Professional Documents
Culture Documents
Ref. No.
Date of issue
Prepared by
Revised by
Method Statement______________________________________________
Contents:
1. Introduction.
3. Construction equipment
4. Personnel
6. Construction procedures
7. Quality assurance
3. Construction equipment:
4. Personnel
5.1. Maintain safety warning signs and safety warning tapes around the
workplace.
5.2. Provide a safe access for the persons and equipments.
5.3. Assure that all working persons are well known of the safety
instructions and seriously following it.
5.4. Check for clearance of the working place from any other activities.
Method Statement______________________________________________
5.5. Check for damaged concrete weakness, and provide safe method to deal
with.
6. Construction procedures:
6.1. Surveying:
6.1.1. Set out all the coordinate points for Column axis.
6.1.2. Set out the entire coordinate for Column corner points.
6.1.3. Draw the framing lines for the columns.
6.2. Formwork:
6.2.1. ENCO has gained a wealth of expertise in design, fabrication and
installation of various systems of formwork. An internationally
recognized system will be utilized in the project in order to
produce
6.2.2. Concrete with the required quality and within allowable tolerances
in a safe and professional manner.
6.2.3. Formwork quantities have been calculated for the columns and the
time frame allowed in the overall time schedule.
6.2.4. The shuttering will be 25mm thickness softwood with 10 cm
width locally manufactured and steel tie rods.
6.2.5. All carpentry works should be as per the pre-approved shop
drawing and will be full controlled and monitored by the quality
control side.
6.3. Steel Reinforcement:
6.3.1. The Rebar cut/bend will be according to the approved bending
schedules prepared by the engineering team then each bar shall
have a bar mark identifying its location, size and number.
6.3.2. The fabricated steel will be transported when needed according to
the Steel reinforcement transportation schedule and will be placed
in position by using mobile crane, and fixed with Sufficient
numbers of crews according to the drawing.
7. Quality Assurance:
Verification
S/N Process Step
Point
1 Setting out coordinates. Hold
2 Draw the framing lines for the columns. Surveillance
3 Steel Reinforcement. Hold
4 Three sides work form. Hold
5 Full form work. Hold