Professional Documents
Culture Documents
Boiler Estimate
Boiler Estimate
PCC - M10/40 :Providing and placing machine mixed cement concrete Grade
1.3 M10/40 for foundation PCC including compaction, curing, testing and lead m3 3.33 14,350.00 47,785.50
30m. etc. all complete as per specification and drawing.
Abstract of Cost
Page 1
Security Boiler Bldg.
ABSTRACT OF COST
Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur
Location : Janakpur
Structure : Boiler Building (12mx15m)
BILL OF QUANTITIES- SECURITY & BOILER BUILDING
Item Amount
Description Unit Quantity Rate (NRs) Remarks
No. (NRs)
3 Concrete Works
Abstract of Cost
Page 2
Security Boiler Bldg.
ABSTRACT OF COST
Project : Construction and Supervision of Janakpur Oil Refinery Factory, Janakpur
Location : Janakpur
Structure : Boiler Building (12mx15m)
BILL OF QUANTITIES- SECURITY & BOILER BUILDING
Item Amount
Description Unit Quantity Rate (NRs) Remarks
No. (NRs)
4 Flooring
SUB BASE PCC (1:3:6): Providing and laying 75 mm or thicker concrete (1
cement: 3 sand:3 aggregates) on the floor including chipping, cleaning and
4.1 m2 100.00 920.00 92,000.00
wetting the surface and curing the works as per drawings, specifications and
instruction of A/E
500 GAUGE PLASTIC FELT : Supplying, laying of 500 MM GAUGE
4.2 PLASTIC FELT over the prepared sub base PCC with welded joings as per m2 80.00 150.00 12,000.00
drawings, specifications and instruction of A/E.
VITRIFIED TILE FLOORING: Providing and laying non-slip 300x300x8mm
fully vitrified tiles of approved colour, shade, and pattern. To be laid on
4.3 minimum 25mm thick cement screed (1 cement : 4 sand) and jointed with m2 100.00 2,200.00 220,000.00
grouting epoxy matched to the shade of the tile. All as per drawings,
specifications and instruction of A/E.
Total of Item No. 1 To 6 1,587,532.46
Abstract of Cost
Page 3
Security Boiler Bldg.
DETAILED MEASUREMENT SHEET
i) Footing
Footing 1 4 2.200 1.700 2.000 29.92
iii) Lower Tie Beam
Grid 1-1,2-2 2 7.400 0.400 1.000 5.92
Grid A-A,B-B 2 5.700 0.400 1.000 4.56
Total: 40.40
GRAVELLY MIXED SOIL PACKING BELOW FOOTING: Providing,
laying, spreading, watering, levelling and full compaction (90%) of 200
1.2 mm thick gravelly mixed soil subbase grading material as per table m3
12.1 of standard specification(DoR Specification) and instruction of
Engineer.
Footing
Footing 1 4 2.200 1.700 0.300 4.49
Total: 4.49
STONE SOLING AT FOUNDATION: Supplying and placing of 150mm
of dry stone soling with sand filling at foundation and ground flooring
1.3 m3
of the building and lower tie beam as per specification and instruction
of Enigneer.
i) Footing
Footing 1 4 2.200 1.700 0.300 4.49
iii) Lower Tie Beam
Grid 1-1,2-2 2 7.400 0.400 0.300 1.78
Grid A-A,B-B 2 5.700 0.400 0.300 1.37
Ground Floor Flooring 1 10.000 8.000 0.300 24.00
Total: 31.63
Total: 3.33
0.95
Upto Plinth 1 10.000 8.000 1.500 120.00
Total: 120.95
2 Masonry Works
Pedestal
P1 2 0.330 0.600 3.30 1.31
P2 2 0.850 0.650 3.30 3.65
Footing
Footing 1 4 2.154 0.20 1.72 Trapezoidal
4 2.500 2.000 0.20 4.00 Uniform
Lower Tie Beam/Upper Tie beam
Grid 1-1,2-2 4 9.00 0.23 0.30 2.48
Grid A-A,B-B 4 7.17 0.23 0.30 1.98
Total: 15.14
GROUTING CONCRETE LEVELLING COURSE: Providing and laying
in position High compressive non shrink grouting for levelling course of
3.2 steel column base (maximum 75 mm thk.) finished to required line and m3
level, protection and curing etc all complete as per drawings and
specifications.
P1 2 0.330 0.600 0.15 0.06
P2 2 0.850 0.650 0.15 0.17
Total: 0.23
Footing
12.00 mm 4 43.500 0.888 154.48
Pedestal
Main Bar
P1 20.00 mm 16 4.300 2.500 172.00
16.00 mm 16 4.300 1.600 110.08
Stirrups
Rectangular 8.00 mm 172 1.900 0.400 130.72
Single Legged 0.6 8.00 mm 172 0.750 0.400 51.60
Single legger 0.33 8.00 mm 172 0.480 0.400 33.02
Lower Tie Beam
Main Bar 16.00 mm 4 32.340 1.600 206.98
8.00 mm 1 228.536 0.400 91.41
Upper Tie Beam
Main Bar 16.00 mm 4 32.340 1.600 206.98
8.00 mm 1 228.536 0.400 91.41
Projected Part 8.00 mm 3 32.340 0.400 38.81
8.00 mm 216 1.000 0.400 86.24
1,373.73
i) Footing
Footing 1 4 7.800 0.400 12.48
Pedestal
P1 2 1.860 3.300 12.28
P2 2 3.000 3.300 19.80
Footing
Footing 1 4 7.800 0.200 6.24
Lower Tie Beam/Upper Tie beam
Grid 1-1,2-2 4 9.000 0.830 29.88
Grid A-A,B-B 4 7.170 0.830 23.80
Total: 104.48
4 Flooring
SUB BASE PCC (1:3:6): Providing and laying 75 mm or thicker
concrete (1 cement: 3 sand:3 aggregates) on the floor including
4.1 m2
chipping, cleaning and wetting the surface and curing the works as per
drawings, specifications and instruction of A/E
Ground Floor 1 100.000 100.00
Total: 100.00
RATE ANALYSIS
Item No : 6.1
Description of item : Earth work for foundation through all types of soil including relevant lift 1.5m and 20m lead respectively
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
9.07.01 907 Unskilled md 2.000 700.00 1400.00 tools 3 % of labour cost 42.00
Sub - total (A) 1400.00 Sub - total (B) 0.00 Sub total (c) 42.00
Direct Cost (A+B+C) = NRs. 1442.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 216.30
Total Item Rate = NRs. 1658.30
Say per cu.m. 1658.30
Item No : 2.1
Description of item : Earth work for foundation through all types of soil including relevant lift more than 1.5m up to 3.0m and 20m lead respectively
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
0.00
0.00
9.07.01 907 Unskilled md 3.000 700.00 2100.00 0.00 tools 3 % of labour cost 63.00
Sub - total (A) 2100.00 Sub - total (B) 0.00 Sub total (c) 63.00
Direct Cost (A+B+C) = NRs. 2163.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 324.45
Total Item Rate = NRs. 2487.45
Say per cu.m. 2487.45
RATE ANALYSIS
Item No : 3.9
Description of item : Backfilling with the graded filter material in layer with necessary watering and compaction,lead 30m, lift 1.5m.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
24.11 2404 Skilled md 0.000 960.00 0.00 Gravel cu.m 1.1000 3309.98 3640.98
3110 Unskilled md 0.800 700.00 560.00 filter
Sub - total (A) 560.00 Sub - total (B) 3640.98 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4200.98
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 630.15
Total Item Rate = NRs. 4831.13
Say per cu.m. 4831.13
Item No : 3.10
Description of item : Backfilling in layers in foundation pits,trenches,etc including compaction and watering etc. complete lead10m.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
9.1 908 Unskilled md 1.140 700.00 798.00 Diesel Ltr. 0.11 55.500 6.11
tools % 3 % of labour cost 23.94
Vibrator Roller hr. 0.11 500 55
1-1.5tons
Sub - total (A) 798.00 Sub - total (B) 6.11 Sub total (c) 78.94
Direct Cost (A+B+C) = NRs. 883.05
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 132.46
Total Item Rate = NRs. 1015.50
Say per cu.m. 1015.50
RATE ANALYSIS
Item No : 6.2
Description of item : Providing and fabricating gabion crates of more than 50 cm height mesh size with 100 mm x 120 mm hexagonal mess and heavy coated including rolling,
cutting, weaving filling of broken stones etc. complete (mess wire 10 SWG, weaving wire 12 SWG and Selvedge wire 7 SWG), lead 10m lift 1.5m
Unit:(2*1*1) 2.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
24.01.02 2401 Skilled md 0.840 960.00 806.40 G.I wire(Mesh) kg 25.4500 110.21 2804.84
24.02.01 Unskilled md 2.750 700.00 1925.00 G.I wire(Salvage )kg 3.4100 110.21 375.82 3 % of labour cost 81.94
24.02.04 Stone cum 2.2000 2691.63 5921.59
Sub - total (A) 2731.40 Sub - total (B) 9102.25 Sub total (c) 81.94
Direct Cost (A+B+C) = NRs. 11915.60
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1787.34
Total Item Rate = NRs. 13702.93
Say per cu.m. 6851.47
Item No : 6.4
Description of item : Providing and fabricating gabion crates of less than 50 cm height mesh size with 100 mm x 120 mm hexagonal mess and heavy coated including rolling,
cutting, weaving filling of broken stones etc. complete (mess wire 10 SWG, weaving wire 12 SWG and Selvedge wire 7 SWG), lead 10m lift 1.5m
Unit:(2*1*.5) 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
24.01.02 2401 Skilled md 0.480 960.00 460.80 G.I wire(Mesh) kg 17.3000 110.21 1906.63
24.02.01 Unskilled md 1.390 700.00 973.00 G.I wire(Salvage )kg 2.8000 110.21 308.59 3 % of labour cost 43.01
24.02.04 Stone cum 1.1000 2691.63 2960.80
Sub - total (A) 1433.80 Sub - total (B) 5176.02 Sub total (c) 43.01
Direct Cost (A+B+C) = NRs. 6652.83
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 997.92
Total Item Rate = NRs. 7650.76
Say per cu.m. 7650.76
RATE ANALYSIS
Item No : 6.5
Description of item : Providing and laying random rubble stone masonry of hard stone in 1 : 4 cement sand mortar including stone dressing,mortar transportation all complete, masoned height 0 to 5 m
lead 30m
Unit: 1.00 cu.m.
Norms Specification
activity Clause Resources
Labour (A) Materials (B) Equipment (C)
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 4590.00 Sub - total (B) 7360.41 Sub total (c) 137.70
Direct Cost (A+B+C) = NRs. 12088.11
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1813.22
Total Item Rate = NRs. 13901.33
Say per cu.m. 13901.33
Item No : 2.3 (i)
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.500 960.00 480.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 0.10 19.80
Sub - total (A) 2930.00 Sub - total (B) 8045.77 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 11288.27
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1693.24
Total Item Rate = NRs. 12981.52
Say per cu.m. 12981.52
RATE ANALYSIS
Item No : 3.1
Description of item : a) Providing and placing machine mixed cement concrete for the abutement, pier, wall etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iii) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.900 960.00 864.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 9.000 700.00 6300.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 0.10 19.80
Sub - total (A) 7164.00 Sub - total (B) 10434.96 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 17911.46
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2686.72
Total Item Rate = NRs. 20598.18
Say per cu.m. 20598.18
Item No : 3.2
Description of item : a) Providing and placing machine mixed cement concrete for the abutement, pier, wall etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.900 960.00 864.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 9.000 700.00 6300.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.2000 55.50 177.60
Water lit. 225.0000 0.10 22.50
Sub - total (A) 7164.00 Sub - total (B) 11280.37 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 18756.87
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2813.53
Total Item Rate = NRs. 21570.40
Say per cu.m. 21570.40
RATE ANALYSIS
Item No : 4.1
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
i) Grade M20/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.3300 17736.60 5853.08 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 198.0000 3.00 594.00
Sub - total (A) 4968.00 Sub - total (B) 11009.16 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 16289.66
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2443.45
Total Item Rate = NRs. 18733.11
Say per cu.m. 18733.11
Item No : 4.2
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
ii) Grade M25/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5800 3309.98 1919.79 vibrator hr 0.2500 50.00 12.50
Operator md 0.200 960.00 192.00 10mm- downagg cu.m 0.3000 3309.98 992.99
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 225.0000 0.10 22.50
Sub - total (A) 5160.00 Sub - total (B) 11269.27 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 16741.77
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2511.27
Total Item Rate = NRs. 19253.03
Say per cu.m. 19253.03
RATE ANALYSIS
Item No : 4.3
Description of item : a) Providing and placing machine mixed cement concrete for the super structure, deckslab, girder etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iii) Grade M30/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.03 2000 Skilled md 0.800 960.00 768.00 Cement t 0.4100 17736.60 7272.01 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 6.000 700.00 4200.00 10-20mm-agg cu.m 0.5700 3309.98 1886.69 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3300 3309.98 1092.29
C. Sand cu.m 0.4400 3346.35 1472.40
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 246.0000 0.10 24.60
Sub - total (A) 4968.00 Sub - total (B) 11924.89 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 17205.39
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 2580.81
Total Item Rate = NRs. 19786.19
Say per cu.m. 19786.19
Item No : 2.5
Description of item : Providing , Preparing and Installing form work including necessary supports and removing after completion for foundation and footings.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 38mm thick m3 0.0525 43502.23 2283.87
18.01 1804 Skilled md 1.500 960.00 1440.00 (0.42m3/8 times)
1805 Unskilled md 2.000 700.00 1400.00 Struts balis etc cu.m 0.0150 43502.23 652.53
(.18/12 times)
Nails kg 2.7500 90.00 247.50
Sub - total (A) 2840.00 Sub - total (B) 3183.90 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 6023.90
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 903.59
Total Item Rate = NRs. 6927.49
Say per sq.m. 692.75
RATE ANALYSIS
Item No : 3.4
Description of item : Providing , Preparing and Installing form work including necessary supports and removing after completion for walls.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 9mm thick m2 1.3750 1850.44 2544.36
18.02 1804 Skilled md 2.400 960.00 2304.00 (11m2/8 times)
(i and ii
avg.) 1805 Unskilled md 2.500 700.00 1750.00 Struts balis etc cu.m 0.0750 43502.23 3262.67
(.45/12 times)
Nails kg 2.7500 90.00 247.50
Sub - total (A) 4054.00 Sub - total (B) 6054.53 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 10108.53
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1516.28
Total Item Rate = NRs. 11624.81
Say per sq.m. 1162.48
Item No : 4.5
Description of item : Providing , Preparing and Installing form work & removing after completion for Slab & beam structure.
a) Using Timber Unit: 10.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Planks 38mm thick cu.m 0.1000 43502.23 4350.22
18.05 1804 Skilled md 3.000 960.00 2880.00 (0.60m3/6 times)
(I and ii
avg.) 1805 Unskilled md 3.000 700.00 2100.00 Struts balis etc cu.m 0.0150 43502.23 652.53
(.22/8 times)
Nails kg 4.0000 90.00 360.00
Sub - total (A) 4980.00 Sub - total (B) 5362.76 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 10342.76
` Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1551.41
Total Item Rate = NRs. 11894.17
Say per sq.m. 1189.42
RATE ANALYSIS
Item No : 5.2
Description of item : Road way excavation in soft soil including disposal upto 10m and lift upto 1.5 m etc. all complete as per specification.
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
9.01 905 Unskilled md 0.750 700.00 525.00 tools 3 % of labour cost 15.75
Sub - total (A) 525.00 Sub - total (B) 0.00 Sub total (c) 15.75
Direct Cost (A+B+C) = NRs. 540.75
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 81.11
Total Item Rate = NRs. 621.86
Say per cu.m. 621.86
Item No : 5.3
Description of item : Formation of embankment including compaction in layers not exceeding 150mm. Compacted depth, watering and haulage 10m. etc. all complete as per specification.
Skilled md 0.002 960.00 1.92 Suitable Materialm3 1.1000 200.00 220.00 Grader hr 0.0050 3000.00 15.00
9.05.01 903 (2) Unskilled md 0.008 700.00 5.60 Diesel ltr 0.1200 55.50 6.66 Roller hr 0.0167 1500.00 25.05
Sub - total (A) 7.52 Sub - total (B) 226.66 Sub total (c) 40.05
Direct Cost (A+B+C) = NRs. 274.23
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 41.13
Total Item Rate = NRs. 315.36
Say per cu.m. 315.36
RATE ANALYSIS
Item No : 5.4
Description of item : Preparation of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in common soil:
1.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 105.00 Sub - total (B) 0.00 Sub total (c) 3.15
Direct Cost (A+B+C) = NRs. 108.15
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 16.22
Total Item Rate = NRs. 124.37
Say per sq.m. 124.37
Item No : 5.5
Description of item : Providing, laying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard specification lead upto 10m .
Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 32.80 Sub - total (B) 1903.35 Sub total (c) 139.20
Direct Cost (A+B+C) = NRs. 2075.35
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 311.30
Total Item Rate = NRs. 2386.65
Say per cu.m. 2386.65
RATE ANALYSIS
Item No : 5.6
Description of item : Supply and laying grass turfing on the various slope with cutting, watering and transportaion up to 1000m etc. all complete
Unit: 1.00 sq.m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 35.00 Sub - total (B) 39.88 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 74.88
Note :- 1 m3 turffing = 10 m2 Contractor's Overhead @ 15 % of (A+B+C) = NRs. 11.23
Total Item Rate = NRs. 86.11
Say per sq.m. 86.11
Item No : 6.3
Description of item : Providing, laying and fixing of Geo-textile (filter fabrics), lead 30m
Unit: 1.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 11.90 Sub - total (B) 448.50 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 460.40
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 69.06
Total Item Rate = NRs. 529.46
Say per sq.m. 529.46
RATE ANALYSIS
Item No : 3.3 and 4.4
Description of item : Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and drawing.
Diameter above 8mm and 16mm ii and iii average Unit: 1.00 ton
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 17430.00 Sub - total (B) 112309.82 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 129739.82
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 19460.97
Total Item Rate = NRs. 149200.79
Say per ton. 149200.79
Item No : 3.5
Description of item : Supplying and placing of dry stone layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 1976.00 Sub - total (B) 2960.80 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4936.80
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 740.52
Total Item Rate = NRs. 5677.32
Say per cum. 5677.32
RATE ANALYSIS
Item No : 3.6
Description of item : Supplying and placing of dry gravel layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 560.00 Sub - total (B) 1597.92 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 2157.92
Ref is taken same as dry graded filter Contractor's Overhead @ 15 % of (A+B+C) = NRs. 323.69
Total Item Rate = NRs. 2481.60
Say per cum. 2481.60
Item No : 3.7
Description of item : Supplying and placing of dry sand layer at rear of the abutment and bedding as approan.
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 560.00 Sub - total (B) 3680.99 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 4240.99
Ref is taken same as dry graded filter Contractor's Overhead @ 15 % of (A+B+C) = NRs. 636.15
Total Item Rate = NRs. 4877.14
Say per cum. 4877.14
RATE ANALYSIS
Item No : 3.8
Description of item : Providing, jointing and laying HDP pipes with or without collar etc. complete in place as per specification.
Unit: 50.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 3.000 960.00 2880.00 HDP pipe m 50.00 83.30 4165.00 Screw Jack hr 8.00 70.00 560.00
Unskilled md 3.000 700.00 2100.00 Petrol ltr 0.50 104.00 52.00 Blow lamps no 5.00 180.00 900.00
7.01 701
Sub - total (A) 4980.00 Sub - total (B) 4217.00 Sub total (c) 1460.00
Direct Cost (A+B+C) = NRs. 10657.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1598.55
Total Item Rate = NRs. 12255.55
Say per m. 245.11
Item No : 4.6
Description of item : Providing and installing different types of Bearing including all necessary axilliary and incidental works etc. complete as per drawing and specification.
Unit: 1.00 no.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 0.00 Sub - total (B) 20000.00 Sub total (c) 2000.00
Direct Cost (A+B+C) = NRs. 22000.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 3300.00
Total Item Rate = NRs. 25300.00
Say per no 25300.00
RATE ANALYSIS
Item No : 4.7
Description of item : Providing and installing expansion joints including all necessary axilliary and incidental works etc. complete as per drawing and specification.
Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 0.00 Sub - total (B) 1980.00 Sub total (c) 198.00
Direct Cost (A+B+C) = NRs. 2178.00
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 326.70
Total Item Rate = NRs. 2504.70
Say per m 2504.70
Item No : 6.6
Description of item : Providing and laying brick masonry in manual mixed cement mortar including preparation of mortar as per specification.
(Cement :Sand) 1:6 Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
2502 Cement t 0.06 17736.60 1064.20
25.02 2503 skilled md 1.5 960.00 1440.00 Sand m3 0.3 3346.35 1003.91 Tools 3% of labour cost 106.20
2504 Unskilled md 3.00 700.00 2100.00 Bricks no 560 8.50 4761.86
2505 water lit 36 0.1 3.60
2507
Sub - total (A) 3540.00 Sub - total (B) 6833.57 Sub total (c) 106.20
Direct Cost (A+B+C) = NRs. 10479.77
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1571.97
Total Item Rate = NRs. 12051.73
Say per m3 12051.73
RATE ANALYSIS
Item No : 4.8
Description of item : Supply and fixing 100mm G.I. Pipe, medium class for drainage spout necessary accessory complete as per drawing and specification.
0.75 m long (Rate =market price*l) Unit: 1.00 no.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) 0.00 Sub - total (B) 1503.50 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 1503.50
Additional 10% for the cost of pipe for necessary labour,materials, equipment and other consumables 1653.85
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 248.08
Total Item Rate = NRs. 1901.93
Say per no 1901.93
Item No : 4.9
Description of item : Supply and fixing of 50mm G.I. Pipe railing as per drawings all complete
Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Sub - total (A) Sub - total (B) 631.33 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 631.33
Additional 10% for the cost of pipe for necessary labour,materials, equipment and other consumables 694.46
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 104.17
Total Item Rate = NRs. 798.63
Say per m 798.63
RATE ANALYSIS
Item No : 4.11
Description of item : Laying primer course and two coats of readymade Ist grade enamel paint ncluding supply of material all complete
Unit: 100.00 m2
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Painter md 12 700.00 8400.00 Enamel Primer lit 8.1 220.00 1782.00 Tools
13-5(a)+
(b)+© Unskilled md 8.00 700.00 5600.00 Enamel Paint lit 16 272.80 4364.80
Sub - total (A) 14000.00 Sub - total (B) 6146.80 Sub total (c) 0.00
Direct Cost (A+B+C) = NRs. 20146.80
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 3022.02
Total Item Rate = NRs. 23168.82
Say per m2 231.69
Item No : 2.2
Description of item : Preparing well sinking site, opening road access, making island and providing and laying cutting edge of mild steel et. complete.
Unit: 1.00 tonne
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 15.000 960.00 14400.00 Mild Steel tonne 1.1000 106833.66 117517.03 Gas Cutter hr 1.0000 250.00 250.00
Unskilled md 15.000 700.00 10500.00 Nut and Bolts kg 17.0000 106.83 1816.11 Welding Machin hr 0.5000 300.00 150.00
17.02 1703
(4) Electrodes,Gas Etc (5% of Above) 5966.66
Sub - total (A) 24900.00 Sub - total (B) 125299.79 Sub total (c) 400.00
Direct Cost (A+B+C) = NRs. 150599.79
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 22589.97
Total Item Rate = NRs. 173189.76
Say per tonne. 173189.76
RATE ANALYSIS
Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
i) Depth up to 3m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.600 960.00 576.00 Diesel lt. 23.0000 55.50 1276.50 hr 2.3000 3000.00 6900.00
10t. -Crane
Semiskilled md 1.200 790.00 948.00 with Grab
17.06.01 1705 Accesseries
(4)
Sub - total (A) 1524.00 Sub - total (B) 1276.50 Sub total (c) 6900.00
Direct Cost (A+B+C) = D NRs. 9700.50
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 10670.55
Contractor's Overhead @ 15 % of (D) = NRs. 1600.58
Total Item Rate = NRs. 12271.13
Say per m 12271.13
Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
ii) Depth up to 3-6m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.700 960.00 672.00 Diesel lt. 24.0000 55.50 1332.00 hr 2.4000 3000.00 7200.00
10t. -Crane
Semiskilled md 1.400 790.00 1106.00 with Grab
17.06.01 1705 Accesseries
(4)
Sub - total (A) 1778.00 Sub - total (B) 1332.00 Sub total (c) 7200.00
Direct Cost (A+B+C) = D NRs. 10310.00
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 11341.00
Contractor's Overhead @ 15 % of (D) = NRs. 1701.15
Total Item Rate = NRs. 13042.15
Say per m 13042.15
RATE ANALYSIS
Item No : 2.6
Description of item : Sinking of well through different type of soil and rock including clearance of obstructions, correction of shift and tilts etc. complete as per specification and drawing.
iii) Depth up to 6-9m
Dia of Well 5.00m Unit: 1.00 m
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
Skilled md 0.800 960.00 768.00 Diesel lt. 26.0000 55.50 1443.00 hr 2.6000 3000.00 7800.00
10t. -Crane
Semiskilled md 1.600 790.00 1264.00 with Grab
17.06.01 1705 Accesseries
Sub - total (A) 2032.00 Sub - total (B) 1443.00 Sub total (c) 7800.00
Direct Cost (A+B+C) = D NRs. 11275.00
Add 10% of the total cost for kentledges,removal of obstruction and correction against shift, tilt, etc. as required.= 1.10*D 12402.50
Contractor's Overhead @ 15 % of (D) = NRs. 1860.38
Total Item Rate = NRs. 14262.88
Say per m 14262.88
Item No : 2.7
Description of item : Providing and filling sand in well
Unit: 1.00 m3
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
17.08 1707
(4)
Sub - total (A) 9.60 Sub - total (B) 4015.63 Sub total (c) 0.00
Direct Cost (A+B+C) = D NRs. 4025.23
Contractor's Overhead @ 15 % of (D) = NRs. 603.78
Total Item Rate = NRs. 4629.01
Say per m3 4629.01
Item No : 5.8
Description of item : Providing and Laying RCC hume Pipes 900mm Dia
RATE ANALYSIS
Sub - total (A) 1423.64 Sub - total (B) 8388.31 Sub total (c) 0.00
Direct Cost (A+B+C) = D NRs. 9811.95
Additional Cost 3% for ballies, crow,bars,chain,pulley,blocks &ropes etc.= 1.03*D 10106.31
Contractor's Overhead @ 15 % of (1.03*D) = NRs. 1515.95
Total Item Rate = NRs. 11622.25
Say per m 11622.25
Item No : 5.9
Description of item : a) Providing and placing machine mixed cement concrete for the foundation and footing etc. including compaction, curing, testing and lead 30m. etc. all complete as per specification and drawing.
iv) Grade M15/20 Unit: 1.00 cu.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.01 2000 Skilled md 0.500 960.00 480.00 Cement t 0.2600 17736.60 4611.52 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4600 3346.35 1539.32
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 156.0000 0.10 15.60
Sub - total (A) 2930.00 Sub - total (B) 6866.94 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 10109.44
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1516.42
Total Item Rate = NRs. 11625.86
Say per cu.m. 11625.86
RATE ANALYSIS
Item No : 5.12
Description of item : Providing, Mixing and Pointing Cement Mortar over rubble masonry works including all complete as per spec.
Cement:Sand (1:3)
100.00 sq.m.
Resources
Norms Specification Labour (A) Materials (B) Equipment (C)
activity Clause
Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount Category Unit Quantity Rate Amount
20.02 2000 Skilled md 0.500 960.00 480.00 Cement t 0.3750 17736.60 6651.23 Mixer(.28/.20m3) hr 0.6000 500.00 300.00
Unskilled md 3.500 700.00 2450.00 10-20mm-agg cu.m 0.5800 595.00 345.10 vibrator hr 0.2500 50.00 12.50
10mm- downagg cu.m 0.3000 595.00 178.50
C. Sand cu.m 0.4500 3346.35 1505.86
Petrol lit. 0.1000 104.00 10.40
Diesel lit. 3.0000 55.50 166.50
Water lit. 225.0000 0.10 22.50
Sub - total (A) 2930.00 Sub - total (B) 8880.08 Sub total (c) 312.50
Direct Cost (A+B+C) = NRs. 12122.58
Contractor's Overhead @ 15 % of (A+B+C) = NRs. 1818.39
Total Item Rate = NRs. 13940.97
Say per cu.m. 13940.97
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
#REF!
#REF!
Transportation by Truck
Speed of Truck: 20 km/hr
Capacity of truck: 8 tons
Specification clause no: 800
Activity No: 8.04.03
Timber Unit :m3
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.3 700 210 ltr 0.14 55.50 7.77 hr 0.09 844.40 78.95 296.72
For 2 KM md 0.3 700 210 ltr 0.28 55.50 15.54 hr 0.10 844.40 88.24 313.78
For3 KM md 0.3 700 210 ltr 0.42 55.50 23.31 hr 0.12 844.40 97.53 330.84
For 4 KM md 0.3 700 210 ltr 0.56 55.50 31.08 hr 0.13 844.40 106.82 347.90
For5 KM md 0.3 700 210 ltr 0.70 55.50 38.85 hr 0.14 844.40 116.11 364.96
For 6 KM md 0.3 700 210 ltr 0.84 55.50 46.62 hr 0.15 844.40 125.39 382.01
For 7 KM md 0.3 700 210 ltr 0.98 55.50 54.39 hr 0.16 844.40 134.68 399.07
For 8 KM md 0.3 700 210 ltr 1.12 55.50 62.16 hr 0.17 844.40 143.97 416.13
RCC Hume Pipe(900mm Dia) Unit :m
Unskilled labour skilled labour Diesel Truck
Description Cost Remark
unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount unit Quantity Rate Amount
For 1 KM md 0.4 700 280 md 0.04 960 ltr 0.08 55.50 4.33 hr 0.11 844.40 93.73 378.06
For 2 KM md 0.4 700 280 md 0.04 960 ltr 0.16 55.50 8.66 hr 0.12 844.40 98.79 387.45
For3 KM md 0.4 700 280 md 0.04 960 ltr 0.23 55.50 12.99 hr 0.12 844.40 103.86 396.85
For 4 KM md 0.4 700 280 md 0.04 960 ltr 0.31 55.50 17.32 hr 0.13 844.40 108.93 406.24
For5 KM md 0.4 700 280 md 0.04 960 ltr 0.39 55.50 21.65 hr 0.14 844.40 113.99 415.64
For 6 KM md 0.4 700 280 md 0.04 960 ltr 0.47 55.50 25.97 hr 0.14 844.40 119.06 425.03
For 7 KM md 0.4 700 280 md 0.04 960 ltr 0.55 55.50 30.30 hr 0.15 844.40 124.13 434.43
For 8 KM md 0.4 700 280 md 0.04 960 ltr 0.62 55.50 34.63 hr 0.15 844.40 129.19 443.83
BILL OF QUANTITY 1
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
PCC - M10/40 :Providing and placing
machine mixed cement concrete Grade
M10/40 for foundation PCC including
1.3 m3 3.33
compaction, curing, testing and lead 30m.
etc. all complete as per specification and
drawing.
2 Masonry Works
BRICKWORK: Good quality local brick
Brickwork in 1:4 (cement:sand) mortar in
perfect line level finish including wetting the
2.1 bricks, racking the joints, scaffolding and m3 22.64
curing the work for at least 7 days all
complete as per specification and
instruction of Engineer.
BILL OF QUANTITY 2
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
3 Concrete Works
BILL OF QUANTITY 3
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
FORMWORK/SHUTTERING: Providing
and laying, centering and shuttering with
approved materials for all kinds RCC works
including all necessary mild steel
propping,scaffolding, staging, supporting,
3.4 etc. all complete net as per drawings, m2 104.48
specifications and instructions of the
engineer, all complete. a) 19mm thick
waterproof Ply Wood or steel Form Work
for plain slab,column, Beams, foundations,
etc
4 Flooring
SUB BASE PCC (1:3:6): Providing and
laying 75 mm or thicker concrete (1
cement: 3 sand:3 aggregates) on the floor
4.1 including chipping, cleaning and wetting the m2 100.00
surface and curing the works as per
drawings, specifications and instruction of
A/E
BILL OF QUANTITY 4
Item
Description Unit Quantity Rate (NRs) Rate in Words Amount (NRs) Remarks
No.
500 GAUGE PLASTIC FELT : Supplying,
laying of 500 MM GAUGE PLASTIC FELT
4.2 over the prepared sub base PCC with m2 80.00
welded joings as per drawings,
specifications and instruction of A/E.
Sub Total:
VAT 13%
Total :
In Words:
Submitted By:
BILL OF QUANTITY 5