ECRS_R - Opl

Plant:
One Point Lesson (OPL) WCOM™

Basic Knowledge Problem Improvement N°

Filled by: Date:

Before E C R S After

Problem: Before WCOM™ the fixture trolley was all messy Improvement: Fixtures are all tidily arranged on a new trolley

Results: Faster set-up

Training date - - - - - - - -

Trainer - - - - - - - -

Trainee - - - - - - - -

Opl ECRS_R Solving Efeso © 1999 -1-


ECRS_R - Opl

Plant:
One Point Lesson (OPL) WCOM™

Basic Knowledge Problem Improvement N°

Filled by: Date:

Before E C R S After

24

trolley

24

Problem: Bushes were not in order. Their diameter was measured by Improvement: Bushes placed in order in the trolley every position marked
means of a sliding gage with Ø
Results: It is no longer necessary to measure bushes. The operator dismounts and mounts without the need to measure
Training date - - - - - - - -

Trainer - - - - - - - -

Trainee - - - - - - - -

Opl ECRS_R Solving Efeso © 1999 -2-