Professional Documents
Culture Documents
The deliverables matrix, shown in Attachment 6-1, summarizes field deliverables for field non-manual
and manual jobhour and cost control and deliverables related to materials/(sub)contract control. Both
Design Office (DO) and Field (F) responsibilities are noted for each category. As the project
progresses, a number of the reports listed may be transferred to the field.
• Maintained by Payroll/Accounting
• Reconciled by Field Project Controls
Bechtel Services(Hrs/$)
Jobhours
Quantities
Engineering Performance
Jobhours
Dates
Drawing Lists
CO/CO/Contracts
Commitments
Payments
Craft Performance
Actual Hours
Wages
Quantities Installed
Automation
PCWorks is the primary automation tool used for cost control at the construction site. Figure 6-1
provides a diagram mapping the levels of information exchange between PCWorks and other standard
automation tools. Accounting, through its various automated programs, provides cost and jobhour data
for nonmanual labor, materials and subcontracts, and manual labor under direct hire situations.
Nonmanual jobhours for many years have been captured exclusively through manual input to
handwritten time-sheets. In the last few years, an electronic system has been established. The goal is
to implement electronic nonmanual timekeeping throughout Bechtel over time.
The Bechtel Electronic Time Record (BETR) is standard electronic timekeeping system for all
nonmanual employees. For projects that do not have adequate communication abilities or other
circumstances prohibit the use of BETR, manual time records should be gathered by a project
administrator with access to BETR, entered by the administrator as proxy. Nonmanual payroll may
then be processed out of central location. This time-related information from BETR is electronically
transferred to CFIS Payroll and passed on to the CFIS Labor System from which it is then made
available to project controls. Currently, this information is available in the Controller Reporting System
(CRS) but in the future will be available directly via the Information Exchange Layer(IEL).
For materials and subcontract, the standard program to be used in the future for this purpose is
Oracle-based although a number of other applications are currently being used. Other accounts
payable systems in use include Timberline, Clipper, and various DBase and Access applications.
Work is ongoing to enhance Oracle Accounts Payable. Maximizing its use will greatly enhance the
efficiencies of the electronic imaging. It is the intent to have procurement electronically feed purchase
orders and receiving reports from the Bechtel Procurement System (BPS) into the Oracle Accounts
Payable system as well as have vendors bill us electronically. Automatic electronic exchanges of
information between the commercial system and PCWorks through a Project Accounting Sub-ledger
(Information Exchange Layer) are also planned. .
Gateworks and Foretime are automated programs used to monitor craft attendance and accrue craft
hours by cost code. Foretime is the preferred and most cost effective application for craft timesheets.
The information from Foretime is electronically passed to the manual labor payroll program. The option
is the manual, hard copy system in use for many years and currently still being used particularly in the
international arena.
Timberline is a commonly used manual labor payroll application. Where there are complexities of
foreign currency exchange rates, Micro Payroll is used. Other applications such as Concord have also
been used for manual labor payroll.
Some of the financial applications noted here will be referred to in other sections of these Principles.
Again, it is noted that Oracle Financials will be used globally. Each region will have its own setup, but it
is anticipated that they will be somewhat similar to the one presented here.
Use of Centralized Accounting Function Approaches
As the accounting process becomes more automated with electronic information exchange interfaces,
the use of centralized processing center concept will have advantages since there will be
instantaneous access by users. The centralization of accounts payable and manual labor payroll would
eliminate the need for field operating bank accounts.
Figure 6-2 highlights the near term system employed to maximize automation and provides definition
of the data flow. The manual payroll system depicted happens to be Timberline but as noted others
may be used.
Phoenix
FIGURE 6-2 - PROJECT DATA FLOW USING HIGH LEVEL OF AUTOMATION (NEAR TERM)
PROPOSED BSAP
CATS ??
• CRAFT TRAINING & CERTIFICATIONS • WAGE & BENEFIT BULLETINS
E
OYE
MPL VA
PAYROLL CHECKS REN
TE CHRIS LID
CR
Proposals
CUR U S AF
/S TAT TR
D ATA OS
TE
• EMPLOYEE NEW-HIRE DATA R
• EMPLOYEE CHANGE-OF-STATUS
RECORD
LABO
DA
T
S
IL
Y/ AF
COST CODE
CR
AF
W
EE CR E
KL •CRAFT HOURS PER COST CODE L Y NC
T
HO Y AI DA
UR
D N ENGR’G BSAPS’s
TE
S AT 3DM/PDS/IPID/CAIES/
FORETIME
EQUIPMENTWorks
SDS
(Safety Data Systems) S
DE
CO TEAMWorks SETROUTE
ST UR
S
CO O
L YH
EK
WE
PCWorks QRS
• QUANTITY AND UNIT-RATE REPORTS
• INSTALLED QUANTITIES PER COST CODE
The Superintendent is responsible for checking the timesheet entries for assigned craft and verifying
the work descriptions and allocation of total jobhours. The superintendent signs-off the timesheets
prior to release to the Cost Engineer. The Field Cost Engineer reviews the completed time sheet
entries to verify proper coding to the Project Code of Accounts.
REVIEW
Cost Engineer:
REVIEW
Construction Superintendent:
- Timesheet overview
- Accuracy
- Signature
PROCESS
Accounting Manager:
ANALYSIS REVIEW
Cost Engineer:
- Craft productivity
- Quantities
- Identify Trend
FIGURE 6-4 - FIELD MANUAL LABOR JOBHOUR/COST CONTROL INFORMATION FLOW CHART
In general, the following time sequence is typical for checking the time sheet entries:
• The time sheet entries will be coded and be available for the field superintendent and/or field
engineer to review no later than quitting time on the day worked.
• All checks of the entries should be complete so that the information is available for use by
Accounting, no later than 1:00 p.m. of the next day. This may not be required daily, although it
is good practice, as hours are automatically posted each day. This may only be required on
the day payroll is done.
The Foretime database is used to update the Timberline files electronically on a weekly basis(in the
hard copy option, the data has to be keyed directly into the payroll system). This allows payrolls to be
prepared, as well as, provides an electronic download from the payroll system to PCWorks on a timely
basis.
PCWorks may then be used to generate the Labor Distribution Ledger (LDL). Refer to Appendix D for
an example Labor Distribution Ledger report. This ledger is balanced weekly against the daily time
sheets and the payroll system. The LDL is a source document to provide project status of labor
jobhours and dollars by cost code and craft for use in forecasting, cash flow, labor performance
monitoring, and other cost/schedule programs.
The Office Manager/Field F&A Supervisor is responsible for maintaining the GateWorks/Foretime
system and ensuring the necessary updates of Timberline and the subsequent electronic download to
PCWorks are available on a timely basis. Also, this person is responsible for timely preparation at the
forecast cutoff date or other intervals, as required by the Field Cost Engineer, for summarizing each
account to the ledger and posting the same to the forecast worksheets.
Format
The Field Cost Engineer should coordinate with the Office Manager prior to the first download file feed
to verify that the purposed file feed is capable of producing the following information by craft within the
account:
1. Straight time hours worked
2. To-date & distribution of jobhours by cost code, by craft.
3. Overtime and double time hours worked
4. Regular Earnings at Straight Time
5. Overtime & Double Time Earnings - Premium Portion of Overtime (PTOT) bare wages.
6. Bare wages, fringe benefits, and statutory payroll additives including earnings subject to:
• Federal Unemployment Insurance (FUI)
• State Unemployment Insurance (SUI)
• Federal Insurance Contribution Act (FICA)
• Workers Compensation
The information above should be by cost code by craft and should subtotal by Category, Unit/Area,
and Total Project.
The Field Cost Engineer reviews the LDL information and posts the labor weekly hours to the weekly
Labor Craft Performance Report covered later in this manual. Earnings will be summarized by craft
and cost code on a monthly basis. The summarization allows for the calculation of average hourly
rates by craft or by cost code which will be used in forecasting, cash flow, and other control programs.
In addition to normal weekly checks, the Field Cost Engineer cross-checks the to-date information, with
the field accounting payroll summary, to identify any adjustments.
The typical time period for the Cost Engineer to review the information is one to two days after the
close of the weekly payroll.
<---------------WAGE RATE-----------------> <--------------TO DATE LABOR COSTS---------------> <----------THIS PERIOD LABOR COSTS------------>
CUR CUR TO V A R I-
STEM DESCRIPTION BGT FCST DATE ANCE EARNED $ ACTUAL $ VARIANCE PERF EARNED $ ACTUAL $ VARIANCE PERF
==== ===============================================
====== ====== ====== ====== ============ ============ ============ ===== ============ ============
============ =====
11 FORMS $32.17 $32.17 $18.51 $13.66 $116,110.00 S50,166 $65,944.00 0.43 S50,122
12 METAL DECKING $32.68 $32.68
13 REBAR $32.05 $32.05 $30.94 $1.11 $148,411.00 $77,222.00 $71,189.00 0.52 S31,650
14 EMBEDS $32.00 $31.98 $24.21 $7.80 $28,861.00 $34,151.00 -$5,290.00 1.18 $9,77O
15 CONCRETE $31.96 $31.96 $15.26 $16.7O $115,774.00 $21,551.00 $94,224.00 0.19 $S61,928
17 WATERPROOFING $32.09 $32.10 $33.23 -$1.14 $277.00 $233.00 $45.00 0.84
------ ------ ------ ------ ------------ ------------ ------------ ----- ------------ ------------ ------------ -----
CAT 1: CONCRETE $32.11 $32.11 $22.81 $9.30 $409,434.00 $183,322.00 $226,111.00 0.45 $153,470.00
21 STRUCTURAL STEEL $38.51 $38.51
22 MISC STEEL $38.30 $38.30
23 LINERS $32.01 $32.01
25 ARCHITECTURAL FINISHES $32.14 $32.14
26 EARTHWORK $33.18 $33.16 $17.41 $15.77 $81,937.00 $29,613.00 $52,323.00 0.36 $S40,498
28 SITE IMPROVEMENTS $32.10 $32.10 $0.00 $32.10
29 PRE-ENGINEERED BUILDINGS $32.00 $32.00
------ ------ ------ ------ ------------ ------------ ------------ ----- ------------ ------------ ------------ -----
CAT 2: STEEL $36.29 $36.27 $17.37 $18.92 $81,937.00 $29,613.00 $52,323.00 0.36 $40,498.00
31 HRSG $37.95 $37.95
32 HRSG STEAM DRUMS $37.91 $37.9l
36 HRSG MODULE SEAL WELDING $37.95 $37.95
37 HRSG INLET DUCT $37.95 $37.95
39 HRSG MISC OPERATIONS $37.96 $37.96
CAT 3: HRSG $37.95 $37.95
41 STEAM TURBINE GENERATOR $36.42 $36.42
42 WET SURFACE AIR COOLED CONDENSER $ 36.34 $36.34
43 MECH EQUIP, PUMPS,SUMPS & SKIDS $38.46 $38.46 $0.00 $38.46
44 COMBUSTION TURBINE $36.13 $36.13
45 TANKS $36.57 $36.57
46 WATER TREATMENT & CHEMICAL FEED $36.43 $36.43
47 STACK $36.84 $36.84
48 MISC MECHANICAL EQUIPMENT $36.35 $36.35 $0.00 $36.35
------ ------ ------ ------ ------------ ------------ ------------ ----- ------------ ------------ ------------ -----
CAT 4: MECHANICAL EQUIPMENT $36.48 $36.48 $0.00 $36.48
50 TIE IN TO MONSANTO $34.53 $34.53
51 LARGE PIPE $34.58 $34.58
53 STRESS RELIEVE PIPE
54 U/G, CIRC WATER & RELOCATE MONS’TO$34.58
DRAIN $34.58 $19.49 $15.09 $96,056.00 $52,355.00 $43,701.00 0.55 $10,395.00
55 SMALL $34.58 $34.58
57 PIPE SUPPORTS $37.36 $37.36
59 LARGE PIPE HANGERS $34.59 $34.59
CAT 5: PIPE $35.18 $35.15 $19.49 $15.70 $96,056.00 $52,355.00 $43,701.00 0.55 $10,395.00
Figure 6-6 shows example unit rate, performance factor, craft mix, wage rate, and overtime percent
calculations. It is important to note that wages, craft mix, and percent overtime can be measured by
craft, commodity, category and total job. Refer to the Glossary of Terms included in Appendix A and
to PCDP 4.06 for further information and guidance on labor cost analysis methods.
To Date Performance
To-date unit rate 3.1 jhr/sq. ft
EXAMPLE: Budget unit rate = 2.7 jhr/sq. ft = 1.15 Performance
OVERTIME PERCENT
% Overtime versus straight time charged to an account:
10 hours worked overtime
100 hours total worked = 10% overtime
This report is similar to the Quantity and Unit Rate Report and is the standard report for open shop
projects.
It shows labor costs, wage rates, and PF's in addition to standard QURR report data. It is produced by
the PCWorks craft performance module and examples are to be found in Appendix E.
NOTE: This chart references a PC based system. The above could be accomplished manually
if job size requires.
The procurement department is responsible for all purchasing, expediting, and inspection functions in
the home office, field, and in vendor’s shops. Engineering issues the specification/material requisitions
and is responsible for the technical evaluation of the bids. Procurement evaluates the commercial
sections of the bids.
Commitment Authorization
JOB NO. PROJECT NAME / CUSTOMER DATE APPROVED
DOCUMENT NUMBER (P.O., S.C., CONTRACT) REVISION / AMENDMENT NO. (INSERT N.A. IF NONE) COMMITMENT AUTHORIZATION NO. (SEE NOTE 1)
DESCRIPTION OF WORK TO BE AUTHORIZED BY THIS COMMITMENT (CONTINUE UNDER REMARKS IF ADDITIONAL SPACE REQUIRED)
A. $
OTHER BIDDERS (IF ORIGINAL COMMITMENT)
B. $
C. $
D. $
E. $
F. $
G. $
$ $ $ $
VALUE OF ORIGINAL COMMITMENT + TOTAL OF PREVIOUS + THIS COMMITMENT = TOTAL COMMITMENT
COMMITMENTS (EXCEPT ORIGINAL AND OTHER (INCLUDING THIS COMMITMENT)
(EXCEPT ORIGINAL) PREVIOUS COMMITMENTS)
REMARKS - FOR AMPLIFICATION / CLARIFICATION OF ANY ABOVE STATEMENTS (USE ADDITIONAL SHEET IF NECESSARY)
(TYPE / PRINT AND SIGN NAME) DATE (TYPE / PRINT AND SIGN NAME) DATE
NOTE 1: COMMITMENT AUTHORIZATION NUMBERS ARE SEQUENTIAL FOR EACH DOCUMENT BEGINNING WITH NO. 1 FOR ORIGINAL COMMITMENT.
NOTE 2: INDICATE L.S. (LUMP SUM) OR EST. (ESTIMATED). IF TOTAL EVALUATED COST IS DIFFERENT FROM “PROPOSAL (BID) PRICE” SHOW TO LEFT OF
PROPOSAL (BID) PRICE UNDER HEADING “TOTAL EVALUATED COST.”
1993 Bechtel Corporation - All Rights Reserved FORM 2.15.4-A (12/93)
C-CA.FRM/Dec93/Rev1
FORMATION STAGE
PERFORMANCE STAGE
Backcharges 4 1 2 3 5 5 6 4 4 (F&A)
Legend:
1 Initiates lead project operational responsibility for assigning, delegating, and coordinating. If shown for more than one person, the activity may originate in several places.
2 Executes; action is taken.
3 Provides input; providing input is mandatory unless footnoted.
4 Reviews; timely review is required in order not to delay the responsible department.
5 Approves; the review required and the responsibility for obtaining management approval outside the project team are included if noted.
6 Interfaces with client.
NOTE: The function of the Field Project Controls Supervisor is included under Project Controls
Field construction is responsible for receiving, warehousing, handling, and field inspections.
Procurement and construction share the responsibility of close out of purchase orders and
subcontracts.
Finance and Accounting produces the Accounts Payable General Ledger on a monthly basis providing
cost-to-date information for materials and subcontracts. Much of this system was covered earlier in this
section.
Project controls is responsible for establishing the budgets for all goods and services to be purchased.
Project controls also reviews procurement documents to ensure conformity with the project budget
requirements. Project controls is responsible for coordination with engineering, procurement, and
construction to establish and monitor budgets. Significant deviations from the budget are reported
through the Trend Program to facilitate any necessary corrective action.
Overall responsibilities for subcontractor interfaces for the Bechtel personnel are shown in Figure 6-9.
A narrative of the process used in control of subcontracts is given below.
For subcontracts bid out of the home office, the (on-)Project Controls Manager reviews and comments
on the bid packages emphasizing those areas that have cost impact on the entire project. This review
is completed before the package is issued for the client review and/or bid. Specifically, the (on-)Project
Controls Manager reviews scope definition, general conditions, special conditions, bid pay items,
payment terms and schedules, the technical specification, and the drawing index. Deviations from
budget/forecast scope and technical specifications as well as planned scheduled dates shall be noted
and, if appropriate, trended.
Additionally, the field project controls manager provides a budget breakdown by bid item based on
quantities supplied by the engineering or information available from the latest estimate. The bid
package must define the method of measurement and allocation of quantities to the different bid
items. Attention must also be given to methods of price adjustments which may be necessary over the
life of the contract.
The (on-)Project Controls Manager should participate in the reviews of the bid item breakdown to
ensure that it provides satisfactory detail for controlling and forecasting as well as tying into the
schedule. The bid item breakdown must be logical, easily administered, and support scheduling and
historical reporting requirements. Specifically, during the review by project controls, attention should
be given to the specific pay items which may be one, or a combination of payment types. This may
include fixed priced items, unit price items and/or time and materials items. A reasonable
understanding of the ability of a potential contractor to provide a realistic bid for each type of pay item
must be considered when requesting bids. Subcontractor monitoring may depend heavily on
information supplied through billings by pay item.
The typical support provided by project controls in the evaluation of a subcontract consist of analyzing
submitted data for the reasonableness with regard to execution. This includes, but is not limited to,
review and analysis of contractor/subcontractor staffing levels over time for manual and nonmanual
personnel, construction equipment scheduling, schedule durations for executing specific activities
versus estimated quantities, etc. Other analyses should include, but not be limited to, extensions of
unit rates, total potential cost exposure due to changes, understanding and inclusion of interfaces
where appropriate, etc.
The (on-)Project Controls Manager should also participate in the pre-bid and pre-award meetings to
discuss the particular commercial issues. It is noted that if the subcontract is bid out of the field, the
Field Controls Manager would attend these meetings and take on the lead responsibility noted above
for the (on-) projects controls manager.
C O N T R A C T F O R E C A S T W O R KS H E E T
DATE : 05-Apr-91
CP# : 01
D E S C R IP T IO N : STEAM GENERATOR
CONTRACTOR : C O M B U S T IO N E N G IN E E R IN G
******************************** C O S T S U M M A R Y *******************************
(in $1,000s)
O R IG IN A L C O M M IT M E N T ................. $17,950.0
CHANGE ORDERS PROCESSED ................. $685.0
-------
C U R R E N T C O M M IT M E N T . . . . . . . . . . . . . . . . . $18,635.0
C H A N G E O R D E R S IN P R O C E S S ................. $0.0
U N R E S O LVED CHANGES ................. $0.0
P O T E N T IAL CHANGES ................. $470.0
G R O W T H A L LO W A N C E ( fo r a b o v e ) ................. $200.0
UNAWARDED/UNCMT'D SCOPE ................. $0.0
-------
T O G O C O M M IT M E N T ................. $670.0
=======
CURRENT FORECAST ................. $19,305.0
---------------------------------------
C . C U R R E N T F O R E C A S T -T O - B U D G E T C O M P A R IS O N
CURRENT FORECAST (+ = OVERRUN; ( ) = UNDERRUN)
VS . C U R R E N T B U D G E T : $766.0
VS . F O R E C A S T # 1 : ($130.0)
---------------------------------------
D. CONTRACT COST TO-DATE $10,528.0
---------------------------------------
E . R E M A R KS
1) C O ' s # 1 - 4
2) W E L D IN G , S T L M O D S , P C C H A R G E S , A F G IS
3) IN C L . 1 5 4 K F O R F W O , 1 9 6 F O R O T & S H IF T W O R K
2 0 K F O R 5 - 1 B O IL O U T , 1 0 0 K F O R 7 - 7 F U L L L O A D
4) S E E T R A N S F E R L O G
While the subcontract bid evaluation and award may take place either in the home office or the field,
execution will always be under the field’s purview.
In the field, the Cost Engineer should review the scope of pay items and cost code them to applicable
accounts. It may be necessary to temporarily cost code into suspense accounts until the detailed
breakdown, as outlined in the contract and/or required by the Project Code of Accounts, is obtained.
In the event the awarded subcontract price is different from that originally budgeted or previously
forecasted, this information, plus allowances for anticipated changes, is inputted to the field trend
program after appropriate review with the Field Contracts Administrator (FCA) and the Site Manager.
Throughout the life of a subcontract, the FCA may receive requests from a subcontractor to amend the
scope, cost, or schedule aspects of a particular subcontract. Such request may be prompted by a
change in scope which was initiated by the client, Bechtel, or the subcontractor or by changing
conditions at the site or in the general market. Based on the nature of these proposed changes, the
FCA may request that the Field Controls Manager supply information for preparing an amendment
analysis. This information may be in the form of an engineer’s estimate, an independent manpower
loading, etc. Based on the scope of the work outlined by the FCA, the Field Controls Manager
performs the study and gives it to the FCA in a format that will allow comparison with the
subcontractor’s proposal. Specific guidelines on the FCA/Field Project Controls Manager interface
must be developed for each project.
THIS TO DATE
THRU PERIOD THRU
NUMBER OF 12/91 03/92 03/92
As with the initial review of all subcontracts, the Field Controls Manager ensures that the effect of all
approved change orders is reported in the field trend program, cost and commitment ledgers, cash
flow analysis, forecast, schedule analysis, and construction intermediate schedules.
Work performed by Bechtel personnel at the request of a subcontractor or which was within the scope
of a subcontractor’s contracted scope of work should be backcharged to that subcontractor. The FCA
acts as a backcharge originator for all backcharges related to subcontractors. The Field Controls
Manager assists the FCA in preparing the backcharge.
Progress payment verification and approvals are the responsibility of the FCA and the field finance and
accounting department. The FCA is responsible for verifying the basis of payment, whether they are
based on installed quantities, percent complete against individual bid items, or any other method that
might have been developed for monitoring progress. (Note: QRS is a possible mechanism for
monitoring subcontracts, see section on the Quantity Reporting System for further information
including the role of the field project engineer). The project accounting manager is responsible for
verifying the arithmetical accuracy of all invoices and conformance with the terms, conditions, and
rates stated in the subcontract.
The Field Controls Manager is responsible for cost coding of subcontract invoices, when necessary,
and review of the current commitments.
The Subcontract Forecast Worksheet, shown in Figure 6-10, is developed and maintained jointly by
the Field Cost Engineer and the appropriate contracts administrator for each contract package.
Together they review the Change Notice Summary Report shown in Figure 6-11 and identify to-go
activities.
FINAL
SETTLEMENT
INITIAL vs
CONTRACTOR'S BECHTEL FINAL CONTRACTOR'S
DATE CP # CONTRACTOR DESCRIPTION OF PROPOSAL PROPOSAL ESTIMATE SETTLEMENT PROPOSAL
(A) (B) (C) (D)
(C-A)
17-Mar-91 08 WINZINGER REMOVAL OF EXISTING CONCRETE SLAB 53,000 38,000 38,000 (15,000)
27-Apr-91 12 ROUSE CHANGE NOTICES #1 - 19A PLUS #23 SLUDGE PIT & WTB PIPE 411,000 215,000 248,000 (163,000)
27-Apr-91 12, 31 ROUSE, I & S YARD TANK FDNS (ROUSE PROPOSAL REJECTED, REBID & AWARDED TO I&S) 37,000 22,000 20,600 (16,400)
29-May-91 12 ROUSE YARD UTILITY RACK FOUNDATION (CN #43) 26,000 21,000 23,500 (2,500)
22-Jun-91 12 ROUSE CHANGE NOTICE #20, 21, 22, 26, 27, 28, 29, 31, & 32 73,000 38,000 47,500 (25,500)
27-Jun-91 12 ROUSE CHANGE NOTICE #33 TO 42, 44, & 45 147,137 59,000 83,043 (64,094)
29-Jun-91 10 I&L CHANGE NOTICE #11, 13, 14, & 18 27,500 18,000 20,200 (7,300)
17-Jul-91 12 ROUSE CHANGE NOTICE #46 TO 98 (PLUS UNSOLICITED PROPOSALS) 49,000 39,300 40,300 (8,700)
17-Jul-91 15 C. H. SCHWERTNER CHANGE NOTICE #2, 3, 5, 6, 8, 9, 12, & 28 48,783 34,326 40,972 (7,811)
28-Aug-91 10 IRWIN & LEIGHTON MIXED LOADS 73,217 27,300 38,345 (34,872)
28-Aug-91 10 IRWIN & LEIGHTON CRANE DOWN TIME 8,745 6,800 7,040 (1,705)
28-Aug-91 10 IRWIN & LEIGHTON ROADWAY MATS 14,077 2,300 5,170 (8,907)
The Site Manager reviews the worksheet monthly. These worksheet reports are the primary tool used
to monitor projected contract costs with emphasis being placed on estimated to-go costs and review of
Allowance For Growth In Scope (AFGIS). Deviations from the previous month’s report are trended to
the home office to be incorporated into the Project Trend Report.
As mentioned above, the Change Notice Log is developed to assist in the statusing of the active
contracts to identify outstanding changes. This report is also used by project controls to status the
backlog of unevaluated changes and is used in preparing the Listing of Negotiated Proposals shown in
Figure 6-12.
Field project controls provides support to field contracts administration for other contract monitoring
reports including the Monthly Subcontractor Progress Table shown in Figure 6-13 and the
Subcontractor Data Report shown in Figure 6-14. Also a copy of the Subcontract Analysis Report is
shown in Appendix E and this document allows for evaluation of subcontract unit rate performance on
cost code/area/facility basis. More detailed tracking of contracts may be done on a bid item/pay item
basis in the contract monitoring submodule within PCWorks (See Appendix E for examples)
CO/CO Automation
The values for budgets, commitments, current estimates etc., are the basis for input to the Cost and
Commitment Program and other associated reports. The Cost and Commitment Program covers
materials as well as subcontracts. In the initial phase of the project when contracts are being awarded,
this program is run in the home office, but may be transferred to the field during the execution phase.
Contra c t No: Contra c to r Na m e : Contra c t S c o p e : Sched. Ac tual Fcst #2 Sched. Sched. Ac tual Fcst #2 Ac tual
T o ta l Dire c t Subcontracts
PCWorks contains a Cost and Commitment module which handles the cost control reporting of all
commitment and actual cost to-date information for all subcontracts and materials.
On a monthly basis, the field finance and accounting department updates the cost to-date information
from the accounts payable records. Project controls reviews the cost-to-date totals with accounting
and verifies the correctness of commitment totals for materials with field procurement and for
subcontracts with the FCA during execution.
The purpose of a Cost and Commitment Report is to visually display and compare committed values
versus the budgeted and forecasted values so that discrepancies and/or inappropriate relationships
between the values can be identified, investigated and resolved. Refer to the Glossary of Terms
included in Appendix A for additional information.
Figure 6-15 shows a typical Cost and Commitment Variance Report. Additional Cost and Commitment
Report formats are included in Appendix E, Section 7. Shown in columns 1 through 4 of Figure 6-15,
are the current budget (allocated), the current forecast (to be committed), job-to-date (JTD)
commitments, and the job-to-date (JTD) paid (i.e. actual cost). Important variances or deltas are
calculated by comparing:
• The JTD commitments minus actual cost paid (Commitments To Pay - Column 5)
• The total forecasted cost minus the to-date committed cost (Forecast To Be Committed - Col. 6)
• The purchase orders(PO’s) and contracts for which commitments exceed the forecast
(Committed Over Forecast - Column 7), and
• The current budget allocated minus the current forecast(Column 8),
XYZ Project - Job No. 12345 Current Contract Value = Contract Award Value + Total Amendments Value
SUBCONTRACT DATA REPORT Estimated Final S/C Value = Current Contract Value + Potential Changes Value
Updated through February, 1997 Gross Paid Value = Invoice Value (Cost to Project for work performed) C = CONTRACT DATE
REPORT NO. 2 Current Contract Budget Value = Original Budget Value + Scope Changes Value F = FORECAST DATE
Current Contract Forecast Value = Current Budget Value + Scope Changes Value + Approved Trends Thru Trend Report No. 6 A = ACTUAL DATE
CONTRACT IDENTIFICATION COST SUMMARY PROGRESS AND COST INFORMATION
CONTRACT CONTRACT CURRENT CONTRACT ESTIMATED G R O S S P A I D SCHEDULE INFO. CURRENT CURRENT
CONTRACT CONTRACT DESCRIPTION CONTRACTOR A W A R D E D AMEND/AUTH CONTRACT POTENTIAL FINAL S/C TO-DATE PROGRESS START: C OR A CONTRACT CONTRACT
NO. TYPE AMOUNT AMOUNT VALUE CHANGES VALUE $ COMPL: BUDGET FORECAST
$ $ $ (ESTIMATED) $ (RETENTION) COMPL: F OR A $ $
LS: X Temporary Constr. Collins Electric $47,850 $54,200 $102,050 $0 $102,050 $100,698 PMT: 100% Start: 11-SEP-91 A $85,070 $85,070
FSC-001 UP: Pow e r PROG: 100% Compl: 17-JAN-92 C
TM: $0 Compl: 17-JAN-92 A
LS: CANCELED $0 $0 $0 $0 $0 $0 PMT: 0% Start: $0 $0
FSC-002 UP: PROG: 0% Compl:
TM: N/A Compl:
LS: X Site Preparation, Major J.H. Maxymillian, Inc. $433,452 $384,559 $818,011 $0 $818,011 $818,011 PMT: 100% Start: 22-OCT-91 A $835,392 $835,392
FSC-003 UP: Fnd Excavation, Sheet PROG: 100% Compl: 24-JAN-92 C
TM: Piling $0 Compl: 24-JAN-92 A
LS: Labor for Electrical Collins Electric $50,000 $37,350 $87,350 $0 $87,350 $30,042 PMT: 34% Start: 09-DEC-91 A $87,350 $87,350
FSC-004 UP: X Installation PROG: 81% Compl: 01-APR-92 C
TM: $0 Compl: 01-APR-92 F
LS: X Hook up water - D & M Mechanical $2,621 $0 $2,621 $0 $2,621 $2,621 PMT: 100% Start: 18-DEC-91 A $3,000 $2,621
FSC-005 UP: Temp. Office Contractor PROG: 100% Compl: 20-DEC-91 C
TM: N/A Compl: 20-DEC-91 A
LS: Guard Service Pinkerton $60,000 $0 $60,000 $100,000 $160,000 $8,635 PMT: 5% Start: 02-DEC-91 A $310,400 $160,400
FSC-006 UP: X PROG: 5% Compl: 16-JUL-93 C
TM: N/A Compl: 16-JUL-93 F
LS: X Railroad Spur New England Rail - $55,950 $0 $55,950 $0 $35,950 $0 PMT: 0% Start: 23-MAR-92 A $73,100 $73,100
FSC-007 UP: road Construction Co. PROG: 0% Compl: 17-APR-92 C
TM: N/A Compl: 27-MAR-92 F
LS: Plumbing Installation Henry Grodsky & Co. $60,000 $0 $60,000 $0 $60,000 $35,240 PMT: 59% Start: 02-JAN-92 A $60,000 $60,000
FSC-008 UP: X PROG: 59% Compl: 01-APR-92 C
TM: $0 Compl: 01-APR-92 F
LS: X Temporary Fencing Glidden Fence, Inc. $9,358 $0 $9,358 $0 $9,358 $9,358 PMT: 100% Start: 13-JAN-92 A $10,000 $10,000
FSC-009 UP: PROG: 100% Compl: 18-JAN-92 C
TM: N/A Compl: 18-JAN-92 A
LS: X Heavy Hauling Shaughnessy & Ahern $609,500 $0 $609,500 $0 $609,500 $0 PMT: 0% Start: 20-APR-92 C $288,000 $673,000
FSC-010 UP: PROG: 0% Compl: 01-OCT-92 C
TM: $0 Compl: 01-OCT-92 F
LS: X Underground Utilities J.H. Maxymillian, Inc. $407,996 $0 $407,996 $0 $407,996 $0 PMT: 0% Start: 16-MAR-92 A $396,700 $396,700
FSC-011 UP: PROG: 0% Compl: 12-JUN-92 C
TM: $0 Compl: 12-JUN-92 F
LS: X Condensate Pump J.H. Maxymillian, Inc. $9,470 $650 $10,120 $0 $10,120 $10,120 PMT: 100% Start: 24-FEB-92 A $0 $0
FSC-012 UP: Casing PROG: 100% Compl: 28-FEB-92 C
TM: $0 Compl: 27-FEB-92 A
LS: X Railroad Subgrade Joseph Rosati, Inc. $9,250 $0 $9,250 $0 $9,250 $0 PMT: 0% Start: 16-MAR-92 A $0 $0
FSC-013 UP: Preparation PROG: 100% Compl: 23-MAR-92 C
TM: $0 Compl: 20-MAR-92 A
LS: Site Electrical Work Collins Electric $2,000,000 $0 $2,000,000 $0 $2,000,000 $0 PMT: 0% Start: 06-APR-92 C $2,210,000 $2,210,000
FSC-014 UP: PROG: 0% Compl: 19-JUL-93 C
TM: X $0 Compl: 19-JUL-93 F
If either of the first two above deltas result in a negative variance, then the variance should be reduced
to zero employing the appropriate adjustments after making a thorough investigation. The third delta
requires adjustments to be made if the delta is positive. Finally, the last delta may be either positive or
negative. If negative, then the forecast exceeds the budget due to overruns.
This report is the first produced by the Cost Engineer and serves to flag any problems that need
resolution before the formal report is issued. This report is developed in accordance with the cost
codes and is one of the more detailed CO/CO reports produced. An example of a Cost Commitment
Management Report is shown in Figure 6-16. Other cost and commitment summaries and detailed
report options by PO/Contract and by cost code are displayed in Appendix E. Also refer to PCDP 4.07
for additional information.
ZZ54.58 FIELD GENERAL EXPENSES / PETTY CASH 250,000 250,000 13,397 13,397 0 236,603 0 0
ZZ54.61 FIELD TELEPHONE & FAX SERVICE 100,000 100,000 6,558 6,558 0 93,442 0 0
ZZ54.71 FIELD COMPUTER HARDWARE / SOFTWARE 400,000 400,000 112,261 112,261 0 287,739 0 0
ZZ54.72 FIELD OFFICE FURNITURE / EQUIPMENT 500,000 500,000 60,310 60,310 0 439,690 0 0
ZZ61.2 FIELD CAMP BULIDING FACILITIES 25,000 25,000 38,810 38,810 0 -13,810 13,810 0
Run date:
Data date: Cost Commitment Management Report
RMCT: 1.3 By Category
(Pre-Committed and Committed-As-Paid)
======= TOTAL PROJECT ======= 75130640.30 7338158.70 82468799.00 35113374.13 895058.23 36008432.36 0.00 0.00 0.00
DISTRIBUTABLE REPORTS
Distributables control tools, which should be set up for monthly statusing, consist of the following:
1. Material and Subcontract expenditure curves for all major distributable accounts (i.e. 51, 52, and
53), showing budget, forecast, and cost to-date
2. Manual jobhour curve, including manual support labor for all major distributable jobhour accounts,
showing budget, current forecast, and expended to-date.
3. Curve showing distributable manual jobhours spent as a percentage of direct manual jobhours, to-
date and over selected intervals of time (e.g. monthly or weekly as appropriate).
4. Field Non-Manual Organization Chart.
5. Field Non-Manual Bar Chart Schedule showing budget, forecast, and actual durations by position.
Actual start dates and release dates should be recorded.
6. Construction Equipment Schedules showing count by type of equipment for budget, forecast, and
actual by month.
Figure 6-18 summarizes a typical informational flow for distributable material and subcontracts.
Approved by 2. 3. VIA 20
1.
5. 6. SHIP DATE 21
4.
Item Quantity Stock Code - DESCRIPTION - Full Detail cost code unit cost total cost unit cost total cost unit cost total cost
12 13 14 15 22
Field Material Requisitions (FMRs) as shown in Figure 6-17 are initiated by the Field Engineers or
Superintendents. FMRs are typically approved by the Site Manager, Field Superintendent, or Project
Field Engineer. The FMR is reviewed by the Field Cost Engineer for cost coding and analysis for
deviations against the budget/forecast for the identification of a possible trend. Field Procurement
purchases the material or services utilizing the FMR during the bid, evaluation and award process.
Invoices reviewed by accounting are paid referencing the FMR for proper project cost code distribution
on the Accounts Payable Ledger (APL). The APL is the source document that provides actual cost
information to the Field Cost Engineer on distributable material and subcontract cost. Also, the CO/CO
report is another source of this information.
REVIEW
Project Superintendent:
REVIEW
Cost Engineer:
PROCESS
Field Procurement Manager:
PROCESS
Field Accounting Manager:
PROCESS
Field Cost Engineer:
- Input into Cost Control Program
Product Output:
- Cost and Commitment Report
- Construction and Tools Report
ANALYSIS REVIEW
Cost Engineer:
- Construction Equipment Schedules
- Construction Equipment and Tools Report
- Identify Trend TREND PROGRAM
Cost / Schedule Engineer:
Construction Manager:
The formats of the FMR and APL are established at the beginning of the project to verify if they are
compatible with procurement, accounting and cost programs. It is noted that FMR can be used to
purchase direct cost related materials in the field as well.
D IS T R IBUTABLE M A T E R IALS A N D S U B C O N T R A C T S C O S T S U M M A R Y
TO-DATE CURRENT
CURRENT CURRENT PLANNED TO-DATE @ COMPLETION
BUDGET FORECAST EXPENDITURE ACTUALS FORECAST
T E M P O R A R Y C O N S TRUCTION FACILITIES
MIS C E L L A N E O U S C O N S TRUCTION S E R V I C E S
Typically, FMRs are written, approved, and cost coded daily. Field procurement purchases the
material or services to meet the delivery dates on the FMR. The Field Accounting Office Manager
issues the APL on the seventh working day of the month. The Field Distributable Report is normally
issued by the 20th day of the month.
The Field Distributables Report compares the accrued actuals by account for material and/or
subcontract costs and may include jobhour actuals against budget, forecast, or target. These are
typically compared to a planned value, as shown in Figure 6-19, and presented graphically for major
distributable accounts, as shown in Figures 6-20, 6-21, and 6-22. This summarization allows the
project to monitor cost against the plan which can be used for forecasting, cash flow, and other control
programs.
Detailed information for distributable materials and subcontracts are tracked in the project CO/CO
which is covered earlier in this section in the subsection on subcontract/materials cost control.
Examples of summary presentation for distributable materials are included in Section 4, Project
Summary Reports. Refer to PCDP 4.07 (Part D) for additional information on distributable materials
and subcontracts.
500 $1,500
400 $1,200
Cumulative Costs($1,000s)
Monthly Costs ($1,000s)
300 $900
200 $600
100 $300
0 $-
Jul-96
Budget Sep-96
Monthly Nov-96
Distrib Matl Jan-97 Mar-97 Fcst
May-97 Jul-97 MatlSep-97
Monthly Distrib Nov-97 Jan-98 Actual Monthly Distrib Matl
Budget Cum Distrib Matl Fcst Cum Distrib Matl Actual Cum Distrib Matl
Distrib Material Jul-96 Aug-96 Sep-96 Oct-96 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 Oct-97 Nov-97 Dec-97 Jan-98 Feb-98
Monthly Budget $0 $25 $76 $181 $69 $36 $31 $31 $34 $34 $42 $37 $35 $35 $34 $33 $34 $32 $28 $32
Distrib Fcst $27 $32 $79 $28 $24 $30 $25 $15
Matl Actual $0 $0 $138 $125 $246 $35 $52 $42 $29 $18 $24 $20
Distrib Material Jul-96 Aug-96 Sep-96 Oct-96 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 Oct-97 Nov-97 Dec-97 Jan-98 Feb-98
Cum Budget $0 $25 $101 $282 $351 $387 $418 $449 $483 $517 $559 $596 $631 $666 $700 $733 $767 $799 $827 $859
Distrib Fcst $729 $756 $788 $867 $895 $919 $949 $974 $989
Matl Actual $0 $0 $138 $263 $509 $544 $596 $638 $667 $685 $709 $729
D IST R I B U T A B L E M A T E R I A L & S / C C O S T S
Construction Services (52 Accts)
200 $800
160
Cumulative Costs($1,000s)
Monthly Costs ($1,000s)
$600
120
$400
80
$200
40
0 $-
Jul-96 Sep-96 Nov-96 Jan-97 Mar-97 May-97 Jul-97 Sep-97 Nov-97 Jan-98
Budget Monthly Distrib Matl Fcst Monthly Distrib Matl Actual Monthly Distrib Matl
Budget Cum Distrib Matl Fcst Cum Distrib Matl Actual Cum Distrib Matl
Distrib Material Jul-96 Aug-96 Sep-96 Oct-96 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 Oct-97 Nov-97 Dec-97 Jan-98 Feb-98
Monthly Budget $0 $4 $16 $22 $29 $39 $44 $48 $44 $46 $43 $46 $46 $45 $34 $30 $23 $19 $13 $12
Matl Actual $0 $0 $7 $13 $48 $24 $57 $39 $47 $41 $21 $34
Distrib Material Jul-96 Aug-96 Sep-96 Oct-96 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 Oct-97 Nov-97 Dec-97 Jan-98 Feb-98
Cum Budget $0 $4 $20 $41 $70 $109 $153 $201 $245 $291 $334 $380 $426 $471 $505 $535 $558 $577 $591 $603
Distrib Fcst $330 $357 $395 $440 $475 $504 $534 $544 $549
Matl Actual $0 $0 $7 $20 $68 $92 $149 $188 $235 $275 $296 $330
1,000 $4,000
800
$3,000
Cumulative Costs($1,000s)
Monthly Costs ($1,000s)
600
$2,000
400
$1,000
200
0 $-
Jul-96 Sep-96 Nov-96 Jan-97 Mar-97 May-97 Jul-97 Sep-97 Nov-97 Jan-98
Budget Monthly Distrib Matl Fcst Monthly Distrib Matl Actual Monthly Distrib Matl
Budget Cum Distrib Matl Fcst Cum Distrib Matl Actual Cum Distrib Matl
Distrib Material Jul-96 Aug-96 Sep-96 Oct-96 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 Oct-97 Nov-97 Dec-97 Jan-98 Feb-98
Monthly Budget $2 $48 $96 $203 $321 $354 $309 $246 $234 $224 $221 $214 $195 $160 $174 $106 $78 $58 $49 $25
Distrib Fcst $120 $191 $196 $15 $160 $110 $50 $20
Matl Actual $0 $0 $47 $125 $328 $291 $247 $209 $234 $220 $189 $211
Distrib Material Jul-96 Aug-96 Sep-96 Oct-96 Nov-96 Dec-96 Jan-97 Feb-97 Mar-97 Apr-97 May-97 Jun-97 Jul-97 Aug-97 Sep-97 Oct-97 Nov-97 Dec-97 Jan-98 Feb-98
Cum Budget $2 $50 $146 $349 $670 $1,024 $1,333 $1,579 $1,813 $2,037 $2,258 $2,472 $2,667 $2,827 $3,001 $3,107 $3,185 $3,243 $3,292 $3,317
Distrib Fcst $2,101 $2,221 $2,412 $2,608 $2,623 $2,783 $2,893 $2,943 $2,963
Matl Actual $0 $0 $47 $172 $500 $791 $1,038 $1,247 $1,481 $1,701 $1,890 $2,101
FIGURE 6-22 - DISTRIBUTABLE MATERIAL AND SUBCONTRACT COSTS - CONSTRUCTION TOOLS AND
EQUIPMENT
Detailed performance information for distributable manual labor is tracked in the QURR covered earlier
in a related subsection. Examples of summary presentations are included in Section 4, Project
Summary Reports. Refer to PCDP 4.06 for more information on distributable labor.
The key planning tool for developing the field nonmanual plan is the bar chart, shown in Figure 6-23,
which displays the staffing requirements, types of assignments, durations and grades for each
position. A chart may be prepared during the proposal stage by construction. If not, construction will
prepare one at time of award. The Site Manager has overall responsibility for controlling nonmanual
jobhours for the project. Individual functional area field supervisors are responsible for controlling
staffing within their groups. The field nonmanual bar chart is updated showing status on a monthly
basis.
Once the field non-manual bar chart has been developed, the field non-manual labor analysis, as
shown in Figure 6-24, can be prepared. For positions for which candidates have not been identified,
the Field Cost Engineer should use average rates for an identified grade. The wage rate input for
each position should be the bare wage without payroll adds. Payroll adds and escalation are bottom
line adjustments. The analysis is statused and revised on a monthly basis.
The Field Nonmanual Cost Report, including graphs, serves as the overall summary for field
nonmanual jobhours and costs. The report is issued monthly with updated actuals as soon as
practical after the Bechtel accounting cut-off date. Scheduled and forecast expenditures are reviewed
and updated quarterly. In lieu of issuing a separate document, this report is often included as part of
the Field Distributables Report shown in Figure 6-25. The Field Cost Engineer compares actual cost to
budgets and forecasts, analyzes and points out potential impacts. The Field Planner must evaluate
staffing for consistency with the schedule.
Examples of related nonmanual summary graphs are included in Section 4 under Field Progress,
Performance, and Resource Curves. Refer to PCDP 4.05 for more information. The overall work
process flow chart for nonmanual cost control is shown in Figure 6-26.
91 92 93 94
TOT S/T O/T O/T TOTAL
POSITION NAME A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J MAN HOURS % HOURS HOURS
MTH 161
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
S A F E T Y / S E C U R IPT Y
DeMEIO, P. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 20 3226 5% 161 3387
NURSE L FORZIATI, M. 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15 2420 5% 121 2541
ESCALATION: 81,681
DI S T R I B' S B U D G E T v s ACTUAL AS OF _ _ _ _ _ _
F I ELD OFFI CE 100, 000 19, 048 43, 975 500 240 171
WAREHOUSES 40, 300 6, 300 9, 644 500 110 160
CHANGE HOUSE 32, 000 6, 000 18, 990 200 91 58
FABRI CATI ON SHOP 10, 000 2, 000 0 0 0 0
BRASS ALLEY 4, 200 1, 000 1, 572 100 56 54
F I RST AI D OFFI CE 40, 000 13, 500 9, 068 200 121 5
WAREHOUSE, OF F S I TE 164, 000 21, 600 0 0 0 0
ACCESS ROAD DEVELOPMENT 50, 000 10, 000 0 200 59 8
T E MPORARY PARKI NG & LAYDOWN AREA 82, 000 38, 800 30, 884 600 114 135
T E MPORARY FENCI NG 12, 000 4, 000 930 0 0 0
CONSTRUCTI ON WATER 3, 500 3, 500 2, 353 400 241 21
CONSTRUCTI ON SEWER 90, 000 38, 000 26, 092 200 113 86
CONSTRUCTI ON POWER 148, 000 107, 091 71, 465 3, 000 452 367
MI S C . T E MPORARY CONST. ( I NCL SAFETY) 35, 000 4, 200 26, 818 4, 000 592 1, 129
TOTAL CONSTRUCTI ON FACI L I T I E S 811, 000 275, 039 241, 791 9, 900 2, 188 2, 194
TOTAL CONSTRUCTI ON SERVI C E S 1, 189, 340 369, 235 177, 148 48, 200 9, 131 10, 225
TOTAL EQUI P MENT, TOOLS & SUPPLI E S 1 , 4 2 9 , 0 0 0 337, 400 437, 246 0 0 0
DI S T R . MANUAL 3, 429, 340 981, 674 856, 186 58, 100 11, 319 12, 419
TOTAL MANUAL 4, 497, 348 981, 674 856, 186 78, 029 11, 319 12, 427
TOTAL FI ELD & STARTUP NON- MANUAL 1, 392, 554 426, 597 289, 970 109, 371 25, 145 19, 457
I NSURANCE 0 0 2, 770
P E R MI TS & LI CENSES 0 0 10, 306
TOTAL I NSURANCE & PERMI T S 0 0 13, 076
AWARDED CONTRACT,
APPROVED SCOPE CHANGES &
FIELD DEPARTMENT INPUT
TO-GO MANMONTHS
TO DATE JOBHOURS,
SALARIES, ADDS
F&A
TO DATE COSTS
BY CATEGORY
F&A
COST
REPORTS
LEGEND
CIVIL / STRUCTURAL
ARCHITECTURAL
AC00 Elevator
AK01 Pre-Engineered
Buildings
AM01 Concrete Masonry Unit
AT44 Roofing
ROTATING EQUIPMENT
MA01 3PS-MA- MR- ID Fans
B01 MA01-
00001
MC01 3PS-MC- MR- Fuel Gas Compressor
B01 MC01-
00001
MC09 3PS-MC- MR- Air Compressors
B09 MC09-
00001
MC12 3PS-MC- MR- Vacuum Pumps
B12 MC12-
00001
THERMAL EQUIPMENT/TANKS
JV14 3PS-JV- MR-JV14- Relief Valves
B14 00001
MB06 3PS-MB- MR- Auxiliary Boilers
B06 MB06-
00001
MB07 3PS-MB- MR- Steam Reboiler
B07 MB07-
00001
ME03 3PS-ME- MR- Air Cooled Heat
B03 ME03- Exchangers
00001
ME04 3PS-ME- MR- Plate Heat Exchangers
B04 ME04-
00001
ME09 3PS-ME- MR- Condenser
B09 ME09-
00001
ME11 3PS-ME- MR- Cooling Tower
B11 ME11-
00001
ME14 3PS-ME- MR- Shell & Tube Heat
B14 ME14- Exchangers
00001
ME15 3PS-ME- MR- Air Cooled Condenser
B15 ME15-
00001
ME16 3PS-ME- MR- Feedwater Heaters w/ Integral
B16 ME16- Deaerator
00001
ME17 3PS-ME- MR- Deaerator
B17 ME17-
00001
ME26 3PS-ME- MR- Dump Condenser
ELECTRICAL COMMODITIES
EB01 3PS-EB- MR-EB01- Isophase Bus &
505 00001 Accessories
EB04 3PS-EB- MR-EB04- Non-Segregated Bus
515 00001
EC01 3PS-EC- MR-EC01- High Voltage Motor
901 00001 Control Centers
EC02 3PS-EC- MR-EC02- 480V Motor Control ‚ w/ EY09
518 00001 Centers
EC02 3PS-EC- MR-EC02- Low Voltage Motor
902 00001 Control Centers
EH01 MR-EH01- Electric Heat Tracing
00001
EK01 3PS-EK- MR-EK01- 400V Load Center Unit ‚ w/ EY09
502 00001 Subs.
EK02 3PS-ES- MR-EK02- Low Voltage