Professional Documents
Culture Documents
Understand and apply the revenue recognition, measurement and disclosure issues
relating to construction contracts under FRS 115
Required readings:
FRS 115 Revenue from Contracts with Customers (including Illustrative Examples)
Amendments to FRS 115 Clarifications to FRS 115 Revenue from Contracts with
Customers (2016)
Picker Chap 4
Attached illustrations
In 20x3, A Ltd enters into a contract (Project A) to build an overhead bridge. The project
is expected to be completed in 20x4. The contract price is $1,000,000 and the other data
pertaining to the project during the construction period are as follows:
20x3 20x4
$'000 $'000
A Ltd has also entered into another contract (Project B) to build a stretch of road in 20x1.
The project is expected to be completed in 20x4. The contract price is $6,000,000 and the
other data pertaining to the project during the construction period are as follows:
1
20x1 20x2 20x3 20x4
$'000 $'000 $'000 $'000
In 20x3, A Ltd enters into another contract (Project C) to build an expressway. The project
is expected to be completed in 3 years, i.e. by 20x5. The contract price is $15,000,000.
The current costs incurred in 20x3 are $5,000,000. The additional costs to complete the
expressway cannot be estimated reliably. The progress billings and cash collected in 20x3
is $4,000,000. No other information is provided.
Required
(a) Record the transactions for Project A for both 20x3 and 20x4 with journal entries.
(b) Record the transactions for Project B for 20x1 to 20x4 with journal entries.
(Seminar 19 Team Activity - As a team, complete the table needed to prepare the
journal entries for Illustration 1 Project B – 20x1, 20x2 and 20x4.)
(c) Record the transactions for Project C for 20x3 with journal entries.
Project A
Project A – 20x3
2
(d) End of Each Accounting Period
20X3 20X4
$’000 $’000
Contract Price 1,000 1,000
Less: Estimated Total Cost (800) (820)
Estimated Total Profit/Loss 200 180
Step 4: Compute the Construction Revenue Earned for the current period
3
Project A – 20x4
4
Project B (Team Activity)
Project B – 20x1
20X4:
5
Step 3: Compute the Construction Profit/(Loss) for the current period
20X4:
Less: Previously
- (180) (250)
Recognised
Step 4: Compute the Construction Revenue Earned for the current period
6
Project B – 20x2
Project B – 20x3
7
Project B – 20x4
Dr Progress Billings
Cr Construction in progress
(to close off the accounts upon completion of contract)
8
Project C
Project C – 20x3