TEKNIK PEMBORAN II
PENDAHULUAN :
AGENDA PERKULIAHAN
DAFTAR PUSTAKA
MATERI PEMBELAJARAN\
REVIEW MATERI KULIAH GEOMETRI LUBANG BOR :
- MENGHITUNG : VOLUME LUBANG BOR, ANNULUS, STRING,
- MENGHITUNG : LAG TIME, LAG STROKE DARI SURFACE KE
BOTTOM, BOTTOM KE SURFACE, 1 CYCLE
AGENDA PERKULIAHAN
CLASS MEETING : 16 KALI ( 14 KALI
PERKULIAHAN + 2 KALI EVALUASI )
SISTEM PENILAIAN :
(1) (2)
- PRAKTIKUM : 20 % 20
- KEHADIRAN : 10 % 10
- TUGAS : 10 % 10
- KUIS : 10 % -
- UTS : 20 % 30
- UAS : 30 % 30
NILAI :
- A: 80 –100
- B: 67 –79.99
- C: 55 –66.99
- D: 41 –54.99
- E: 0 –40.99
DAFTAR PUSTAKA
Rubiandini R.R.S, "Teknik Opreasi Pemboran", TM-
ITB, Bandung, 2008
Adam N.J, “Drilling engineering”, Penwell Book
Publishing Co, 1985
Adam T., Bourgoyne jr, “Applied Drilling engineering”,
SPE, 1986
Hussain Rabia, “Well engineering & Construction
MATERI PEMBELAJARAN
PENDAHULUAN
TEKANAN FORMASI DAN GRADIEN TEKANAN
PRESSURE CONTROL
HOLE PROBLEM
TEKNIK PENYEMENAN
TEKNIK PEMBORAN MIRING
Capacities and Volumes
Open Hole Capacity (Bbl/ft) (OH cap) =
( )
.
• Open Hole Volume Bbl (OH vol) =
OH cap, bbl/ft x Length, ft
Casing Capacity Bbl/ft (Csg Cap) =
( )
.
• Casing Volume bbl (Csg vol) =
Csg cap, bbl/ft x Length, ft
CAPACITY DAN
VOLUME OPEN HOLE Misal :
Sumur dibor dg 8½” hole dengan kedalaman lubang bor
1000 ft, Hitung Open hole Capacity nya dan volume
Lubang Bor lumpur yg berada didalam lubang bor.
Jawab :
• Open Hole Capacity (Bbl/ft) (OH cap) =
( ) .
Dh = = 0.07 bbl/ft
. !"#.$
L
• Volume lumpur didalam lubang bor (OH vol)
(bbl) =
OH cap, bbl/ft x Length, ft
0.07 bbl/ft x 1000 ft = 70 bbl
8½” hole
Dh = diameter lubang
bor (ft).
L = Kedalaman (ft)
CASING VOLUME DAN Contoh :
CAPACITY
Casing 9-5/8” (ID 8.835”) mempunyai panjang
500 ft. Hitung kapasitas casing dan volume
ID lumpur yg berada didalam casing
Jawab :
• Casing Capacity Bbl/ft (Csg Cap) =
( ) %.%&'
= = 0.0758 bbl/ft
. .
L
• volume lumpur yg berada didalam
casing :
Casing Volume bbl (Csg vol) =
Csg cap, bbl/ft x Length, ft
OD = 0.0758 bbl/ft x 500 ft = 37.9 bbl
ID = Inside Diameter (inch)
OD = Outside Diameter (inch)
L = Length (panjang) (ft)
OPEN HOLE DAN CASING Contoh :
VOLUME
Dari gambar disamping hitung volume
lumpur dilubang bor.
Jawab :
9 5/8”csg
(ID:8.835”) • Vol.lumpur casing + vol.lumpur OH =
= (Csg cap, bbl/ft x Length, ft) + (OH cap,
bbl/ft x Length, ft)
%.%&' %.'
=( x 2000’ ) + ( x 500’)
. .
9 5/8” csg
shoe @
2000 FT = 151.66 bbl + 35.09 bbl = 186.75 bbl
OH = 500 ft
2500 ft
8½ HOLE
Drill String Capacity bbl/ft (DS cap) =
(( )
.
• Drill String Volume bbl (DS vol) =
DS cap bbl/ft x Length ft
Annular Capacity :
OH-DS annular Capacity bbl/ft :
()*+, -./+ 0123+4+5 1,67) 8 ()0 9451,: 1,67)
!"#.$
Casing – DS annular Capacity, bbl/ft
(;2<1,: =0 1,67) 8 ()0 9451,: 1,67)
!"#.$
DRILL STRING CAPACITY AND
Contoh :
VOLUME
1. Hitung besarnya capacity dan volume 5” DP
(ID 4.276”) dengan panjang 1000 ft.
OD ID Jawab :
• DP Capacity bbl/ft (DS cap) =
(( ) . >?
= = 0.0178 bbl/ft
OD = diameter luar (inch) . .
• Annular Volume :
OH - Drill String annular Volume, bbl :
6½”DC (ID:1½”) ( ) 8 ( E )
x Length ft
DC .
L DC ?
9 5/8” csg Vol.annulus lubang bor =
shoe @ Vol.annulus DP+Vol.annulus DC
8½” Hole 2500 FT 8.835² − 5² 8.835² −6½²
=( G ′) I ( x(2500’−2000’)
. .