ACCOMPLISHMENT REPORT FOR BILLING OF PORTLAND CEMENT CONCRETE PAVEMENT (PCCP)

SAN GUILLERMO SAN NICOLAS, ILOCOS NORTE


JUNE 26 – JULY 2, 2020

I. DETAILS OF PORTLAND CEMENT CONCRETE PAVEMENT (RIGHT LANE)


STATION LENGTH WIDTH AREA
FROM TO (m) (m) Sq.m
0 + 000 0 + 015.4 15.4 2.5 38.5
AREA 38.5

II. DETAILS OF PORTLAND CEMENT CONCRETE PAVEMENT (LEFT LANE)


STATION LENGTH WIDTH AREA
FROM TO (m) (m) Sq.m
0 + 000 0 + 059.4 59.4 2.5 148.5
AREA 148.5

Amount per square meter: Php 150.00


Total Area: 187.00 sq.m
Sub total: Php 28,050.00
10% Retention: Php 2,805.00
Total Amount: Php 25,245.00

Prepared and Verified by: Conformed:

ENGR. JAY-AR BARANGAY MR. LOUIE QUIDEZ


ENGINEER IN CHARGE SUB-CONTRACTOR

CHECKED BY: APPROVED BY:

ENGR. ELMER T. AGREGADO JOHN A. QUIDEZ


PROJECT MANAGER GENERAL MANAGER