Professional Documents
Culture Documents
1.1. GENERAL
1.1.1.1. Although not limited to, the scope of work shall be as follows:
1.1.2. References
1.1.3. Submittals
1.1.3.2. Contractor shall submit a complete method statement for the Engineer’s approval,
not less than 20 days prior to commencement of anchor installation, including the
following information:
Material submissions
1.1.3.3. Shop drawings shall be submitted for approval by Supervision including, but not
limited to:
B. Shop drawings shall be submitted for review prior to proceeding with the work.
· Stressing length
· Anchorage, and
c. Calculations: Design calculations shall be submitted for review. Design calculations shall
include a determination of the bonded length for each rock anchor.
2. The Contractor shall also submit the following information for review not less than 20
working days prior to the commencement of rock anchor installation:
a. Prestressing steel bar manufacturer’s mill test reports for the rock anchors.
b. Applicable literature from cement grout suppliers giving details on setting times as a function
of temperature, strength gain with time, and recommended storage, mixing and placement
procedures.
c. Applicable manufacturer certification and/or literature for anchorage fittings and accessories:
d. Detailed description of the proposed procedures, including specific makes and models of
equipment to be used for drilling, placing, grouting, and post-tensioning rock anchors.
e. Detailed description of proposed procedures and applicable manufacturer’s literature for the
equipment to be used for testing rock anchors, including but not limited to the following:
(1) The description shall include diagrams showing the arrangement of the testing equipment
relative to the rock anchor and anchorage hardware, the method for locking-off the required
transfer load, and calibration data for the system of jack and gauges.
(2) The calibration of the testing equipment shall have been performed by a certified independent
testing laboratory no more than twenty working days prior to the initial testing on site of rock
anchors and shall be presented in the form of gauge pressure vs. actual jack force.
b) 3. During grouting operations, the following data shall be recorded by the Contractor and
submitted:
c)
e) b. Type of grout
f) c. Water/grout ratio
Types of additives and their concentrations in mix
1.1.4.4. Logging of core and preparation of drilling logs and records shall be
performed by a competent Geologist or Geotechnical Engineer who has at least
five years experience in identifying and logging rock core and soil samples.
4/4