Professional Documents
Culture Documents
Biological Treatment of Waste Water & Design Calculation of Sequencing Batch Reactor Process
Biological Treatment of Waste Water & Design Calculation of Sequencing Batch Reactor Process
&
DESIGN CALCULATION OF SEQUENCING
BATCH REACTOR PROCESS
A Technical Seminar Report
Submitted to
Mewar University, Chittorgarh
Towards the Part Time of
The degree of
Master of Technology
In
Environmental Science & Engineering
Session: -2013-2016
Submitted to Submitted by
Mr. Mahboob Alam Ajay Kumar
(Assistant Professor) MUR 1302657
August– 2015
2
DECLARATION
I declare that the work presented in the report is my own work except as
acknowledged in the text and footnotes, and that to my knowledge this
material has not been submitted either in whole or in part, for a degree at this
University or at any other such Institution.
ACKNOWLEDGEMENT
I also extend my sincere thanks to all the authors of books whose I read
duration of seminar report preparation.
Ajay Kumar
4
ABSTRACT
CONTENTS PAGE
I –INTRODUCTION
2.1- Concept 11
2.4-Design Calculation 14
III- Conclusion 24
IV- References 26
6
CHAPTER 1
INTRODUCTION
7
After primary treatment removes large floating materials, Grits and a large portion of the
heavy inorganic suspended solids which present in the waste water. The colloidal and
dissolved solids, mainly organic in nature, still remain in the effluent. Remain content
use by population of microorganisms. Microorganisms are able to utilize the colloidal
and dissolved biodegradable organic matter as food for their growth and multiplication.
Microorganisms found in biological treatment system where they does break down waste
organics and remove organic matter from solution.
The Microbes convert these solids into simpler end products like water (H2O) and carbon
dioxide (CO2) and synthesize their own new cells. These cells are known as biomass or
biological floc. As the floc thus produced has a specific gravity which slightly greater
than that of water, it settles easily by gravity. Therefore, the new cells produced are
removed by settling process and settle sludge known as biological sludge or secondary
sludge.
1- To coagulate and remove both organic and inorganic non – settleable colloidal
particles which do not get removed in primary treatment.
2- To Stabilize the dissolved organic matter ( normally Carbonaceous BOD) that remains
in the effluent from primary treatment.
The biological process or treatment system have been broadly classified into two
categories.
(1) Aerobic Process: - The process that essentially required the presence of molecular
oxygen for metabolic activity of microorganisms is called an aerobic process. The
process can be designed to supply required oxygen either naturally ( such as in
trickling filter, aerobic stabilization pond) or by artificial/mechanical means ( as
in activated sludge process, aerated lagoons) in the reactor. The process normally
fails in the absence of the oxygen.
(2) Anaerobic process:- The process that operates in the absence of molecular oxygen
in the reactor for the growth of microbes and normally fails in the presence of
excessive oxygen is called an anaerobic process e.g. anaerobic sludge digester,
and anaerobic up flow filters.
(3) Facultative process :- The process that can operate both in the presence or
absence of oxygen in the reactor for the growth of facultative bacteria is called a
facultative process, e.g. facultative stabilization ponds
(4) Anoxic process: - This is the biological process in which microbes convert nitrate
nitrogen of waste water into nitrogen gas in the absence of oxygen . it is also
known as denitrification process.
Process According to microbial maintenance in the system
9
CHAPTER 2
PROCESS
2.1 Concept
11
A reactor or basin in which four steps viz. filling, aeration, settling (clarification) and
decanting for the biological treatment of waste water are carried out in a sequence is
known as sequencing batch reactor (SBR) when the activated sludge process is used for
treatment of waste water in SBR, it is known as SBR process.
Normally two or four basin are provided for aerobic biological treatment of waste water
by SBR process.
The basins are usually designed completely to provide the diffuser system for aeration.
2.2.4-Decanter
13
the complete operation of SBR divided into a number of cycles that will be carried per
day in single reactor or basin , the duration of each cycle is 3-6 hours and each cycle
comprises of the following phase which are repeated.
Fill
Aeration
Settling
Decanting
b) No. of Basin – 4
= 10416.66
4
= 2604.16 m3 ~ 2700 m3
17
b) Providing depth - 6 m
= Volume
Depth
= 2604.16
6
= 434.02 m 2
d) Providing length - 30 m
Q= V
T
Q= 2700
13
Q= 207.69 ~ 208 m3 /hr
18
= 240 X 20 X106
106
19
= 4800 kg / d
Safety factor theoretical kg O2 required per kg of BOD – 10 %
= 1.2 X 110
100
= 1.32
O2 For N Removal
NO 3- N Generated
20 X 21 X 0.75
= 315 kg / d
20
= 115 X 2.86
= 328.9 kg / d
Total kg of O2 required /day
= 6336 + 1932
= 8268 kg / d
=8268-328.9 (O2 from denitrification)
= 7939.1 kg /d
Safety factor 10%
= 7939 X 110
100
= 8733.01 kg/d
SOR = 8733
9.17
= 2079.85 kg/d
= 8733
4
= 2183 kg
= 2183 X 100 X 100
31.36 X 23.2 X 1.204
= 24920.87 N M 3/ d/ basin
Hours of aeration time per basin per day= 12 hrs /d/basin
Air required per hours per basin
= 24920.87
12
= 2076.73 N M 3 /hr/basin
Number of operating blower any time in
Basin -2
2076.73
= 1038 N M 3/hr
l) Calculation for air blower
Assume 70 % of capacity of at standards condition and blowers are capable
1.5 kg per KWH at standard condition.
So power required = 2183
0.7 X 1.5
= 2079.04 kWh
4
= 960 kg/d/basin
Consistency of sludge solids – 0.8 %
Specific Gravity of sludge - 1.5
Density of water - 1000 kg/ M 3
Total volume of sludge wasted
3840 X 100
1000 X 1.5 X 0.8
= 320 M 3/d
n) Pump capacity
= 10 X 60
15
= 40 M 3/hr
Provide 2 nos (1 working + 1 stand by) each capacity 45 M 3/hr
24
CHAPTER -3
CONCLUSION
25
3.1 Conclusion
CHAPTER- 4
REFERENCES
27
4.1 References
1. Dr. B.C. Punmia , Arun Kumar jain , Ashok Kumar Jain : Waste
water Engineering , Laxmi publication (p) ltd ,volume -I
(2011 edition)
2. Santosh kumar Garg : water supply Engineering , khanna Publishers,
Volume- I,II,( 16th revised 2012 edition )
3. G.L. Karia , R.A. Christian : PHI Learning Private Limited
(2013 edition)
4. Metcalf & Eddy , Inc. : Waste water Engineering Treatment ,Disposal
& Reuse ,Tata McGraw Hill New Dehli ( 4th 2003 edition)