Professional Documents
Culture Documents
PERT CPM
By Ar. Marc Christian Y. Ruz
Introduction
What is PERT
What is CPM?
Introduction
What is PERT
Program Evaluation
and Review Technique
Introduction
What is CPM
1.Planning
2.Scheduling
3.Control – Monitoring
Three Phases of PERT CPM
1. Planning
It is defined as determining the relationship between the work operation and
the sequence in which they are to be performed.
Scheduling or sequence involves distribution of work time to each work
operation and determining when to start and when to finish.
Each work operation can be performed in different ways at different costs and
in different time duration.
Most construction projects have specified time of start and time of
completion.
Three Phases of PERT CPM
1. Planning
When the contract time is less, in effect it requires higher indirect cost.
Thus,
In order to catch up with the allotted time, some of the operations must be speeded
up.
Consequently, to speed construction work requires higher direct cost because of
overtime, shift of work, additional manpower and equipment and various expensive
methods which are not done on normal construction operations with sufficient time
duration.
Three Phases of PERT CPM
Planning
CPM offers the solution through systematic approach:
1. PERT/CPM pinpoints the particular work operations whose completion times are
responsible for controlling the complete date.
2. It provides a means of speeding up a project without excessive cost for overtime.
Without the use of PERT/CPM when speeding up the project overtime expenditures
may be in total waste.
3. It gives a time leeway or float available for each of the non-critical work
operations. The information on the float time will give the project manger that
opportunity to maneuver in their planning and control of the operations.
4. It establishes time boundaries for operation with possibilities of shifting resources,
equipment and manpower to meet time requirements.
Three Phases of PERT CPM
Planning
CPM offers the solution through systematic approach:
5. PERT/CPM indicates the earliest starting date for each work operation and sub-
contracts for supply and delivery of materials
6. It shows the most advantageous scheduling for all operations.
This gives planning information as to time and cost in choosing methods, equipment,
crew and work hours.
7. It offers a means of assessing the effect on the overall project variations in one
operation such as change orders.
8. In case of change order where the owner would not want to extend the contract
time, PERT/CPM offers a means of rescheduling the operations but still to be
completed at the least increase in cost.
Three Phases of PERT CPM
Planning
CPM offers the solution through systematic approach:
9. With the critical path schedule as revised to reflect the change order, any claim if
any, for additional payment will be understood both by the owner and the
contractor.
10. In case of serious delay due to weather, late material or equipment delivery, the
network can be revised at that stage and new computation is made to determine
the new critical operation if any and revised float times determined for the non-
critical operations.
Three Phases of PERT CPM
Planning
In project construction undertakings, PLANNING is the most important consideration
which includes:
1. Gathering of all the necessary input data to make the PERT/CPM works
2. Planning phase is the main work of the contractor for being familiar and
knowledgeable of his costing methods of doing business.
3. The contractor can seek assistance for the accomplishment of his work
particularly the gathering of data, but his basic responsibility on this matter
cannot be delegated to any outsider group.
4. The contractor has the complete perception, experiences, resources, and
interest in getting the project done in the best possible time and cost.
Three Phases of PERT CPM
Planning
In project construction undertakings, PLANNING is the most important consideration
which includes:
5. The planning stages give the contractor a “Dry Run” on the construction of the
project.
6. If the contractor wants an effective approach and use of the construction
management, he must do it himself.
7. By performing the work personally, one obtains intimate first hand knowledge of
the job and gain insights and details of anticipated problems.
Three Phases of PERT CPM
Scheduling
In PERT/CPM, Scheduling is defined as the process of translating the arrow diagram
into time table of calendar days.
This is done by the day date table converting working days into calendar days which
permits the inclusion of weekends, holidays, weather and other time lost.
The PERT/CPM schedule shows the relationships between the operations and the
leeway limitations. All activities should be checked with the day to day table.
All crew and management restraints along the critical path should be verified and
the restraints should be adjusted to give satisfactory project completion.
Non critical activities can be scheduled to more efficiently utilize manpower and
available resources.
Three Phases of PERT CPM
Scheduling
Job control through the use of PERT /CPM gives the management a reliable system
identifying job problems within days instead of months.
Progress along the arrow diagram should be updated for immediate references.
The diagram must show the status of the project at any time and indicate which
activities can be started and to pinpoint the cause of the delay.
Three Phases of PERT CPM
Scheduling
The PERT/CPM diagram should be updated periodically to account for:
1. Time discrepancies
2. Deliveries
3. Weather
4. Change orders
5. Unexpected events or conditions
* Updating of the diagram is based on the number of days the project is out of
schedule.
Three Phases of PERT CPM
Output Phase
Consists of the ff:
1. Time status report
2. Revised schedule
3. Revised bar chart/ arrow diagram
4. Revised resource analysis
5. Revised cash flow predictions
6. Cost status reports
Three Phases of PERT CPM
1. Unbalance organization
2. Lack of financial planning
3. Poor cost control