Professional Documents
Culture Documents
1 Scope............................................................ 2
2 Conflicts And Deviations............................... 2
3 References.................................................... 2
4 Identification Of Materials............................. 3
5 Storage......................................................... 3
6 Handling........................................................ 3
7 Pipe Fit-Up And Tolerances.......................... 4
8 Fabrication.................................................... 5
9 Cleaning........................................................ 5
10 Buried Installation......................................... 7
11 Pressure Testing........................................... 8
1 Scope
This standard supplements ASME B31.3 code and defines additional requirements
governing the fabrication and installation of metallic plant piping as well as piping
assemblies such as jumpovers for cross-country pipelines.
2.1 Any conflicts between this standard and other applicable Saudi Aramco
Engineering Standards (SAESs), Materials System Specifications (SAMSSs),
Standard Drawings (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this standard in writing to the Company or
Buyer Representative, who shall follow internal company procedure SAEP-302
and forward such requests to the Manager, Consulting Services Department of
Saudi Aramco, Dhahran.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this standard shall comply with the latest
edition of the references listed below, unless otherwise noted.
Page 2 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
4 Identification Of Materials
All pipe and fittings shall have the material specification and grade stamped, stenciled,
or otherwise marked.
5 Storage
5.1 Pipe shall not be stored directly on the ground. Pipe shall be placed on mounds
or sleepers.
5.2 Stacking shall be made in a manner to avoid damage to pipes or coatings. Refer
to SAES-H-200.
5.4 End protectors on flanges, weld bevels, threads, and socket ends shall be firmly
attached.
6 Handling
6.1 All material shall be handled with care during fabrication and installation to
prevent damage.
Page 3 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
6.2 Lined and coated pipes and fittings shall be lifted with wide fabric or rubber-
covered slings and padding shall be used to prevent damage to lining or coating
in accordance with SAES-H-200.
7.1 The tolerance for axial dimensions, face-to-face, center-to-face and location of
attachments shall be ± 3 mm maximum.
7.2 Flattening of bends, measured as the difference between the largest and the
smallest outside diameter at any cross section, shall not exceed 5% of the
nominal diameter of the pipe. Flattening of bends at weld ends shall not exceed
3% of the nominal pipe diameter.
7.3 Lateral transition of branches and connections from the centerline of the run
shall not exceed ± 1.5 mm.
7.4 Flange bolt holes shall straddle the established centerlines. Rotation of flanges,
measured as the offset between elevation of bolt holes on opposite sides of a
flange centerline, shall not exceed ± 2.4 mm.
7.5 The tilt of a flange measured at the periphery across any diameter shall not
exceed 1.6 mm from the square position.
d) Flange face tilt across diameter: 0.001 inch per inch of flange outside
diameter up to a maximum of 0.030 inch, and 0.010 inch for all flanges
with an outside diameter less than 10 inches.
Page 4 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
If these tolerances can not be met when connecting the existing piping to new
equipment, the actual misalignment and piping layout shall be reviewed and
approved by the Chairman of Piping Standards Committee in CSD.
Page 5 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
Commentary Note:
8 Fabrication
8.3.2 The flange joints should be assembled and bolts tightened in accordance
with Appendix A of this standard.
8.3.3 Deviation from Appendix A for less critical services shall be resolved by
mutual agreement among proponent representative, SAPMT, Inspection
and the Piping Committee Chairman or his representative.
8.4 If post-weld heat treatment (PWHT) of pipe spools is required (refer to SAES-
W-011), non-pressure containing welded attachments such as shoe support for
insulated lines, dummy extensions and legs, and wear pads shall be welded to
the pipe spools before stress relieving. PWHT of piping spools with flanged
joints shall be done before flange assembly.
8.5 The inside surface of welded joints at orifice flanges shall be ground or
machined smooth.
9 Cleaning
9.1 Prefabricated pipe spools shall be visually inspected for cleanliness, and shall
have foreign material removed from the inside, and shall have end protectors
installed.
9.2 After assembly and installation, the piping shall be cleaned inside to remove all
loose material. The cleanliness shall be verified visually and/or by video
inspection techniques. Use any combination of the following techniques to
effect cleaning.
Page 6 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
9.2.1.2 All piping systems shall be flushed using high pressure (60.8
mPa (8.8 ksi) minimum) jet such as rotating hose or rotating
nozzle.
9.2.2 Pneumatic flushing with dry air (dew point –1 °C or less) or steam with a
minimum exit velocity of 15 m/s. Repeat flushing until cleanliness is
verified by observing the absence of any solids impact on a polished
metal target at the exit.
9.2.3.1 Use PASB for initial cleaning for instrument air, plant air and
as an alternative method for initial cleaning of small bore pipe
(less than 2 inch). Use PASB if there are problems removing
trapped liquid in the piping, or to verify cleanliness of small
bore pipe where video inspection is impossible or inadequate
due to pipe dimension or configuration.
9.2.3.2 The air shocking pressure shall never exceed the working
pressure of the system and shall never be more than 810 kPa
(117 psi). Safety precaution shall be taken when this method is
used.
Page 7 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
9.3.1 The interior of carbon steel piping for the following specific services
shall be cleaned after hydrostatic pressure testing to remove oil, grease,
preservatives, rust and mill scale per approved procedures. (refer also to
01-SAMSS-017, SAES-G-116, SAEP-1024).
9.3.3 Lines to be chemical cleaned shall be identified on the P&ID's and Line
Index. The systems to be cleaned shall have high and low point vents
and drains installed.
10 Buried Installation
10.1 Buried metallic plant piping (if permitted by SAES-L-003) shall have corrosion
protection in accordance with the applicable Saudi Aramco Coating Standards
and SAES-X-600. Buried installations shall comply with requirements in
SAES-L-051.
10.2 The minimum cover in paved or stabilized areas shall be in accordance with
SAES-L-012.
11 Pressure Testing
Revision Summary
29 December, 1999 Major revision.
Page 8 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
A-1 Scope
A-2 This procedure defines minimum requirements for flanged joints assembly
including bolts tightening. Contractor shall be responsible to assure that proper
leak proof joints are achieved.
A-3.1 Bolts shall be visually checked for proper size, dimension and for any
physical damage to shanks or threads which would interfere with bolt
assembly or performance. Also, check the material and suitability of
the stud bolts for service temperature.
A-3.2 The flange facing, particularly the seating area, shall be visually
examined for cleanliness and insure that no damage, such as scratches
exist.
A-3.3 The gasket shall be verified for correct type, rating, and dimension.
Also, it shall be free from any damage particularly in the seating
element. Insure that spiral wound gaskets are stored flat specially for
large sizes, 24 inch and larger.
A-3.4 Verify that proper lubricant is used. Lubricant for bolts and nuts shall
be Jet-Lube SS-30 or other acceptable lubricants listed in Table A.1.
A-4 Torque values vary according to flange rating, bolt size, type of gasket, and
friction factor of the lubricant.
Table A-2 applies to all gasket listed in SAES-L-009, except for isolating
gaskets, based on a friction factor of 0.10, using graphite and oil.
Table A-3 applies to isolating gaskets (e.g. Pikotek), based on a friction factor of
0.125.
Table A-4 are torque values for various flange ratings, bolt sizes and friction
factors.
Page 9 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
A-5.1 There are various types of tools available to achieve the proper torque
value. Selection of the proper tool depends on the stud bolt size,
physical location of the flanged joint, and criticality of the flange.
Identifying the proper tools shall be resolved between Contractor,
SAPMT, Proponent and Inspection prior to commencing the erection
of the piping.
Step 2: Apply lubricant to stud threads over length and nut engagement and to
face of nut which contacts flange. Insure that the nuts run freely down
the thread of the studs.
Step 3: Install all studs and nuts hand tight, insure that studs pass freely
through the flange holes. Position the nut on one end of the stud such
that only the crown of the stud projects beyond the face of the nut. The
excess stud length should project beyond the nut on the other side.
Commentary Note:
By doing this, the nut that is installed nearly flush with the end of the stud can
be easily removed since the threads are not coated, and normally have not
been subjected to corrosion. The side of the stud with the flush nut should be
chosen by taking into consideration factors such as whether one side has better
access for maintenance personnel and/or tightening tools, e. g., torque wrench
or impact wrench, etc.
Step 4: Number each stud according to its position in the flange as shown on
Figure A.1. Stud Bolt Tightening Sequence.
Step 5: Tighten studs per Stud Bolt Tightening Sequence with an appropriate
tool such as air impact wrench or equal.
Step 6: For joints containing RTJ or Spiral Wound Gaskets, repeat step 5.
Page 10 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
Step 7: Tighten the stud bolts in stages to obtain the final required torque from
the appropriate torque table. The first stage should not be more than
30% of the final torque. Apply the torque evenly to each stud
following the stud bolt tightening sequence. The final torque must be
within ± 5 percent of the required values per paragraph A-4.
A.7 Stud Bolt Additional Tightening Procedure Where Leaks Occur During Pressure
Testing.
Step 1: Depressurize the piping system and retorque stud bolts to maximum
torque value shown on table.
Step 2: If leak does not stop after retorquing has been performed, disassemble
the flange joint and inspect as follows:
Step 3: After all defective and damaged items have been repaired or replaced,
reassemble the flange joint using a new gasket and tighten the bolts
using the maximum torque values.
Page 11 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
Page 12 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
Note (1): Torque values based on 0.12 Average Friction Factor and 30,000 psi
prestress on stud bolts. A combination of various elements such as the
conditions of the threads, the condition of the flange to the nut bearing
surface and the type of lubricant used, makes up the friction factor which
can vary from .04 to .20 or as much as 500%.
Note (2): Torque values for stainless steel or other alloy stud bolts can be obtained by
multiplying the ratio of the specified minimum yield strength (SMYS) of
stainless steel stud bolts to A193 B7 stud bolts, to the torque values in the
table. The SMYS values for all bolting materials are listed in Table A-2 of
ASME B31.3 code (Note: SMYS depends on grade, class and size).
Page 13 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
Table A-3 Torque Values For Isolating Gaskets (Pikotek) On ASME B16.5
And ASME B16.47 Series A & B, Class 150 Through Class 2500 Flanges
Note (1) Torque values based on 30,000 psi tension load and 0.125
Friction Factor from API-5A2 thread compound. See Table
A-2 Note (1) for other factors.
Commentary Notes:
(a) For ASME Class 900 through Class 2500, API-6B and API-6BX
Class 2000 through Class 15000, and RTJ Flanges, the maximum
compressive stresses induced during installation should not exceed
25,000 psi. Design to 12,500 psi when possible.
Page 14 of 15
Document Responsibility: Piping SAES-L-050
Issue Date: 29 December, 1999 Construction Requirements
Next Planned Update: 1 December, 2002 For Metallic Plant Piping
Page 15 of 15