Maintenance Procedure

 Machine Name:
BRB (Automatic Labeling Machine)
 Purpose:
Routine and extraordinary maintenance for the machine in different
time of year.
 Procedure:
o Lubrication:

- Grease gears and chain placed underneath the machine


basement every 3000 working hours.
- Inject grease every 3000 working hours through the special
greasers placed on the machine supports.
- The oil replacement in the plates moving cam must be made
for the first time after 3000 working hours and later on every
9000 working hours.
- The automatic greasing of plates movement cam and gears
placed underneath the machine basement, this automatic
cartridge shall be replaced after six months after activation.

o General checking of maintenance:

- The worm gear reduction is equipped with permanent


lubrication with synthetic oil, check monthly the oil level.
- check for handle tighten which locks the head stopping
bracket monthly.
- check for the machine is perfectly clean daily.
- check the machine is connect to the compressed air circuit.

Page 1 of 3 done by Eng. Loay al-bzour


- Check the presence of oil in the air lubricator weekly.
- check all sensor and photocells in appropriate place and clean
it by wet fabric weekly.
- Check temperature established on digital thermostat monthly.
- Check for general pressure at 5-6 bar approx. weekly.
- Be sure that doors of protections against accidents are locked
daily.
- Check stop pushbuttons (red mushroom pushbuttons) if they
are pushed, rotate them to release them weekly.
- check the electrical panel for machine is totally cleaned from
dust monthly.
- Check tighten for all cable terminal screw in electrical panel
monthly.
- Check the tighten for all nuts and screw in two head weekly.
- Clean the heads by wet fabric daily.

Page 2 of 3 done by Eng. Loay al-bzour


 Change format:
This table contain all format changing part:

Part for Number


changing F1 F2 F3 F4 F5
format 140 gr 240 gr 500 gr 285 gr 910 gr
Infeed screw 1 2 3 2 3
infeed star IN 1 IN 2 IN 3 IN 2 IN 5
Central arc 1 2 3 4 5
Outfeed star OUT 1 OUT 2 OUT 3 OUT 2 OUT 5
Infeed stop 1 2 3 2 3
device
plate 1 2 3 2 3
Ejector 1 2 3 2 3
Head 1 2 2 2 2
Smoothing 1 2 2 2 2

Page 3 of 3 done by Eng. Loay al-bzour