per drawings, specifications and instruction of A/E.

Ground Floor 1 80.000 80.000


80.00

Measurement Sheet Page 8 Main Building Block


DETAILED MEASUREMENT SHEET

Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur


Location : Janakpur
Measurement Sheet
Measurement
S.No Description of works Unit Nos L B H Quantity Remarks
m m m

VITRIFIED TILE FLOORING: Providing and laying non-slip


300x300x8mm fully vitrified tiles of approved colour, shade, and
4.3 pattern. To be laid on minimum 25mm thick cement screed (1 cement : m2
4 sand) and jointed with grouting epoxy matched to the shade of the
tile. All as per drawings, specifications and instruction of A/E.

Ground Floor 1 100.00 100.00


100.00

Measurement Sheet Page 9 Main Building Block


#REF!
#REF!

RATE ANALYSIS
Item No : 6.1
Description of item : Earth work for foundation through all types of soil including relevant lift 1.5m and 20m lead respectively
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

9.07.01 907 Unskilled md 2.000 700.00 1400.00 tools 3 % of labour cost 42.00

Sub - total (A) 1400.00 Sub - total (B) 0.00 Sub total (c) 42.00
Direct Cost (A+B+C) = NRs. 1442.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 216.30
Total Item Rate = NRs. 1658.30
Say per cu.m. 1658.30
Item No : 2.1
Description of item : Earth work for foundation through all types of soil including relevant lift more than 1.5m up to 3.0m and 20m lead respectively
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
0.00
0.00
9.07.01 907 Unskilled md 3.000 700.00 2100.00 0.00 tools 3 % of labour cost 63.00

Sub - total (A) 2100.00 Sub - total (B) 0.00 Sub total (c) 63.00
Direct Cost (A+B+C) = NRs. 2163.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 324.45
Total Item Rate = NRs. 2487.45
Say per cu.m. 2487.45

ITECO N - SASCON JV Page 22


#REF!
#REF!

RATE ANALYSIS
Item No : 3.9
Description of item : Backfilling with the graded filter material in layer with necessary watering and compaction,lead 30m, lift 1.5m.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

24.11 2404 Skilled md 0.000 960.00 0.00 Gravel cu.m 1.1000 3309.98 3640.98
3110 Unskilled md 0.800 700.00 560.00 filter

Sub - total (A) 560.00 Sub - total (B) 3640.98 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4200.98
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 630.15
Total Item Rate = NRs. 4831.13
Say per cu.m. 4831.13

Item No : 3.10
Description of item : Backfilling in layers in foundation pits,trenches,etc including compaction and watering etc. complete lead10m.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

9.1 908 Unskilled md 1.140 700.00 798.00 Diesel Ltr. 0.11 55.500 6.11
tools % 3 % of labour cost 23.94
Vibrator Roller hr. 0.11 500 55
1-1.5tons
Sub - total (A) 798.00 Sub - total (B) 6.11 Sub total (c) 78.94
Direct Cost (A+B+C) = NRs. 883.05
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 132.46
Total Item Rate = NRs. 1015.50
Say per cu.m. 1015.50

ITECO N - SASCON JV Page 23


#REF!
#REF!

RATE ANALYSIS
Item No : 6.2
Description of item : Providing and fabricating gabion crates of more than 50 cm height mesh size with 100 mm x 120 mm hexagonal mess and heavy coated including rolling,
cutting, weaving filling of broken stones etc. complete (mess wire 10 SWG, weaving wire 12 SWG and Selvedge wire 7 SWG), lead 10m lift 1.5m
Unit:(2*1*1) 2.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

24.01.02 2401 Skilled md 0.840 960.00 806.40 G.I wire(Mesh) kg 25.4500 110.21 2804.84
24.02.01 Unskilled md 2.750 700.00 1925.00 G.I wire(Salvage )kg 3.4100 110.21 375.82 3 % of labour cost 81.94
24.02.04 Stone cum 2.2000 2691.63 5921.59

Sub - total (A) 2731.40 Sub - total (B) 9102.25 Sub total (c) 81.94
Direct Cost (A+B+C) = NRs. 11915.60
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1787.34
Total Item Rate = NRs. 13702.93
Say per cu.m. 6851.47

Item No : 6.4
Description of item : Providing and fabricating gabion crates of less than 50 cm height mesh size with 100 mm x 120 mm hexagonal mess and heavy coated including rolling,
cutting, weaving filling of broken stones etc. complete (mess wire 10 SWG, weaving wire 12 SWG and Selvedge wire 7 SWG), lead 10m lift 1.5m
Unit:(2*1*.5) 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

24.01.02 2401 Skilled md 0.480 960.00 460.80 G.I wire(Mesh) kg 17.3000 110.21 1906.63
24.02.01 Unskilled md 1.390 700.00 973.00 G.I wire(Salvage )kg 2.8000 110.21 308.59 3 % of labour cost 43.01
24.02.04 Stone cum 1.1000 2691.63 2960.80

Sub - total (A) 1433.80 Sub - total (B) 5176.02 Sub total (c) 43.01
Direct Cost (A+B+C) = NRs. 6652.83
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 997.92
Total Item Rate = NRs. 7650.76
Say per cu.m. 7650.76

ITECO N - SASCON JV Page 24


#REF!
#REF!

RATE ANALYSIS

Item No : 6.5
Description of item : Providing and laying random rubble stone masonry of hard stone in 1 : 4 cement sand mortar including stone dressing,mortar transportation all complete, masoned height 0 to 5 m
lead 30m
Unit: 1.00 cu.m.
Norms Specification
activity Clause Resources
Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

26.04 Skilled md 1.500 960.00 1440.00 Cement t 0.1550 17736.60 2749.17


Unskilled md 4.500 700.00 3150.00 Sand cu.m 0.4500 3346.35 1505.86 3 % of labour cost 137.70
Stone cu.m 1.1500 2691.63 3095.38
Water lt 100.00 0.10 10.00

Sub - total (A) 4590.00 Sub - total (B) 7360.41 Sub total (c) 137.70
Direct Cost (A+B+C) = NRs. 12088.11
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1813.22
Total Item Rate = NRs. 13901.33
Say per cu.m. 13901.33
Item No : 2.3 (i)
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.02 2000 Skilled md 0.500 960.00 480.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 0.10 19.80

Sub - total (A) 2930.00 Sub - total (B) 8045.77 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 11288.27
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1693.24
Total Item Rate = NRs. 12981.52
Say per cu.m. 12981.52

ITECO N - SASCON JV Page 25


#REF!
#REF!

RATE ANALYSIS
Item No : 3.1
Description of item : a) Providing and placing machine mixed cement concrete for the abutement, pier, wall etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iii) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.02 2000 Skilled md 0.900 960.00 864.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 9.000 700.00 6300.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 0.10 19.80

Sub - total (A) 7164.00 Sub - total (B) 10434.96 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 17911.46
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2686.72
Total Item Rate = NRs. 20598.18
Say per cu.m. 20598.18
Item No : 3.2
Description of item : a) Providing and placing machine mixed cement concrete for the abutement, pier, wall etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.02 2000 Skilled md 0.900 960.00 864.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 9.000 700.00 6300.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.2000 55.50 177.60
Water lit. 225.0000 0.10 22.50

Sub - total (A) 7164.00 Sub - total (B) 11280.37 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 18756.87
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2813.53
Total Item Rate = NRs. 21570.40
Say per cu.m. 21570.40

ITECO N - SASCON JV Page 26


#REF!
#REF!

RATE ANALYSIS
Item No : 4.1
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
i) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 3.00 594.00

Sub - total (A) 4968.00 Sub - total (B) 11009.16 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 16289.66
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2443.45
Total Item Rate = NRs. 18733.11
Say per cu.m. 18733.11
Item No : 4.2
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
ii) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
Operator md 0.200 960.00 192.00 10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 225.0000 0.10 22.50

Sub - total (A) 5160.00 Sub - total (B) 11269.27 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 16741.77
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2511.27
Total Item Rate = NRs. 19253.03
Say per cu.m. 19253.03

ITECO N - SASCON JV Page 27


#REF!
#REF!

RATE ANALYSIS
Item No : 4.3
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iii) Grade M30/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.4100 17736.60 7272.01 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5700 3309.98 1886.69 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3300 3309.98 1092.29
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 246.0000 0.10 24.60

Sub - total (A) 4968.00 Sub - total (B) 11924.89 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 17205.39
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2580.81
Total Item Rate = NRs. 19786.19
Say per cu.m. 19786.19

Item No : 2.5
Description of item : Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 38mm thick m3 0.0525 43502.23 2283.87
18.01 1804 Skilled md 1.500 960.00 1440.00 (0.42m3/8 times)
1805 Unskilled md 2.000 700.00 1400.00 Struts balis etc cu.m 0.0150 43502.23 652.53
(.18/12 times)
Nails kg 2.7500 90.00 247.50
Sub - total (A) 2840.00 Sub - total (B) 3183.90 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 6023.90
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 903.59
Total Item Rate = NRs. 6927.49
Say per sq.m. 692.75

ITECO N - SASCON JV Page 28


#REF!
#REF!

RATE ANALYSIS
Item No : 3.4
Description of item : Providing , Preparing and Installing form work including necessary supports and removing after completion for walls.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 9mm thick m2 1.3750 1850.44 2544.36
18.02 1804 Skilled md 2.400 960.00 2304.00 (11m2/8 times)
(i and ii
avg.) 1805 Unskilled md 2.500 700.00 1750.00 Struts balis etc cu.m 0.0750 43502.23 3262.67
(.45/12 times)
Nails kg 2.7500 90.00 247.50
Sub - total (A) 4054.00 Sub - total (B) 6054.53 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 10108.53
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1516.28
Total Item Rate = NRs. 11624.81
Say per sq.m. 1162.48

Item No : 4.5
Description of item : Providing , Preparing and Installing form work & removing after completion for Slab & beam structure.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 38mm thick cu.m 0.1000 43502.23 4350.22
18.05 1804 Skilled md 3.000 960.00 2880.00 (0.60m3/6 times)
(I and ii
avg.) 1805 Unskilled md 3.000 700.00 2100.00 Struts balis etc cu.m 0.0150 43502.23 652.53
(.22/8 times)
Nails kg 4.0000 90.00 360.00
Sub - total (A) 4980.00 Sub - total (B) 5362.76 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 10342.76
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1551.41
Total Item Rate = NRs. 11894.17
Say per sq.m. 1189.42

ITECO N - SASCON JV Page 29


#REF!
#REF!

RATE ANALYSIS

Item No : 5.2
Description of item : Road way excavation in soft soil including disposal upto 10m and lift upto 1.5 m etc. all complete as per specification.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

9.01 905 Unskilled md 0.750 700.00 525.00 tools 3 % of labour cost 15.75

Sub - total (A) 525.00 Sub - total (B) 0.00 Sub total (c) 15.75
Direct Cost (A+B+C) = NRs. 540.75
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 81.11
Total Item Rate = NRs. 621.86
Say per cu.m. 621.86

Item No : 5.3
Description of item : Formation of embankment including compaction in layers not exceeding 150mm. Compacted depth, watering and haulage 10m. etc. all complete as per specification.

Unit: 1.00 cu.m.


Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.002 960.00 1.92 Suitable Materialm3 1.1000 200.00 220.00 Grader hr 0.0050 3000.00 15.00
9.05.01 903 (2) Unskilled md 0.008 700.00 5.60 Diesel ltr 0.1200 55.50 6.66 Roller hr 0.0167 1500.00 25.05

Sub - total (A) 7.52 Sub - total (B) 226.66 Sub total (c) 40.05
Direct Cost (A+B+C) = NRs. 274.23
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 41.13
Total Item Rate = NRs. 315.36
Say per cu.m. 315.36

ITECO N - SASCON JV Page 30


#REF!
#REF!

RATE ANALYSIS

Item No : 5.4
Description of item : Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in common soil:

1.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

10.05 1003 Unskilled md 0.150 700.00 105.00 3 % of labour cost 3.15

Sub - total (A) 105.00 Sub - total (B) 0.00 Sub total (c) 3.15
Direct Cost (A+B+C) = NRs. 108.15
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 16.22
Total Item Rate = NRs. 124.37
Say per sq.m. 124.37

Item No : 5.5
Description of item : Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m .
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

skilled md 0.005 960.00 4.80


12.01 1201 Unskilled md 0.040 700.00 28.00 Sub base agg cu.m 1.2800 1452.65 1859.39 V.Roller hr 0.0220 1500.00 33.00
Diesel lt 0.7920 55.50 43.96 Water bowser hr 0.0380 1000.00 38.00
Motor Grader hr 0.0220 3000.00 66.00
Loader hr 0.0011 2000.00 2.20

Sub - total (A) 32.80 Sub - total (B) 1903.35 Sub total (c) 139.20
Direct Cost (A+B+C) = NRs. 2075.35
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 311.30
Total Item Rate = NRs. 2386.65
Say per cu.m. 2386.65

ITECO N - SASCON JV Page 31


#REF!
#REF!

RATE ANALYSIS

Item No : 5.6
Description of item : Supply and laying grass turfing on the various slope with cutting, watering and transportaion up to 1000m etc. all complete
Unit: 1.00 sq.m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

28.14.01 Unskilled md 0.050 700.00 35.00 Trasportation m2 1.0000 39.88 39.88

Sub - total (A) 35.00 Sub - total (B) 39.88 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 74.88
Note :- 1 m3 turffing = 10 m2 Contractor's Overhead @ 15 % of (A+B+C) = NRs. 11.23
Total Item Rate = NRs. 86.11
Say per sq.m. 86.11

Item No : 6.3
Description of item : Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m
Unit: 1.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Unskilled md 0.017 700.00 11.90 Geotextile sq.m. 1.2000 373.75 448.50


24.09 2404

Sub - total (A) 11.90 Sub - total (B) 448.50 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 460.40
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 69.06
Total Item Rate = NRs. 529.46
Say per sq.m. 529.46

ITECO N - SASCON JV Page 32


#REF!
#REF!

RATE ANALYSIS
Item No : 3.3 and 4.4
Description of item : Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Diameter above 8mm and 16mm ii and iii average Unit: 1.00 ton
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 10.500 960.00 10080.00 Reinforcement t 1.1500 96820.00 111343.00


Unskilled md 10.500 700.00 7350.00 Binding Wire kg 9.5000 101.77 966.82
20.07 2000

Sub - total (A) 17430.00 Sub - total (B) 112309.82 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 129739.82
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 19460.97
Total Item Rate = NRs. 149200.79
Say per ton. 149200.79
Item No : 3.5
Description of item : Supplying and placing of dry stone layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.600 960.00 576.00 Stone m3 1.1000 2691.63 2960.80


Unskilled md 2.000 700.00 1400.00
24.03.01 2403
(4)

Sub - total (A) 1976.00 Sub - total (B) 2960.80 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4936.80
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 740.52
Total Item Rate = NRs. 5677.32
Say per cum. 5677.32

ITECO N - SASCON JV Page 33


#REF!
#REF!

RATE ANALYSIS
Item No : 3.6
Description of item : Supplying and placing of dry gravel layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.000 960.00 0.00 Gravel m3 1.1000 1452.65 1597.92


Unskilled md 0.800 700.00 560.00
24.11 2404
3110

Sub - total (A) 560.00 Sub - total (B) 1597.92 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 2157.92
Ref is taken same as dry graded filter Contractor's Overhead @ 15 % of (A+B+C) = NRs. 323.69
Total Item Rate = NRs. 2481.60
Say per cum. 2481.60

Item No : 3.7
Description of item : Supplying and placing of dry sand layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.000 960.00 0.00 sand m3 1.1000 3346.35 3680.99


Unskilled md 0.800 700.00 560.00
24.11 2404
3110

Sub - total (A) 560.00 Sub - total (B) 3680.99 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4240.99
Ref is taken same as dry graded filter Contractor's Overhead @ 15 % of (A+B+C) = NRs. 636.15
Total Item Rate = NRs. 4877.14
Say per cum. 4877.14

ITECO N - SASCON JV Page 34


#REF!
#REF!

RATE ANALYSIS

Item No : 3.8
Description of item : Providing, jointing and laying HDP pipes with or without collar etc. complete in place as per specification.
Unit: 50.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 3.000 960.00 2880.00 HDP pipe m 50.00 83.30 4165.00 Screw Jack hr 8.00 70.00 560.00
Unskilled md 3.000 700.00 2100.00 Petrol ltr 0.50 104.00 52.00 Blow lamps no 5.00 180.00 900.00
7.01 701

Sub - total (A) 4980.00 Sub - total (B) 4217.00 Sub total (c) 1460.00
Direct Cost (A+B+C) = NRs. 10657.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1598.55
Total Item Rate = NRs. 12255.55
Say per m. 245.11

Item No : 4.6
Description of item : Providing and installing different types of Bearing including all necessary axilliary and incidental works etc. complete as per drawing and specification.
Unit: 1.00 no.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Bearing no 1.00 20000.00 20000.00

Add10% of the cost of bearing for necessary


labour,materials, equipment and other
19.01 701 consumables. 2000.00

Sub - total (A) 0.00 Sub - total (B) 20000.00 Sub total (c) 2000.00
Direct Cost (A+B+C) = NRs. 22000.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 3300.00
Total Item Rate = NRs. 25300.00
Say per no 25300.00

ITECO N - SASCON JV Page 35


#REF!
#REF!

RATE ANALYSIS

Item No : 4.7
Description of item : Providing and installing expansion joints including all necessary axilliary and incidental works etc. complete as per drawing and specification.
Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Expansion joint m 1.10 1800.00 1980.00

Addl 10% of the cost of expansion joint for


necessary labour,materials, equipment and other
19.01 701 consumables. 198.00

Sub - total (A) 0.00 Sub - total (B) 1980.00 Sub total (c) 198.00
Direct Cost (A+B+C) = NRs. 2178.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 326.70
Total Item Rate = NRs. 2504.70
Say per m 2504.70

Item No : 6.6
Description of item : Providing and laying brick masonry in manual mixed cement mortar including preparation of mortar as per specification.
(Cement :Sand) 1:6 Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
2502 Cement t 0.06 17736.60 1064.20
25.02 2503 skilled md 1.5 960.00 1440.00 Sand m3 0.3 3346.35 1003.91 Tools 3% of labour cost 106.20
2504 Unskilled md 3.00 700.00 2100.00 Bricks no 560 8.50 4761.86
2505 water lit 36 0.1 3.60
2507

Sub - total (A) 3540.00 Sub - total (B) 6833.57 Sub total (c) 106.20
Direct Cost (A+B+C) = NRs. 10479.77
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1571.97
Total Item Rate = NRs. 12051.73
Say per m3 12051.73

ITECO N - SASCON JV Page 36


#REF!
#REF!

RATE ANALYSIS
Item No : 4.8
Description of item : Supply and fixing 100mm G.I. Pipe, medium class for drainage spout necessary accessory complete as per drawing and specification.
0.75 m long (Rate =market price*l) Unit: 1.00 no.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Pipe no 1.00 1503.50 1503.50

Sub - total (A) 0.00 Sub - total (B) 1503.50 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 1503.50
Additional 10% for the cost of pipe for necessary labour,materials, equipment and other consumables 1653.85
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 248.08
Total Item Rate = NRs. 1901.93
Say per no 1901.93

Item No : 4.9
Description of item : Supply and fixing of 50mm G.I. Pipe railing as per drawings all complete
Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Pipe no 1.00 631.33 631.33

Sub - total (A) Sub - total (B) 631.33 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 631.33
Additional 10% for the cost of pipe for necessary labour,materials, equipment and other consumables 694.46
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 104.17
Total Item Rate = NRs. 798.63
Say per m 798.63

ITECO N - SASCON JV Page 37


#REF!
#REF!

RATE ANALYSIS

Item No : 4.11
Description of item : Laying primer course and two coats of readymade Ist grade enamel paint ncluding supply of material all complete
Unit: 100.00 m2
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Painter md 12 700.00 8400.00 Enamel Primer lit 8.1 220.00 1782.00 Tools
13-5(a)+
(b)+© Unskilled md 8.00 700.00 5600.00 Enamel Paint lit 16 272.80 4364.80

Sub - total (A) 14000.00 Sub - total (B) 6146.80 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 20146.80
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 3022.02
Total Item Rate = NRs. 23168.82
Say per m2 231.69

Item No : 2.2
Description of item : Preparing well sinking site, opening road access, making island and providing and laying cutting edge of mild steel et. complete.
Unit: 1.00 tonne
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 15.000 960.00 14400.00 Mild Steel tonne 1.1000 106833.66 117517.03 Gas Cutter hr 1.0000 250.00 250.00
Unskilled md 15.000 700.00 10500.00 Nut and Bolts kg 17.0000 106.83 1816.11 Welding Machin hr 0.5000 300.00 150.00
17.02 1703
(4) Electrodes,Gas Etc (5% of Above) 5966.66

Sub - total (A) 24900.00 Sub - total (B) 125299.79 Sub total (c) 400.00
Direct Cost (A+B+C) = NRs. 150599.79
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 22589.97
Total Item Rate = NRs. 173189.76
Say per tonne. 173189.76

ITECO N - SASCON JV Page 38


#REF!
#REF!

RATE ANALYSIS

Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
i) Depth up to 3m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.600 960.00 576.00 Diesel lt. 23.0000 55.50 1276.50 hr 2.3000 3000.00 6900.00
10t. -Crane
Semiskilled md 1.200 790.00 948.00 with Grab
17.06.01 1705 Accesseries
(4)

Sub - total (A) 1524.00 Sub - total (B) 1276.50 Sub total (c) 6900.00
Direct Cost (A+B+C) = D NRs. 9700.50
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 10670.55
Contractor's Overhead @ 15 % of (D) = NRs. 1600.58
Total Item Rate = NRs. 12271.13
Say per m 12271.13

Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
ii) Depth up to 3-6m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.700 960.00 672.00 Diesel lt. 24.0000 55.50 1332.00 hr 2.4000 3000.00 7200.00
10t. -Crane
Semiskilled md 1.400 790.00 1106.00 with Grab
17.06.01 1705 Accesseries
(4)

Sub - total (A) 1778.00 Sub - total (B) 1332.00 Sub total (c) 7200.00
Direct Cost (A+B+C) = D NRs. 10310.00
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 11341.00
Contractor's Overhead @ 15 % of (D) = NRs. 1701.15
Total Item Rate = NRs. 13042.15
Say per m 13042.15

ITECO N - SASCON JV Page 39


#REF!
#REF!

RATE ANALYSIS

Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
iii) Depth up to 6-9m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.800 960.00 768.00 Diesel lt. 26.0000 55.50 1443.00 hr 2.6000 3000.00 7800.00
10t. -Crane
Semiskilled md 1.600 790.00 1264.00 with Grab
17.06.01 1705 Accesseries

Sub - total (A) 2032.00 Sub - total (B) 1443.00 Sub total (c) 7800.00
Direct Cost (A+B+C) = D NRs. 11275.00
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 12402.50
Contractor's Overhead @ 15 % of (D) = NRs. 1860.38
Total Item Rate = NRs. 14262.88
Say per m 14262.88

Item No : 2.7
Description of item : Providing and filling sand in well

Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.010 960.00 9.60 Sand M3 1.2000 3346.35 4015.63

17.08 1707
(4)

Sub - total (A) 9.60 Sub - total (B) 4015.63 Sub total (c) 0.00
Direct Cost (A+B+C) = D NRs. 4025.23
Contractor's Overhead @ 15 % of (D) = NRs. 603.78
Total Item Rate = NRs. 4629.01
Say per m3 4629.01
Item No : 5.8
Description of item : Providing and Laying RCC hume Pipes 900mm Dia

ITECO N - SASCON JV Page 40


#REF!
#REF!

RATE ANALYSIS

iii) 900mm dia Unit: 1.00 m


Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 0.344 960.00 330.24 RCC Pipe m 1.0000 8142.83 8142.83


Unskilled md 1.562 700.00 1093.40 Cement Kg 9.0620 17.74 160.73
7.02 701 Sand m3 0.0130 3346.35 43.50
(4) Jute kg 0.3750 110.00 41.25

Sub - total (A) 1423.64 Sub - total (B) 8388.31 Sub total (c) 0.00
Direct Cost (A+B+C) = D NRs. 9811.95
Additional Cost 3% for ballies, crow,bars,chain,pulley,blocks &ropes etc.= 1.03*D 10106.31
Contractor's Overhead @ 15 % of (1.03*D) = NRs. 1515.95
Total Item Rate = NRs. 11622.25
Say per m 11622.25

Item No : 5.9
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M15/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.01 2000 Skilled md 0.500 960.00 480.00 Cement t 0.2600 17736.60 4611.52 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4600 3346.35 1539.32
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 156.0000 0.10 15.60

Sub - total (A) 2930.00 Sub - total (B) 6866.94 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 10109.44
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1516.42
Total Item Rate = NRs. 11625.86
Say per cu.m. 11625.86

ITECO N - SASCON JV Page 41


#REF!
#REF!

RATE ANALYSIS
Item No : 5.12
Description of item : Providing, Mixing and Pointing Cement Mortar over rubble masonry works including all complete as per spec.
Cement:Sand (1:3)
100.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

Skilled md 10.000 960.00 9600.00 Cement t 0.3060 17736.60 5427.40


26.08 2602 Unskilled md 14.000 700.00 9800.00 C. Sand cu.m 0.6300 3346.35 2108.20 3 % of labour cost 582.00
2603 Water lit. 50.0000 0.10 5.00
2510
Sub - total (A) 19400.00 Sub - total (B) 7540.60 Sub total (c) 582.00
Direct Cost (A+B+C) = NRs. 27522.60
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 4128.39
Total Item Rate = NRs. 31650.99
Say per sq.m. 316.51
Item No : 2.3 (ii)
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
v) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount

20.02 2000 Skilled md 0.500 960.00 480.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 225.0000 0.10 22.50

Sub - total (A) 2930.00 Sub - total (B) 8880.08 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 12122.58
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1818.39
Total Item Rate = NRs. 13940.97
Say per cu.m. 13940.97

ITECO N - SASCON JV Page 42


TRANSPORTATION RATES

#REF!
#REF!

Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03

1) Excavated earth work (Soil Material) Unit :1 cu.m


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
First one km md 0.4 700 280 ltr 0.20 55.50 11.10 hr 0.13 844.40 107.66 398.76
First two km md 0.4 700 280 ltr 0.40 55.50 22.20 hr 0.38 844.40 320.87 623.07
First three km md 0.4 700 280 ltr 0.60 55.50 33.30 hr 0.42 844.40 354.65 667.95
First four km md 0.4 700 280 ltr 0.80 55.50 44.40 hr 0.46 844.40 388.42 712.82
First five km md 0.4 700 280 ltr 1.00 55.50 55.50 hr 0.50 844.40 422.20 757.70

2) Sand Unit :1 cu.m


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.3 700 210 ltr 0.17 55.50 9.44 hr 0.11 844.40 93.31 312.74
For 2 KM md 0.3 700 210 ltr 0.34 55.50 18.87 hr 0.12 844.40 104.28 333.15
For3 KM md 0.3 700 210 ltr 0.51 55.50 28.31 hr 0.14 844.40 115.26 353.57
For 4 KM md 0.3 700 210 ltr 0.68 55.50 37.74 hr 0.15 844.40 126.24 373.98
For5 KM md 0.3 700 210 ltr 0.85 55.50 47.18 hr 0.16 844.40 137.22 394.39
For 6 KM md 0.3 700 210 ltr 1.02 55.50 56.61 hr 0.18 844.40 148.19 414.80
For 7 KM md 0.3 700 210 ltr 1.19 55.50 66.05 hr 0.19 844.40 159.17 435.21
For 8 KM md 0.3 700 210 ltr 1.36 55.50 75.48 hr 0.20 844.40 170.15 455.63

ITECO N - SASCON JV Page 47


TRANSPORTATION RATES

#REF!
#REF!

Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03

3 Gravel,rivershingle,brokenstone aggegate and bats. Unit :1 cu.m


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.5 700 350 ltr 0.21 55.50 11.66 hr 0.14 844.40 114.84 476.49
For 2 KM md 0.5 700 350 ltr 0.42 55.50 23.31 hr 0.15 844.40 128.35 501.66
For3 KM md 0.5 700 350 ltr 0.63 55.50 34.97 hr 0.17 844.40 141.86 526.82
For 4 KM md 0.5 700 350 ltr 0.84 55.50 46.62 hr 0.18 844.40 155.37 551.99
For5 KM md 0.5 700 350 ltr 1.05 55.50 58.28 hr 0.20 844.40 168.88 577.16
For 6 KM md 0.5 700 350 ltr 1.26 55.50 69.93 hr 0.22 844.40 182.39 602.32
For 7 KM md 0.5 700 350 ltr 1.47 55.50 81.59 hr 0.23 844.40 195.90 627.49
For 8 KM md 0.5 700 350 ltr 1.68 55.50 93.24 hr 0.25 844.40 209.41 652.65

Boulder,Quarry stones. Unit :1 cu.m


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.5 700 350 ltr 0.27 55.50 14.99 hr 0.18 844.40 150.73 515.71
For 2 KM md 0.5 700 350 ltr 0.54 55.50 29.97 hr 0.20 844.40 168.46 548.43
For3 KM md 0.5 700 350 ltr 0.81 55.50 44.96 hr 0.22 844.40 186.19 581.15
For 4 KM md 0.5 700 350 ltr 1.08 55.50 59.94 hr 0.24 844.40 203.92 613.86
For5 KM md 0.5 700 350 ltr 1.35 55.50 74.93 hr 0.26 844.40 221.66 646.58
For 6 KM md 0.5 700 350 ltr 1.62 55.50 89.91 hr 0.28 844.40 239.39 679.30
For 7 KM md 0.5 700 350 ltr 1.89 55.50 104.90 hr 0.30 844.40 257.12 712.01
For 8 KM md 0.5 700 350 ltr 2.16 55.50 119.88 hr 0.33 844.40 274.85 744.73

ITECO N - SASCON JV Page 48


TRANSPORTATION RATES

#REF!
#REF!

Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03

Bricks Unit :1000 nos.


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.6 700 420 ltr 0.40 55.50 22.20 hr 0.26 844.40 222.50 664.70
For 2 KM md 0.6 700 420 ltr 0.80 55.50 44.40 hr 0.29 844.40 248.68 713.08
For3 KM md 0.6 700 420 ltr 1.20 55.50 66.60 hr 0.33 844.40 274.85 761.45
For 4 KM md 0.6 700 420 ltr 1.60 55.50 88.80 hr 0.36 844.40 301.03 809.83
For5 KM md 0.6 700 420 ltr 2.00 55.50 111.00 hr 0.39 844.40 327.21 858.21
For 6 KM md 0.6 700 420 ltr 2.40 55.50 133.20 hr 0.42 844.40 353.38 906.58
For 7 KM md 0.6 700 420 ltr 2.80 55.50 155.40 hr 0.45 844.40 379.56 954.96
For 8 KM md 0.6 700 420 ltr 3.20 55.50 177.60 hr 0.48 844.40 405.73 1003.33

Cement Unit :1 ton


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.4 700 280 ltr 0.15 55.50 8.33 hr 0.10 844.40 86.13 374.45
For 2 KM md 0.4 700 280 ltr 0.30 55.50 16.65 hr 0.11 844.40 96.26 392.91
For3 KM md 0.4 700 280 ltr 0.45 55.50 24.98 hr 0.13 844.40 106.39 411.37
For 4 KM md 0.4 700 280 ltr 0.60 55.50 33.30 hr 0.14 844.40 116.53 429.83
For5 KM md 0.4 700 280 ltr 0.75 55.50 41.63 hr 0.15 844.40 126.66 448.29
For 6 KM md 0.4 700 280 ltr 0.90 55.50 49.95 hr 0.16 844.40 136.79 466.74
For 7 KM md 0.4 700 280 ltr 1.05 55.50 58.28 hr 0.17 844.40 146.93 485.20
For 8 KM md 0.4 700 280 ltr 1.20 55.50 66.60 hr 0.19 844.40 157.06 503.66

ITECO N - SASCON JV Page 49


TRANSPORTATION RATES

#REF!
#REF!

Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03

Reinforcement Steel and Gabion Wire Unit :1 ton


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.6 700 420 ltr 0.15 55.50 8.33 hr 0.10 844.40 86.13 514.45
For 2 KM md 0.6 700 420 ltr 0.30 55.50 16.65 hr 0.11 844.40 96.26 532.91
For3 KM md 0.6 700 420 ltr 0.45 55.50 24.98 hr 0.13 844.40 106.39 551.37
For 4 KM md 0.6 700 420 ltr 0.60 55.50 33.30 hr 0.14 844.40 116.53 569.83
For5 KM md 0.6 700 420 ltr 0.75 55.50 41.63 hr 0.15 844.40 126.66 588.29
For 6 KM md 0.6 700 420 ltr 0.90 55.50 49.95 hr 0.16 844.40 136.79 606.74
For 7 KM md 0.6 700 420 ltr 1.05 55.50 58.28 hr 0.17 844.40 146.93 625.20
For 8 KM md 0.6 700 420 ltr 1.20 55.50 66.60 hr 0.19 844.40 157.06 643.66

GI,CI,Pipe and Fittings Unit :1 ton


Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 1 700 700 ltr 0.15 55.50 8.33 hr 0.10 844.40 86.13 794.45
For 2 KM md 1 700 700 ltr 0.30 55.50 16.65 hr 0.11 844.40 96.26 812.91
For3 KM md 1 700 700 ltr 0.45 55.50 24.98 hr 0.13 844.40 106.39 831.37
For 4 KM md 1 700 700 ltr 0.60 55.50 33.30 hr 0.14 844.40 116.53 849.83
For5 KM md 1 700 700 ltr 0.75 55.50 41.63 hr 0.15 844.40 126.66 868.29
For 6 KM md 1 700 700 ltr 0.90 55.50 49.95 hr 0.16 844.40 136.79 886.74
For 7 KM md 1 700 700 ltr 1.05 55.50 58.28 hr 0.17 844.40 146.93 905.20
For 8 KM md 1 700 700 ltr 1.20 55.50 66.60 hr 0.19 844.40 157.06 923.66

ITECO N - SASCON JV Page 50


TRANSPORTATION RATES

#REF!
#REF!

Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
Timber Unit :m3
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.3 700 210 ltr 0.14 55.50 7.77 hr 0.09 844.40 78.95 296.72
For 2 KM md 0.3 700 210 ltr 0.28 55.50 15.54 hr 0.10 844.40 88.24 313.78
For3 KM md 0.3 700 210 ltr 0.42 55.50 23.31 hr 0.12 844.40 97.53 330.84
For 4 KM md 0.3 700 210 ltr 0.56 55.50 31.08 hr 0.13 844.40 106.82 347.90
For5 KM md 0.3 700 210 ltr 0.70 55.50 38.85 hr 0.14 844.40 116.11 364.96
For 6 KM md 0.3 700 210 ltr 0.84 55.50 46.62 hr 0.15 844.40 125.39 382.01
For 7 KM md 0.3 700 210 ltr 0.98 55.50 54.39 hr 0.16 844.40 134.68 399.07
For 8 KM md 0.3 700 210 ltr 1.12 55.50 62.16 hr 0.17 844.40 143.97 416.13
RCC Hume Pipe(900mm Dia) Unit :m
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.4 700 280 md 0.04 960 ltr 0.08 55.50 4.33 hr 0.11 844.40 93.73 378.06
For 2 KM md 0.4 700 280 md 0.04 960 ltr 0.16 55.50 8.66 hr 0.12 844.40 98.79 387.45
For3 KM md 0.4 700 280 md 0.04 960 ltr 0.23 55.50 12.99 hr 0.12 844.40 103.86 396.85
For 4 KM md 0.4 700 280 md 0.04 960 ltr 0.31 55.50 17.32 hr 0.13 844.40 108.93 406.24
For5 KM md 0.4 700 280 md 0.04 960 ltr 0.39 55.50 21.65 hr 0.14 844.40 113.99 415.64
For 6 KM md 0.4 700 280 md 0.04 960 ltr 0.47 55.50 25.97 hr 0.14 844.40 119.06 425.03
For 7 KM md 0.4 700 280 md 0.04 960 ltr 0.55 55.50 30.30 hr 0.15 844.40 124.13 434.43
For 8 KM md 0.4 700 280 md 0.04 960 ltr 0.62 55.50 34.63 hr 0.15 844.40 129.19 443.83

ITECO N - SASCON JV Page 51


BILL OF QUANTITIES- MAIN BUILDING BLOCK
###
###
Structure : Boiler Building (12mx15m)
BILL OF QUANTITIES- SECURITY & BOILER BUILDING
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
1 Foundation Works

MECHANICAL EARTHWORK: Excavation


in foundations in all types of soils for
foundation, trenches, footing, pits etc to the
required depth including dewatering by
manual or mechanical means etc (including
supporting and butressing for shallow
1.1 m3 40.40
excavation work) as per specifiations with
all contractor's own machinary and
equipments and disposing off the
surplus/unusable earth to outside the
constuction premises etc all complete as
per drawings and specifications.

### #REF! ### #REF!

STONE SOLING AT FOUNDATION:


Supplying and placing of 150mm of dry
stone soling with sand filling at foundation
1.2 m3 31.63
and ground flooring of the building and
lower tie beam as per specification and
instruction of Enigneer.

BILL OF QUANTITY 1
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
PCC - M10/40 :Providing and placing
machine mixed cement concrete Grade
M10/40 for foundation PCC including
1.3 m3 3.33
compaction, curing, testing and lead 30m.
etc. all complete as per specification and
drawing.

EARTHWORK BACKFILL :Backfilling in


foundation, floors and sides of foundation
with approved gravel materials/soil in layer
not exceeding 15cm thick (compacted
thickness) including purchasing and
2.5 m3 120.95
transportation of soil, spreading in required
line and level, sprinkling water, ramming,
compacting with mechanical rammers,
testing etc all complete as per drawing and
specification.

2 Masonry Works
BRICKWORK: Good quality local brick
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
2.1 bricks, racking the joints, scaffolding and m3 22.64
curing the work for at least 7 days all
complete as per specification and
instruction of Engineer.

BILL OF QUANTITY 2
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
3 Concrete Works

M20/20 CONCRETE: Providing and laying


in position machine mixed and machine
vibrated design mix cement concrete M25
grade for reinforced cement concrete
work(Footing and Column Pedestal) using
OPC 53 grade cement with 20 mm graded
3.1 machine crushed stone aggregate of m3 15.14
approved quality in various locations and
heights including transportation of concrete
to site of placing, compaction, finished to
required line and level, protection and
curing etc all complete as per drawings and
specifications.

GROUTING CONCRETE LEVELLING


COURSE: Providing and laying in position
High compressive non shrink grouting for
levelling course of steel column base
3.2 m3 0.23
(maximum 75 mm thk.) finished to required
line and level, protection and curing etc all
complete as per drawings and
specifications.

BILL OF QUANTITY 3
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.

REINFORCEMENT: Providing and fixing in


position Fe 500 TMT steel reinforcement of
various diameter confirming to relevant IS
code in RCC works including straightening,
cutting, bending, binding with 20 SWG
annealed wire for tying the reinforcement
bars at each junctions (binding wire shall
not be measured separately) including all
3.3 waste and cut pieces, provision for mt 1.37
adequate number of spacers, chairs,
providing and placing cement mortar (1:1)
cover blocks to keep the bars in intended
position at all levels all complets as per
drawings, specifications and instructions of
the Engineer. (The item shall include the
installation of the anchhor bolts in line and
level (Client Provided).

FORMWORK/SHUTTERING: Providing
and laying, centering and shuttering with
approved materials for all kinds RCC works
including all necessary mild steel
propping,scaffolding, staging, supporting,
3.4 etc. all complete net as per drawings, m2 104.48
specifications and instructions of the
engineer, all complete. a) 19mm thick
waterproof Ply Wood or steel Form Work
for plain slab,column, Beams, foundations,
etc

4 Flooring
SUB BASE PCC (1:3:6): Providing and
laying 75 mm or thicker concrete (1
cement: 3 sand:3 aggregates) on the floor
4.1 including chipping, cleaning and wetting the m2 100.00
surface and curing the works as per
drawings, specifications and instruction of
A/E

BILL OF QUANTITY 4
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
500 GAUGE PLASTIC FELT : Supplying,
laying of 500 MM GAUGE PLASTIC FELT
4.2 over the prepared sub base PCC with m2 80.00
welded joings as per drawings,
specifications and instruction of A/E.

VITRIFIED TILE FLOORING: Providing


and laying non-slip 300x300x8mm fully
vitrified tiles of approved colour, shade, and
pattern. To be laid on minimum 25mm thick
4.3 m2 100.00
cement screed (1 cement : 4 sand) and
jointed with grouting epoxy matched to the
shade of the tile. All as per drawings,
specifications and instruction of A/E.

Sub Total:

VAT 13%

Total :

In Words:

Submitted By:

BILL OF QUANTITY 5

You might also like