Professional Documents
Culture Documents
Abstract— This paper deals with an imbalance problem in Step 2 : Decide how to exploit the system constraint.
a shoes company that produces the upper and bottom soles at Step 3 : Subordinate all other decisions to the above. If it
two production lines, and then they are assembled at the is desired to improve the performance of the
assembly line. The imbalance is caused by bottlenecks at the system to a level higher than possible with the
one site of the production lines. It occur waste of waiting at the current constraint, then it must be
next process, i.e. the assembly line. It impacts the production Step 4: Elevate the system constraint. This step can
target cannot be met, while throughput cannot be maximized. change the constraint or the decisions on how to
In this paper, the bottlenecks are managed by Theory of exploit the constraint. Hence, go to Step 5.
Constraints (TOC) approach that adopt linear programming
Step 5: If, in Step 4, the constraint is broken, then go
to optimize the production planning, and adopt the Drum
back to Step 1. Don’t let inertia become the
Buffer Rope (DBR) to control the flow of production. The
buffers are determined by considering the output gap between constraint.
the two production lines. This paper also proposes 3 solution The Theory of Constraints concepts have drawn attention
alternatives to meet the production target. The main goal of by researchers. Review of the Theory of Constraints
this research is the implementation of Theory of Constraints evolution literature has been carried out by [3] which
concepts to reduce imbalance problem at the bottleneck work provides five eras; the optimized product technology era, the
stations. The result shows that application of DBR as well as
goal era, the haystack syndrome era, the it’s not luck era and
the three alternatives of proposed overtime based on the
the critical chain era. Implement the five steps of Theory of
optimal production rate can reduce the problem of imbalance
between upper and outsole at the shoe production lines from
Constraints can present productivity gains and a change in
18.96% to 4.28%. the organizational culture in less than a year the productive
process [4]. A combination of Theory of Constraints and
Keywords— capacity constraint, Drum Buffer Rope, Linear Lean tools allow to demonstrate the successful application of
Programming, time buffer the model in the footwear industry with a reduction in non-
value-added time and inventory [5]. A dynamic bottleneck
can be eliminated by applying Goldratt and Cox’s Theory of
I. INTRODUCTION
Constraints, i.e. capacity enhancements to increase
A shoes company produces upper and outsole (bottom) productivity [6]. The potential implementation of the Theory
at two different production lines. If these two production of Constraints concepts in the management of distribution to
lines have imbalance problem, it creates work in process at improve the logistic performance has been studied by [7, 8
the next process, i.e. assembly line. Therefore, it is necessary and 9]. The implementation of Theory of Constraints for
to eliminate the imbalance problem in order to cut the work project management to improve the timeliness of order
in process. delivery, communication and standardization of processes
This study is motivated by a practical situation of related to order delivery has been studied by [10]. The main
imbalance problem of PT X, a shoes manufacturer located in goal of this research is the implementation of Theory of
Bandung, Indonesia. The imbalance problem is caused by Constraints concepts to reduce imbalance problem at the
bottlenecks at the one site of the production lines. The bottleneck work stations.
bottleneck can restrict the production rate, so that it can be a
constraint. However, if the constraint is managed properly, II. PROBLEM DEFINITION
the production line will flow smoothly. In this paper, Theory There are 2 production lines used to produce upper shoes
of Constraints is adopted to manage the bottlenecks in order on one line and outsole (bottom) shoes on the other line. The
to reduce the imbalance of the production lines of upper and upper manufacturing process consists of cutting, preparation
bottom. Finally, the production target can be achieved. of materials and sewing, while the bottom manufacturing
Theory of constraints can be interpreted as a philosophy process consists of rolling kneader, cutting outsole, pressing,
of continuous improvement that focuses on identifying and trimming and soldering, and sizing. The upper and the
setting constraints to achieve company goals [1]. outsole are then assembled into shoes at assembly line.
Improvement based on Theory of Constraints consists of five Each process is defined as a work station as seen at Table
steps in [2], are as follows: I. There are 4 kinds of shoes product, i.e. man, women,
Step 1 : Identify (or choose) the system constraint. junior and child shoes. Table II shows demand and
171
Fig. 1 Production process
Demand shown at Table I are still in each kind of shoes, Exploitation the constraint means that the performance of
so that they cannot be added directly. It is needed to convert the system should be maximized [2]. The management must
the unit as aggregate unit, by multiplying demand for each focus on maximizing the constraint. In this study, preparation
kind of shoes and its conversion factor. Calculation of the and sewing machines are constraints that should produce at
converted demand at cutting work station is shown at Table their maximum capacity, in such a way maximize
IV. In a similar way, demand for each work station can be throughput.
seen at Table IV.
Linear programming is then adopted to optimize the
production rate. The objective is to maximize throughput,
TABLE IV. CONVERTED DEMAND FOR CUTTING WORK STATION subject to machine load for each work station does not
(AGGREGATE) exceed the available capacity, and production for each kind
Kind of Demand Conversion Converted Demand of shoes do not exceed the demand, but greater than the
Shoes (unit) Factor (aggregate) minimum production rate. The equations of the linear
Man 24,008 0.977 23,457 programming can be expressed as equations below.
Women 21,950 1.000 21,950
Junior 48,946 0.910 44,528 Objective function:
Child 10,196 0.875 8,920 Maximize
Total 98,855
Z = 55,000 X1 + 52,000 X2 + 50,000 X3 + 32,000 X4 (3)
In a similar way, the converted demand for each work
station is shown at column 2 of Table V. A bottleneck is then Subject to:
treated as a constraint, when machine load shows a higher
value than the availability of the resource. Table V shows 0.977 X1 + X2 + 0.910 X3 + 0.875 X4 ≤ 105120 (4)
status for each work station at the production process. Refer
to Table V, the bottlenecks are preparation and sewing work
stations. Fig. 2 shows the position of the bottlenecks.
0.999 X1+ X2 + 0.986 X3+ 0.931 X4 ≤ 86373 (5)
172
Fig. 2 Existing production rate and positon of the bottlenecks
173
Fig. 3 Positioning of Drum, Buffer and Rope (proposed production rate)
This result can be converted to time unit by multiplying maximum output of 24,000 pairs of shoes, the difference
with the standard time of the sewing work station for women output between the upper and outsole is around 4.3%.
shoes, i.e. 172.4 second/pair. The result indicates the total
additional working time (overtime) of 2,862 minutes or IV. DISCUSSION
about 47.697 hours.
Refer to the results, it is found that there are some
E. Step 4: Elevate the constraints differences between the current conditions and the proposed
We propose three alternatives to increase capacity of the improvements (see Table VI).
constraint by implementing the overtime so that the Table VI shows some differences between demand rate at
bottleneck will be eliminated. The three alternatives are the existing condition and at the proposed condition (the
described as follows: optimal production rate). It shows that if the production rate
is determined by considering the actual capacity without any
1) Alternative #1 additional overtime, the demand cannot be met in order to
Based on the calculation results to balance the number of maximize throughput. However, when the production rate is
upper and outsole, the required overtime is 2,862 minutes in only provided towards meeting demand, it will generate
one month, or 114.48 minutes/day. It means that the bottleneck and WIP at the assembly line. Therefore, overtime
company should implement minimum 1 hours overtime/day is required.
for each machine. This is able to handle the imbalance The overtime of proposed condition is shorter than the
between the upper and outsole, because capacity for each existing condition, because the proposed overtimes are
sewing machine increases of to 4,469 pairs of shoes / month. designed by considering capacity requirements and the
accumulation occur at the production line. In addition there
2) Alternative #2 is also a decrease in imbalance between the upper and
Consider overtime is 3 hours/day, which is the maximum outsole in the production line from 18.96% to 4.28%
overtime currently applied by the company. This means that (alternative #3). This is influenced by the application of the
to overcome upper and outsole imbalances, the company DBR as well as the alternatives proposed overtime based on
should implement overtime along 4 working days. The the optimal production rate. This indicates a performance
adoption of this alternative can increase the capacity of each improvement of bottleneck working station.
sewing work station to 4427 pairs of shoes / month In this study, it is shown that implementing DBR at
optimal production rate can reduce imbalances in the upper
3) Alternative #3 and outsole production lines. However, combining DBR and
Consider the smallest capacity of work station in the the proposed overtimes only increase the production rate for
outsole (bottom) production line, i.e. press outsole work Junior shoes, and they have not been able to meet demand
station of 24,000 units of capacity. If an alternative overtime (see Table VI). Therefore, it is requiered other alternatives so
with 3 hours on each working day is applied, the total that the customer demand can be met, for example, creating
capacity of the sewing work station will increase to 22,972 another alternative overtime, or adding machines and
pairs of shoes. If the outsole production line produces a operators.
174
V. CONCLUSION In this study it is shown that implementation of DBR as
The results of calculations and analysis show that the well as the proposed overtime based on the optimal
Theory of Constraints which adopts DBR can be used to production rate will reduce the problem of imbalance
manage bottlenecks as constraints so that bottlenecks can be between upper and outsole at the shoes production lines from
reduced. However, combination of Theory of Constraints 18.96% to 4.28%.
and DBR cannot eliminate the imbalance between the two Nevertheless, further research is required to develop
production lines. It is required overtime to overcome the other patterns of overtime, or to add machines and operators
imbalance problem. for increasing the overall capacity of the system.
Proposed condition
Element Existing condition Reguler Regular time + Regular time + Regular time +
time Alternative #1 Alternative #2 Alternative #3
Man 23,482 23,482 23,483 23,483 23,483
Production Woman 21,950 4,000 4,000 4,000 4,000
rate Junior 44,759 21,268 28,238 24,666 41,944
Child 9,205 4,000 4,000 4,000 4,000
1-3 hour/day
(5 working days) 3 hours/day
1 hour/day 3 hours/day
Overtime (4 working
8-11 hours (Saturday and (5 working days) (5 working days)
days)
Sunday)
Imbalance between
18,96% 4,28% (Alternative #3)
Upper and Outsole
REFERENCES
[1] R. J. Tersine: Principles of Inventory and Materials Management,
PTR Pretice-Hall Inc., New Jersey (1994)
[2] J. F. Coxx III and J. G. Scheier Jr.: Theory of Constraints Handbook,
Mc. Graw Hill, New York (2010)
[3] Z. T. Şimşit , N. S. Günay, and Ö. Vayvay: Theory of Constraints: A
Literature Review, 10th International Strategic Management
Conference, Procedia - Social and Behavioral Sciences 150, pp. 930 –
936, ( 2014 )
[4] P. Vargas, L. M. Kipper, A. L. E. Silva, F. L. da Silva, and G. Z.
Kessler: TOC’S Five-Step Cycle: An Approach to Instant Results and
Cultural Change, International Journal of Engineering Research &
Science (IJOER), Vol-3 (10), pp. 1 – 9 (2017)
[5] K. Álvarez, D. Aldas, and J. Reyes: Towards Lean Manufacturing
from Theory of Constraints: A Case Study in Footwear Industry,
International Conference on Industrial Engineering, Management
Science and Application (ICIMSA), Seoul, South Korea, 13-15 June
2017, pp. 1-8, IEEE publisher (2017)
[6] E. Gundogar, M. Sari, and A. H. Kokcam: Dynamic Bottleneck
Elimination in Mattress Manufacturing Line Using Theory of
Constraints, SpringerPlus 5:1276, pp. 1-15 (2016)
[7] T. A. R. Filho, D. A. de J. Pacheco, and I. Pergher: A New Approach
for Decision Making in Distribution Supply Chains: A Theory Of
Constraints Perspective, Int. J. Logistics Systems and Management,
Vol. 25 (2), pp. 266-281 (2016)
[8] Y. Kamada and F. Kojima: Efficient Matching under Distributional
Constraints: Theory and Applications, American Economic Review,
105(1): pp. 67–99 (2015) http://dx.doi.org/10.1257/aer.20101552
[9] V. Šukalová and P. Ceniga: Application of The Theory of Constraints
Instrument in The Enterprise Distribution System, Procedia
Economics and Finance 23 , pp. 134 – 139 (2015)
[10] J. Trojanowska and E. Dostatni: Application Of The Theory Of
Constraints For Project Management, Management and Production
Engineering Review 8 (3), pp.87-95 (2017) DOI: 10.1515/mper-2017-
0031
[11] M. M. Umble and M. L. Srikant: Synchronous Manufacturing-
Principles for World-Class Excellence, The Spectrum Publishing
Company, America (1996)
[12] Blocher, Stout and Cokin: Cost Manajement: a Strategic Emphass,
McGraw-Hill Companies Inc., New York (2010)
175