HSE Findings

Random HSE Inspection Observations.


To Nicolas Dumas Date 18 October 2016

From AEB Construction Supervision Team Excellent 3

Ref. Fair 2
3100-AEB-HSEDR-00128-Rev.00
Poor 1

Safety Rating Assessment

Project 3100 Main Mall

Subject Random HSE Inspections Report from 15– 18 Oct. 2016

S/N Observations: Risk


Rating

1 Area1, 4 & 7: M

- Working MEWP’s found holds plant certification of 1 year contrary to QCS


2014 local regulation.
- No exclusion zone below the working spider man riding basket (MEWP).
Action Taken.
- Hot work station in poor condition + found out permit to work is filled out with
wrong information, no spot check being carried out + no fire watcher
present. Action Taken.

Refer to photographs A, B.

Remedy:

- JV to contact the MEWP supplier and present the local regulation stipulated
on QSC 2014. They need to re-test the plant which holds 1 year validity to
conform to the legal requirement.
- JV to ensure before commencing MEWP into operation – working radius
shall be demarcated with orange mesh or physical barrier – to prevent any
unauthorized access.
- JV to re-train person how fill out the hot work correctly + no hot work will be
issue unless physical inspection is being done upon satisfactory by the
issuer – safe system in place.

2 Area 2A, 5A: M

- Permanent protection – cables and wires on floor.


- Unsafe use of scaffolding tower observed.
- Housekeeping issue found blocking off the staircase with mixed waste.
Action Taken.

Refer to Photographs C, D.
HSE Findings

Remedy:

- JV Engineers/supervisor and others has a duty of care to protect permanent


finishes from getting damage.
- JV to re-instate the tower to its working standard or use podium to low level
ceiling.
- JV to make clear all access staircases in any way and all times.

3. Area 7A & 8A. M

- 3 no. operatives working unsafely in related to cable pulling e.g. low level
mobile tower + no induction and supervision.
- Working on a ladder unsafely.
- Housekeeping at the TPS 6 corridor.
Refer to Photographs E, F.
Remedy:
- JV had temporary stop the activity and send the operatives into induction
room. Investigate who put them into work (supervisor) and impose
appropriate violation as necessary.
- JV to use mobile tower as working platform instead of ladder – which should
only be use as short duration and access.
- JV to carry out a sensible housekeeping need attention on corridors.
4. Area 2, 5 and Phase 1 logistic/External: M

- Housekeeping issue e.g. formworks at hoarding fence + redundant material


along way of parapet MSCP roof.
- Travelling cherry picker (MEWP) on a busy area mixed up with pedestrians
without present of flagman.
- Operatives were unsafely positioned closed to operational breaking
excavator at risk of ejecting debris/stuck by machine.
- Suspended load over the team of rebar ignoring the whistle of rigger.
- Missing edge protection in some area of slab retention tank. Action Taken.
- Reversing water lorry into restricted area without present of flagman.
- Spider MEWP without exclusion zone + untidy workplace.
- Roof staircases to update signage blocking access and alternative
directional arrows as these staircases are primarily planned as escape
routes. Action Taken.
Refer to Photographs G, H, I, J, K, L.
Remedy:

- JV to clear off materials at parapet wall roof to allow wider space for traffic.
- JV to ensure no operator shall travel alone without the assistance of flagman
guiding vehicle especially on mixed pedestrians or constraint location.
- JV to conduct safety stand down to the team ref. to men machine interface.
- JV to re-brief the steel fixer group not to ignore rigger instructions/signal
during lifting – never work or pass under the load.
- JV to coordinate with the logistic team in related to closure of staircases and
helps to plan alternative routes putting directional signage.
HSE Findings

5 Area 3A, 4A: M

- Damaged and delaminated ply woods covering/protection under high


voltage cables.
- Urinals cubicles provided at roof not being maintained cleaning and
disinfectants.
- Redundant materials + trailing extension leads. Action Taken.
- Missing exclusion zone below block laying wall. Action Taken.
- Unsafe use of low level railing mobile scaffold. Action Taken.
Refer to Photographs L, M, N.
Remedy:
- JV to replace protection of cable with more durable materials and made of
fire hazard materials.
- JV to assign person dedicated to clean and disinfectant temporary urinals.
- JV to remove unwanted materials at undercroft pocket areas as the building
on the finishing stage.
- JV to install exclusion zone below the block laying.

6 Area 3 & 6: M
- Unidentified cables laid over ground unprotected + no warning signs.
- Improvised cutting knife is used by operative + himself using unsafe and
untagged mobile tower.
- Unauthorized toilet found at BOH corridor.
- Planned stone work closing balcony with no coordination to safety/logistic
failing to provide alternative access directional arrows at 1st level floor.
- Housekeeping issues observed.
- Unguarded abrasive wheel presumed it was used by operative.

Refer to Photograph O, P, Q, R.

Remedy:

- JV to call out concern person/electrician to trace the cables be protected


and put out warning signage.
- JV to confiscate and condemn any makeshift equipment or devices + need
to communicated to team during DSTI.
- JV to apply lime power to clean removing foul-odor. Security personnel
assigned on mall shall continuously patrolling esp. at BOH and staircases.
Anyone will be caught shall immediately be terminated from site.
- JV to establish coordination to stone laying team before closing section of
floor/s to develop plans providing alternative access and arrow signage.
- JV to randomly check power tools that was being used + end user never to
modified or made alteration if not authorized to do so. Never operate rotating
machine without guards.
HSE Findings

7. Area 1A, 6A and 8: M


- Unsafe working on mobile scaffold + poor in lighting and supervision during
coring concrete.
- Arrangement of cables required.
- Missing door on energized TPS 7 room – JV to speed up the installation of
permanent door.
- Protection of equipment – dust escalator.
- Used of extremely unstable /narrow mobile scaffold.
- Loose /unsecured edge protection on floor edge balustrade glass + warning
signs.
- Empty wooden stillage + waste and unwanted materials noted in several
areas.

Refer to Photographs R, S, T, U, V, W.

Remedy:

- JV must enforce a close supervision to certain activity which is classified as


high risk job to ensure safe method of work is being followed.
- JV to improve cable management site wide by routing cables
overhead/regular checks of temporary cables condition.
- JV Engineer /supervisor/workers have the duty of care to protect permanent
finishes – escalator must be covered with blue sheeting.
- JV to use suitable mobile tower – narrow structure is permitted to use on
toilet areas which with limited space.
- JV to replace loose combi safe with wooden board and secured and posting
warning signs.
- JV to make sure daily removal of wooden stillage was this identified as fire
hazards + redundant materials in pocket areas.

8 Area Phase 2 Logistic and External: M


- Construction waste observed e.g. striking formworks, tunnel cable pulling,
mountain-like steel cut outs, and arrangement of VAFE temporary staging
materials.
- Reversing grader machine without the present of flagman.

Refer to Photographs X, Y, Z, A1.

Remedy:
- JV to start cleaning /clearing waste and redundant materials, expedite the
collection of steel cut-outs to contractor.
- JV to make sure engineer/supervisor in-charge shall arrange or allocate
flagman to plant during operation at all times.
HSE Findings

Main Mall Package – Quarterly Area HSE Rating Tracker

Inspection Dates

Area/ 08/09 15/09 20/09 22/09 27/09 29/09 04/10 06/10 11/10 13/10 18/10 20/10
Zone

1A

2A

3A

4A

5A

6A

7A

8A

Logistic
Area
Exter-
nal
Area

Legends:
Excellent Fair Poor Not Inspected/No
Issue
HSE Findings

Inspection Photography

MEWP (scissor lift) with 1 year valid TPC Missing exclusion zone

Failed to provide exclusion zone Poor Hot work condition + Permit not being filled in
correctly

Protection of permanent cables Unsafe mobile tower – pulling cables


HSE Findings

Unsafe – wrong selection of working platform – low Housekeeping / fire hazards obstructed stair well
level ceiling

Unsafe working on scaffold + no induction Unsafely working on ladder

Housekeeping – BOH TPS 6 Housekeeping BOH TPS 6


HSE Findings

Housekeeping - formworks Unnecessary materials along parapet wall

Missing flagman travelling MEWP in a busy Unsafe acts – close proximity to operational excavator
pedestrians

Team ignores warning whistle (rigger) during lifting Missing pocket edge protection
HSE Findings

Reversing lorry truck without the aid of flagman Missing demarcation + untidy

Blocking primary escape route without alternative Blocking primary escape route without alternative
access arrows signage access arrows signage

Poor /delaminated protection Poor condition - urinals at MSCP roof.


HSE Findings

Redundant materials Cable Management

Missing exclusion zone Low railing scaffold

Unprotected cables Makeshift knife


HSE Findings

Unsafe mobile tower Unauthorized toilet – BOH

Closed floor due to stone work – no alternative access Housekeeping


and signage

Unguarded tool Unsafe working – coring concrete


HSE Findings

Cable management Cable management

Missing permanent door – energized TPS 7 Protection of equipment - Escalator

Used of narrow /unstable tower Loose /unsecured protection


HSE Findings

Empty wooden stillage – fire hazard Empty wooden stillage – fire hazard

Housekeeping Housekeeping

Housekeeping Mountain-like steel cut outs


HSE Findings

Arrangement of VAFE materials Housekeeping – Tunnel interchange

Housekeeping – Tunnel interchange Housekeeping approaching ramp

A1

Housekeeping approaching ramp Reversing grader machine without the assistance of


flagman