You are on page 1of 123

OFFICE OF INDUSTRIAL

TECHNOLOGIES

Energy

Energy Management for Motor Driven Systems


Management for
Motor Driven
Systems

The energy savings network—plug into it

OFFICE OF INDUSTRIAL TECHNOLOGIES


ENERGY EFFICIENCY AND RENEWABLE ENERGY • U.S. DEPARTMENT OF ENERGY
Energy
Management
for Motor-Driven
Systems

Prepared by
Gilbert A. McCoy and
John G. Douglass
Washington State University
Cooperative Extension Energy Program
Olympia, Washington

Funded by
The Bonneville Power Administration

Reproduced by
The U.S. Department of Energy
Office of Industrial Technologies

Revision 2 March 2000


Acknowledgments
The authors wish to thank the Disclaimer
Bonneville Power Administration
(BPA) for funding this project. This guidebook was prepared by
Particular thanks are due to Craig the Washington State Energy
Wohlgemuth of Bonneville’s Techni- Office and Washington State
cal Assessment/R&D Group for his University Cooperative Extension
encouragement, direction and sup- Energy Program with funding
port. Portions of this guidebook have from the Bonneville Power
been adapted from two unpublished Administration. Neither the
1994 reports prepared by Carroll, United States, the Bonneville
Hatch & Associates for the Power Administration, the State of
Bonneville Power Administration. Washington, the Washington State
Appreciation is extended to John Energy Office, the Washington
Vranizan of Carroll, Hatch & Associ- State University Cooperative
ates and to Rob Gray of the Washing- Extension Energy Program, nor
ton State Energy Office’s Spokane any of their contractors, subcon-
office for information and/or reviews tractors, or their employees,
provided. Vicki Zarrell provided makes any warranty, expressed or
review, proofing, and technical implied, or assumes any legal
editing services. responsibility for the accuracy,
completeness, or usefulness of
A first version of this guidebook was any information, apparatus,
completed in 1996 by the Washington product, or process disclosed
State Energy Office with funding within this guidebook.
from BPA contract No. DE-B179-
93BP08158, Task Order No.
96AT63464. Subsequently, enhance-
ments and research results were
incorporated into this revision by the
Washington State University Coop-
erative Extension Energy Program
using Power Washington oil over-
charge funds.

The U.S. Department of Energy,


Office of Industrial Technologies
would like to thank the Bonneville
Power Administration for their
efforts in producing this document.

This publication has been repro-


duced by DOE/Office of Industrial
Technologies.

i
ii Energy Management for Motor-Driven Systems
Executive Summary

This publication will assist you to establish a facility energy-manage-


ment program, to identify and evaluate energy conservation opportu-
nities involving motor-driven equipment, and to design a motor
improvement plan. These actions will help you:

ü Reduce energy costs,


ü Improve motor-driven system reliability and
efficiency,
ü Increase productivity, and
ü Minimize unscheduled downtime.

In the Guide you will find:

• How to set up a successful energy management program


(Chapter 1).

• How you can use utility bills, plant production data, and utility
rate information to “target” potentially cost-effective energy
conservation, demand reduction and power factor correction
opportunities (Chapter 2).

• Plant distribution system troubleshooting and “tune-up” tips


(Chapter 3).

• A description of motor testing instruments and field survey tech-


niques (Chapter 4).

• Methodologies for analyzing motor improvement opportunities


(Chapter 5). Chapter 5 illustrates how you can use measured
information to determine the load imposed on the motor by driven
equipment and its efficiency at that load point.

• How to determine the dollar benefits associated with appropriate


energy conservation and demand reduction actions (Chapter 6).

• Motor improvement planning basics (Chapter 7). This chapter


provides advice regarding the assessment of new motor purchase,
repair, downsizing, and replacement decisions and shows how to
incorporate findings into your motor improvement plan.

• Power factor correction assessment techniques (Chapter 8). This


chapter gives examples illustrating the sensitivity of power factor
correction benefits to utility rate schedules.

• How to establish both preventative and predictive maintenance


programs (Chapter 9).

iii
Throughout this guidebook we identify sources of additional informa-
tion, such as MotorMaster+. MotorMaster+ is an energy-efficient
Call the OIT Clearinghouse
motor selection and energy management software package. The
(800) 862-2086 to obtain capabilities of MotorMaster+ include:
your copy of MotorMas-
ter+. Both the OIT Clear- • Automatic motor load and efficiency estimation based upon field
inghouse and the Electric data measurements.
Ideas Clearinghouse (800) • Ability to select replacement motors from an internal database of
872-3568 [(360) 956-2237 over 27,000 one-to-2,000 hp NEMA Design B, C and D motors.
outside BPA’s service
• Ability to analyze conservation benefits due to purchase and use of
territory] stand ready to energy efficient motors in new, rewind, or retrofit applications.
assist you regarding motor
and motor-driven equip-
ment efficiency issues.

iv Energy Management for Motor-Driven Systems


Contents

Chapter 1 Energy Management for Motor-Driven Systems.......... 1-1


Elements of a Successful Energy Management Program .......... 1-2
1. Secure Top Management Commitment ............................. 1-2
2. Appoint an Energy Coordinator ........................................... 1-2
3. Obtain Employee Cooperation ............................................ 1-3
4. Conduct Energy Surveys ..................................................... 1-3
5. Organize Energy Data .......................................................... 1-4
6. Analyze Survey Results ....................................................... 1-5
7. Set Conservation Goals ....................................................... 1-5
8. Develop Organization-Wide Energy Management Plan .. 1-5
9. Implement Engineering Changes ........................................ 1-5
10. Monitor and Evaluate Results .............................................. 1-7
Conclusion .......................................................................................... 1-7
Chapter 2 Understanding Your Utility Bill................................... 2-1
Organizing Utility Bills and Production Data ................................... 2-1
Interpreting Utility Charges ................................................................ 2-4
Service Charge ............................................................................. 2-5
Energy Charge .............................................................................. 2-5
Demand Charge ........................................................................... 2-6
Power Factor Charges................................................................. 2-6
Optional Rate Schedules .................................................................. 2-9
Time-of-Use Rates ....................................................................... 2-9
Interruptible, Curtailment and Customer Generator Rates ..... 2-9
Using Billing Data to Identify Opportunities .................................. 2-10
Checklist for Electricity Cost Savings ...................................... 2-11
Chapter 3 Industrial Electrical Systems ......................................... 3-1
The Plant Electrical Distribution System ........................................ 3-2
Over and Under Voltage ............................................................... 3-2
Voltage Unbalance ........................................................................ 3-3
Troubleshooting and Tuning your In-Plant Distribution System ... 3-5
Troubleshooting Poor Contacts .................................................. 3-5
Voltage Drop Survey ............................................................. 3-6
Infrared Thermography ......................................................... 3-6
Troubleshooting Voltage Unbalance ........................................... 3-7
Troubleshooting Over and Under Voltage .................................. 3-8
Troubleshooting Low Power Factor ........................................... 3-9
Troubleshooting Undersized Conductors .................................. 3-9
Troubleshooting Insulation Leakage ........................................... 3-9

v
Chapter 4 Taking Field Measurements ........................................... 4-1
Safety Considerations ....................................................................... 4-1
Constructing the Motor List and Inventory Database .................... 4-2
Acquiring Motor Nameplate Data ..................................................... 4-2
Load-Time Profiles ............................................................................. 4-3
Measuring Operating Values ............................................................ 4-4
Data Gathering Approaches ............................................................. 4-5
Safety Issues in Data Gathering ................................................. 4-6
Voltage Measurements................................................................. 4-6
Current Measurements ................................................................ 4-7
Power Factor Measurements ..................................................... 4-7
Purchasing Motor Testing Instruments ........................................... 4-8
Voltage Meters ............................................................................... 4-8
Current Meters .............................................................................. 4-8
Tachometers .................................................................................. 4-9
Power and Power Factor Meters .............................................. 4-10
Multi-channel Power Loggers .................................................... 4-11
Motor Analyzers........................................................................... 4-11
Industrial Practices .......................................................................... 4-12
Chapter 5 Motor Load and Efficiency Estimation Techniques ........ 5-1
Input Power Measurements .............................................................. 5-1
Line Current Measurements ............................................................. 5-2
The Slip Method .................................................................................. 5-3
Variable Load Levels .......................................................................... 5-5
Determining Motor Efficiency ........................................................... 5-6
Computerized Load and Efficiency Estimation Techniques ... 5-8
Chapter 6 Energy, Demand, and Dollar Savings Analysis .............. 6-1
Calculating Annual Energy and Demand Savings ........................ 6-1
Assessing Economic Feasibility ...................................................... 6-2
Chapter 7 Motor Improvement Planning ........................................ 7-1
Energy Efficient Alternatives ............................................................. 7-1
Upon Failure Alternatives ............................................................. 7-2
Without an Existing Motor Failure ............................................... 7-5
MotorMaster+: Motor Energy Management Software ................. 7-2
Motor Resizing .................................................................................... 7-6
Conclusion ........................................................................................ 7-10

vi Energy Management for Motor-Driven Systems


Chapter 8 Power Factor Correction ................................................ 8-1
The Concept of Power Factor .......................................................... 8-1
Power Factor Penalties ..................................................................... 8-2
Power Factor Improvement .............................................................. 8-3
Sizing and Locating Power Factor Correction Capacitors .......... 8-4
Sizing Capacitors for Individual Motor and Entire Plant Loads .... 8-6
Benefits of Power Factor Correction ............................................... 8-8
Additional Benefits of Power Factor Correction ........................... 8-10
Power Factor Correction Costs ..................................................... 8-11
Avoiding Harmonic Resonances When Installing Capacitors ... 8-12
Chapter 9 Preventative and Predictive Maintenance Planning ........ 9-1
Cleaning ............................................................................................... 9-2
Lubrication ........................................................................................... 9-3
Mountings, Couplings, and Alignment ............................................. 9-5
Operating Conditions ......................................................................... 9-6
Thermal, Vibration and Acoustic Tests ........................................... 9-9
Electrical Tests ................................................................................. 9-10
Storage and Transport ..................................................................... 9-11
Appendixes ................................................................................. A-1
Appendix A: Motor Nameplate and Field Test Data Form ........... A-1
Appendix B: Average Efficiencies for Standard and Energy Efficient
Motors at Various Load Points .................................................. B-1
Appendix C: Motor Energy Savings Calculation Form ............... C-1
Appendix D: Power Factor Correction Capacitor Suppliers ...... D-1

vii
Figures and Tables

Figures

1-1 Typical Energy Management Team Organization Chart


1-2 Steps in an Energy Management Program
2-1 Energy Use Profile Reports
2-2 Sawmill Energy Consumption Disaggregation
2-3 Billing Statement
2-4 Electric Demand Meters
3-1 Typical Facility Single-Line Diagram
3-2 Acceptable Voltage Range for Systems and Motors
3-3 Motor Voltage Unbalance Derating Curve
3-4 Effects of Voltage Unbalance on Motor Losses
4-1 Motor Nameplate
4-2 Industrial Three Phase Circuit
4-3 Instrument Connection Locations
5-1 Relationships Between Power, Current, Power Factor and Motor Load
5-2 Depiction of Motor Losses
7-1 Motor Performance at Part-Load
7-2 Motor Efficiency Improvement Action Plan
8-1 The “Power Triangle”
8-2 Power Factor as a Function of Motor Load
8-3 Locating Capacitors on Motor Circuits
8-4 Apparent Power Requirements Before and After Adding Power Factor
Correction Capacitors
9-1 Effect of Voltage Variation on Induction Motor Performance
Characteristics

viii Energy Management for Motor-Driven Systems


Tables

2-1 Sawmill Energy End Use Summary


3-1 Acceptable System Voltage Ranges
4-1 Typical Motor Load Types
4-2 Coupling Types
5-1 Induction Motor Synchronous Speeds
5-2 Characteristics of Motor Loads
7-1 Motor Repair Versus Replace Analysis
7-2 Existing Motor Replacement Analysis
7-3 Motor Downsizing Example
8-1 Industries That Typically Exhibit Low Power Factor
8-2 Sizing Guide for Capacitors on Individual Motors
8-3 Multipliers to Determine Capacitor Kilovars Required for Power
Factor Correction
9-1 Grease Compatibility

ix
Glossary for
Equations

The following variable names are used in equations in this publication:


Pi = Three phase power in kW
PJ = Power dissipated in a junction in watts
P2 = Corrected input power
P1 = Input power before correction
P Apparent = Apparent power in kVA
P Apparent1 = Apparent power before PF correction in kVA
P Apparent2 = Apparent power after PF correction in kVA
P Reactive = Reactive power in kVAR
P ir = Input power at full rated load in kW
Po = Actual output horsepower
P o2 = Corrected output power
P o1 = Output power before correction
P or = Nameplate rated horsepower
PF = Power factor as a decimal
PF1 = Original power factor
PF2 = Power factor after correction
V = RMS voltage, mean line to line of 3 phases
V maxdev = Line to line phase voltage deviating most from mean of
3 phases
VJ = RMS voltage across a junction
Vr = Nameplate rated voltage
I = RMS current, mean of 3 phases
IJ = RMS current through a junction
Ir = Nameplate rated current
kWh = Electric energy in kWh
kWh savings = Annual electric energy saved in kWh
kW billed = Adjusted or billable demand
kW demand = Measured electric demand in kW
k W saved = Savings from efficiency improvement in kW

x Energy Management for Motor-Driven Systems


kVA demand1 = kVA demand before PF correction
kVA demand2 = kVA demand after PF correction
N = Number of days in billing period
e = Efficiency as operated in %
e2 = Corrected efficiency
e1 = Efficiency before correction
e std = Efficiency of a standard motor as operated in %
e EE = Efficiency of an energy efficient motor as operated in
%
efl = Efficiency at full rated load as a decimal
Load = Output power as a % of rated power
S = Measured speed in RPM
Sr = Nameplate full load speed
Ss = Synchronous speed in RPM
Slip = Synchronous speed - Measured speed in RPM
hours = Annual operating hours
$ savings = Total annual dollar savings
$ demand = Monthly demand dollar charge
$ energy = Dollar charge per tailblock kWh
$ premium = Price premium for energy efficient motor compared
to standard
$ rebate = Utility rebate for energy efficient motor
$ new = New motor cost
$ inst = Installation cost
PB = Simple payback in years
% reduction = Percent reduction in distribution losses
R = Resistance in ohms
Unbal = Voltage unbalance in %

xi
xii Energy Management for Motor-Driven Systems
Chapter 1
Energy Management
for Motor-Driven
Systems
Introduction profits, industries that take
advantage of energy efficiency
This energy management guidebook opportunities often gain addi-
is designed to assist the industrial tional benefits such as:1-4
facility engineer to reduce energy n More productive state-of-the-
costs through: art-technology that improves
n Identifying and analyzing a facility’s competitive edge
motor driven system energy and improves global competi-
conservation opportunities, tiveness;

n Troubleshooting and tuning n Improved environmental


the in-plant electrical distribu- performance and compliance
tion system, with environmental and
pollution abatement regula-
n Correcting for power factor, tions; and
n Understanding utility billing n An enhanced public image as
statements, and an environmentally friendly
n Establishing a preventative or “green” company.
and predictive maintenance Energy management is not a one-
program. person responsibility or a one-
Why should industrial plant staff time investment in conservation
work to save energy? One answer measures. Energy management is
is money.1-1 Ever-increasing an ongoing effort marked by
utility costs reduce profits, erode gradual improvements in energy-
capital and maintenance budgets, efficiency.1-2 A successful energy
increase product costs, and management process is marked
reduce competitiveness. by:

A common misconception within n Maximizing production


industry has been to equate an efficiency,
energy reduction or conservation n Minimizing energy consump-
program with the concept of tion,
turning off equipment and shut-
ting down processes. Instead, the n Maintaining a high energy
program of energy management load factor,
challenges plant staff to produce
n Correcting for low power
the products or services with the
factor, and
absolute minimum energy con-
sumption.1-2 The objective is to n Acquiring and using economi-
minimize energy usage through cal supplies of energy.
production efficiency gains, while
procuring the lowest cost and Energy management does not just
most reliable supplies of fuel and happen. Effective energy man-
power. 1-3 agement occurs when the idea
and practices associated with
In addition to reduced energy energy management become part
costs and potentially increased of the “corporate culture.”

Energy Management for Motor-Driven Systems 1-1


Elements of a Successful The energy coordinator can be
likened to a coach: mobilizing
A rule-of-thumb is one Energy Management resources, providing sound
person-year for each Program advice, motivating others, and
$1 million of annual energy providing support. 1-1 The
expenditures. coordinator should be respon-
Energy-management consists of a sible for energy management
As progress is made, the
well structured team effort to activities such as:1-2
commitment can be create energy awareness: collect
reduced to one person-year and organize energy cost and n Making energy manage-
ment an integral part of
for every $2 - $5 million consumption data; identify,
analyze and implement energy every department.
spent annually.
conservation opportunities; and n Providing operators,
monitor results. The program foremen, and maintenance
must be accomplished without staff with tools they need
placing an undue burden on to be part of an energy
plant maintenance or engineering management team.
staff.1-2
n Analyzing trends in
Ten “Key Elements” that are energy use and efficiency
crucial to success of an energy and identifying areas of
management program are: concern.
n Informing plant manage-
1. Secure Top Management ment of roadblocks to
Commitment energy use reduction
Top management must be while suggesting ways to
committed to a motor-driven remove them.
systems energy conservation
n Stimulating interest in the
program.1-6 To a substantial
installation of energy
degree, management’s atti-
saving measures.
tude toward energy conserva-
tion will determine the suc- n Assisting in the develop-
cess of the energy plan.1-1 ment of energy use stan-
Management must be willing dards.
to provide both personnel and n Reviewing plans for plant
financial resources. expansions, process
Employees will apply their modifications, and equip-
best efforts to an energy ment purchases to ensure
conservation program only if that energy is used effi-
their management displays ciently.
awareness of the program’s n Directing the activities of
importance. 1-6 outside consultants, and
2. Appoint an Energy n Preparing monthly or bi-
Coordinator monthly facility energy
efficiency reports so that
A plant energy coordinator
management can be
should be appointed to guide
continuously updated on
energy management efforts.1-2
motor-driven system
The energy coordinator
improvements, energy
should have an energy back-
savings, and cost reduc-
ground with energy manage-
tions.
ment being a primary duty.1-7

1-2 Energy Management for Motor-Driven Systems


3. Obtain Employee 4. Conduct Energy Surveys
Cooperation An initial plant energy survey
The cooperation of operations shows where and how energy
and maintenance staff is vital is being used and/or wasted. 1-6
to the success of any energy An inventory of energy-using
management effort.1-2 In most equipment should be pre-
cases, the effectiveness of an pared, showing basic energy
energy improvement program use data (usually obtained
is proportional to the effort from equipment nameplates)
and time the energy coordina- and indicating typical running
tor and department represen- time and operating profiles.
tatives are allowed to spend Without basic audit informa-
on it.1-6 Recognize and sup- tion, it is impossible to tell
port internal “idea champi- whether equipment is operat-
ons”. An idea champion is the ing unnecessarily or waste-
prime mover: the person with fully. The basic survey infor-
the vision, desire, and persis- mation is also needed to set
tence to promote a conserva- standards, and to measure the
tion project or approach and performance of an individual
to see it through to comple- piece of equipment, a process-
tion.1-1 ing line, or a department.1-6
An energy committee should Survey information also assists
be established, with represen- the energy coordinator to
tatives from each department “target” and focus efforts on
expected to make recommen- the most energy-intensive
dations and conduct investi- equipment in a facility. Poten-
gations. Participants in an tial conservation savings are
energy committee help create greatest where losses are the
that “critical mass’ that is largest. Auditors should
crucial for success. A sense of concentrate on motor-driven
“ownership” develops com- systems where: 1-8
mitment.1-1 A typical energy
management team organiza- n The motor running time
tional chart is depicted in exceeds 1,000 hours per
Figure 1-1.1-6 year;

Figure 1-1 Typical Energy Management Team Organization Chart

Energy Management for Motor-Driven Systems 1-3


n Applications require larger n Determine the cost of
horsepower motors. energy wasted.
Typically, motors above 20
hp represent only 20 n Request that department-
percent of the overall level energy committee
motor population yet members develop proce-
consume 60 percent of dures to reduce waste or
motor driven equipment to identify barriers or
energy. equipment limitations
that prevent waste reduc-
n Loads are nearly constant tion.
and operation is at or near
the full-load point for the 5. Organize Energy Data
majority of the time. To convince plant manage-
n Energy and power or ment of the value of motor
demand charges are high. systems management, you
In some locations, energy must make them aware of
rates are as high as $.12/ energy’s impact on opera-
kWh. With higher electri- tions. High-energy costs may
cal rates, expenditures for not be perceived as a concern
conservation measures until energy costs can be
yield a much more rapid compared with other costs at
payback on investment. the facility level.1-1 In order
n Utility rebate or demand for energy conservation
management program opportunities to compete for
incentives exist. resources, top level managers
must understand the scope of
The initial physical plant survey the problem.
should be conducted department
by department. It should docu- The logical place to begin
ment wasteful operations and gathering information on
identify obvious sources of losses energy use is with utility bills.
that can be corrected immediately. Obtain a copy of your rate
The survey will also reveal where schedule from your electric
energy and/or process flow utility and determine whether
metering should be installed. alternative schedules are
(One rule of thumb states that in- available for your facility.
plant metering is economically Obtain electrical energy
justified when the annual cost of consumption and cost data
energy exceeds five times the cost for at least a one-year period
of the meter.)1-6 in order to establish a base
period. 1-5 Check whether
One survey approach is to:1-2 patterns exist in the use and
n Determine the energy cost of energy. Is the amount
consumption rates and of money spent for energy
costs for major equipment higher during certain portions
in each department. of the year? It is helpful to
graph energy use and costs
n Ask the department-level
using an energy accounting or
energy committee mem-
spreadsheet program.
bers to determine how
long equipment operates Chapter 2 shows you how to
and how long it is in interpret your utility’s rate
service without perform- schedule and use billing data
ing a useful task.

1-4 Energy Management for Motor-Driven Systems


to target potentially cost- 7. Set Conservation Goals
effective energy-conservation, Energy management programs
power factor correction and typically set yearly goals for
demand reduction opportuni- specific reductions in baseline
ties. energy intensity, usage, or cost.
Although realistic goals may
6. Analyze Survey Results be difficult to set initially, goals
After the plant energy survey are absolutely necessary.
is complete, construct energy Without goals, there is no
balances for each department, method for measuring perfor-
process, and piece of energy- mance. 1-2
consuming equipment in
your facility. An energy 8. Develop an Organization-
balance quantifies the total Wide Energy Management
energy output against the Plan
total energy supplied to a
Good energy management
system, indicating how
begins and ends with decision
effectively the supplied
makers. The energy manage-
energy is utilized.1-6 By
ment program, depicted in
comparison with process
Figure 1-2, illustrates informa-
requirements or known
tion necessary for making
energy intensity standards,
informed decisions. 1-9
you can detect whether
energy is being used ineffi- The energy management or
ciently and, if so, to what motor improvement plan
extent? On-line monitoring includes policies, goals, assign-
systems may have to be ments, training needs, an
installed to compute energy assessment of the costs and
balances at the department, benefits (energy savings,
process, or equipment level.1-6 demand reduction, productiv-
ity gains) associated with
Energy surveys and balances
conservation opportunities,
provide the basic information
implementation time-lines,
necessary for analyzing
and a description of feedback
energy conservation opportu-
and reporting mechanisms.
nities. The analysis is typi-
cally conducted by a plant
engineer and examines the 9. Implement Engineering
capital and installation costs, Changes
and annual energy and dollar Energy audits or technical
savings associated with assistance studies gathering
alternative conservation dust represent lost opportuni-
actions. The analyst must ties to save money.1-1 Imple-
address considerations such ment engineering changes!
as disruption of industry
operations, effect on product The energy-management plan
quality and yield, technologi- generally calls for identifying
cal risk, maintenance require- and implementing the most
ments, technology availabil- cost-effective measures first.
ity, vendor reliability, and Ideally, all measures meeting
training and skilled personnel the company’s return-on-
requirements. 1-4 investment criteria are funded.

Energy Management for Motor-Driven Systems 1-5


Often, however, the first step momentum to build, which is
in starting an energy manage- necessary to overcome
ment program is to install barriers and change an
measures that enable energy organization’s culture.
savings to build quickly.1-7
One approach to incremen-
This approach builds confi-
tally “growing” a compre-
dence and trust and allows
hensive program is to choose

Figure 1-2 Steps in an Energy Management Program

1-6 Energy Management for Motor-Driven Systems


a small, low-investment
project from your list of
Conclusion
possibilities that can be The average energy cost as a
charged to a routine mainte- proportion of manufacturing
nance budget. Once you have production costs is about three
selected a small project, percent. Historically, industrial
double check its payback. firms have viewed energy costs as
Errors can be embarrassing largely outside their control, and
and you are out to prove your as fixed costs that are not signifi-
and your energy committee’s cant enough to warrant special
abilities as energy managers. attention. Today, a host of en-
Complete the project and ergy-efficient technologies, tech-
thoroughly document costs, niques, and approaches has
performance and energy emerged and energy management
savings. Then submit a is being increasingly recognized
project summary to plant for its potential to improve the
management. Once you have “bottom line”. For example, if
completed the first project, energy represents three percent
choose another. Size doesn’t of production costs, and profits
matter. Once the two projects amount to 20 percent of produc-
have been successfully com- tion costs, then reducing net
pleted, approach plant man- energy costs by one-third can
agement with a larger en- result in a five percent gain in
deavor that cannot be fi- profits.1-4
nanced within maintenance
budgets. 1-10 Energy management is worth
pursuing, with the greatest
10. Monitor and Evaluate Re- benefit potential within energy-
sults intensive industries that have not
implemented aggressive energy-
Monthly, bi-monthly, or
efficiency programs in the past.1-4
quarterly reports of energy
use are essential feedback for
The level of effort justified de-
making the energy manage-
pends on how much money is
ment program visible to both
spent for energy each year. A
plant management and
rule-of-thumb is one person-year
department level staff. Evalu-
for each $1 million expended
ate conservation measure
annually. As progress is made
performance and periodically
and energy management becomes
report energy intensity, usage
the normal way of operating, the
and cost data so that manage-
level of involvement can be
ment “sees” the benefits
reduced to one person-year for
associated with conservation
every $2 - $5 million spent annu-
investments.
ally.1-2
Share success to build sup-
port. Make the program
visible. Monitoring data can
also provide recognition or
awards for exceeding energy
reduction goals or for exem-
plary performance or team-
work.

Energy Management for Motor-Driven Systems 1-7


References
Chapter 1

1-1 Washington Association of School Administrators,


“Energy Excellence in Public Schools.” Washington
State Energy Office

1-2 Wayne L. Stebbins, “Keeping the Energy Management


Process Alive,” Plant Engineering, June 3, 1993

1-3 J. Smith,“Developing a Coherent Corporate Energy


Strategy,” Energy Management and Environmental
Sourcebook, Proceedings of the 14th World Energy
Engineering Congress, October 23-25, 1991.

1-4 M.F. Hopkins, et. al., “Industrial Demand Side


Management: A Status Report,”Battelle Pacific
Northwest Laboratory, PNL-10567, May 1995

1-5 Thomas Bear and Karl Peters, “Getting an Energy


Management System Up and Running,”I&CS, July
1994.

1-6 “Energy Management for Industry” Electric Ideas


Clearinghouse Technology Update, Bonneville Power
Administration, February 1993

1-7 David L. Lewis, Washington State Energy Office


“Turning Rust into Gold: Planned Facility
Management,” Public Administration Review, Vol. 51,
No. 6, November/December 1991

1-8 Reliance Electric, “A-C Motor Efficiency: A Guide to


Energy Conservation,” B-7087-5

1-9 A & C Consultants, Inc., “Managing Energy in Local


Government Facilities,” Washington State Energy
Office, WAOENG-87-07, March 1987

1-10 “Selling Energy Management,” Energy Access


Washington State Energy Office, WAOENG-89-47,
September 1989

1-8 Energy Management for Motor-Driven Systems


Chapter 2

Understanding Your
Utility Bill
This section illustrates
The first step in reducing energy n Compare the energy efficiency various billing strategies that
costs is understanding where of your facility or process to
your energy dollars go.2-2 How similar facilities or processes.
may be applicable at your
much energy goes to lighting, air facility. Contact your utility
To initiate an energy accounting
conditioning, air compressors, or program: account representative for
to refrigeration systems? What detailed information about
n Locate all meters and
portion of the electrical bill is for
submeters within a facility. your rate schedule.
electrical energy consumption
(kWh) versus peak power de- n Determine which building or
mand (kW)? Are demand process is served by each
charges ratcheted, i.e. monthly meter.
charges linked to the highest n Obtain copies of all utility bills
power draw over the preceding for at least a one-year period.
year? Is a power factor penalty n Obtain monthly and annual
or kVA charge levied? Are rates feedstock, production, or
seasonally differentiated or throughput data at the facility
higher during certain periods of and/or process level.
the day? Is a declining or in-
verted block structure used for n Sort utility bills by building
assessing energy charges? The and/or meter, and organize
answers to these questions tell bills into 12-month blocks
you where to look for both using meter read dates.
energy and dollar savings. 2-2 n Organize historical energy
and production data so that
Organizing Utility Bills energy management perfor-
and Production Data mance can be measured
against a baseline year. Typi-
Energy accounting involves cally, the year prior to initiat-
recording and analyzing both ing an energy management
energy use and cost data. This program is selected as the
process helps you:2-3 baseline. 2-3
n Account for current energy n Ensure that your facility is on
use, the proper utility rate sched-
n Identify or target areas with ule. Often, electrical utilities
the greatest savings potential, offer different schedules —
such as General Service, Large
n Justify capital expenditure General Service, Primary
decisions, General Service, High Voltage
n Observe the results of conser- General Service, or High
vation investments, Voltage Interruptible Service
n Gain management support, — based upon the type and
reliability of services pro-
n Detect consumption in- vided.2-1 The “best” schedule
creases, for your facility may change
n Identify billing errors; and over time.

Understanding Your Utility Bill 2-1


You can present information a unit of product. Information
Concepts of Power and typically presented in graphs
about your energy use in a
Energy graphical format as shown in includes: 2-3
Figure 2-1. Energy management n Electricity consumption by
The basic unit of power in electri- performance is often indicated in month (kWh) for a given
cal terms is the watt. Since this terms of 12-month rolling average facility, meter, or process
unit is very small, a unit one energy consumption. Because
n Electrical demand by month
thousand times as large (the industrial plants may expand or
(kW)
kilowatt) is frequently used. One undertake modifications to
increase production rates, the n Energy and demand costs
megawatt is one thousand kilo-
rolling average is typically nor- by month
watts. One horsepower is 746
watts or 0.746 kW. malized to reflect an energy- n “Rolling Average” energy
intensity ratio such as kWh/ consumption
square foot-year or kWh/unit of n “Rolling Average” energy
Power is the rate of energy use.
production per year. For indus- intensity (kWh/unit of
The amount of energy used by a trial facilities, energy efficiency is product)
motor-driven system is directly properly expressed as a reduction
proportional to the power draw of n Facility production by
in the energy required to produce month
the system times the length of
time it is in operation. Since Figure 2-1
power is expressed in kilowatts Energy Use Profile Reports
and time in hours, the conven-
tional unit of energy is kilowatt-
hours (kWh).2-1

Power and energy measurements


are used to determine loads on
equipment, energy consumption,
running costs, and to verify
proper system sizing and opera-
tion. To measure power, we use a
power meter or take advantage of
the fact that power is proportional
to the product of circuit voltage
(V) amperage or current (I) and
power factor (PF).2-1 For a three-
phase system:
V x I x PF x 3
Pi =
1 0 00
Where:
Pi = Three phase power in kW
V = RMS voltage, mean line
to line of 3 phases
I = RMS current, mean of 3
phases
PF = Power factor as a decimal

2-2 Energy Management for Motor-Driven Systems


In the rolling average method of Once a baseline energy consump-
energy accounting, you calculate tion profile is established, you can
billing data each month by drop- identify the load with the process
ping the oldest month from the and ultimately with the motor-
total and adding the newest. This driven equipment. You can then
method eliminates widely- begin to identify where to focus
fluctuating values due to variable your energy conservation efforts.
meter reading dates or seasonal A summary of energy end uses in
processes. It allows for simple a sawmill is given in Table 2-1 and
comparison of the present year’s shown in Figure 2-2. You should
energy use or energy intensity also examine seasonal loads,
with any previous year. A graph consumption trends, annual
of this type remains flat if no energy and cost savings, and
significant changes in energy anomalies or unexplained peaks
consumption or process efficiency in energy use or demand. Such
occur. 2-3 peaks may indicate equipment
malfunction or a meter reading
error. 2-3
Table 2-1.
Sawmill Energy End Use Summary

Process Electricity Use, kWh Percentage of Total Use Cost


Blowers 484,600 4.8% $12,115
Chippers 101,600 1.0% 2,540
Air Compressors 1,911,200 19.0% 47,480
Hog 76,700 0.8% 1,917
Hydraulic Motors 857,800 8.5% 21,445
Saw Motors 2,092,000 20.8% 52,300
Planer Motors 132,700 1.3% 3,317
Kiln Fans 2,033,800 20.2% 50,845
Boiler Fans 268,900 2.7% 6,722
Lights 376,400 3.7% 9,410
Misc. 1,741,390 17.3% 43,534
Totals 10,077,090 100.0% $251,925

Figure 2-2
Sawmill Energy Consumption Disaggregation

Understanding Your Utility Bill 2-3


Interpreting Utility used in calculating the kW
demand, total kWh consumption
Charges or total kVARh consumption is
Look at your electric bill. A on the front of the meter.
typical bill is shown in Figure 2-3. 6. Consumption - The actual meter
The bill tells you how much to reading multiplied by the meter
pay, but generally does not tell multiplier in units of kWh or
you where the total came from or kVARh. Reactive power is the
why. In fact, most bills include non-working power caused by
two, three, or four separate magnetizing currents required to
charges.2-1,2-2 These different operate inductive devices such as
charges vary widely from utility transformers, motors and lighting
to utility. Therefore, your strate- ballasts and is used as the basis
gies to reduce energy costs for power factor charges.
depend heavily upon the rate 7. Demand - This is the actual kW
structure applicable to your demand and is calculated by
facility. multiplying the kW meter reading
While your utility bill indicates by the meter multiplier. The
how much energy and power you demand kW shown is the highest
used, the rate structure is your kW recorded by the meter in any
guide for determining how costs one 15 minute period for the
are allocated and computed. 2-2 billing period.
Let’s examine the most common 8. Power Factor - The Power Factor
charges shown in Figure 2-3, a % shown on the bill is determined
sample monthly commercial/ from the kVARh consumption
industrial billing statement. The described above, along with the
descriptions below relate to real (working) power and appar-
numbers on Figure 2-3. ent (total) power. The actual
charge for power factor below
1. Service days - The number of
95% is calculated by multiplying
days in the billing cycle.
the kVARh consumption by the
2. Meter number - The number kVARh rate.
shown on the face of the meter.
9. Rate Code - This is the rate that
3. Meter type - You could have one applies to the meter number
or more of the following types of shown. For customers with
meters; multiple meters, more than one
A. Energy and Demand - this rate schedule may apply.
measures kWh (Kilowatt- 10. Unit Charge - The rate being
hours) and kW (Kilowatt), charged for the rate code shown.
B. Reactive Energy only - this If the rate is not shown, you have
measures kVARh (Kilovolt- a time-of-use meter. In this
amp-hour reactance) which circumstance, a second statement
is used to bill for power is included with your bill which
factor less than 95%, and shows the off peak and on peak
C. Energy, Demand, and Power schedule charges.
Factor - this meter has the 11. Service Charge - A monthly
capability to measure all charge often referred to as the
three. basic, facilities, or customer
4. Meter Reading - The actual charge. It is generally stated as a
reading taken from the meter. fixed cost based on transformer
size.
5. Multiplier - This meter multiplier

2-4 Energy Management for Motor-Driven Systems


Service Charge Energy Charge
This monthly charge is often All rate schedules include an You may be able to lower
referred to as the basic, facilities, energy charge.2-2 The energy your plant’s electricity costs
or customer charge. The service charge is based upon the total by revising operating
charge is designed to recover number of kWh consumed over schedules, replacing ineffi-
fixed utility costs associated with the billing period. Many utilities cient equipment, or selecting
activities such as operations and offer energy charges that are a different utility rate
maintenance, administration, seasonally differentiated while schedule that better fits your
metering, and billing. It is gener- some offer rates which vary with pattern of electricity use.
ally stated as a fixed cost based on the time of day. Some utilities
transformer size. Some utilities charge the same rate for all kWh Ask your electric utility
establish a minimum billing used, while others charge differ-
representative for printed
amount or offer a variable service ent rates for different quantities or
rate schedules that describe
charge which is dependent upon “blocks” of energy. You should
peak demand. 2-2 Typical service use the “tailblock” or marginal the various rates available
charge structures are given in energy cost when calculating the and illustrate how charges
Example 1. feasibility of conservation invest- are calculated. Most electric
ments. utilities are willing to change
Example 1: Basic Service Charge a customer’s rate schedule
With a declining block schedule,
Structures free of charge.2-4
the charge per kWh is reduced for
n Basic monthly charge: each successive block, making the
$760 cost-per-unit less when more
n Facilities charge: electricity is used.2-1 With an
$2,865 per month “inverted” block structure, the
unit price increases for each
Figure 2-3
Billing Statement

Understanding Your Utility Bill 2-5


incremental block. Consolidate ten-second start-up of a motor (or
Ratcheted Demand meters to take full advantage of start-up of motors after a power
Charges declining block rate schedules. A outage) can significantly affect
sample declining block rate demand. Eliminate spikes by
Some utilities use what is structure is depicted in Example 2. sequencing the start-up of large
motors so that their peak de-
called a “ratchet” clause. The
Example 2: Declining Block Rate mands are staggered.
concept is that the demand Structure
charge should reflect the n 3.636¢ per kWh for the first
generating, transmission, and Types of Demand Charges
40,000 kWh
distribution capacity required Direct Demand Charges
to meet your peak demand 3.336¢ per kWh for all addi-
over the year, not just for the tional kWh You may be billed directly for
current billing period. For demand charges at a rate from
example, your monthly Demand Charge less than $2/kW per month to
over $25/kW, depending upon
demand charge may be the Peak demand charges can account your utility.2-2 In the Northwest,
greater of the metered de- for half of the electric bill in an both demand and energy charges
mand or a percentage of the industrial plant. Demand is a are higher in the winter months
greatest demand recorded charge based upon your maxi- than the summer months.
during the preceding 11 mum or peak rate of energy use.
months. With this type of The demand charge is designed to Like energy, demand charges may
recover utility costs associated be levied in a declining or in-
rate structure, indicated in
with providing enough generat- verted block structure. Some-
Example 6, abnormal electri-
ing, transmission and distribution times the initial block is offered at
cal consumption from using no charge, with a fixed charge
capacity to meet your peak electri-
backup equipment during an assessed for all demand exceed-
cal load.
upset period or from a plant ing the minimum value. Typical
restart can affect charges over A typical demand meter averages rate schedule language for direct
an entire year. demand over a specified “demand demand charges is illustrated in
interval,” usually 15 or 30 min- Example 3.
utes. (In this instance, short
periods of intense use, such as a Example 3: Direct Demand Charge
ten-second start-up of a motor, n For each kW of billing demand
have little or no effect on de-
Winter Summer
mand.) At the end of each inter-
$1.69 $1.13
val, the meter resets to zero and
the measurement begins again. 2-2 n All kW of maximum demand
The meter, however, stores or between 7:00 a.m. and 10:00
records the largest average de- p.m., Monday through Friday at
mand interval in the billing $1.16 per kW
period. “Sliding window” de-
mand meters record demand and Demand Incorporated Into
then scan for the largest demand Service Charges
interval regardless of starting
time.2-2 You are then billed for a Some utilities incorporate a
peak demand that is somewhat demand component into their
higher than that obtained with a basic charges. Others vary the
conventional meter. A demand basic charge based upon the
meter is depicted in Figure 2-4.2-3 facility demand. This type of rate
structure is indicated in Example
A few utilities base their demand 4. This charge may be in addition
charge on a facility’s instanta- to other demand charges. 2-2
neous peak. In this case, short
periods of intense use such as a

2-6 Energy Management for Motor-Driven Systems


Example 4: Incorporation of Demand Racheted Demand Charges
into Basic or Service Charges
Some utilities use what is called a Reduce ratchet charges by
n If load size is over 300 kW: $115
“rachet” clause. The concept is reducing your maximum
+ $0.80 per kW
that the demand charge should demand. For example,
reflect the generating, transmis- avoid simultaneously
Linkage of Demand and Energy sion, and distribution capacity operating large pumps and
Charges required to meet your peak compressors that are needed
Some utilities have rate schedules demand over the year, not just for only occasionally. Carefully
that include demand payments in the current billing period. For plan when to operate large
their energy charges. The energy example, your monthly demand
equipment during the
charge in this case is broken into a charge may be the greater of the
months of your greatest
block structure where block size metered demand or a percentage
of the greatest demand recorded electric demand. The more
varies according to facility de- level your month-to-month
mand. For instance, you might during the preceding 11 months.
With this type of rate structure, demand, the closer you will
pay a higher rate for the first 100
indicated in Example 6, abnormal come to paying only for
kWh per kW of demand, with a
lower rate for all additional electrical consumption from using actual demand each
energy use. This type of rate backup equipment during an month.2-4
structure is depicted in Example 5. upset period or from a plant
restart can affect charges over an
Example 5: Linkage of Demand and entire year.
Energy Charges
Example 6: Ratcheted Demand
n 6.510¢ per kWh for the first 85 Charges
kWh per kW of demand but for n The minimum charge is 100
not less than the first 1,000 kWh percent of the maximum demand
4.199¢ per kWh for the next charge established during the
8,000 kWh preceding eleven months.
3.876¢ per kWh for all additional n Billing months of April through
kWh November: the highest demand
n 2.815¢ per kWh for the first 200 established during the month,
kWh per kVA of demand but not but not less than 60 percent of
less than 1,000,000 kWh the highest demand established
2.394¢ per kWh for all additional during the previous winter
kWh season.

Figure 2-4
Electric Demand Meters

Understanding Your Utility Bill 2-7


Minimum Demand Charges ness of power factor correction
actions are given in Chapter 7.
If you are on a time-of-use rate, Some utilities build a minimum
shift as many operations to off- monthly charge into their assess- Utilities generally assess a penalty
peak as possible. Significant ment of demand charges. With for low power factor. Various
investments in added equipment this type of rate structure, given methodologies exist for calculat-
may be justified by savings in in Example 7, energy conserva- ing the penalty. You need to
energy and demand charges. You tion or demand-limiting measures understand your utility’s calcula-
may be able to use automation to would produce no additional tion method in order to determine
benefit once the monthly demand the benefits associated with
control start-ups, minimizing the
drops below the minimum value. potential power factor improve-
need for additional people to work
ments.
during off-peak hours. Example 7: Minimum Demand
Charges
If your facility is not on a time-of- n $5,500 for the first 3,000 kVA or
Types of Power Factor
use rate, find out whether your less. $1.10 for each additional Penalties
electric utility offers such rates. kVA.
You may be able to reduce costs
n The highest average 30-minute kVA Billing
by switching to time-of-use rates. demand recorded during the
As shown in Example 8, the
month, or 4,400 kVA, whichever
utility may measure and bill for
is higher.
every kilovolt-amp of apparent
power or primary period (peak)
Power Factor Charges kVA supplied, including reactive
Inductive motor loads require an current.
electromagnetic field to operate.
Reactive power, measured in Example 8: kVA Billing
kilovolt-amperes reactive, circu- n Demand charge: $2.49 per kVA
lates between the generator and of billing demand
the load to excite and sustain the
n Primary kVA charge: $24,000
magnetic field. Reactive power
which includes 2,000 primary
does not perform “work” and is
kVA plus $12.10 for each addi-
not recorded on the utility’s
tional primary kVA.
energy or demand meters, yet the
utility’s transmission and distri-
bution system must be large Direct Reactive Energy Charges
enough to provide it. Working As indicated in Example 9, reac-
power, measured in kW, and tive power may be measured and
reactive power together make up a reactive energy charge levied (in
the apparent power (measured in ¢/kVARh).
kilovolt-amperes or kVA).
Example 9: Direct Reactive Energy
Power factor is the ratio of work- Charges
ing power to apparent power. n Reactive power charge: 0.061¢
Power factor measures how per reactive kilovolt ampere-hour
effectively electricity is being (kVARh)
used. A high power factor indi-
cates the efficient use of electrical
Demand Billing with a Power
power, while a low power factor
indicates poor utilization of the Factor Adjustment
incoming electrical current sup- In the following calculation the
plied by the utility.2-6 Techniques utility bills at normal demand
for sizing and locating power rates with a demand surcharge or
factor correction capacitors and multiplier included to account for
for determining the cost-effective- low power factor.

2-8 Energy Management for Motor-Driven Systems


Equation 2-1 Demand Charges
n The maximum 15-minute
kW dem and x 0.95 Find out whether your electric
kW = reactive demand for the month in
billed
PF kilovolt amperes in excess of 40 utility offers “interruptible,”
Where: percent of the kilowatt demand “curtailment,” or “customer
for the same month will be billed generator” rates. If you are
kWbilled = Adjusted or billable at 45¢ per kVAR of such excess thinking of using an emer-
demand reactive demand. gency generator on a regular
kWdemand= Measured electric basis, analyze operating
demand in kW Optional Rate Schedules conditions as well as your
ability to maintain the genera-
PF = Power factor as a Time-of-Use Rates tor. Talk with your account
decimal
By charging more during the peak representative about a load
Given a facility power factor of 84 period, when incremental costs management agreement.
percent, the utility would obtain a are highest, time-of-use utility
13 percent increase in billable rates send accurate marginal-cost
demand. price signals to customers. Peri-
ods of heavy electricity use are
typically defined as “peak” hours;
Example 10 shows a rate schedule periods of lower use are “shoul-
with a penalty for facilities oper- der” hours, with times of lowest
ating below a 95 percent power use deemed “off-peak.” Energy
factor. charges between peak and off-
peak times might vary by over
Example 10: Demand Billing with 10¢/kWh.
a Power Factor Adjustment
n The demand charge, before Similarly, your demand charges
adjustment for power factor, will may be computed at a much
be increased 1 percent for each 1 higher rate if your highest-de-
percent by which the average mand interval occurs during the
power factor is less than 0.95 “peak” hours. 2-4
lagging.
Interruptible, Curtailment, and
Excess kVar Reactive Demand Customer Generator Rates
Charges Upon request from the electric
With this method the utility utility, customers on interruptible
imposes a direct charge for the rates must lower their demand.
use of magnetizing power in They can do this by turning off
excess of some percentage of kW some or all of their large electri-
demand. For example, if the cally-driven equipment or they
charge was 60 cents per kVAR for can use emergency generators or
everything over 40 percent of kW, engine-driven pumps instead of
and a 4,000 kW peak load existed, utility-supplied power. 2-4
then the utility would provide up To obtain interruptible, curtail-
to 1,600 kVAR at no cost. Excess ment, or customer generator
kVAR is billable at the specified rates, the customer enters into a
rate. This type of rate structure is load management agreement to
illustrated in Example 11. interrupt or reduce plant loads at
the request of the power company
Example 11: Excess kVAR Reactive during the occasional times of
peak demand. In return, the

Understanding Your Utility Bill 2-9


power company applies lower With energy data in hand, you
Ask your utility account represen- rates to the demand charge on the can assess the feasibility of
tative the following questions:2-4 bill for the duration of the agree- demand management measures
ment. Penalties for nonconfor- by computing the facility load
n What other rate schedules mance, however, are high. 2-4 factor. Load factor is the ratio of
are available for the plant? your facility’s average to peak-
demand and indicates how
Would they be less costly?
effectively demand is allocated.
Using Billing Data to Calculate your monthly load
n What are the months in the
power company’s “peak
Identify Opportunities factor for a 12-month period so a
minimum, maximum, and annual
season?” Understanding your electric average can be determined.2-5 A
utility bill — knowing how your sample load factor calculation is
n Do time-of-use rates exist? demand meter works and how given in Example 12.
How are the peak, shoulder power factor penalties are as-
and off-peak periods defined sessed — is crucial for the energy If your load factor varies signifi-
and what are the corre- coordinator. Energy and demand cantly from billing period to
costs are controllable, and the billing period, your operation
sponding energy costs?
benefits of implementing energy should be carefully reviewed. If
conservation, demand manage- your annual load factor is less
n Is there a ratchet clause? ment, or power factor correction than 80 percent, opportunities for
Which months in the past are directly related to the way in-plant demand reduction
year were affected by the your facility operates and the measures might exist. In contrast,
ratchet clause? What was structure of your rate schedule. if your facility has a load factor
the additional annual cost? While power factor correction is which is constantly above 80
not generally undertaken for percent, there is likely little
n What was the peak month energy conservation reasons potential for demand-limiting
kW demand? How much (power factor correction does measures in your plant. 2-5
lower must it be to elimi- result in a reduction in electrical
nate ratchet charges in the resistance or I2 R losses within the If your facilities have low load
plant distribution system), it can factors, you must determine the
future?
be very cost-effective and result in load profile — or load variation
significant reductions in your by time of day or month — for
n Are there any power factor utility bill. major processes or pieces of
penalties in effect for this
plant? What is the annual
cost? Example 12: Determining Your Load Factor

kWh
n Is a “customer generator” LF = x 100%
or other load management
kWdemand x 24 x N
Where
rate available? What are
LF = Load factor in %
the requirements? What are
the benefits? kWh = Electric energy in kWh
kWdemand = Electric demand in kW
N = Number of days in billing period
Sample Billing Information —
Energy Use Demand Period
1,132,000 kWh 2,880 kW 30 Days
Sample Load Factor Calculation —
1132
, ,000
LF = x 100% = 54.6%
2,880 x 24 x 30

2-10 Energy Management for Motor-Driven Systems


equipment within the plant.
Compile load data through
Checklist for Electricity
conducting periodic measure-
ments at a predetermined sam- Cost Savings
pling rate or by installing continu-
ous metering or data logging ✓ Compare rate schedules
equipment. and use the one best
suited to your operation.
Finally, you must be familiar with
a host of energy conservation as
well as demand management ✓ Train operators and
approaches. Demand manage- maintenance workers to
ment requires that you know how be aware of the time of
and why tasks are performed at day for utility on-peak
specific times; you can then charges. Run motors
determine whether any jobs can and other electric loads
be scheduled at a different time off-peak whenever
with little or no effect on produc- possible.
tion.2-5 You must also understand
the weekly demand profile in
✓ Encourage routine
each season to determine whether
energy-saving practices
opportunities exist to reduce peak
demand or shift load to off-peak and follow recommended
periods. maintenance procedures.

Demand control measures include ✓ Use sequenced start-ups,


energy conservation measures and avoid scheduling
plus equipment scheduling, load periodic equipment
shedding, time clocks and duty testing during peak
cyclers, interlocks, programmable hours.
controllers, energy management
systems, adjustable speed drives, ✓ Install capacitors to
and the use of emergency genera-
reduce power factor
tors to displace large loads during
charges.
peak demand periods. 2-5
✓ Use standby generators
to reduce peak demand.2-4

Understanding Your Utility Bill 2-11


References
Chapter 2
2-1 A & C Consultants, Inc., “Managing Energy in Local Gov-
ernment Facilities,” Washington State Energy Office,
WAOENG-87-07, March 1987

2-2 Washington Energy Extension Service, “Under-


standing Commercial Electric Bills,” January 1986

2-3 “Energy Accounting,” Electric Ideas Clearinghouse


Technology Update, Bonneville Power Administration,
November 1991

2-4 Electric Power Research Institute, “Understanding Your


Electric Bill: Cost-Saving Strategies for Industrial and
Large Electric Power Consumers,” BR-104028, 1994.

2-5 “Electrical Demand Control For Industry” Electric Ideas


Clearinghouse Technology Update, Bonneville Power
Administration, February 1993

2-6 “Power Factor Correction: A Guide for the Plant


Engineer,” Commonwealth Sprague Capacitor, Inc., PF-
2000E, October 1991

2-12 Energy Management for Motor-Driven Systems


Chapter 3
Industrial Electrical
Systems
The plant energy coordinator is distribution system voltage.
the person who can be most Additional transformers may be
effective in increasing electrical present to reduce the distribution
energy efficiency in the plant. voltage to a motor’s nominal
However, in order to do so, the voltage, i.e. 480 volts. The utiliza-
energy coordinator needs some tion voltage, the voltage value at
basic measurement tools and an the motor leads, is the nominal
understanding of how induction voltage less the voltage drops
motors relate to the in-plant between the points of transforma-
electrical distribution system. tion and end use. The single-line
diagram in Figure 3-1 shows the
The electrical utility delivers
service voltage, distribution
power to the industrial user at a
voltage, and utilization voltage
specified service voltage. A step-
values.
down transformer converts the
utility voltage to the in-plant

Figure 3-1
3-6
Typical Facility Single-Line Diagram

Source: Thumann, Albert, P.E., 1991, p.22

Industrial Electrical Systems 3-1


system is brought into compli-
ance. Service voltage correction
usually begins by contacting the
The Plant Electrical serving utility.
Voltage Definitions
Distribution System
Utilities are concerned with Figure 3-2 illustrates the relation-
All voltages are phase-to- meeting two principal criteria ship between system voltage and
phase voltage, unless specifi- when they supply power to their motor voltage.
cally designated otherwise. customers. First, the utility strives
to deliver power at a voltage that In most northwest industrial
is within an acceptable voltage facilities the nominal in-plant
■ Service Voltage
range. Second, the utility makes voltage is 480V. Delta type elec-
describes the voltage
efforts to provide polyphase trical systems always refer to “line
value at the point to line” voltage values. “Wye”
(three phase) power where the
where the utility type electrical systems refer to
phase-to-phase voltage is bal-
delivers service to the anced or close to being the same “line to line” and “line to neutral”
industrial user. between all phases.3-1 voltage values. One will fre-
quently see a voltage described as
■ Nominal Voltage Over and Under Voltage 277/480. This means that the
describes the general voltage from the line-to-neutral is
The utility is obligated to deliver 277V and the voltage from line-to-
voltage class that
power to the 480V industrial line is 480V.3-1
applies to the system, user’s service entrance in the
i.e., 120V, 240V, 480V. range from a low of 456V to a Usual utilization voltage condi-
high of 504V (480 ± 5%). In tions, defined in the National
■ Utilization Voltage practice, the service voltage is Electrical Manufacturers Associa-
describes the value of usually maintained within a tight tion (NEMA) Standards Publica-
voltage at the motor range. It is common to experience tion MG 1-1993, Rev. 1, Motors and
leads. the service voltage remaining in a Generators, include operation
range of 475V to 485V.3-2 within a tolerance of ± 10 percent
of a motor’s rated voltage.3-2
Acceptable in-plant distribution
system delivery voltage values as The custom by NEMA members is
defined by IEEE and ANSI stan- to rate motors at 95.8 percent of
dards are summarized in Table 3- nominal system voltage. For
1.3-2 When the average of the example, motors intended for use
three-phase voltages exceeds the on 480V systems are rated at 460V
value ranges in Table 3-1, the (95.8% x 480V) and motors in-
system is out of compliance. No tended for use on 240V systems
field measurements or analysis are rated at 230V (95.8% x 240V).
should be undertaken until the Motors can be allowed to operate

Table 3-1
Acceptable System Voltage Ranges

Nominal Allowable Allowable


System Voltage Limits % Voltage Range

120V (L - N) ± 5% 114V - 126V

240V (L - L) ± 5% 228V - 252V

480V (L - L) ± 5% 456V - 504V

3-2 Energy Management for Motor-Driven Systems


on voltages as low as 95.6 percent operation. Low voltages can also
of their specified voltage rating. prevent the motor from develop-
Thus, a motor rated at 460V can ing an adequate starting torque. 3-2
operate at 440V (460V x 0.956). As
long as the phase-to-phase volt- Voltage Unbalance
ages are balanced, the motor need
A voltage unbalance occurs when
not be derated.3-1
there are unequal voltages on the
lines to a polyphase induction
If the voltage at the motor feeder motor. This unbalance in phase
is increased, the magnetizing voltages causes the line currents
current increases. At some point, to be out of balance. The unbal-
depending upon design of the anced currents cause torque
motor, saturation of the core iron pulsations, vibrations, increased
will increase and overheating will mechanical stress on the motor,
occur. At about 10 to 15 percent and overheating of one and
over voltage both efficiency and possibly two of the phase wind-
power factor significantly de- ings. Voltage unbalance has a
crease for standard efficiency detrimental effect on motors.
motors while the full-load slip Motor efficiency suffers when
decreases. The starting current, motors are subjected to significant
locked rotor torque, and break- voltage unbalances. When
down torque all significantly efficiency falls, energy drawn by
increase with over voltage condi- the motor dissipates as heat in the
tions. core and in the windings. Useful
torque at the shaft is reduced.
If a motor is operated under
voltage, even within the allow- Ultimately, the motor can fail
able ten percent limit, the motor from insulation breakdown.
will draw increased current to Figure 3-3 is a derating curve
produce the torque requirements published by NEMA. The
imposed by the load. This causes amount of derating for a motor is
an increase in both stator and described by the curve as a
rotor I2R losses, and overheating function of voltage unbalance.
at full-load or service factor

Figure 3-2
Acceptable Voltage Range for Systems and Motors

Industrial Electrical Systems 3-3


Figure 3-3
Motor Voltage Unbalance Derating Curve

Unbalance of more than one NEMA defines voltage unbalance


percent requires that a motor be as 100 times the maximum devia-
derated and may void a tion of the line voltage from the
manufacturer’s warranty. NEMA average voltage on a three-phase
recommends against the use of system, divided by the average
motors where the unbalance is voltage (see example below).
greater than five percent.3-1, 3-2, 3-3 Most utilities attempt to control
the service voltage unbalance to
less than two percent.
Example 3-1
Determining Voltage Unbalance
Voltage unbalance is defined by NEMA as 100 times the maximum
deviation of the utilization voltage from the average voltage on a
three-phase system divided by the average voltage.
maxdev -V
Unbal = 100 x V
V
Where:

Unbal = Voltage unbalance in %


V = Line to line phase voltage deviating most
maxdev
from mean of 3 phases
V = RMS voltage, mean line to line of 3 phases

For example, if the measured line-to-line voltages are 462, 463,


and 455 volts, the average is 460 volts. The voltage unbalance is:

(460-455)/460 x 100%=1.1%

3-4 Energy Management for Motor-Driven Systems


With a well-designed electrical uled downtime, and lost produc-
distribution system in the plant, tivity. Safety Considerations
the amount of unbalance at the
load and motor control centers See the Bonneville Power Admin-
should be about the same as the istration publication, Keeping the This guidebook discusses the
degree of unbalance at the service Spark in Your Electrical System: An type of measurements the
entrance. When the unbalance is Industrial Electrical Distribution electrician must take. The
significantly different at the load System Guidebook, for additional guidebook is not meant to
centers, there is a phase voltage information. instruct a person on how to be
drop problem between the service an electrician, nor is it meant
entrance panel and the load You can improve efficiency to train a person in proper
centers. The unbalancing prob- through eliminating common safety techniques. The
lems must be found within the problems such as poor contacts, guidebook assumes instruc-
plant and corrected prior to voltage unbalance, over and tions will be followed by
recording motor data.3-1, 3-3 under voltage, low power factor, qualified electricians who are
undersized conductors, and
trained in safety practices
A utility attempts to load indi- insulation leakage. 3-4, 3-5 You
regarding industrial electrical
vidual phases in a balanced should troubleshoot and correct
fashion through the process of the in-plant distribution system systems. Persons who are not
alternating single phase loads and before taking field data measure- properly qualified in indus-
other similar practices. An indus- ments. trial electrical techniques
trial user must also exert an effort should not attempt to take
to balance loads. Analytical Begin the electrical distribution any measurements.
techniques for balancing loads are system tune-up with a search for
straightforward and are discussed and correction of poor contacts,
in the Troubleshooting and since these are most likely to
Tuning Your In-Plant Distribution result in a catastrophic system
System section of this chapter. failure and possibly a fire. Cor-
rection of poor power factor is the
A qualified person should take next step, since this is generally
utilization voltage measurements the source of the greatest utility
at each motor control center or cost savings. The system should
principal motor feeder. When a then be examined for voltage
utilization voltage unbalance is unbalance and over/under
in excess of one percent, the voltage conditions due to their
system can benefit from voltage detrimental effect on motor
correction. The effect of unbal- performance and motor life.
ance not only distorts potential Finally, survey for insulation
energy savings, but it may cause leakage and undersized conduc-
irreparable damage to equip- tors. 3-4
ment. 3-1, 3-3
Troubleshooting Poor Contacts
Troubleshooting and The first step in optimizing your
Tuning your In-Plant industrial electrical distribution
system is to detect and correct any
Distribution System problems due to poor connec-
Maintenance of in-plant electrical tions. High temperatures are
distribution systems is often commonly caused by loose and
neglected, with increased costs dirty contacts. Such contacts are
ultimately being paid in the forms found in switches, circuit break-
of decreased safety (due to in- ers, fuse clips, and terminations.
creased fire hazard), decreased These problems are the most cost
motor life, increases in unsched- effective to correct. Poor contacts
can be caused by:3-4

Industrial Electrical Systems 3-5


■ Loose cable terminals and bus vidually testing each component.
bar connections. Use extreme caution and wear
■ Corroded terminals and lineman’s gloves. Voltage drop
connections. measurements are taken first
from the main distribution
■ Poor crimps or bad solder joints. panel to the motor control
■ Loose, pitted, worn, or poorly center, then from the
adjusted contacts in motor motor control center to the motor
controllers or circuit breakers. leads. An example for a typical
■ Loose, dirty, or corroded fuse motor circuit is to measure the
clips or manual disconnect voltage drop from the bus bar to
switches. the load side of the motor starter.3-4

Detection should begin with Comparing the magnitude of


either infrared thermography or a voltage drop with other phases
voltage drop survey of the power supplying the load can alert the
panels and motor control centers. electrician to poor connections.
Advantages of a voltage drop The electrician can make compo-
survey are that the survey can be nent-by-component voltage drop
done in-house with existing measurements on suspect circuits
equipment and that problems can to isolate and eliminate poor
often be detected before they connections. 3-4
would be with infrared thermog-
raphy. Voltage drop measure- Infrared Thermography
ments should be taken at a time
when the plant is heavily loaded. 3-4 Infrared thermography is a quick
and reliable method for identify-
During the voltage drop or ing and measuring temperatures
infrared survey, the electrician can of components operating at
visually inspect suspected trouble unreasonably elevated tempera-
areas for: 3-4 tures. High temperatures are a
■ Discoloration of insulation or strong indication of both energy
contacts. wastage and pending failure.
High resistance connections are
■ Compromised insulation
self aggravating since they gener-
ranging from small cracks to
ate high temperatures which
bare conductors.
further reduce component con-
■ Oxidation of conductor ductivity and increase the operat-
metals. ing temperature. 3-4
■ Presence of contaminants
Once the infrared survey is
such as dirt.
complete, the plant electrician can
■ Mismatched cables in com- focus on the located hot spots. A
mon circuits. millivolt meter or milliohmmeter
■ Aluminum cables connected is recommended for measuring
to lugs marked for copper the voltage drop and resistance,
wire. respectively, across high tempera-
ture connections and connections
not shown on the thermographs.
Voltage Drop Survey These measurements can be used
A voltage drop survey can be to determine if the hot spot
done with a simple hand-held indicated in the infrared image is
millivolt-meter. You can use a due to a problem with the compo-
two-stage process to quickly nent itself or if heat is being
identify problems without indi- radiated from an adjacent source.3-4

3-6 Energy Management for Motor-Driven Systems


Troubleshooting Voltage ■ Highly reactive single-phase
Unbalance loads such as welders.

Further efforts to optimize your ■ Irregular on/off cycles of large


electrical distribution system loads such as arc furnaces or
should include a survey of loads major banks of lights.
to detect and correct voltage ■ Unbalanced or unstable
unbalances. Unbalances in excess polyphase supply from the
of one percent should be corrected grid.
as soon as possible. A voltage
The following problems may be
unbalance of less than one per-
more critical in nature, resulting
cent is satisfactory.
in two-phase operation 3-4:
Figure 3-4 displays motor loss
■ An open phase on the pri-
increases caused by voltage
mary side of a three-phase
unbalance. Left uncorrected, the
transformer in the distribution
increased losses require motor
system.
derating per Figure 3-3. The
following causes of voltage ■ Single phase-to-ground faults.
unbalance can be detected by ■ Failure or disconnection of
sampling the voltage balance at a one transformer in a three-
few locations:3-4 phase delta-connected bank.
■ Selection of wrong taps on the
■ Faults, usually to ground, in
distribution transformer. the power transformer.
■ Presence of a large, single-
■ A blown fuse or other open
phase distribution trans-
circuit on one or two phases
former on a polyphase sys-
of a three-phase bank of
tem, whether it is under load
power-factor correction
or not.
capacitors.
■ Asymmetrical (unbalanced)
transformer windings deliver- ■ Certain kinds of single-phase
ing different voltages. failures in adjustable fre-
quency drives and other
■ Faulty operation of automatic
motor controls.
equipment for power factor
correction.
■ Unbalanced three-phase loads Figure 3-4
(such as lighting or welding). Effects of Voltage Unbalance on Motor Losses
■ Single-phase loads unevenly
distributed on a polyphase
system, or a large single-phase
load connected to two con-
ductors on a three-phase
system.
■ Well-intentioned changes,
such as improvements in the
efficiency of single-phase
lighting loads, which inad-
vertently bring a previously
balanced polyphase supply
into unbalance (possibly
wasting more energy than
was saved).

Industrial Electrical Systems 3-7


The following problems can be Troubleshooting Over and Under
isolated to a particular circuit and Voltage
may require a load-by-load
Over or under voltage conditions
survey to detect:
can result from:3-4
■ Unequal impedances in
■ Incorrect selection of motors
power-supply conductors,
for the rated voltage. Ex-
capacitors, or distribution
amples include a 230 volt
wiring.
motor on a 208 volt circuit.
■ Certain kinds of motor defects.
■ Incorrect transformer tap
Constant loads can be checked by settings.
measuring voltage-to-ground on
■ Unequal branch line losses
each phase with a hand-held
resulting in dissimilar voltage
voltmeter. Highly variable loads
drops within the system.
may require simultaneous mea-
Often a panel will be supplied
surement of all three phases with
with a slight over voltage in
monitoring over time. Monitor-
the hope of supplying the
ing instruments can periodically
correct voltage to the motor
measure and record the voltage,
control centers (MCCs).
current, power factor, and total
However, voltage drop differ-
harmonic distortion on each
ences can result in an over
phase.
voltage at some MCCs while
Proper system balancing can be others are under voltage.
maintained by: 3-4 A common situation involving
■ Checking that unloaded under voltage occurs in applica-
transformer voltage balance tion of 208-230 volt motors on 208
does not exceed a minimum volt systems. Commercial build-
1.25 percent step per tap. ings frequently use 208 volt three-
phase power. It is the three phase
■ Checking and verifying line-to-line voltage corresponding
electrical system single-line to 120 volts line-to-neutral pro-
diagrams to ensure that vided for single phase lights and
single-phase loads are evenly receptacles. There is no change in
distributed. motor wiring connection for the
■ Regularly monitoring voltages two voltages. While 208-230 volt
on all phases to verify that a motors tolerate 208 volts, they are
minimal unbalance exists. optimized for the more common
230 volts.
■ Installing ground fault indicators.
■ Conducting annual infrared 208 volts is a nominal system
voltage; voltage at the motor
thermographic inspections.
terminals may even be lower.
■ Installing sensitive phase Additional losses occur when a
voltage monitors. 208-230 volt motor is operated at
or below 208 volts. The motor
will exhibit a lower full-load
efficiency, run hotter, slip more,
Before making changes to your
produce less torque, and may
distribution system, consider the
have a shorter life. It is best to
impact on the resulting phase-to-
supply 200 volt motors for use on
phase balance.
a 208 volt system, especially if
voltage at the motor terminals
sometimes falls below 208 volts.

3-8 Energy Management for Motor-Driven Systems


Until 200 volt motors can be standpoint of energy cost savings.
provided, it is recommended that However, the cost may be sub-
system voltage be tapped at the stantially less when done during
high end of the acceptable range expansion or retrofit projects.3-4
for single phase loads and that
distribution losses are minimized. Troubleshooting Insulation
System voltage can be modified by: Leakage
■ Adjusting the transformer tap Electrical insulation leakage can
settings. occur as a result of extreme
temperature, abrasion, moisture
■ Installing automatic tap-
or chemical contamination, and
changing equipment where
age.
system loads vary greatly
through the course of the day. Resistance is approximately
■ Installing power factor correc- halved for every 10°C tempera-
tion capacitors that raise the ture increase. Abrasion occurs
system voltage while correct- due to vibration or movement
ing for power factor. under magnetic forces such as
occurs with poorly secured end
turns in a motor’s winding. Some
Troubleshooting Low Power
of the worst chemical contamina-
Factor tion is that associated with
Analysis of utility bills will usu- electroconductive particles like
ally reveal if you have a power salt or coal dust. Moisture often
factor problem. Even if the utility intrudes when a motor has long
does not bill directly for power enough off time to completely
factor, a low power factor can cool and is in an environment
raise your kWh and demand with high relative humidity. Even
billing. This is because of real without such harsh threats,
power wasted in excess trans- insulation testing and trending, at
former and line losses associated least annually, is advisable.
with the flow of reactive power.
Correcting power factor will Insulation leakage can only be
reduce the line current and the detected by use of a
associated I2R losses in the entire megohmmeter. It is possible to
distribution system. A compre- perform testing at the motor
hensive discussion of power control panel so that cables are
factor including detecting and tested as well as the motor.
correcting low power factor is Cables are not usually a source of
presented in Chapter 8. significant leakage unless they are
very old and contaminated, but
Troubleshooting Undersized they provide easy electrical access
to the motor from the motor
Conductors control system. Information on
As plants expand, conductors performing insulation testing is
sized for the original load are provided in Chapter 9.
often undersized for the new
loads they are required to carry.
Undersized conductors present an
additional resistive load on the
circuit, similar to a poor connec-
tion. The cost of replacing or
supplementing these conductors
is often prohibitive from the

Industrial Electrical Systems 3-9


References
Chapter 3

3-1 Carroll, Hatch & Associates, Inc., “An Electric


Motor Energy Efficiency Guide and Technical
Reference Manual”, (Draft) June 1994,
Bonneville Power Administration, Revision 4,
April 1995 (Draft)

3-2 Gilbert A. McCoy and John G. Douglass, “Energy


Efficient Electric Motor Selection Handbook,” U.S.
Department of Energy, DOE/GO-10096-290, August
1996

3-3 Carroll, Hatch & Associates, Inc., “A Procedure for


Developing an Energy Efficiency Plan for the Use of
Electric Motors in an Industrial Setting,” (Draft) June
1994

3-4 “Electrical Distribution System Tune-Up,” Electric Ideas


Clearinghouse Technology Update, Bonneville Power
Administration, January 1995

3-5 Rob Gray, Washington State Energy Office, “Keeping


the Spark in Your Electrical System: An Industrial
Electrical Distribution Maintenance Guidebook,”
Funded by Bonneville Power Administration, U.S.
Department of Energy, PacifiCorp, Portland General
Electric and Tacoma City Light, October 1995

3-6 Albert Thumann, P.E., “Introduction to Efficient Electri-


cal Systems Design,” The Fairmont Press, Inc., GA, 1991.

3-10 Energy Management for Motor-Driven Systems


Chapter 4
Taking Field
Measurements
Field evaluation of motors is conflicts with your company
essential in making informed safety procedures, conflicts with
decisions regarding motor selec- your safety training, creates
tion and use. The amount of exposure beyond your normal
money you can save by purchas- workday experience, or simply
ing an energy efficient over a seems unsafe, should be omitted!
standard motor depends upon
Particular caution is recom-
motor size, annual hours of use,
mended when working with
load factor, efficiency gain (at the
current- or power-recording
load point), and the serving
devices. Many of these are either
utility’s charges for electrical This guidebook
assembled from components or
energy and demand. 4-1 Field assumes
designed with the expectation
measurements are necessary to
that they will be connected when instructions will be followed
establish the load imposed upon
circuits are unpowered, then left by qualified electricians.
an existing motor by its driven
alone after they are powered.
equipment and to determine Persons who are not properly
Some have alligator clips that
motor efficiency at its load point. qualified in industrial
require fingers to be close to
conductors or are hard to connect electrical techniques should
when wearing line worker’s
Safety gloves. Some (particularly multi-
not attempt to take any
measurements.
Considerations channel devices intended for
research-oriented monitoring)
Safety is an important consider-
have wiring panels that do not
ation when using test instru-
separate 480 volt terminal areas
ments. Plant electricians and
from low voltage sensor wires.
equipment operators are hope-
Others have metal enclosures that
fully well trained in safety and
require grounding which is
guided by company policies for
sometimes challenging in por-
working close to live circuits and
table applications. Some have
moving machinery. This guide-
enclosures which may not be
book will occasionally recom-
sufficient for the environmental
mend caution in making certain
exposure they will experience
measurements. This is not in-
while deployed. Use of any
tended to be a replacement for
recording device may require that
thorough safety training and
control panel doors be left open,
adherence to company policies.
exposing personnel to danger
unless you mark the area with
The absence of a caution state-
ribbon and signs. Regrettably,
ment certainly does not mean an
most voltage leads are unfused. If
action is inherently safe. Com-
possible, leads should be fused,
pany policies vary depending
ideally at the clip end. Fuses
upon plant environment, insur-
should be fast-blow and 1/4 amp
ance requirements, government
or less. Even 1/4 amp can be fatal
regulations, and management’s
or cause permanent neurological
commitment to safety. Any action
damage if sustained for several
described in this book which
seconds.
Taking Field Measurements 4-1
Constructing the Motor Chapter 7.) Create an inventory
database with a file for each
List and Inventory motor. Appendix A contains a
Database Motor Nameplate and Field Test
Data Form, while Appendix C
The energy coordinator should provides a Motor Energy Savings
prepare a strategy for surveying Calculation Form. Examine
and analyzing plant motors. replacement alternatives and
Divide the plant into logical areas develop a contingent plan of
and make a list of motors to be action. Then when a motor fails,
reviewed. Motors which are you can quickly implement the
significant energy users should preferred repair or replacement
head the list. Motors that operate plan. 4-2, 4-3Include the following
for extended periods of time and information in your inventory
larger motors should also be on database:
the list. Conversely, small motors n Individual motor identifica-
that run intermittently should be tion and nameplate data
placed toward the end of the list.
4-2, 4-3 n Full load efficiency, speed,
and amperage
Depending upon size of the plant n Operating motor voltage,
and complexity of the manufac- amperage, and power factor
turing process, it may be appro- n Speed of motor and driven
priate to list only motors which equipment while under load
exceed minimum size and operat-
ing duration criteria. Each plant n Annual hours of operation
will have to establish appropriate n Accurate motor load (in kW)
thresholds. Typical selection
criteria include: n Motor efficiency at its operat-
ing point
■ Three phase, NEMA Design B
motors n Action to be taken at failure,
i.e., repair or replacement
■ 10 to 600 hp specifications
At least 2,000 hours per year
Acquiring Motor

of operation
■ Constant load (not intermit- Nameplate Data
tent, cyclic or fluctuating) Motor analysis requires that
■ Older and/or rewound information from the motor
standard efficiency motors nameplate be entered into your
inventory database. A typical
■ Easy access motor nameplate, indicated in
■ A readable nameplate Figure 4-1, contains both descrip-
tive and performance-based data
■ Non-specialty motors
such as full-load efficiency, power
factor, amperage, and operating
Once you have a short list of
speed. You can use this informa-
motors, you can collect data on
tion to determine the load im-
each motor and use the Motor-
posed upon the motor by its
Master+ software to determine
driven equipment and the motor
the benefits of replacing it with an
efficiency at its load point.
energy-efficient unit. (MotorMas-
ter+ is discussed in detail in

4-2 Energy Management for Motor-Driven Systems


Depending upon the motor age Load-Time Profiles
and manufacturer practices, not
all of the desired information The energy coordinator needs to
appears on every motor name- determine the hours per year each
plate. It is not unusual for power motor operates. Annual operat-
factor and efficiency to be miss- ing hours can be estimated by
ing. When data is not present, constructing a motor operating
you must find the required data profile. Such a profile, included
elsewhere. The motor manufac- in Appendix A—Motor Nameplate
turer is a logical source.4-2, 4-3 and Field Test Data Form, requires
you to provide input regarding
The motor age in years and its motor use on various shifts
rewind history should also be during work days, normal week-
recorded. Obtain this data from ends, and holidays.
company records or from the
recollection of people who have The nature of the load being
worked at the plant and can recall served by the motor is also impor-
motor histories. Identify the tant. Motors coupled to variable
coupling type, describe the motor speed drives and operating with
load (device being driven), iden- low load factors or that serve
tify load modulation devices such intermittent, cyclic, or randomly
as throttling valves or inlet damp- acting loads are not cost-effective
ers, and record the driven-equip- candidates for replacement with
ment speed. Lists of load and energy efficient units.
coupling types are contained in
Tables 4-1 and 4-2.

Figure 4-1
Motor Nameplate

Taking Field Measurements 4-3


Table 4-1 Measuring Operating
Typical Motor Load Types
Values
Load List In a three-phase power system it
Centrifugal Fan is necessary to measure the
Centrifugal Pump following at each motor:
Compressor—screw compressor, ■ phase-to-phase voltage
reciprocating compressor, between all three phases,
centrifugal compressor
■ current values for all three
Extruder phases,
Conveyer ■ power factor in all three
Crushers/Milling phases, and

Blenders/Mixers ■ operating speed of motor and


driven load.
Grinder
Equipment necessary for these
Machine Tools (Lathes, Sanders)
measurements include:
Crane
■ voltmeter or multimeter
Planer
■ clamp-on ammeter
Positive Displacement Pump ■ power factor meter
ASD1/Centrifugal Fan
■ tachometer
ASD1/Centrifugal Pump
Meters should be of adequate
ASD1/Compressor quality to read true RMS values.
Other This guidebook proceeds on the
basis that adequate quality meters
1
Adjustable speed drive are being used by the electrician.

When the motor operates at a


constant load, only one set of
Table 4-2 measurements is necessary.
When the motor operates at two
Coupling Types or three distinct load points,
Direct Shaft measurements are required at
Worm Gear each load because the current and
power factor values vary with
Helical Gear
changes in load level. The electri-
Bevel Gear cian can then determine the
Roller Chains weighted average motor load.

Silent Chains A motor that drives a random-


V-Belts acting load presents a difficult
measurement problem. The
Synchronous Belts
electrician should take a number
Flat Belts of measurements and estimate the
Other current and power factor that best
represent the varying load. These
values are used with the voltage
to determine the typical power
required by the load.4-1,4-3

4-4 Energy Management for Motor-Driven Systems


Motor and driven-equipment
speeds must be measured as
closely as possible, ideally with a Sensitivity of Motor Load to Operating Speed
strobe tachometer. Motor speed is
important because a replacement For centrifugal loads such as fans or pumps, even a minor change
motor should duplicate the in a motor’s full-load speed translates into a significant change in
existing motor speed. When load and annual energy consumption. Fan or “affinity” laws
driving centrifugal loads (fans indicate that the horsepower loading imposed on a motor by
and pumps), the motor load is
highly sensitive to operating centrifugal load varies as the third power or cube of its rotational
speed. An energy efficient motor speed. In contrast, the quantity of air flow or water delivered
usually operates at a slightly varies linearly with speed.
higher speed than a standard
motor. The higher speed may Some energy-efficient motors tend to operate with reduced “slip”
result in an increase in speed- or at a slightly higher speed than their standard-efficiency
sensitive loads; this can negate counterparts. This small difference - an average of only 5 to 10
savings due to improved motor
RPM for 1800-RPM synchronous speed motors - is significant. A
efficiency. A speed comparison is
necessary to properly evaluate an seemingly-minor 20 RPM increase in a motor’s full-load
energy-efficient motor conserva- rotational speed from 1740 to 1760 RPM can result in a 3.5
tion opportunity. 4-1,4-3 percent increase in the load placed upon the motor by the rotating
equipment. A 40 RPM increase can boost energy consumption by
Enter field measurement values
seven percent, completely offsetting the energy and dollar savings
for each motor on the Motor
Nameplate and Field Test Data Form typically expected from purchase of an energy efficient motor.4-1
(Appendix A).
To maximize energy savings with cube law loads, be sure to select
an energy-efficient replacement motor that has a full-load
Data Gathering operating speed that is the same or less than that of your original
Approaches motor. With belt driven equipment, motor speed is not important
A diagram of a typical three- if you replace pulleys so that the original rotating equipment speed
phase power system serving a is maintained.
“delta” motor load configuration
is shown in Figure 4-2. To evalu-
ate the motor operation, you need
to collect nameplate data plus use
a multimeter and analog power
factor meter to record voltage,
amperage, and power factor on
each service phase or leg. Take Figure 4-2
readings on all three legs and Industrial Three-Phase Circuit
average them. Figure 4-3 indi-
cates how measurements are
taken with hand-held instru-
ments. It is also useful to use a
strobe tachometer to measure the
speed of both the motor and the
driven equipment.

Taking Field Measurements 4-5


Figure 4-3
Instrument Connection Locations

Power supplied to the motor can meaning it has an internal


be measured with a single instru- precision shunt resistor
ment when a “direct reading” shorting the secondary; the
meter is available. The direct output leads are connected
reading meter uses current trans- across the internal shunt so a
formers and voltage leads to low voltage output is pro-
reliably sense and display power vided. The current output
in watts or kW. Direct reading type is merely an unloaded
instruments are more costly than transformer, so the output is a
typical multimeters. Until re- current, requiring a current-
cently, it was not common for sensing device. Always
direct reading meters to be found connect a current output CT
in industrial plants. This situa- to the recording device before
tion is improving with the avail- closing it around a live con-
ability of digital direct-reading ductor. Otherwise, danger-
power meters. 4-2, 4-3 ously high voltage will appear
across the open leads.
Safety Issues in Data
Gathering Voltage Measurements
n Hand-held instruments are
not recommended for sensing Utilization Voltage
voltage levels above 600 volts. Utilization voltage should be
n Line-worker’s gloves should checked first. A convenient place
be used. to take measurements is at a
n The unconnected leads of motor starter enclosure. A hand-
some current transducers held voltmeter or multimeter can
(CTs) can inflict a dangerous be used to measure the phase-to-
electrical shock. This is of phase voltages. In a three-phase
significance when connecting system the electrician should
a CT to a separate readout or measure three values, Vab V bc and
, ,
recording device. The wound Vca (See Figure 4-3.) For a 480
.
or conventional CTs have volt system, utilization and
either a voltage or current service voltage levels should be
output. The safer (voltage within the range of 456V to 504V
output) type is an internally- (480V ± 5%).
loaded current transformer,

4-6 Energy Management for Motor-Driven Systems


Current
The voltage unbalance should be
calculated. The utilization volt- Measurements Before a valid motor energy
age unbalance should not be savings analysis can take
A hand-held ammeter with a
greater than one percent. System clamp-on CT (current transducer) place, you need to correct
voltage unbalance and over and is convenient and effective for system voltage unbalance and
under voltage problems need to measuring the line current. It is under voltage problems.
be corrected before valid motor only necessary to enclose the
analyses can take place. A conductor within the clamp-on
system voltage unbalance exceed- device. The current may be read
ing one percent aggravates motor directly from the meter. Current
performance to the extent that readings, designated I a I b, and I c
recorded data may be meaning- ,
should be taken for each phase.
less. Line-worker’s gloves should be
used.
Service Voltage
When the utilization voltage Power Factor
unbalance is greater than one Measurements
percent, the electrician must
check the voltage values at the Power factor should be measured
service entrance. Measurements with a power factor meter. Mea-
should be made at or as close to sure phase power factor by
the service entrance as possible. clamping the current sensing
This set of measurements allows element on one phase while
the electrician to determine attaching voltage leads to the
voltage balance as delivered by other phases. Take care that the
the utility. If the service voltage proper voltage lead is used with
unbalance is less than one per- the current sensing device.
cent, the utilization unbalance
problem is within the plant An alternative to power factor
distribution system. It is then the measurement is power measure-
electrician’s responsibility to find ment. Some instruments can
and fix the problem.4-3 measure both. With either power
or power factor known, the other
Service voltage unbalance greater can be calculated (see Chapter 5,
than one percent should be Equation 5-1)
brought to the attention of the
local electric utility for correction.
Data acquisition techniques
discussed in this guidebook are
intended for the secondary side of
in-plant distribution system
power transformers. Hand-held
instruments are not recom-
mended for sensing voltage levels
above 600 volts. 4-2, 4-3

Taking Field Measurements 4-7


Purchasing Motor Testing the high resistance scales they
have insufficient source voltage
Instruments for measuring insulation resis-
tance. The ampere scales are not
When shopping for electrical directly useful for measuring
testing instruments, one can motor current, but many product
easily be overwhelmed by the lines accommodate a clamp-on
variety of choices and wide range AC current transducer as an
of prices. Three things tend to accessory. Some manufacturers
affect the price: harmonics han- even have clamp-on accessories
dling capability, range, and that can be used in conjunction
features. To be a smart shopper with the voltage leads for measur-
requires knowledge of your plant ing power and or power factor.
environment.
2. Current Meters
Most manufacturers are well
represented in industrial catalogs Clamp-on
that market “instruments”. ammeters are
Many manufacturers also use an about as com-
extensive chain of independent monplace as
“local reps”. It is good to get multimeters.
connected with a local representa- Two kinds are
tive. A good local rep can usually in common use.
supply extensive manufacturer’s One is a clamp-
information about a product and on current
may also represent competing transducer that
products for comparison. Ideally, feeds an output
they will have a good under- signal to a
standing of the advantages and separate multi-
disadvantages of each product. meter for
reading on the
milliamp or
1. Voltage Meters milivolt scale.
The other is a
Hand held
self-contained
multimeters
direct clamp-on device. With the
usually are
latter, reading the instrument may
used for
be a challenge because it some-
measuring AC and
times must be thrust deep into a
DC voltage,
box and oriented at an inconve-
current, and
nient angle to access a conductor.
resistance.
Many instruments accommodate
this problem with a pivoting
The upper voltage range should
display or a hold switch that can
not exceed 600 volts. No attempt
lock the display for reading after
should be made to measure
the instrument is removed from
higher voltages with hand held
the conductor. This is an impor-
instruments.
tant feature.
Multimeters are used mainly as
Clamp-on current meters sense
voltmeters in an industrial plant.
current in one of two alternative
The resistance scales generally do
ways, either by a simple current
not go low enough for measuring
transformer or a Hall-effect
motor winding resistance, and at

4-8 Energy Management for Motor-Driven Systems


sensor. The latter are less com- Range is particularly important
mon and more expensive. Both with ammeters or current trans-
have operable iron jaws that ducers. These generally do not
clamp around the conductor, span the entire range of plant
forming an iron ring in which needs without overloading at the
magnetic flux is induced by the high end or providing poor
conductor current. The current accuracy at the low end. Also,
transformer type has a simple physical size is a limitation. It
multi-turn winding around the may be difficult to squeeze large
ring to inductively sense the CTs into a small panel. Likewise
changing flux. The Hall-effect it may be difficult to reach around
type has no winding, but a nar- large conductors with CTs of
row gap in the iron ring in which lower range, which tend to be
a sensor is placed. The advantage smaller. Care must be taken to
of the Hall-effect sensor is its select the product or products
frequency range. It works for DC that will span the necessary
and very low frequencies as well range. Power monitors that use a
as responding better to higher lot of CTs because of unbalanced
frequencies. Current and power three-phase capability or multi-
meters intended for use on either channel monitoring usually use
side of variable frequency drives internally shunted CTs. Often a
often use Hall-effect current wide range of relatively inexpen-
sensors to handle the severe sive CTs can be provided and
harmonics and sometimes low accommodated with a minor
fundamental frequencies. scaling change to the recorder’s
program.
The unconnected leads of
some CTs can inflict a dangerous 3. Tachometers
electrical shock. This is of signifi-
cance when connecting a CT to a
separate readout or recording
device. The wound or conven-
tional current transducers (CTs)
have either a voltage or current
output. The safer (voltage out-
put) type is an internally-loaded
There are several types of
current transformer, meaning it
tachometers. Some require
has an internal precision shunt
making contact with the rotating
resistor shorting the secondary;
machinery while others do not.
the output leads are connected
Avoid the contact type.
across the internal shunt so a low
voltage output is provided. The
The most common type of non-
current output type is merely an
contact tachometer is the strobe
unloaded transformer, so the
tach. Strobe tachs are simply
output is a current, requiring a
electronic strobe lights with an
current-sensing device. Always
adjustable strobe rate and a very
connect a current output CT to
precise readout in flashes per
the recording device before
minute. Battery-powered units
closing it around a live conductor.
are somewhat less common than
Otherwise, dangerously high
120-V plug-in models, but for
voltage will appear across the
most users the convenience is
open leads.
definitely worth the extra cost.

Taking Field Measurements 4-9


Strobe tachs are very accurate, but
subject to certain operator errors
Power Quality Considerations which can be reduced with
practice. The operator adjusts the
If variable speed drives, induction heaters, or other electronic
strobe rate until the rotating
loads are on the system, voltage harmonics should be expected. equipment appears to freeze or
Extreme current harmonics are present in circuits feeding stop in the light. The rpm of the
these loads. The purchaser should describe this electrical equipment is hopefully equal to
environment to the equipment supplier and determine the the strobe rate displayed, but it
might also be an integer multiple
capability of alternative devices to accurately measure such
of the displayed strobe rate.
“dirty” power. Rotating equipment with repeat-
ing features (like blades on a fan)
At the minimum, devices which sense voltage or current must
can also trick the user. Always
operate on a true RMS principle. Those that do not, will read watch a single feature, like a shaft
inaccurately when harmonics are present. keyway, and start at the lowest
plausible strobe rate.
Even knowing an instrument operates on the true RMS
principle is not completely sufficient because all are limited by Some non-contact tachometers are
the magnitude and frequency of harmonics they can handle and passive, i.e., they do not require
still read accurately. One index of this capability is the crest the operator to adjust a strobe
rate while watching for motion to
factor, which is the ratio of peak value to RMS value of a wave
freeze. These determine speed by
form. A perfect sine wave has a crest value of 1.414. True sensing reflected natural light or
RMS instruments should have a crest factor of 3.0 or better. light from their own source which
may be a laser and/or infrared.
Unfortunately, crest value alone is not a complete descriptor of This can be convenient, but
harmonic content. Harmonics caused by most electronic loads beware of models that require
cause the current crest factor to be higher and the voltage crest you to stop the machinery and
factor to be lower than sinusoidal. An instrument needs to be affix a reflector to the rotating
part before speed can be read.
capable of measuring accurately across the frequency range of
the harmonics. The frequency of harmonics is expressed either 4. Power and Power Factor
in Hz or the order of harmonic. To convert order to frequency, Meters
simply multiply by 60. Most high quality electrical testing
There are many instruments
instruments specify the frequency range over which their available which measure power,
accuracy is maintained. power factor, or both. Having the
ability to directly read power
eliminates the need to calculate it
as described in chapter 5. The
simplest instruments have con-
nections as shown in figure 4-3.
Be sure to choose a model with 3-
phase capability; many can be
switched between 3-phase and
single phase.

The one-CT instrument shown in


Figure 4-3 can only be accurate
with balanced voltage and cur-
rent. If it is unbalanced, three
readings must be taken with the

4-10 Energy Management for Motor-Driven Systems


CT on each phase and the read- equipped with a computer inter-
ings averaged. Better results face, phone modems, or radio
under unbalanced conditions can transmitters for remote data
be obtained using an instrument retrieval.
with three CTs. These tend to be
more expensive, especially if they 6. Motor Analyzers
are configured as a multi-function
power analyzer.

5. Multi-channel Power
Loggers
Probably the most complicated
instrument system likely to be
used in a plant is a multi-channel
power logger. These are available
in more than one configuration.
In packaged units, there is usually
a central module with three
voltage leads and a terminal block
for two or more trios of CTs. The
central module is both a logger
and a transducer; it computes
power based upon voltage and
the current from the CTs and
records the power. All loads must
be on the same voltage source
since there is only one set of There are a variety of products
voltage leads. CTs are marked by that are termed motor analyzers.
phase, so phase identification Of special interest are three
markings must be present at each substantial but portable units
load. which have recently appeared on
the market, claiming to compute
There are numerous variations on motor efficiency. These are the
the above configuration. Some Motor Monitor, developed by
products consist of a central Vectron for the Energy Corpora-
logger with remote power trans- tion of New Zealand, the MAS-
ducers. Interconnections typically 1000 of Niagara Instrument
follow voltage, current, or pulse Corporation of New York, and
conventions used in industrial Motor-Check, a German product
Programmable Logic Controller manufactured by Vogelsang &
(PLC) systems. Often they can be Benning and marketed in the U.S.
by the A.H. Holden Com-
pany of Minnesota.
All have connections to the
motor to sense current,
voltage and speed. Speed
is sensed magnetically or
optically. Certain name-
plate information must be
entered via keyboard. The
devices all require winding
resistance, which must be

Taking Field Measurements 4-11


obtained with the motor shut
down; usually the required micro-
ohmmeter is built into the tester.
All require no-load data which
must be obtained with the motor
uncoupled and running at idle.
Fortunately, none require any sort
of torque sensor, because it would
be nearly impossible to affix one
in many field situations.

Industrial Practices
A survey was conducted regard-
ing the capability of industrial
plant personnel to obtain field
measurements which are used to
predict motor performance.

Surveys were sent to 65 industries


in northwest Oregon and south-
west Washington. There were 29
responses. Every firm had a
voltmeter and an ammeter.
Twenty-two responded that their
company had a tachometer. Only
eight respondents indicated they
had the ability to measure power
factor. The survey provides a
basis for concluding that most
companies estimate motor load
based solely on speed or current
readings. 4-2, 4-3

4-12 Energy Management for Motor-Driven Systems


References
Chapter 4

4-1 Gilbert A. McCoy and John G. Douglass


“Energy Efficient Electric Motor Selection
Handbook,” U.S. Department of Energy, DOE/
GO-10096-290, August 1996.

4-2 Carroll, Hatch & Associates, Inc., “An Electric Motor


Energy Efficiency Guide and Technical Reference
Manual”, (Draft) June 1994

4-3 Carroll, Hatch & Associates, Inc., “A Procedure


for Developing an Energy Efficiency Plan for
the Use of Electric Motors in an Industrial
Setting,” (Draft), June 1994

Taking Field Measurements 4-13


4-14 Energy Management for Motor-Driven Systems
Chapter 5

Motor Load and


Efficiency Estimation
Techniques
To compare operating costs of an
existing motor and a more effi-
Equation 5-1
cient replacement unit, you need
to determine operating hours, V x I x PF x 3
efficiency improvement values, Pi =
1000
and load. Part-load is a term used
Where:
to describe the actual load served
by the motor as compared to the
rated full-load capability of the Pi = Three phase power in kW
motor. Motor part-loads may be V = RMS voltage, mean line to line of 3 phases
estimated through using input
power, amperage, or speed I = RMS current, mean of 3 phases
measurements. Several load PF = Power factor as a decimal
estimation techniques are briefly
discussed. Equation 5-2

Input Power 0.7457


P ir = P or x
Measurements e fl
Where:
When “direct-read” power mea-
surements are available, we
recommend using them to esti- P ir = Input power at full rated load in kW
mate motor part-load. With P or = Nameplate rated horsepower
measured parameters taken from
hand-held instruments, you can e fl = Efficiency at full rated load
use Equation 5-1 to calculate the
three-phase input power to the Equation 5-3
loaded motor.
Pi
Load = x 100%
You can then quantify the motor’s Pi r
part-load by comparing the Where:
measured input power under
load to the power required when Load = Output power as a % of rated power
the motor operates at rated Pi = Measured three phase power in kW
capacity. The relationship is
shown in Equation 5-3. P ir = Input power at full rated load in kW

Motor Load and Efficiency Estimation Techniques 5-1


Example 5-1
Input Power Calculation
An existing motor is identified as a 40 hp, 1,800 rpm unit with an
open drip-proof enclosure. The motor is 12 years old and has
not been rewound.
The electrician makes the following measurements:
Measured Values:
V ab = 467V I a = 36 amps PF a = 0.75
Vbc= 473V I b = 38 amps PF b = 0.78
Vca = 469V I c = 37 amps PF c = 0.76

V=(467+473+469)/3=469.7 volts
I=(36+38+37)/3=37 amps
PF=(0.75+0.78+0.76)/3=0.763

Equation 5-1 reveals:

469.7 x 37 x 0.763 x 3
Pi = = 22.97 kw
1000

Line Current Measurements


The current load estimation method is recommended when only
amperage measurements are available. The amperage draw of a
motor varies approximately linearly with respect to load, down to
about 50 percent of full load. (See Figure 5-1) Below the 50 percent
load point, due to reactive magnetizing current requirements, power
factor degrades and the amperage curve becomes increasingly non-
linear. In the low load region, current measurements are no longer a

Figure 5-1
Relationships Between Power, Current, Power Factor and Motor Load

5-2 Energy Management for Motor-Driven Systems


useful indicator of load. The actual speed of the motor is
Both nameplate full-load and no- less than its synchronous speed
load current values apply only at with the difference between the
the rated motor voltage. Thus, synchronous and actual speed
root mean square current mea- referred to as slip. The amount of
surements should always be slip present is proportional to the
corrected for voltage. If the load imposed upon the motor by
supply voltage is below that the driven equipment. The motor
indicated on the motor name- load can be estimated with slip
plate, the measured amperage measurements as shown in
value is correspondingly higher Equation 5-5 and Example 5-2.
than expected under rated condi-
tions and must be adjusted Table 5-1
downwards. The converse holds Induction Motor Synchronous
true if the supply voltage at the Speeds
motor terminals is above the
motor rating. The equation that Poles 60 Hertz
relates motor load to measured
current values is shown in Equa- 2 3,600
tion 5-4. 4 1,800
6 1,200
The Slip Method 8 900
10 720
The slip method is recommended 12 600
when only motor operating speed
measurements are available. The
synchronous speed of an induc-
tion motor depends on the fre-
quency of the power supply and
on the number of poles for which
the motor is wound. The higher
the frequency, the faster a motor
runs. The more poles the motor
has, the slower it runs. Table 5-1
indicates typical synchronous
speeds.

Equation 5-4
I V
Load = x x 100%
Ir Vr
Where:

Load = Output power as a % of rated power


I = RMS current, mean of 3 phases
Ir = Nameplate rated current
V = RMS voltage, mean line to line of 3 phases
Vr = Nameplate rated voltage

Motor Load and Efficiency Estimation Techniques 5-3


Equation 5-5
Slip
Load = x 100%
Ss - Sr
Where:

Load = Output power as a % of rated power


Slip = Synchronous speed - Measured speed in RPM
Ss = Synchronous speed in RPM
Sr = Nameplate full load speed

Example 5-2: Slip Load Calculation


Given: Synchronous speed in RPM = 1,800
Nameplate full load speed = 1,750
Measured speed in RPM = 1,770
Nameplate rated horsepower = 25 HP

Determine actual output horsepower.

From Equation 5-5

1,800 -1,770
Load = x 100%=60%
1,800 -1,750
Actual output horsepower would be 60%x25HP=15HP

The speed/slip method of deter- and may be thought of as insignifi-


mining motor part-load has been cant, the slip method relies on the
favored due to its simplicity and difference between full-load name-
safety advantages. Most motors plate and synchronous speeds. Given
are constructed such that the shaft a 40 rpm “correct” slip, a seemingly
is accessible to a tachometer or a minor 5 rpm disparity causes a 12
strobe light. percent change in calculated load.

The accuracy of the slip method Slip also varies inversely with
is, however, limited by multiple respect to the motor terminal
factors. The largest uncertainty voltage squared—and voltage is
relates to the 20 percent tolerance subject to a separate NEMA
that NEMA allows manufacturers tolerance of ± 10 percent at the
in their reporting of nameplate motor terminals.5-6 A voltage
full-load speed. correction factor can, of course, be
inserted into the slip load equa-
Given this broad tolerance, manufac- tion. The revised slip load, can be
turers generally round their reported calculated as shown in Equation
full-load speed values to some 5-6.5-3
multiple of 5 rpm. While 5 rpm is but
a small percent of the full-load speed

5-4 Energy Management for Motor-Driven Systems


Equation 5-6

Where:

Load = Output power as a % of rated power


Slip = Synchronous speed - Measured speed in RPM
Ss = Synchronous speed in RPM
Sr = Nameplate full load speed
V = RMS voltage, mean line to line of 3 phases
Vr = Nameplate rated voltage

An advantage of using the current- When loads fluctuate randomly,


based load estimation technique is hand-held instruments provide only a
that NEMA MG1-12.47 allows a glimpse of the overall load profile.
tolerance of only 10 percent when To obtain valid data in random load
reporting nameplate full-load current. situations you need to use recording
In addition, motor terminal voltages meters with integrating capabilities.
only affect current to the first power, Examples of various load types are
while slip varies with the square of given in Table 5-2.5-2, 5-3
the voltage. 5-6

While the voltage-compensated


slip method is attractive for its
simplicity, its precision should not
be overestimated. The slip
method is generally not recom-
mended for determining motor
loads in the field.

Variable Load Levels


When the load is variable, you
must determine the average load Table 5-2
imposed upon the motor. That Characteristics of Motor Loads
can be accomplished through Description of Motor Use Type of Load
long-term monitoring of the input
Centrifugal Supply Air Fan Motor Constant, but will change slightly with
power. If there are two load
outside air temperature.
levels (for instance a water supply
pump motor that operates con- Conveyor with Continuous and Constant
tinuously but against two differ- Constant Load
ent static heads), both motor Boiler Feed Water Pump Motor, Starts/stops. Constant while on.
loads can be measured. Deter- “On-Off” Control
mine the weighted average load Hydraulic Power Unit Motor, Two levels of different but constant
by timing each motor load period. “On and Bypass” Control values.
When many load levels exist, you
Air Compressor Motor with Two levels of different but constant
must monitor loads over a period
“Load/Unload” Control values.
of time and estimate the weighted
average load level. Air Compressor Motor with Random load.
“Inlet Valve” Control

Motor Load and Efficiency Estimation Techniques 5-5


Determining Motor NEMA design A, B, and E motors up
to 500 hp in size are required to have
Efficiency a full-load efficiency value (selected
from a table of nominal efficiencies)
The NEMA definition of energy stamped on the nameplate. Most
efficiency is the ratio of its useful analyses of motor energy conserva-
power output to its total power tion savings assume that the existing
input and is usually expressed in motor is operating at its nameplate
percentage as shown in Equation efficiency. This assumption is
5-7. reasonable above the 50 percent load
point as motor efficiencies generally
By definition, a motor of a given peak at around 3/4 load with perfor-
rated horsepower is expected to mance at 50 percent load almost
deliver that quantity of power in identical to that at full-load. Larger
a mechanical form at the motor horsepower motors exhibit a rela-
shaft.5-4, 5-5 tively flat efficiency curve down to
Figure 5-2 is a graphical depic- 25 percent of full-load.
tion of the process of converting
electrical energy to mechanical
energy. Motor losses are the
difference between the input and
output power. Once the motor
efficiency has been determined
and the input power is known,
you can calculate output power.

Equation 5-7
0.7457 x Por x Load
e=
Pi
Where:

e = Efficiency as operated in %
P or = Nameplate rated horsepower
Load = Output power as a % of rated power
Pi = Three phase power in kW

Figure 5-2
Depiction of Motor Losses

5-6 Energy Management for Motor-Driven Systems


It is more difficult to determine the Appendix B. Finally, derive a revised
efficiency of a motor that has been in load estimate using both the power
service a long time. It is not uncom- measurement at the motor terminals
mon for the nameplate on the motor and the part-load efficiency value as
to be lost or painted over. In that shown in Equation 5-8.
case, it is almost impossible to locate
efficiency information. Also, if the For rewound motors, you should
motor has been rewound, there is a make an adjustment to the effi-
probability that the motor efficiency ciency values in Appendix B.
has dropped slightly. Tests of rewound motors show
that rewound motor efficiency is
When nameplate efficiency is missing less than that of the original motor.
or unreadable, you must determine To reflect the typical rewind losses,
the efficiency value at the operating you should generally subtract two
load point for the motor. If available, points from your standard motor
record significant nameplate data and efficiency on smaller motors (<40 hp)
contact the motor manufacturer. and subtract one point for larger
With the style, type, and serial motors. Shops with the best
number, the manufacturer can quality-control practices can
identify approximately when the often rewind with no significant
motor was manufactured. Often the efficiency degradation.
manufacturer will have historical
records and can supply nominal
efficiency values as a function of
load for a family of motors.5-4, 5-4

When the manufacturer cannot


provide motor efficiency values,
you may use estimates from
Appendix B. Appendix B con-
tains nominal efficiency values at
full, 75, 50, and 25 percent load
for typical standard-efficiency
motors of various sizes and with
synchronous speeds of 900, 1200,
1800, and 3600 rpm. Appendix B
is derived from the MotorMaster+
database and indicates “industry
average” full and part-load
performance for all standard-
efficiency motors currently on the
Equation 5-8
market. 5-5
Pi x e
Three steps are used to estimate Load =
efficiency and load. First, use Por x 0.7457
power, amperage or slip measure- Where:
ments to identify the load im-
posed on the operating motor.
Second, obtain a motor part-load Load = Output power as a % of rated power
efficiency value consistent with Pi = Three phase power in kW
the approximated load either e = Efficiency as operated in %
from the manufacturer or by interpo-
P or = Nameplate rated horsepower
lating from the data supplied in

Motor Load and Efficiency Estimation Techniques 5-7


Computerized Load and
Efficiency Estimation Recently at least two manufacturers
Techniques of motor current-signature predictive
maintenance analyzers have intro-
The Oak Ridge National Labora- duced products that advertise capa-
tory has developed ORMEL96 bility for determining efficiency. The
(Oak Ridge Motor Efficiency and manufacturers claim that this is
Load, 1996), a computer program accomplished without necessity for
which uses an equivalent circuit uncoupling. Connecting through
method to estimate the load and existing potential transducers and
efficiency of an in-service motor. current transducers allows testing on
Only nameplate data and a medium voltage motors.
measurement of rotor speed are
required to compute both the
motor efficiency and load factor.
Dynamometer tests have shown that
the method produces efficiency
estimates that average within ± 3
percentage points of actual. This
accuracy is valid for motor loads
ranging from 25 to 100 percent of
rated capacity.5-7 The program
allows the user to enter optional
measured data, such as stator
resistance, to improve accuracy of
the efficiency estimate.
Motor efficiency estimation methods
and devices were evaluated at the
Motor Systems Resource Facility at
Oregon State University in 1997.
Efficiencies calculated by three
motor analyzers and several algo-
rithms and computer programs were
compared to dynamometer deter-
mined efficiencies on five motors
under numerous operating conditions.
The three analyzers and one analyti-
cal method performed well. Errors
were less than three percent for all
motors and less than one percent for
newer motors in good condition on a
balanced power suply. These meth-
ods were also demonstrated in the
field but were not embraced because
of the labor-intensive necessity to
uncouple the mtors and perform a no-
load run. The analytical method
avoids an expensive tester, but still
requires a wattmeter with good
accuracy at very low power factor.

5-8 Energy Management for Motor-Driven Systems


References
Chapter 5

5-1 J. D. Kueck, J.R. Gray, R. C. Driver and J. S. Hsu,


“Assessment of Available Methods for Evaluating
In-Service Motor Efficiency,” Oak Ridge National
Laboratory, (Draft) January 1996

5-2 “MChEff: A Computer Program for In-Service Estimation of


Motor Efficiency and Load Using the ORNL Nameplate
Equivalent Circuit Method,” Oak Ridge National Laboratory;
August 1995

5-3 Gilbert A. McCoy and John G. Douglass, “Energy Efficient


Electric Motor Selection Handbook,” U.S. Department of
Energy, DOE/GO-10096-290, August 1996.

5-4 Carroll, Hatch & Associates, Inc., “An Electric Motor Energy
Efficiency Guide and Technical Reference Manual” (Draft)
June 1994

5-5 Carroll, Hatch & Associates, Inc., “A Procedure for


Developing an Energy Efficiency Plan for the Use of Electric
Motors in an Industrial Setting,” (Draft) June 1994

5-6 Richard L. Nailen, “Finding True Power Output Isn’t


Easy,” Electrical Apparatus, February 1994

5-7 P. J. Otaduy, “ORMEL96 (Oak Ridge Motor Efficiency and


Load, 1996) User’s Guide,” Oak Ridge National Laboratory,
March 1996

5-8 Annette von Jouanne, Alan Wallace, Johnny Douglass,


Craig Wohlgemuth, and Gary Wainwright, “A Laboratory
Assessment on In-Service Motor Efficiency Testing
Methods” submitted for publication at the IEEE-International
Electric Machines and Drives Conference Milwaukee, WI,
May 1997

Motor Load and Efficiency Estimation Techniques 5-9


5-10 Energy Management for Motor-Driven Systems
Chapter 6
Energy, Demand,
and Dollar Savings
Analysis
This chapter illustrates how to use having different efficiencies,
field measurements to determine Equation 6-1 is used to calculate
demand reductions, energy sav- the kW reduction.6-3 The kW
ings, and the simple payback on savings are the demand reduction.
investment in a new or replace- The annual energy savings are
ment energy efficient motor. then calculated as shown in
Equation 6-2.
Calculating Annual Energy
Equations 6-1 through 6-3 apply
and Demand Savings to motors operating at a specified
To determine the annual dollar constant load. For varying loads,
savings from the purchase of an you can apply the energy savings
energy efficient motor, you first equation to each portion of the
need to estimate the annual energy cycle where the load is relatively
savings. Energy efficient motors constant for an appreciable period
require fewer input kilowatts to of time. The total energy savings
provide the same output as a is then the sum of the savings for
standard-efficiency motor. The each load period. The equations
difference in efficiency between are not applicable to motors
the energy-efficient motor and a operating with pulsating or random
comparable standard motor deter- loads or for loads that cycle at
mines the demand or kilowatt rapidly repeating intervals.
savings. For two similar motors
operating at the same load, but

Equation 6-1

Where:
kWsaved = Savings from efficiency improvement in kW
Por = Nameplate rated horsepower
Load = Output power as a % of rated power
estd = Efficiency of a standard motor as operated in %
e EE = Efficiency of an energy efficient motor as
operated in %

Energy, Demand, and Dollar Savings Analysis 6-1


Equation 6-2

kWh savings = kWsaved x hours


Where:
kWh savings = Annual electric energy saved in kWh
kW saved = Savings from efficiency improvement in kW
hours = Annual operating hours
You can now use the demand savings and annual energy savings along
with utility rate schedule information to estimate your annual reduc-
tion in operating costs. This calculation of total annual cost savings is
shown in Equation 6-3. Be sure to apply any seasonal and declining
block energy charges.

Equation 6-3

Where:
$savings = Total annual dollar savings
kWsaved = Savings from efficiency improvement in kW
$demand = Monthly demand dollar charge
kWhsavings = Annual electric energy saved in kWh
$energy = Dollar charge per tailblock kWh

Assessing Economic Most industrial plant managers


Feasibility require that, based on a simple
payback analysis, investments be
Because of better design and recovered through energy savings
higher quality materials, premium within one to three years. The
efficiency motors typically cost simple payback is defined as the
15 to 30 percent more than their period of time required for the
energy efficient counterparts. In savings from an investment to
many situations (new motor equal the initial or incremental
purchase, repair, or motor cost of the investment. For initial
replacement) you quickly recover motor purchases or replacement
this price premium through of burned-out and rewindable
energy cost savings. To deter- motors, the simple payback
mine the economic feasibility of period for the extra investment in
installing premium efficiency an premium efficiency motor is
motors, examine the total annual the ratio of the price premium
energy savings in relation to the (less any available utility rebate)
price premium. Appendix C to the total annual electrical
contains a Motor Energy Savings dollar savings. This calculation is
Calculation Form. shown in Equation 6-4.

6-2 Energy Management for Motor-Driven Systems


Equation 6-4
$ prem ium − $ rebate
PB =
$ savings

Where:
PB = Simple payback in years
$premium = Price premium for premium efficiency motor compared to
energy efficient
$rebate = Utility rebate for premium efficiency motor
$savings = Total annual dollar savings

For replacements of operational motors, the simple payback is the


ratio of the full cost of purchasing and installing a new premium or
energy efficient motor relative to the total annual electrical savings.
This calculation is shown in Equation 6-5.
Equation 6-5
$ new +$ inst −$ rebate
PB =
$ savings

Where:
PB = Simple payback in years
$new = New motor cost
$inst = Installation cost
$rebate = Utility rebate for premium efficiency motor
$savings = Total annual dollar savings

Energy, Demand, and Dollar Savings Analysis 6-3


Example:

The following analysis for replacing a 100 hp TEFC motor oper-


ating at 75 percent of full rated load illustrates how to use Equa-
tions 6-1 through 6-4. The analysis determines the cost-effective-
ness of purchasing a replacement premium efficiency motor
having a 3/4-load efficiency of 95.7% instead of an energy effi-
cient motor.
Kilowatts saved:
From Equation 6-1

This is the amount of power conserved by the energy efficient


motor during each hour of use. Multiply this by the number of
operating hours at the indicated load to obtain annual energy
savings.
Energy saved:
From Equation 6-2
kWh savings = 0.74 x 8000 =5,936

Assuming utility energy and demand charges of $0.04/kWh and


$5.00 per kW per month:
From Equation 6-3

In this example, installing an premium efficiency motor reduces


the utility billing by $576 per year. The simple payback for the
incremental cost associated with a premium efficiency motor
purchase is the ratio of the price premium or incremental cost to
the total annual cost savings.
Assuming a price premium of $900, the simple payback on
investment is:
From Equation 6-4
$900-$0
PB = = 3.2 yrs
$282

The additional investment required to buy an energy efficient


motor is recovered within 1.6 years. Premium efficient motors can
often rapidly pay for themselves through reduced energy con-
sumption. After this initial payback period, the annual savings will
continue to be reflected in lower operating costs and will add to
your firm’s profits.

6-4 Energy Management for Motor-Driven Systems


References
Chapter 6

6-1 Gilbert A. McCoy and John G. Douglass, “Energy


Efficient Electric Motor Selection Handbook,” U.S.
Department of Energy, DOE/GO-10096-290,
August 1996.

Energy, Demand, and Dollar Savings Analysis 6-5


6-6 Energy Management for Motor-Driven Systems
Chapter 7
Motor
Improvement
Planning

A company should plan ahead so meets your company guidelines,


that it can make timely decisions a change may be warranted right
on energy-efficient motor replace- away. Most of the time the “trig-
ments. Take the following plan- gering event” is that the existing
ning steps for each motor in the motor must be replaced. By
plant that meets minimum size planning ahead, you can execute
requirements: the plan on short notice and
n Accurately determine motor acquire the best available motor for
load in kW. your particular need.
n Accurately establish the power Energy Efficient Alternatives
factor for each motor at load.
After you determine the load,
n Establish the existing motor operating hours, and efficiency of
efficiency. each existing motor, you are ready
n Determine annual operating to develop an action plan. There
hours. are a number of alternatives to
n If the motor is under 50% consider and analyze. There are
loaded, consider replacement two principal types of situations
with a smaller motor either encountered. One set of analyses
from company inventory or is based on the event of existing
from new stock. If a new motor failure, while the second set
motor alternative is preferred, of analyses assumes no failure of
compare an energy-efficient the existing motor. The alternatives
with a standard-efficiency are:
unit.
n Upon Failure of Existing
n If the existing motor were to Motor
fail, analyze the use of a
rewound motor against use of n Repair the motor.
a new standard and a new n Replace motor with a new
energy-efficient motor. standard motor.
n Replace motor with a new
n Recommend the most cost- energy-efficient motor.
effective alternative.
n Without Existing Motor
n Obtain prior approval to use
Failure
the “best” approach.
n Establish an action plan to be n The motor can be left to
carried out once the “trigger- operate just as it is.
ing event” takes place. n The motor can be replaced
immediately with a higher
If the analysis indicates a simple efficiency motor.
payback period or other eco-
nomic performance value that

Motor Improvement Planning 7-1


With either situation, the alternatives
MotorMaster+: Motor Energy Management Software can include downsizing if the existing
motor is oversized. MotorMaster+
The Bonneville Power Administration and the U.S. Department of allows for side-by-side comparison
of annual energy costs due to
Energy Motor Challenge Program have supported the development of
operation of motors of different
MotorMaster+, an energy efficient motor selection and energy-manage-
horsepower.
ment tool.
Upon Failure Alternatives
MotorMaster+ software supports industrial energy management
activities by providing: When a motor fails, there are two
alternatives.
n The ability to select the “best” available new or replacement
motor through accessing an internal database of price and
Repair the Motor
performance information for over 27,000 1-to-2000 hp industrial The least capital cost approach is
motors; generally to repair the failed motor.
This often means rewinding of the
n A plant motor inventory module where motor nameplate data, stator in addition to mechanical
operating information and field measurements are linked to repairs such as bearing replacement.
utility, facility, and process information; The motor must be out of service
during repair.
n Capability to automatically estimate in-place motor load and
efficiency; For a major rebuild to be justified,
the original stator and rotor must be
n The ability to scan for motors which operate under abnormal or
in serviceable or reasonably-repair-
sub-optimum power supply conditions;
able condition. Repair of significant
n Descriptor search capability to assist you in targeting energy- rotor or stator core damage is
intensive systems and replacing inefficient motors; generally only cost effective on
larger motors.
n Inventory management functions including maintenance logs and
spare tracking; Replace with a New Motor

n Analysis features for rapidly determining the annual energy, When replacement is chosen, it is
demand and dollar savings resulting from selecting and using an
often cost effective to select a new
premium efficiency motor. Excep-
energy-efficient motor in a new purchase or retrofit application;
tions can occur if there is an existing
n The ability to analyze “batches” or selected populations of standard motor in inventory and/or
inventory for motor rewind, downsizing, or replacement of annual operating hours are very low.
operable standard with energy-efficient motors;
When a previously rewound stan-
n Energy accounting features including utility billing, plant pro- dard efficiency motor fails, the
duction and energy conservation and greenhouse gas emission opportunity to replace it with an
reduction summary reports; energy efficient model can tip the
scale from repair to replacement.
n Life cycle costing capability, including the ability to compute the Replacing the motor with another
after-tax return on investment in an energy-efficient product. standard efficiency motor is usually
not cost effective unless annual
Call the Motor Challenge Information Clearinghouse (800) 862-2086 operating hours are very low or
to obtain information on motors and motor-driven equipment, for electricity is very inexpensive.
technical consultation, and for your copy of MotorMaster+.
The economic analysis for deciding
whether to repair or replace a failed
motor is straight-forward. The “do

7-2 Energy Management for Motor-Driven Systems


nothing” alternative doesn’t exist. (kWh). The difference in operating
The least capital cost alternative, cost is readily computed upon
repairing the failed motor, becomes examining the utility rate schedule.
the base case. The biggest challenge
is estimating the cost of the motor
repair and its prospective efficiency In the following example (Table 7-
after repair. 1), MotorMaster+ identified a new
premium efficiency motor. The
The principal difference in all of the software determined comparative
alternatives is the amount of energy performance values based on an
that will be used to satisfy motor energy cost of $.04/kWh and a
losses. The logic used to evaluate monthly demand charge of $2/kW.
the alternatives will seek to identify You can also calculate these values
the operating cost for each alterna- with the equations provided in
tive. It is then possible to compare Chapter 6. The comparison of
both the incremental cost of the alternatives, provided in Table 7-1,
alternative and also the operating indicates an attractive 1.0 year
cost reduction associated with the simple payback on the investment in
alternative. a premium efficiency replacement
motor. The failed motor could either
Energy consumed in motor losses is be rewound and retained as a spare,
computed in terms of kilowatt-hours junked, or sold for its salvage value.

Table 7-1
Motor Repair Versus Replace Analysis

Original Repair New Motor


Standard Motor Premium Units
Efficiency Motor Efficiency

Motor Size 40 40 40 hp
Load 75 75 75 %
Nominal Efficiency 88.5 88.5 94.5 %
Motor Rewind Loss - 2.0 - %
Operating Hours 6,000 6,000 6,000 Hours
Cost (Repair/Purchase) - $880 $1,764 $
Premium efficiency motor rebate - - $300 $
Annual Energy Use 151,729 155,237 142,095 kWh/Year
Annual Energy Cost $6,069 $6,209 $5,684 $/Year
Demand Charge $607 $621 $568 $/Year

Savings compared to repair Savings


Energy 13,142 kWh/Year
Energy Value $525 $/Year
Demand 2.2 kW
Demand Cost $53 $/Year
Total Saved $578 $/Year
Simple Payback 1.0 Years

Motor Improvement Planning 7-3


varies with the extent of damage,
Additional alternatives may be geographical location, overtime
considered. There could be a requirements, and type of stator
suitable surplus or repaired motor impregnation. Moreover, repairs
in inventory, which would avoid the are usually provided by other than
new motor purchase price. As manufacturers’ shops, so there is
discussed earlier in this chapter, not an annual update of repair
either an inventory motor or a new costs in the MotorMaster+
motor could be a smaller size. The database. Two sources of better
MotorMaster+ “Compare” information on repair cost exist.
routine will compare motors of Users can maintain their own cost
different horsepowers. It will even database from records of recent
adjust the output power for part repairs. Users can also subscribe to
load operating speed differences an annually-updated motor repair
when “cube law” loads (e.g., cost guide. Vaughens’ Price Pub-
centrifugal pumps or fans) are lishing Inc. produces a price
driven. estimator that is widely used.7-1
Determining an “appropriate”
You must weigh several factors in rewind efficiency loss is somewhat
making a good decision. These like projecting how many points
include: the home team will score when you
don’t know who they are playing.
1. Cost of the proposed replace- The default efficiency loss in
ment motor MotorMaster+ is merely intended
2. Efficiency of proposed motor to be central to a plausible range of
3. Downtime cost for each zero to about five percent. There
alternative (if different) have not been enough before/after
4. Cost to repair the existing studies done to establish a statisti-
motor cally-valid mean efficiency reduc-
5. Efficiency of the existing tion. In most cases there will be an
motor after repair efficiency loss between 0.5 percent
6. Availability of a utility rebate and two percent. A two percent
Items 1 and 2 are available from reduction is a reasonable estimate
MotorMaster+, the motor manu- for motors under 40 hp rewound in
facturer, or distributor. Item 3 may a shop with unknown quality
be equal for each alternative. practices, while 0.5 percent is a
Generally it is quicker to repair reasonable estimate for motors
large or special motors, but dis- over 40 hp rewound in a good shop
tributors usually have standard and with a well-run quality manage-
energy-efficient non-specialty ment program.7-2
smaller size motors in stock. Items Motors can be rewound with no
4 and 5 are the most difficult to efficiency loss whatsoever. Effi-
quantify. ciency degradation following
In the motor comparison window rewind is caused either by aspects
of MotorMaster+ a default cost of the original failure that cannot
of repairing an existing motor is economically be completely re-
provided, but it can be overwritten. paired, or by errors or shortcuts
Indeed, it usually needs to be occurring in the repair. Either way,
overwritten because there is too selecting a shop with a sound
much variation in motor repair cost quality management system is the
to rely on the default number for best precaution. Electrical Appara-
investment decisions. Repair cost tus Service Association (EASA)

7-4 Energy Management for Motor-Driven Systems


supports their members with a Table 7-2 illustrates the benefits of
quality management program called replacing an existing standard
EASA-Q. Member shops can efficiency motor with an energy-
participate at various levels. For efficient unit. Again, the new
non-EASA shops, look for evi- motor price and performance
dence of a quality management information is extracted from
program based upon ISO 9000. MotorMaster+. The software
determined comparative perfor-
Without an Existing Motor mance values based on an energy
Failure cost of $.04/kWh and a monthly
demand charge of $2/kW.
Leave the Present Situation As
Is The 6.8 year simple payback in this
example is longer than the criteria
An energy coordinator has a used by most industry decision
number of demands on his or her makers. Replacing a working
time. It may be that the benefit of motor is usually not cost effective.
reducing motor losses is not a high Payback, however, is very sensitive
priority when compared to other to individual circumstances. An
duties competing for the limited operating time of 8,000 hours or a
time available. The immediate cost utility rebate would reduce the
of keeping a working standard payback period, and a higher
motor is zero. Savings may simply demand or energy cost would
accrue too slowly to justify invest- reduce it even further.
ment in a new more efficient
motor. Each plant is different and Other factors can contribute to a
decisions concerning relative decision to replace a working
importance of projects are best left motor. You may be nearing a
to those responsible for operation scheduled downtime for a process
of the plant. line, and age or predictive mainte-
nance trends may portend trouble
Replace Operating Motor with a from an existing motor. It may be
New Energy-Efficient Motor very wise to replace the motor
rather than risk an unscheduled
An energy efficient replacement
shutdown of a process line. See
motor can always be found in the
Chapter 9 for more information on
same frame size and with compa-
predictive maintenance.
rable starting torque and locked
rotor current as the existing motor.
The average energy efficient motor Motor Resizing
turns at a fraction of a percent Historically, the plant electrician is
higher speed than its standard responsible for keeping motors in
counterpart. In many centrifugal good operation. It was, and still is,
pump and fan applications, this common for part of a manufactur-
characteristic will increase flow and ing plant to be down because of a
energy consumption. This can single electric motor failure. Under
diminish expected savings. Fortu- these circumstances, the plant
nately, full load speed varies among electrician works quickly to replace
energy-efficient motors and a the failed unit so there is minimal
model can usually be found to disruption to the plant operating
closely match the speed of all but schedule. The best way to mini-
the slowest standard efficiency mize downtime is to have a re-
motors. placement motor on hand, ready to

Motor Improvement Planning 7-5


Table 7-2
Existing Motor Replacement Analysis
Original New Units
Standard Efficiency Motor Energy- Efficient Motor
Motor Size 40 40 hp
Load 75 75 %
Nominal Efficiency 90.4 94.4 %
Operating Hours 6,000 6,000 Hours
Motor Cost - $1,764 $
Installation Cost - $105 $
Annual Energy Use 148,507 142,246 kWh/Year
Annual Energy Cost $5,940 $5,690 $
Demand Charge $594 $569 $/Year
Savings Savings
Energy 6,261 kWh/Year
Energy Cost $250 $/Year
Demand 1.0 kW
Demand Cost $25 $/Year
Total Saved $275 $/Year
Simple Payback 6.8 Years

install. However, it is too costly to An AC motor turns at a speed


have a spare for every motor in the determined by the AC frequency
plant. Thus, when the proper size and its design (i.e. number of
replacement is not in inventory, the magnetic poles). This speed is
electrician typically places the next absolutely exact in synchronous
larger motor available into service. motors and only varies (with torque
loading) by a few percent in induc-
The intention is to have the failed tion motors. In essence, the motor
motor rebuilt and then put back determines at what speed the load
into service when time permits. will run. Any load (pump, fan,
However, there is rarely enough conveyor, etc.) has a characteristic
time to replace a temporary work- torque demand, i.e. for any running
ing motor, so the motor that is speed, it resists with a certain
returned from the repair shop goes torque. This relationship is the
into inventory, waiting for another torque-speed curve. So, when
motor to fail. In this way, the size motor and load are coupled to-
of motors at many industrial gether, the motor dictates the
facilities grows over time. running speed and the load dictates
the torque required.
The power delivered by a motor is
determined by the interaction Power delivered by the motor is
between the motor and the load. proportional to speed times torque.

7-6 Energy Management for Motor-Driven Systems


This leads to some interesting and n An underloaded motor oper-
counter-intuitive results. Suppose ates less efficiently and with
an 1800 rpm 50 hp motor delivers lower power factor than a
50 hp to a certain load. If it is motor loaded at 75 to 100
replaced by an 1800 rpm 100 hp percent of rated power.
motor, it will still deliver only 50 hp
to the load. The load is oblivious
to the potential power of a motor, Power factor begins to drop off
and only responds by requiring a fairly rapidly as load is reduced, but
certain torque commensurate with there has been some tendency to
its driven speed. overstate the drop in efficiency at
part load. Motor efficiency curves
This requires rethinking the mean- vary by horsepower and model, but
ing of rated horsepower. Rated most peak near 75 percent load and
horsepower is neither the horse- still provide near nameplate effi-
power that is invariably delivered ciency at half load. Below half
nor the maximum horsepower that load, efficiency begins to drop off
can be delivered. It is the nominal dramatically. Performance curves
horsepower for which the manu- for two typical motors are pre-
facturer publishes “full load” sented in Figure 7-1. When com-
parameters such as efficiency, paring an existing motor to a
current, amps, maximum tempera- downsized replacement, be sure to
ture rise, etc. If a certain load use the appropriate part load
resists with a lower torque at motor efficiency for each motor. Since
nameplate speed, the motor will larger motors exhibit higher effi-
oblige, delivering the lower torque ciency over their load range, it is
and less than rated power. If a common to find a larger motor’s
load requires more than the half load efficiency to be greater
motor’s rated torque to operate at than the full load efficiency of a
the motor’s nameplate rpm, the replacement motor rated at half
motor will attempt to deliver more the power output.
than its rated torque and horse-
power. The first step in considering
downsizing is to determine loading
There is, of course, a limit to on the existing motor using meth-
overloading. Small or brief over- ods discussed in Chapter 5. For
loads will be accommodated variable loading, be sure to make
successfully, albeit with a decrease this determination when the motor
in efficiency and an increase in is operating at its highest load. As
operating temperature. With a rule of thumb, it is best not to
greater or longer overloads, motor downsize to where the replacement
lifetime is sharply reduced. With motor is more than 75 percent
still greater overloads, the motor loaded. This rule can be exceeded
will not start and accelerate to when you are certain of the maxi-
running speed, and it will either mum loading.
burn out or trip circuit protectors. Even with the same number of
poles, motors vary slightly in full
Downsizing can be a money saver load speed. This is an important
for two reasons: consideration in resizing because
n When purchasing replacement the torque of some loads is very
motors, smaller motors tend to sensitive to rpm. The most notable
cost less. examples are fans and pumps
which are working primarily against

Motor Improvement Planning 7-7


Figure 7-1
Motor Performance at Part Load

flow friction (as opposed to a high on the number of hours the motor
static discharge head). In these is operated and the cost of electri-
applications, a one percent reduc- cal energy. If the load in this
tion in speed produces a one example were a continuously-
percent reduction in flow, but a operated conveyor with constant
three percent reduction in shaft loading, the value of energy saved
power. (at $0.04 per kWh) would be
almost $600 per year (8,760 hr/yr x
An example will be valuable in 1.7 kW x $0.04/kWh). A new
appreciating the concept of motor costs about $1,500. The
downsizing motors. Table 7-3 is an existing motor would likely be a
analysis of downsizing a lightly good candidate motor for
loaded, existing 75 hp motor. A downsizing.
careful check of motor load by the
electrician reveals that the maxi- The decision to change out the
mum (peak) load encountered is 30 existing motor is also influenced by
hp. The peak load is short in one or more of the following:
duration (one hour per day). The
potential replacement motor (40 n Length of service life in
hp, energy-efficient) is forecast to present motor
operate at 75% load. The values
for efficiency and power factor n Operating hours
have been selected to reflect the n Availability of a smaller motor
load. You will develop data of this in company inventory
nature as you follow the motor
analysis procedures described in n An inducement or incentive
Chapter 5. from the local utility
In the example shown in Table 7-3, n The ability of the energy
installation of a replacement motor coordinator to analyze the
is expected to result in a reduced situation and propose an
electrical demand of 1.7 kW. The economically-sound change
value of energy savings will depend

7-8 Energy Management for Motor-Driven Systems


The skilled electrician will also
notice that with the smaller, en-
ergy-efficient motor the required
power output is being delivered,
while at the same time the current
to the motor has been reduced by
about 25%. Current reductions
decrease the I2R (line) losses
throughout the distribution system
and allow load centers to serve
more load without exceeding
capacity.

Table 7-3
Motor Downsizing Example
Existing Motor Replacement Motor Units
75 hp 40 hp
1 Load Imposed on Motor 40.0% 75.0% %
2 Average Volts - V 476.0 476.0 Volts
3 Average Current - I 44.2 33.9 Amps
4 Power Factor - pf at load point 69.9% 85.0% %
5 Input power - Pin 25.5 23.8 kW
6 Motor Efficiency - ∈ at load point 87.9% 94.1% %
7 Output Power - Pout 22.4 22.4 kW
8 Motor Losses (Pin - Pout) 3.1 1.4 kW
9 Power Savings 0 1.7 kW

Motor Improvement Planning 7-9


Conclusion
A motor systems management plan
has many benefits. The history of
maintenance actions, load levels,
and operating environment is
important information when a
motor goes to the repair shop.

Another very important planning


benefit is that you know in advance
what action to take with each
motor (either immediately, upon a
failure, or during scheduled down-
time). An example of this infor-
mation is presented in Figure 7-2.
This can be accompanied by
individual recommendations for
replacement motors, simple
paybacks computed on an indi-
vidual motor basis, or by a compre-
hensive life-cycle-cost analysis for
batch actions on multiple motors.

Figure 7-2
Motor Efficiency Improvement Action Plan

7-10 Energy Management for Motor-Driven Systems


References
Chapter 7

7-1 “Vaughen’s Complete Price Guide for Motor


Repairs & New Motors,” 1995, Vaughen’s Price
Publishing Co. Inc., Pittsburgh, PA

7-2 Vince Schueler and Johnny Douglass,“Quality Electric


Motor Repair: A Guidebook for Electric Utilities,” 1995,
Bonneville Power Administration, Portland, OR

Motor Improvement Planning 7-11


7-12 Energy Management for Motor-Driven Systems
Chapter 8
Power Factor
Correction

The Concept of Power reactive power that is measured


in kilovolt-amperes reactive
Factor (kVAR). Reactive power doesn’t
Power factor is a measure of how do useful “work,” but circulates
effectively electrical power is between the generator and the
being used. A high power factor load. It places a heavier drain on
(approaching unity) indicates the power source, as well as on the
efficient use of the electrical power source’s distribution system.
distribution system while a low
power factor indicates poor use of The real (working) power-produc-
the system.8-1 ing current is the current that
reacts with the magnetic flux to
Many loads in industrial electrical produce the mechanical output of
distribution systems are inductive. the motor.8-2,8-3 Real power is
Examples include motors, trans- measured in kilowatts (kW) and
formers, fluorescent lighting can be read on a wattmeter. Real
ballasts, and induction furnaces.8-1 (working) power and reactive
The line current drawn by an power together make up apparent
inductive load consists of two power. Apparent power is mea-
components: magnetizing sured in kilovolt-amperes (kVA).8-1
current and power-producing
current. Power factor is the ratio of real
power to apparent power. To
The magnetizing current is the determine power factor (PF),
current required to sustain the divide real power (kW) by appar-
electro-magnetic flux or field ent power (kVA). In a sinusoidal
strength in the machine. This system, the result is also referred
component of current creates to as the cosine 0.

Equation 8-1
Pi
PF = = cosine θ
PApparent
Where:

PF = Power factor as a decimal


Pi = Three phase power in kW
PApparent = Apparent power in kVA

Power Factor Correction 8-1


Another way to visualize power Power Factor Penalties
factor and demonstrate the rela-
Terminology tionship between kW, kVAR and When a utility serves an indus-
kVA, is the right “power” triangle trial plant that has poor power
■ Apparent Power illustrated in Figure 8-1. The factor, the utility must supply
This value is determined by hypotenuse of the triangle repre- higher current levels to serve a
multiplying the current times sents the apparent power (kVA) given load. In a situation where
voltage. In a three-phase circuit, which is simply the system voltage real power demand (kW) at two
multiply the average phase-to- multiplied by the amperage times plants is the same, but one plant
the square root of three (for a has an 85 percent power factor
phase voltage, times the average
three-phase system) divided by while the other has a 70 percent
line current, times the square power factor, the utility must
root of 3 divided by 1,000. 1,000. The right side of the
triangle represents the reactive provide 21 percent more current
The units are kilovolt-amperes to the second plant to meet that
power (kVAR). The base of the
(kVA). same demand. Conductors and
triangle represents the real or
VxIx 3 working power, measured in kW. transformers serving the second
PApparent = The angle between the kW and plant would need 21 percent
1000 more carrying capacity than those
kVA legs of the triangle is the
phase angle 0.8-4 provided to the first plant.
■ Reactive Power Additionally, resistance losses
This term describes the magne- Figure 8-1 (I2R) in the distribution conduc-
tizing requirements of an The Power Triangle tors would be 46 percent greater
electric circuit containing in the second plant.8-2, 8-3
inductive loads. The value of
magnetizing power is deter- A utility is paid primarily on the
mined by multiplying the basis of energy consumed and
Apparent Power by the sine of peak demand supplied. Without
the phase angle, 0, between the a power factor billing element,
voltage and the current. Units the utility would receive no more
income from the second plant
are kilovolt-amperes reactive Example: than from the first. As a means
(kVAR).
If a sawmill was operating at of compensation for the burden
PReactive =PApparentx sine 0 1,000 kW and the apparent power of supplying extra current,
consumed was 1,250 kVA, you utilities typically establish a
■ Real Power would divide 1,000 by 1,250 to “power factor penalty” in their
This term is what electricians come up with a power factor of rate schedules. A minimum
deal with in plant loads. 0.80. The phase angle is arc cosine power factor value is established,
0.80 or 36.8 degrees. usually 95 percent. When the
Previous references in this
customer’s power factor drops
guidebook to “power” have all Power factor is also referred to as below the minimum value, the
meant real power. Real power leading or lagging. In the case utility collects “low power
is related to Apparent Power by of the magnetizing current, the factor” revenue. As shown in the
the cosine of the phase angle, 0, power factor is lagging, in that the “Benefits of Power Factor
between voltage and current. current follows the voltage wave- Correction” section of this
Units are kilowatts (kW). form. The amount of lag is the chapter, the lower the actual
electrical phase angle between the power factor, the greater the
Pi=PApparent x cosine 0 voltage and the current. Power penalty.8-2,8-3
factor is equal to the cosine of the
Pi=PApparent x PF phase angle between the voltage
and current waveforms.

8-2 Energy Management for Motor-Driven Systems


Power Factor than full-load. This often The Bonneville Power Adminis-
Improvement occurs in cyclic processes tration has produced the Indus-
(such as circular saws, ball trial Power Factor Analysis
Some strategies for improving your mills, conveyors, compressors, Guidebook. Software designed
power factor are: grinders, extruders, or punch for the Microsoft© Windows™
presses) where motors are operating environment is available
■ Use the highest-speed sized for the heaviest load. In
motor that an application to make the power factor correc-
these applications, power
can accommodate. tion process as simple as possible.
factor varies from moment to
Two-pole (nominal 3600 rpm) moment. Examples of situa- The Guidebook addresses the
motors have the highest power tions where low power factors following topics:
factors; power factor decreases (from 30 percent to 50 per- ■ How to tell if your plant
as the number of poles in- cent) occur include a surface could benefit from capacitors.
creases.8-5 grinder performing a light cut,
an unloaded air compressor, ■ How to select capacitor
■ Size motors as close as and a circular saw spinning schemes to eliminate power
possible to the horsepower without cutting.8-1 The indus- factor penalties and minimize
demands of the load. tries shown in Table 8-1 losses.
A lightly loaded motor requires typically exhibit low power ■ How to perform detailed plant
little real power. A heavily factors and do not fully utilize surveys to collect sufficient
loaded motor requires more the incoming current supplied data to determine where to put
real power. Since the reactive by the electrical utility.8-1,8-6 capacitors.
power is almost constant, the
ratio of real power to reactive ■ Add power factor correction ■ Why the power system must be
power varies with induction capacitors to your in-plant built with extra capacity to
motor load, and ranges from distribution system. supply power.
about 10 percent at no load to Power capacitors serve as ■ How reactive power contrib-
as high as 85 percent or more leading reactive current gen-
at full load.8-2,8-3,8-5 (See Figure utes to additional losses.
erators and counter the lagging
8-2) An oversized motor, reactive current in the system. ■ How capacitors, synchronous
therefore, draws more reactive By providing reactive current, machines, and static (adap-
current at light load than does they reduce the total amount tive) power compensators
a smaller motor at full load. of current your system must correct for power factor.
Low power factor results when draw from the utility.8-1
■ When to use switched and
motors are operated at less fixed capacitors.
■ How and when capacitors
contribute to harmonic
Figure 8-2
distortion problems and how
Power Factor as a Function of Motor Load to predict this.
■ How capacitors can fall prey
to harmonics and switching
transients and what to do
about it.
The Guidebook ($25) and
Software ($395) are available
from Bonneville Power Adminis-
tration. Send check to Accounting
Operations, Mailstop FRO,
BPA, P.O. Box 6040, Portland
OR 97228.

Power Factor Correction 8-3


Table 8-1
Industries That Typically Exhibit Low Power Factor
Industry Uncorrected Power Factor
Saw mills 45% - 60%
Plastics (extruders) 55% - 70%
Machine shops 40% - 65%
Plating, textiles, chemicals, 65% - 75%
breweries
Foundries 50% - 80%
Chemicals 65% - 75%
Textiles 65% - 75%
Arc welding 35% - 60%
Cement Works 78% - 80%
Printing 55% - 70%

Sizing and Locating Power plant.8-6,8-7 This is a good strategy


when capacitors must be switched
Factor Correction to follow a changing load. If your
Capacitors plant has many large motors, 25 hp
and above, it is usually economical
Once you decide that your facility to install one capacitor per motor
can benefit from power factor and switch the capacitor and
correction, you need to choose the motor together.8-1
optimum type, size, number, and
strategic locations for capacitors in Switched capacitors don’t require
your plant. The unit for rating separate switch control equipment
power factor capacitors is the when they are located on the load
kVAR, equal to 1,000 volt-am- side of motor contactors. Thus,
peres of reactive power. The capacitors installed on the larger
kVAR rating signifies how much motors are nearly as economical as
reactive power a capacitor will fixed banks installed at motor
provide.8-1 control centers. When some
switching is required, the most
The value of individual motor economical method is to install a
reactive power is cumulative base amount of fixed capacitors
toward the overall plant reactive that are always energized, with the
power. Therefore, when you remainder on the larger motors and
improve the power factor of a switched when the motors are
single motor, you are reducing the energized. Observe load patterns
plant’s reactive power require- in order to determine good candi-
ment. date motors to receive capacitors.
The greatest power factor correc- If your plant contains many small
tion benefits are derived when you motors (in the 1/2 to 10 hp size
place capacitors at the source of range), it may be more economical
reactive currents. It is thus com- to group the motors and place
mon to distribute capacitors on single capacitors or banks of
motors throughout an industrial capacitors at, or near, the motor

8-4 Energy Management for Motor-Driven Systems


control centers. If capacitors are n Lower installation costs.
distributed for loss reduction and
n Total plant power factor
also need to be switched, you can
improves which reduces or
install an automatic power factor
eliminates utility power factor
controller in a motor control
penalty charges.
center; this provides automatic
compensation and may be more n Total kVAR may be reduced,
economical than capacitors on as all capacitors are on-line
each of the small motors fed from even when some motors are
that control center.8-6 Often the switched off.
best solution for plants with large
n Automatic switching ensures
and small motors is to specify both
the exact amount of power
types of capacitor installations.8-1,8-6
factor correction and elimi-
Sometimes, only an isolated nates overcapacitance and
trouble spot requires power factor resulting overvoltages.
correction. This may be the case
if your plant operates welding If your facility operates at a
machines, induction heaters, or D- constant load around-the-clock,
C drives.8-1 Facilities with very fixed capacitors are the best
large loads typically benefit from a solution. If load is variable such
combination of individual load, as eight-hour shifts five days a
group load, and banks of fixed and week, you’ll require switched units
automatically-switched capacitor to decrease capacitance during
units. times of reduced load.8-1
If your feeders or transformers are
Advantages of individual capaci-
overloaded, or if you wish to add
tors at the load include8-1:
additional load to already loaded
n Complete control. Capacitors lines, you should apply power
don’t cause problems on the factor correction at the load. If
line during light load condi- your facility has excess current-
tions. carrying capacity, you can install
capacitor banks at main feeders.
n No need for separate switch-
ing. The motor always oper-
ates with its capacitor.
n Improved motor performance
due to reduced voltage drops.
Figure 8-3
n Motors and capacitors can be
Locating Capacitors on Motor Circuits
easily relocated together.
n Easier to select the right
capacitor for the load.
n Reduced line losses.
n Increased system capacity.
The advantages of bank installa-
tions at the feeder or service entry
are8-1:
n Lower cost per kVAR.

Power Factor Correction 8-5


Three options, indicated in Figure Sizing Capacitors for
8-3, exist for installing capacitors
at the motor:8-1 Individual Motor and
Location A — motor side of Entire Plant Loads
overload relay Capacitors which are installed
across the motor terminals and
■ New motor installations in switched with the motor should
which overloads can be sized not be sized larger than the
in accordance with reduced amount of kVAR necessary to
current draw raise the motor no-load power
■ Existing motors when no factor to 100 percent.8-5 Use Table
overload change is required 8-2 to size capacitors for indi-
Location B — between the starter vidual motor loads. Look up the
and overload relay type of motor frame, synchronous
speed (RPM), and horsepower.
■ Existing motors when place- The table indicates the kVAR
ment at A would allow over- necessary to correct the power
load current to surpass code factor to 95 percent.8-1,8-6
Location C — line side of starter
If you know the total plant load
■ Motors that are jogged, (kW), your present power factor,
plugged, reversed and the power factor you intend to
■ Multi-speed motors achieve, use Table 8-3 to identify
the required capacitance.8-1 This
■ Starters with open transition
table is useful for sizing banks of
and starters that disconnect/
capacitors which may be located
reconnect capacitor during
at motor control centers, feeders,
cycle
branch circuits, or the plant
■ Motors that start frequently service entrance.
■ Motor loads with high inertia
Table 8-2
Sizing Guide for Capacitors on Individual Motors
kVAR to correct typical motor to 0.95 PF; motor and capacitor switched as single unit. (ANSI/NEMA MGI - 1978)
NEMA B C D
Code Before 1955 U-Frame T-Frame
Poles 2 4 6 8 10 12 2 4 6 8 10 12 2 4 6 8 10 12 4-6 8 6 Wound
1800 900 1200 Rotor
RPM 3600 1800 1200 900 720 600 3600 1800 1200 900 720 600 3600 1800 1200 900 720 600 1200
HP= 1.5 1.5 1.5 2 2.5 3.5 1 1 1 2 1.5 1.5 2.5 3 3 4
3
5 2 2 2 3 4 4.5 1 2 2 2 2 2.5 3 4 4 5
7.5 2.5 2.5 3 4 5.5 6 1 2 4 4 2.5 3 4 5 5 6
10 3 3 3.5 5 6.5 7.5 2 2 4 5 5 5 4 4 5 6 7.5 8
15 4 4 5 6.5 8 9.5 4 4 4 5 5 5 5 5 6 7.5 8 10 5 5 5 5.5
20 5 5 6.5 7.5 9 12 4 5 5 5 10 10 6 6 7.5 9 10 12 5 6 6 7
25 6 6 7.5 9 11 14 5 5 5 5 10 10 7.5 7.5 8 10 12 18 6 6 6 7
30 7 7 9 10 12 16 5 5 5 10 10 10 8 8 10 14 15 23 7.5 9 10 11
40 9 9 11 12 15 20 5 10 10 10 10 15 12 13 16 18 23 25 10 12 12 13
50 12 11 13 15 19 24 5 10 10 15 15 20 15 18 20 23 24 30 12 15 15 18
60 14 14 15 18 22 27 10 10 10 15 20 25 18 21 23 26 30 35 18 18 18 20
75 17 16 18 21 26 33 15 15 15 20 25 30 20 23 25 28 33 40 19 23 23 25
100 22 21 25 27 33 40 15 20 25 25 40 45 23 30 30 35 40 45 27 27 30 33
125 27 26 30 33 40 48 20 25 30 30 45 45 25 36 35 42 45 50 35 38 38 40
150 33 30 35 38 48 53 25 30 30 40 45 50 30 42 40 53 53 60 38 45 45 50
200 40 38 43 48 60 65 35 40 60 55 55 60 35 50 50 65 68 90 45 60 60 65
250 50 45 53 58 70 78 40 40 60 80 60 100 40 60 63 82 88 100 54 70 70 75
300 58 53 60 65 80 88 45 45 80 80 80 120 45 68 70 100 100 120 65 90 75 85
350 65 60 68 75 88 95 60 70 80 80 50 75 90 120 120 135
400 70 65 75 85 95 105 60 80 80 160 75 80 100 130 140 150
450 75 68 80 93 100 110 70 100 80 90 120 140 160 160
500 78 73 83 98 108 115 70 100 120 150 160 180 180

8-6 Energy Management for Motor-Driven Systems


Table 8-3
Multipliers to Determine Capacitor Kilovars Required for Power Factor Correction

ORIGINAL
POWER
FACTOR
C orre cte d P owe r F a ctor
0.80 0.81 0.82 0.83 0.84 0.85 0.86 0.87 0.88 0.89 0.90 0.91 0.92 0.93 0.94 0.95 0.96 0.99 1.0
0.50 0.982 1.008 1.034 1.060 1.086 1.112 1.139 1.165 1.192 1.220 1.248 1.276 1.306 1.337 1.369 1.403 1.440 1.589 1.732
0.51 0.937 0.962 0.989 1.015 1.041 1.067 1.094 1.120 1.147 1.175 1.203 1.231 1.261 1.292 1.324 1.358 1.395 1.544 1.687
0.52 0.893 0.919 0.945 0.971 0.997 1.023 1.050 1.076 1.103 1.131 1.159 1.187 1.217 1.248 1.280 1.314 1.351 1.500 1.643
0.53 0.850 0.876 0.902 0.928 0.954 0.980 1.007 1.033 1.060 1.088 1.116 1.144 1.174 1.205 1.237 1.271 1.308 1.457 1.600
0.54 0.809 0.835 0.861 0.887 0.913 0.939 0.966 0.992 1.019 1.047 1.075 1.103 1.133 1.164 1.196 1.230 1.267 1.416 1.559
0.55 0.769 0.795 0.821 0.847 0.873 0.899 0.926 0.952 0.979 1.007 1.035 1.063 1.093 1.124 1.156 1.190 1.227 1.376 1.519
0.56 0.730 0.756 0.782 0.808 0.834 0.860 0.887 0.913 0.940 0.968 0.996 1.024 1.054 1.085 1.117 1.151 1.188 1.337 1.480
0.57 0.692 0.718 0.744 0.770 0.796 0.822 0.849 0.875 0.902 0.930 0.958 0.986 1.016 1.047 1.079 1.113 1.150 1.299 1.442
0.58 0.655 0.681 0.707 0.733 0.759 0.785 0.812 0.838 0.865 0.893 0.921 0.949 0.979 1.010 1.042 1.076 1.113 1.262 1.405
0.59 0.619 0.645 0.671 0.697 0.723 0.749 0.776 0.802 0.829 0.857 0.885 0.913 0.943 0.974 1.006 1.040 1.077 1.226 1.369
0.60 0.583 0.609 0.635 0.661 0.687 0.713 0.740 0.766 0.793 0.821 0.849 0.877 0.907 0.938 0.970 1.004 1.041 1.190 1.333
0.61 0.549 0.575 0.601 0.627 0.653 0.679 0.706 0.732 0.759 0.787 0.815 0.843 0.873 0.904 0.936 0.970 1.007 1.156 1.299
0.62 0.516 0.542 0.568 0.594 0.620 0.646 0.673 0.699 0.726 0.754 0.782 0.810 0.840 0.871 0.903 0.937 0.974 1.123 1.266
0.63 0.483 0.509 0.535 0.561 0.587 0.613 0.640 0.666 0.693 0.721 0.749 0.777 0.807 0.838 0.870 0.904 0.941 1.090 1.233
0.64 0.451 0.474 0.503 0.529 0.555 0.581 0.608 0.634 0.661 0.689 0.717 0.745 0.775 0.806 0.838 0.872 0.909 1.068 1.201
0.65 0.419 0.445 0.471 0.497 0.523 0.549 0.576 0.602 0.629 0.657 0.685 0.713 0.743 0.774 0.806 0.840 0.877 1.026 1.169
0.66 0.388 0.414 0.440 0.466 0.492 0.518 0.545 0.571 0.598 0.626 0.654 0.682 0.712 0.743 0.775 0.809 0.846 0.995 1.138
0.67 0.358 0.384 0.410 0.436 0.462 0.488 0.515 0.541 0.568 0.596 0.624 0.652 0.682 0.713 0.745 0.779 0.816 0.965 1.108
0.68 0.328 0.354 0.380 0.406 0.432 0.458 0.485 0.511 0.538 0.566 0.594 0.622 0.652 0.683 0.715 0.749 0.786 0.935 1.078
0.69 0.299 0.325 0.351 0.377 0.403 0.429 0.456 0.482 0.509 0.537 0.565 0.593 0.623 0.654 0.686 0.720 0.757 0.906 1.049
0.70 0.270 0.296 0.322 0.348 0.374 0.400 0.427 0.453 0.480 0.508 0.536 0.564 0.594 0.625 0.657 0.691 0.728 0.877 1.020
0.71 0.242 0.268 0.294 0.320 0.346 0.372 0.399 0.425 0.452 0.480 0.508 0.536 0.566 0.597 0.629 0.663 0.700 0.849 0.992
0.72 0.214 0.240 0.266 0.292 0.318 0.344 0.371 0.397 0.424 0.452 0.480 0.508 0.538 0.569 0.601 0.635 0.672 0.821 0.964
0.73 0.186 0.212 0.238 0.264 0.290 0.316 0.343 0.369 0.396 0.424 0.452 0.480 0.510 0.541 0.573 0.607 0.644 0.793 0.936
0.74 0.159 0.185 0.211 0.237 0.263 0.289 0.316 0.342 0.369 0.397 0.425 0.453 0.483 0.514 0.546 0.580 0.617 0.766 0.909
0.75 0.132 0.158 0.184 0.210 0.236 0.262 0.289 0.315 0.342 0.370 0.398 0.426 0.456 0.487 0.519 0.553 0.590 0.739 0.882
0.76 0.105 0.131 0.157 0.183 0.209 0.235 0.262 0.288 0.315 0.343 0.371 0.399 0.429 0.460 0.492 0.526 0.563 0.712 0.855
0.77 0.079 0.105 0.131 0.157 0.183 0.209 0.236 0.262 0.289 0.317 0.345 0.373 0.403 0.434 0.466 0.500 0.537 0.685 0.829
0.78 0.052 0.078 0.104 0.130 0.156 0.182 0.209 0.235 0.262 0.290 0.318 0.346 0.376 0.407 0.439 0.473 0.510 0.659 0.802
0.79 0.026 0.052 0.078 0.104 0.130 0.156 0.183 0.209 0.236 0.264 0.292 0.320 0.350 0.381 0.413 0.447 0.484 0.633 0.776
0.80 0.000 0.026 0.052 0.078 0.104 0.130 0.157 0.183 0.210 0.238 0.266 0.294 0.324 0.355 0.387 0.421 0.458 0.609 0.750
0.81 0.000 0.026 0.052 0.078 0.104 0.131 0.157 0.184 0.212 0.240 0.268 0.298 0.329 0.361 0.395 0.432 0.581 0.724
0.82 0.000 0.026 0.052 0.078 0.105 0.131 0.158 0.186 0.214 0.242 0.272 0.303 0.335 0.369 0.406 0.555 0.698
0.83 0.000 0.026 0.052 0.079 0.105 0.132 0.160 0.188 0.216 0.246 0.277 0.309 0.343 0.380 0.529 0.672
0.84 0.000 0.026 0.053 0.079 0.106 0.134 0.162 0.190 0.220 0.251 0.283 0.317 0.354 0.503 0.646
0.85 0.000 0.027 0.053 0.080 0.108 0.136 0.164 0.194 0.225 0.257 0.291 0.328 0.477 0.620
0.86 0.000 0.026 0.053 0.081 0.109 0.137 0.167 0.198 0.230 0.264 0.301 .0450 0.593
0.87 0.000 0.027 0.055 0.083 0.111 0.141 0.172 0.204 0.238 0.275 0.424 0.567
0.88 0.000 0.028 0.056 0.084 0.114 0.145 0.177 0.211 0.248 0.397 0.540
0.89 0.000 0.028 0.056 0.086 0.117 0.149 0.183 0.220 0.369 0.512
0.90 0.000 0.028 0.058 0.089 0.121 0.155 0.192 0.341 0.484
0.91 0.000 0.030 0.061 0.093 0.127 0.164 0.313 0.456
0.92 0.000 0.031 0.063 0.097 0.134 0.283 0.426
0.93 0.000 0.032 0.066 0.103 0.252 0.395
0.94 0.000 0.034 0.071 0.220 0.363
0.95 0.000 0.037 0.186 0.329
0.96 0.000 0.149 0.292
0.97 0.108 0.251
0.98 0.060 0.203
0.99 0.000 0.143
0.000

Instructions: 1. Find the present power factor in column 1. 2. Read across to optimum power factor column. 3. Multiply that number by kW demand.
Example: If your plant consumed 410 kW, was currently operating at 73% power factor and you wanted to correct power factor to 95%, you would:
1. Find 0.73 in column 1. 2. Read across to 0.95 column. 3. Multiply 0.607 by 410 = 249 (round to 250).
4. You need 250 kVAR to bring your plant to 95% power factor.
If you don’t know the existing power factor level of your plant, you will have to calculate it before using this table.
To calculate existing power factor: kW divided by kVA = Power Factor

Power Factor Correction 8-7


The power triangle in Figure 8-4
indicates the demands on a plant
distribution system before and
after adding capacitors to improve
power factor. By increasing the
power factor from 70 percent to
95 percent, the apparent power is
reduced from 1,420 kVA to 1,050
kVA, a reduction of 26 percent.

Benefits of Power Factor


Correction
The cost-effectiveness of power
factor correction depends upon
such variables as utility power
factor penalties, the need for
additional system capacity, energy
and demand cost, hours of facility
operation, distribution system wire
sizes, and the distance between
the motor and the electrical
meter.8-8 As shown in the follow-
ing examples, it is critical to
understand your utility’s rate
structure in order to assess the
benefits or reduction in utility
billing due to power factor correc-
tion.8-1

Figure 8-4
Apparent Power Requirements Before and After Adding Power Factor
Correction Capacitors

70% PF
Before

8-8 Energy Management for Motor-Driven Systems


Example 8-1
Utility Rate Schedule: The utility measures and bills based upon total
current used (working plus reactive current) at $3.50/kVA Demand.

Plant Conditions: Assume a constant 4,600 kVA demand with an 80


percent power factor. Correct to 95 percent power factor.

Billing Before Power Billing After Power Factor Corrected to 95%


Factor Correction
4,600 kVA x $3.50 =
$16,100/month kW demand = kVA demand 1 x PF1

= 4,600 x 0.8 = 3,680

kWdemand
kVAdemand 2 =
PF2
3,680
kVA demand 2 = = 3,873
0.95

Where:

kVAdemand 1 = kVA demand before PF correction


kVAdemand 2 = kVA demand after PF correction
kWdemand = Electric demand in kW
PF1 = Original power factor
PF2 = Power factor after correction
Corrected Billing
3,873 kVA x $3.50 = $13,555/month

Savings are ($16,100-$13,555) x 12 months = $30,540/year

Up to $61,000 could be spent on power factor correction equipment if plant manage-


ment would support a two-year simple payback on investment.8-9

Power Factor Correction 8-9


Example 8-2
Utility Rate Schedule: In this scenario, the utility charges according to kW
demand ($4.50/kW) and includes a surcharge or adjustment for low power
factor. The following formula shows a billing adjustment based upon a
desired 95 percent power factor.

0 .95
kW billed = kW dem and x
PF

Where:
kWbilled = Adjusted or billable demand
kWdemand = Measured electric demand in kW
PF = Power factor as a decimal

The multiplier applies to power factors up to 0.95.

Plant Conditions: For our sample facility, the original demand is


4,600 kVA x 0.80 or 3,680 kW.

Billing Before Power Billing After Power


Factor Correction Factor Corrected to 95%

3,680 kW x 0.95
0.80

= 4,370 × $4.50 = 3,680 × $4.50


= $19,665/month or $235,980/year = $16,560/month or $198,720/year

Savings are $37,260/year

Additional Benefits of serving the same kW load.


Through adding power factor
Power Factor Correction correction capacitors to your
The “Industrial Electrical Distri- system, you can add additional kW
bution Systems Guidebook” load without increasing line
contains worksheets for calculat- currents, wire size, transformer
ing the benefits of correcting size, or facility kVA charges. By
individual motor and total plant including power factor correction
power factor.8-10 capacitors in new construction or
facility expansions, you can reduce
Power factor correction capacitors project costs through decreasing
increase system current-carrying the sizes of transformers, cables,
capacity, reduce voltage drops, and busses, and switches.8-1 In prac-
decrease distribution system tice, however, ampacity ratings are
resistance (I2R) losses.8-1 Increas- a function of full-load equipment
ing the power factor from 75 values; therefore, size reductions
percent to 95 percent results in a may be precluded by electrical
21 percent lower current when codes.

8-10 Energy Management for Motor-Driven Systems


Poor power factor contributes to Power Factor Correction
power losses in the in-plant distri-
bution system. Calculate the Costs
power loss by squaring the line The average installed cost of
current and multiplying by the capacitors on a 480-volt system is
circuit resistance (I2R). Generally, about $30 per kVAR. Automatic
distribution system losses are small power factor controllers or
— a typical industrial plant will capacitors with harmonic filters
suffer only a 2 percent loss in the cost more. These features are
cables if the cables are loaded to typically associated with capaci-
full capacity.8-6 Reductions in tors exceeding 100 kVAR. A
losses (upstream of the power single, large capacitor bank has a
factor correction capacitor loca- lower installed cost than multiple
tions) are calculated by the rela- small installations scattered
tionship shown in Equation 8-2:8-1 throughout the plant. The cost
per kVAR for small capacitors on
Excessive current draws due to motors is substantially higher due
low power factors also cause to labor and materials costs. The
excessive system voltage drops. cost for large banks is lower on a
Operating motor-driven equip- per kVAR basis because of the
ment under low voltage conditions economy of scale. The installed
results in efficiency decreases, cost per kVAR of capacitance is
motor overheating, and subse- also lower at higher voltages. At
quent diminished motor life. By higher voltage levels (2400V and
adding power factor correction up) unit costs are generally about
capacitors, you can restore operat- $6 - $12 per kVAR installed.8-6
ing voltage to proper design Suppliers of capacitors are listed
conditions. in Appendix D.

Equation 8-2

Where:

% reduction = Percent reduction in distribution losses


PF1 = Original power factor
PF2 = Power factor after correction

Power Factor Correction 8-11


Avoiding Harmonic
Short circuit MVA repre- If the resonant frequency is near
sents system impedance. It Resonances When to an odd harmonic, consider
is the current (in millions Installing Capacitors reducing capacitor MVA to bring
of amperes) that would be the system out of tune with that
Approximately twenty percent of harmonic. This is particularly
drawn by a short circuit,
industrial plants that install and important if you have a known
multiplied by the no-load
operate capacitors must pay source of these harmonics. For
voltage of the system at the careful attention to the creation of
point of interest. In reality, example, adjustable speed drives
steady state harmonic resonances.8- can be a significant source of 5th
circuit protectors would 6
The resonant frequency created and 7th harmonics.
blow before short circuit with a capacitor and system
current could stabilize, so it inductance is calculated by Equa- Resonant conditions near the 3rd,
is defined by linearly tion 8-3. As shown in the equa- 5th, 7th, 11th, and 13th harmonic
extrapolating the volts-per- tion, the square root of the short are usually the most troublesome.8-
amp system voltage drop, circuit MVA divided by the capaci- 11
Harmonics cause additional
at moderate load, down to tor MVAR indicates the resultant noise on the line and generate
zero system volts. harmonic for the system under heat. This heat can cause failure
study.8-11 of capacitors or transformers.
Consult with your capacitor
Equation 8-3 supplier or a specialist in harmonic
mitigation. Many vendors offer
harmonic analysis services and
will assist you to properly select
and install power factor correction
equipment. Appendix D contains
a list of manufacturers of power
factor correction capacitors.

Example 8-3
Consider a case where a 1200 kVAR capacitor is to be installed on a
12.47 kV system at a location where the three phase short circuit
current is 2800 amps.

3
MVA shortcircuit = 2800 amps x 12.47 kV x 1,000,000 = 60.5

60.5
MVAR capacitor = 1200 kVAR 1000 = 1.2 MVAR and h f = = 7.1
1.2

8-12 Energy Management for Motor-Driven Systems


References
Chapter 8

8-1 “Power Factor Correction: A Guide for the Plant Engineer,”


Commonwealth Sprague Capacitor, Inc., PF-2000E, Octo-
ber 1991

8-2 Carroll, Hatch & Associates, Inc., “An Electric


Motor Energy Efficiency Guide and Technical
Reference Manual,” (Draft) June 1994.

8-3 Carroll, Hatch & Associates, Inc., “A Procedure for Develop-


ing an Energy Efficiency Plan for the Use of Electric Motors
in an Industrial Setting,” (Draft), June 1994.

8-4 “Reducing Power Factor Cost,” Electric Ideas Clearinghouse


Technology Update, Bonneville Power Administration, April
1991.

8-5 Edward Ader and William Finley, Compensating for Low Power
Factor, Plant Engineering, June 17, 1993.

8-6 “Industrial Power Factor Analysis Guidebook,” Bonneville


Power Administration, DOE/BP-42892-1, April 1995.

8-7 Portland General Energy Systems, “Power Quality for


Electrical Contractors: Application Guide, Volume 7:
Recommended Practices,” Electric Power Research Institute,
December 1994.

8-8 Power Factor Correction Equals Big Savings, Georgia Tech


Research Institute, Conserver, March 1991.

8-9 Fred L. Montgomery, The Dollars and Sense of Power Factor


Correction, AIPE Facilities Management, Operations &
Engineering, September/October 1989.

8-10 Rob Gray, Washington State Energy Office, “Keeping the


Spark in Your Electrical System: An Industrial Electrical
Distribution Systems Guidebook,” Funded by the Bonneville
Power Administration, U.S. Department of Energy,
Pacificorp, Portland General Electric and Tacoma City Light,
October 1995.

8-11 PSI Energy, Avoiding Steady-State Harmonic Resonances When


Installing Capacitors, Power Clinic Tech Tip, Issue Number 7.

Power Factor Correction 8-13


8-14 Energy Management for Motor-Driven Systems
Chapter 9
Preventative and
Predictive
Maintenance
Planning
Everyone knows that mainte- separate the tasks on some basis
nance is good. The traditional other than predictive versus
purpose has been two-fold: keep preventative.
equipment from failing prema-
Mechanical tasks like lubrication
turely and keep equipment
and cleaning might require a
calibrated for optimum perfor-
different schedule and different
mance. Both of these objectives
tradespeople than electrical tasks.
can be thought of as preventative
Vibration and acoustic testing
maintenance. A two-year Factory
could fit in either category. Some
Mutual study reveals that effec-
tasks like infra-red scanning or
tive preventative maintenance
dry ice cleaning could require an
programs could have prevented
outside contractor operating on
more than half the losses associ-
yet another schedule. You must
ated with electrical equipment
design a system to fit your unique
failure. It also showed that well-
situation. This chapter will
maintained motors dramatically
discuss key elements of any good
improve a facility’s overall effi-
plan but it can not dictate details.
ciency.9-1
To have an effective maintenance
More recently, attention has been
plan, all four of the following
directed at predictive mainte-
must be executed well:
nance. Predictive maintenance
refers to scheduled testing and n Identify responsible
measurement, and trending of the personnel
results over time. Proper analysis Personnel must be designated
of the results can predict an for the necessary activities.
impending failure so that neces- Best results follow when staff
sary repair, cleaning, or alignment buy in to the concept of PPM.
can be scheduled before a costly This is most likely to occur
catastrophe occurs. when they are given the
necessary training and tools,
A good maintenance program
and they participate in devel-
contains elements of both predic-
oping the maintenance plan.
tive and preventative mainte-
nance (PPM). Both involve n Establish a schedule
scheduled actions to the motors Establishing a schedule is an
and controls as well as record iterative process. It is often
keeping. Depending upon your necessary to prescribe some-
situation, it may be efficient to what frequent intervals at
merge the two activities. How- first, then experiment with
ever, depending upon the organi- lengthening the intervals.
zation of your maintenance staff, Some activities can actually be
and the service intervals you harmful if performed too
select, it may be beneficial to frequently (e.g. high voltage
insulation testing and bearing

Preventative and Predictive Maintenance 9-1


greasing). If you observe that may be the best of all. There
certain test results progress are certain special applica-
uniformly, you can establish a tions software packages that
definite and often longer are tailored to this type of
interval. If bearings survive record keeping and analysis.
well at a given lubrication MotorMaster + contains an
interval, you can experiment excellent motor inventory
with a longer lubrication module that is dedicated to
interval. Revise, but do not keeping track of motor perfor-
abandon the schedule. mance trends and calculating
the most cost effective alterna-
n Keep records
tives when motors fail or
Record keeping can be done
become obsolete.
in a number of different ways.
Using printed cards or data The following sections cover
sheets is the oldest method major categories and make recom-
and may be sufficient. There mendations on servicing and
are certain advantages to testing. Some of the recommen-
going “high tech” with a dations may seem too costly to be
laptop computer or special justifiable for small inexpensive
electronic recording device for motors. If so, omit them, but
data entry. One advantage is remember to consider the total
that analysis routines can be cost of an untimely motor failure.
set up to graph trends with- The unscheduled downtime and
out a second “handling” of loss of materials in process can far
penciled forms by a data entry exceed the cost of the motor.
operator. The costliest ap-
proach involves special test
instruments that connect
Cleaning
electrically and actually enter A clean motor is more than just a
measured data into computer pretty motor. Avoid too many
files. Certain actions like thick coats of paint or dirt build-
recording lubrication and ups which can foul heat transfer
cleaning are not amenable to surfaces. Why is dirt bad? Dirt is
such devices. New products a very general word that can
that bring maintenance into mean many things: dust, corro-
the “information age” are sive buildups, sugary syrups from
evolving rapidly. Keep food processing, electro-conduc-
abreast of these develop- tive contaminants like salt depos-
ments. its or coal dust. It can damage a
motor in three ways. It can attack
n Analyze results the electrical insulation by abra-
Testing and record keeping sion or absorption into the insula-
are only as good as the follow- tion. It can contaminate lubri-
up analysis. There are various cants and destroy bearings.
software tools to help.
Spreadsheets and database A clean motor runs cooler. Dirt
programs are useful for builds up on the fan-cooled motor
storing and manipulating data inlet openings and fan blades.
and especially for graphing This reduces the flow of air and
trends. A third category of increases the motor operating
software, the statistical pack- temperature. Dirt on the surface
age, is often overlooked but of the motor reduces heat transfer

9-2 Energy Management for Motor-Driven Systems


by convection and radiation. This Motor manufacturers’ recommen-
is especially critical for totally dations should be followed Some of these recommendations
enclosed motors since all the initially. Eventually, with some may seem too costly to be
cooling takes place on the outside experimentation and analysis of justifiable for small inexpensive
surface. Heavily loaded motors well-kept records, you may
motors. If so, omit them. But
are especially vulnerable to discover that a different type of
remember to consider the total
overheating, so they have little lubricant or lubrication interval is
cost of an untimely motor
tolerance for dirt. better. It is good to compare
experience with others in your failure.
Surface dirt can be removed by same industry because the operat-
various means, depending upon ing environment has a great effect
its composition. Compressed air upon re-lubrication requirements.
(30 psi maximum), vacuum Consult with your motor repair
cleaning and direct wipe down shop. By inspecting bearings and
with rags or brushes are usually analyzing failures, the repairer
used. There has been a recent may be able to tell if you are using
introduction of dry ice “sand” the wrong lubricants, lubrication
blasting. This is usually done by a methods, or intervals.
special contractor. The dry ice is
less abrasive than mineral depos- Typical lubrication intervals vary
its, is non-electro-conductive, and from less than three months (for
leaves no residue other than the larger motors subject to vibration,
removed dirt. severe bearing loads, or high
temperature) to five years for
Dirt inside the motor is more integral horsepower motors with
difficult to remove. It is best to intermediate use. Motors used
keep it from getting inside. A seasonally should be lubricated
totally enclosed motor helps in annually before the season of
this regard, but fine dust can use. 9-2
invade and destroy even an
explosion-proof motor. Some One cannot merely be conserva-
larger motors can be provided tive and over-lubricate. There are
with a filter in the ventilation air many ways that improper lubrica-
passages to keep out dirt. Keep- tion shortens bearing life. Re-
ing moisture out can decrease the lubrication with a different grease
attachment of dirt inside the can cause bearing failure when
motor and reduce the electrical two incompatible greases mix.
conductivity of some contami- Grease consists of an oil in some
nants. This will reduce the type of constituent to give it body
frequency with which the motor or thickness so that it doesn’t run
must be disassembled for clean- out of the bearing. Mixing
ing. greases with incompatible con-
stituents can cause the compo-
nents of the mixed grease to
Lubrication separate or harden. Table 9-1 is a
Many small or integral horse- guide to compatibility of grease
power motors have factory-sealed bases.9-3
bearings that do not require re-
Adding too much grease or
lubrication. All others require
greasing too frequently can force
lubrication. Unfortunately,
grease past the bearing shield or
lubrication can be more art than
seal into the motor, resulting in
science.
winding damage. Merely having

Preventative and Predictive Maintenance 9-3


too much grease in the bearing or have allowed unexplained
itself can prevent proper flow of bearing failures. In this case,
the grease around the rollers. review alternative lubricant
Sometimes bearing failures due to specifications and select a type
over-lubrication are interpreted as compatible with the known
insufficient lubrication and contaminants in your operating
intervals are made even shorter. environment. For severe situa-
tions, a synthetic lubricant may be
Perhaps the worst problem with best. Consult with lubricant
greasing is introduction of con- vendors, the motor manufacturer,
taminants. Contamination occurs and your repair shop. Lubricants
when strict cleanliness standards vary in their tolerance to tempera-
are not followed in grease storage ture, water, salt or acids.
and application. It may be wise to
buy grease in more expensive Finally, remember to completely
individual cartridges rather than remove old lubricant before
large quantities that are subject to trying a different one. If this is
contamination when refilling impossible, relubricate soon after
grease guns. Take special care introduction of a new lubricant. If
with grease fittings. Clean the there is a plug under a grease
fitting before filling and keep the lubricated bearing, remove this
grease gun nozzle covered when when first greasing with a new
not injecting grease. grease to encourage flushing of
the old. Some authorities recom-
When selecting oil or grease, mend running the motor for
begin with the motor manufactur- about an hour with the plug out
ers’ recommendations. However, to help flush the old grease. The
these sometimes are quite general Electrical Apparatus Service
Table 9-1
Grease Compatibility

9-4 Energy Management for Motor-Driven Systems


Association recommends remov- life of the coupling. One source
ing the plug for all regreasing to attributes 45% to 80% of bearing
purge the bearing of excess and seal failures to misalign-
grease.9-4 The advisability of this ment. 9-5
practice depends upon the geom-
etry of the bearing cavities and Alignment means that the
type of seal/shield. Again, centerline of the motor and load
consult the manufacturer or shaft coincide. If they are parallel,
repairer. but do not coincide, this is parallel
misalignment. If the centerlines
are not parallel but they intersect
Mountings, Couplings, inside the coupling, this is angular
and Alignment misalignment. It is certainly
Mounting is not really a mainte- possible to have misalignment in
nance issue, but if it is inadequate, both respects.
it can result in serious mainte-
nance problems. The entire Misalignment is usually the result
structure must be rigid with a flat of errors in installation. However
coplanar surface for the four misalignment sometimes devel-
mounting legs. The same applies ops after installation. This can
to the structure for mounting the occur if the mounting structure is
load. Both motor and load struc- not completely rigid, if vibration
ture must be rigidly bound to the or impact causes something to
floor or a common structure. slip, or if dirty or bent shims were
Failure to provide a solid mount- originally used. Alignment
ing can lead to vibration or should be checked soon after
deflection which leads to bearing installation and less frequently
failure. after that if there are no condi-
tions likely to cause misalign-
Vertical motors can be even more ment. If there is evidence of
demanding than horizontal misalignment, such as vibration,
motors because the mounting warm bearings or couplings,
circle constitutes a small foot- unusual noise, or rubber crumbs
print for a large mass cantilevered under the coupling, check align-
above. Pliancy in the mounting ment.
structure can exacerbate low
frequency vibration to which Most users align couplings with a
vertical motors are vulnerable. dial indicator. To check for
Always check hold-down bolts/ angular misalignment, mount the
dowels at every maintenance indicator on one shaft and contact
interval and do a visual check for the other coupling flange with the
cracks or other failures of the plunger parallel to the shaft. To
mounting system. check for parallel misalignment,
arrange the plunger radial to the
Coupling alignment is often flange. Rotate the shafts through
promoted for energy efficiency. at least 180° and ideally 360°,
Energy loss in couplings is some- checking for runout.
times overstated, but proper For misalignment in the horizon-
alignment is always important to tal plane, loosen motor mounting
bearing and coupling life. A bolts and reposition the motor.
slight misalignment can dramati- For any misalignment in the
cally increase the lateral load on vertical plane, shims must be
bearings. It can also shorten the added or removed. Angular

Preventative and Predictive Maintenance 9-5


vertical misalignment requires driven pulleys to be in the same
unequal application of shims plane. You can usually check
By trending a motor’s operating between shaft end and opposite both of these conditions with a
conditions over time, you may end feet. Apply shims so that the good straight edge. Once aligned,
detect problems that are motor rests with equal weight on with a rigid base, alignment tends
developing in the motor, load, or both diagonal pairs of feet (i.e., to hold constant much better than
power distribution system. there is no rocking of the motor belt tension.
before tightening bolts). Shims
and the work area around motor When belts appear worn or
feet must be completely clean. require over-tensioning to pre-
Discard any shims that are bent or vent slip, they should be replaced.
scuffed. Always make a final Always replace multiple V-belts at
alignment check after the mount- the same time with a matched set.
ing bolts are torqued. Re-check new V-belt tension
several times until they complete
Alignment is not easy. Many their break-in stretching (usually
frustrating trial and error cycles of within the first 48 operating
position and remeasure can be hours).
required. There are computer
devices and software available to Consider replacing V-belts with
help in choosing shim size and synchronous belts (sometimes
positioning, but nothing makes it called cog belts) to eliminate slip
completely easy. In recent years, loss. However, before doing so,
laser alignment devices have determine whether slip is neces-
become the rage. They are accu- sary in your application to protect
rate and easy to use, particularly the motor and load from jam-
where long extensions would be ming. Slip is sometimes required
required to mount dial indicators. in systems that perform crushing
The laser devices simplify attach- or pumping of fluids with en-
ment, eliminate the problem of trained solids. Operators some-
compliance of dial indicator times rely upon the horrible
mounting arms, and are usually screech to alert them that a jam
associated with (or directly has occurred.
connected to) computer devices
that prescribe the adjustments
necessary at all four legs.
Operating Conditions
Motor operating conditions affect
Belt drives are entirely different efficiency and reliability. Record
from couplings, but they have operating conditions at regular
their own needs for vigilant care. intervals. This will ensure that
The most important thing is to they are within tolerances for the
control their tension. If belts are motor. Also, trending these
too loose, they tend to vibrate, conditions can allow early detec-
wear rapidly, and waste energy tion of problems developing in
though slippage. If they are too the motor, load, or power distri-
tight, they will also wear exces- bution system.
sively and can dramatically
Operating speed and voltage, and
shorten bearing life though
current on all three phases should
excessive lateral loading.
be recorded. Also record power
and power factor; these can both
Belt drives require parallel align-
be determined by using either a
ment between motor and load
power factor meter or power
shaft and require drive and

9-6 Energy Management for Motor-Driven Systems


meter. Refer to Chapter 4 for A change in current is usually
information on selecting appro- associated with a change in shaft
priate test instruments for these load. However, other factors can
measurements. For belt drive be involved such as a change in
applications, also record speed of voltage as discussed above. Refer
the load; it can be compared to to Equation 5-4 to correct load
motor speed over time to detect estimates for a voltage change.
changes in slippage. An increase in current after motor
repair may signal degradation
A significant change in voltage is from the failure and repair, such
not likely to be caused by the as turning down the rotor diam-
motor, but it affects the way the eter to clean up a rub. This will
motor performs. Figure 9-1 shows be accompanied by an increased
how various full load perfor- power factor and lower efficiency.
mance parameters tend to change It is best to determine shaft load
with a departure from nameplate change by determining input
voltage. At part load the changes power with a power meter or
in power factor and efficiency are combining a power factor reading
worse with overvoltage, but only with voltage and current readings
slight at undervoltage. using Equation 5-1. Output
power still needs to be adjusted
Figure 9-1
Effect of Voltage Variation on Induction Motor Performance Characteristics

Preventative and Predictive Maintenance 9-7


for efficiency differences which It is important not to mistake this
are associated with voltage situation for a motor problem. If
change as indicated in Figure 9-1. there is a large current unbalance
with little or no voltage unbal-
When power changes, it usually
ance, the motor may be at fault. A
means something is changing in
delta wound motor will still draw
the load. With a centrifugal
some current from all phases even
pump, a reduction in power may
with an open circuit in one phase
mean damage to an impeller.
winding. Take the motor off line
Inspect for variations in fluid flow
and perform a winding resistance
and discharge pressure. With belt
check. Aim for zero voltage
drives, a reduction in power may
unbalance. Unbalance over 2% is
mean a slipping belt. With fans
cause for immediate action.
and blowers, a reduction in
power generally signals clogging With any of the measured condi-
of filters or obstruction of duct tions, do not assume the condi-
work. Since motor speed only tion has progressively changed
varies by a couple of percent from over time. Many conditions
idle to full load, load changes are associated with the load or power
associated with changes in torque supply vary during the day, even
by the load. Understand how minute to minute. These can be
your load torque requirement picked up with a recording logger
varies with operating conditions. left in place for several hours or
Power changes can then be used days. Often the patterns immedi-
to detect load problems. ately hint at an explanation which
may even be normal behavior.
It is very important to note phase
Other times, certain fluctuations
balance because unbalance can
remain an unsolved mystery.
dramatically reduce motor effi-
ciency and life. Check both volt- An excellent tracking tool for
age and current balance. A slight managing your motor inventory
voltage unbalance can cause a and keeping track of power
larger motor current unbalance. supply and loading conditions is
the MotorMaster+ software.

Equation 9-1

P 02 P 2 x e2
=
P 01 P1 x e1

Where:
Po2 = Corrected output power
Po1 = Output power before correction
e2 = Corrected efficiency
e1 = Efficiency before correction
P2 = Corrected input power
P1 = Input power before correction

9-8 Energy Management for Motor-Driven Systems


Consult the Motor Challenge n Under-voltage,
Information Clearinghouse at n Development of a voltage
(800) 862-2086 for availability of unbalance condition,
this product.
n Line harmonics,
n Recent multiple starts, plug-
Thermal, Vibration and ging, or jogging.
Acoustic Tests In variable speed drive powered
Certain non-electrical tests can motors, low speed without a
reveal problems that either result dramatic torque reduction can
from or cause motor components cause overheating. Check with
to deteriorate. the drive and motor manufac-
turer regarding minimum safe
speed for the torque loading.
Thermal
Some larger motors have tem-
Thermal testing is a good indica- perature sensors built right into
tor. It is not possible to measure the stator slots. This makes
surface temperature of a motor recording and trending tempera-
only once and infer its efficiency ture easy. When rewinding large
or general health. However, over or critical motors that do not have
time, increases in temperature temperature sensors, consider
which cannot be explained by having the sensors installed. Not
other observed factors often only can they allow trending, they
signal problems. can be connected to protection
Use a good contact thermometer equipment that sounds an alarm
at maintenance intervals. (Main- or shuts down the motor when
tenance personnel can sometimes temperature limits are exceeded.
get early warning of a developing
problem by cautiously touching Vibration
the middle of the motor and
bearing locations daily.) Measure A change in vibration often
temperature after the motor has signals a bearing problem. It can
been running long enough for also signal other problems like a
temperature to stabilize. A load imbalance, bent shaft, rotor
greater increase in temperature at damage, coupling misalignment,
the bearing location than in the increase or change in line har-
middle of the motor suggests a monics, or even voltage unbal-
bearing problem. Verify adequate ance.
lubrication and schedule a bear- Many instruments are available to
ing change soon. If it is a small measure vibration. They vary
motor on a non-critical applica- from very sophisticated equip-
tion, it is sometimes sufficient to ment that reads vibration and
obtain a spare and wait. prints frequency profiles to
A temperature increase away simple hand-held gadgets with a
from the bearings is usually row of resonating reeds.
associated with something exter- Increased vibration at multiples of
nal to the motor that can harm the line frequency often signals
motor. Check for: electrical problems like harmon-
ics. Vibration at 120 Hz can be
n An increase in loading,
indicative of phase unbalance.
n Obstruction of cooling air Vibrations at low multiples of
flow, actual rpm suggest mechanical

Preventative and Predictive Maintenance 9-9


imbalance within the motor or materials are available to guide in
load, or failure of some part of the their application.9-8, 9-9, 9-10, 9-11, 9-12, 9-13
mounting. Bearing problems are
The motor circuit needs mainte-
usually high frequency vibrations
nance and inspection, too. Fuses
that may not be exact multiples of
degrade and develop high resis-
either line frequency or rpm.
tance. Connections become loose
Instrument manufacturers usually
because of thermal cycling and
provide analysis documentation
creep. Aluminum components
that assists in diagnosing causes
are particularly vulnerable to
of certain vibration changes.
creep, the tendency to deform
slowly over time with stress.
Acoustic Contacts become burned and
worn so they “make” with high
Audible vibration can often alert
resistance or fail to “make”
experienced personnel to prob-
simultaneously. At annual main-
lems. The most common of these
tenance intervals tighten connec-
are bearing problems. Electronic
tions with a torque wrench. Then,
ultrasonic listening equipment
check connections and contacts
can sometimes detect certain
with a micro-ohmmeter. Trend
bearing problems like pitting
the results to reveal changes. It is
from arcing or the occurrence of
difficult to give guidelines on
arcing in the windings.
acceptable resistance because of
the tremendous difference in
Electrical Tests current between motors of differ-
ent power and voltage. Some-
Certain electrical tests should be
times it helps to determine rea-
periodically performed on the
sonableness by converting the
motor and motor circuit. Tests
resistance values to watts lost or
performed on the motor generally
voltage drop. This is easily done
detect insulation problems. Tests
with the Ohm’s law equations.
performed on the distribution
(See Equation 9-2.)
system frequently detect loose
connections in the motor circuit, It is inconvenient and time con-
and can also detect winding suming to de-energize circuits to
errors in the motor. perform circuit troubleshooting
maintenance. Some people
Insulation resistance testing is the
supplement this with infrared
most important predictive motor
thermography. Smaller firms
electrical test. There are a number
often contract for this service.
of special insulation resistance
Equipment varies from small
tests that can reveal degradation
hand-held non-contact thermom-
in insulation. Some can be used
eters to devices that give color
to trend degradation and foresee
images of equipment with the
impending failures so a motor can
colors correlated to temperature.
be pulled for a clean and bake.
This technology can identify
This can avoid a costly or irrepa-
trouble spots quickly without
rable failure. These tests are
having to de-energize circuits.
known variously as AC or DC
Various ANSI, IEEE, and NEMA
High Potential (Hi-Pot) test, surge
standards give guidance on limits
comparison testing, polarization
of temperature rise and ultimate
index (P-I) test, etc. The methods
temperatures for various electrical
are too involved for complete
system components.
description here, but numerous

9-10 Energy Management for Motor-Driven Systems


Motor circuit analysis is growing Storage and Transport
in popularity. This service is often
offered by private contractors. Motors can fail sitting on the
The process usually consists of shelf. Indeed, they can have a
connecting proprietary test shorter life unpowered than
equipment to the circuit at the continuously running. Lubricant
motor control panel. The equip- can drain away from bearing
ment generally energizes the surfaces and expose them to air
circuit with some sort of low and moisture. Even a tiny rust pit
power signal or pulsing, followed from such exposure can begin a
by an analysis of the circuit progressive failure when the
response with a computerized motor is put into service. High
detector. Circuit resistance in- humidity is also an enemy to the
cluding motor winding resistance winding insulation. Most insula-
is determined. Sources of induc- tion will absorb moisture from the
tance and capacitance are mea- air to a degree that significantly
sured and asymmetries detected. reduces dielectric strength. Vibra-
tions can damage ball and roller
A very comprehensive guidebook bearings when the shaft is not
on maintaining distribution turning. This is most common
system health and symmetry is when motors are installed in high
Keeping the Spark in Your Electrical vibration equipment and subject
System: An Industrial Electrical to long periods not running, but it
Distribution Maintenance Guide- sometimes happens in transporta-
book.9-7 It covers all aspects of the tion and storage areas subject to
electrical distribution system vibration.
including methods of testing and Several things are necessary to
diagnosis, cost of uncorrected reduce the stress of storage. If
problems, and maintenance motors are connected, they
issues. should be started and run up to

Equation 9-2

Vj = Ij x R

P j = I j2 x R

Where:

VJ = RMS voltage across a junction


IJ = RMS current through a junction
R = Resistance in ohms
PJ = Power dissipated in a junction in watts

Preventative and Predictive Maintenance 9-11


temperature at least monthly;
weekly is better in high relative
humidity areas. For motors in
storage, rotate the shaft at least
monthly to reposition the bear-
ings and distribute the lubricant.
Humidity control is imperative in
storage areas. During cold
weather, this can usually be
accomplished by heating the
storage area. If there are no
sources of moisture (people,
coffee makers, rain leaks, etc.), a
15°F rise above outdoor tempera-
ture will bring relative humidity
under 70%, no matter how humid
it is outside. During moderate to
hot weather, dehumidification or
air conditioning may be neces-
sary. Some motors can be
equipped with internal heaters by
the manufacturer or when being
rewound. These can be con-
nected to keep the windings 10-
20°F warmer than ambient when
the motor is not running. When
heaters are not installed, the
motor can be connected to a low
voltage DC power supply so that
the windings serve as a low
power heater. The power supply
needs to be either current regu-
lated or provided at a voltage
determined by winding resis-
tance. Consult your motor re-
pairer for recommendations on a
power supply. If a motor is to be
put into service after prolonged
storage in less than ideal condi-
tions, warm it for a day or more
before powering it.
Before shipping a motor, block the
shaft to prevent axial and radial
movement. If it is oil lubricated,
drain the oil and tag the reservoir
as empty.

9-12 Energy Management for Motor-Driven Systems


References
Chapter 9

9-1 “Quality Partnering: A Guide to Maximizing Your


Electromechanical Systems,” Electrical Apparatus
Service Association, St. Louis, MO

9-2 Todd Litman, “Efficient Electric Motor Systems,” The


Fairmont Press, Inc., 1995, Lilburn, GA

9-3 “Incompatibility of Greases,” NSK Techtalk Vol. 01, No.


02, April 1992, Technical Tip-Sheet of the NSK Corpora-
tion

9-4 “How to Get the Most From Your Electric Motors,”


Electrical Apparatus Service Association, St. Louis, MO

9-5 Richard L. Nailen, “Managing Motors,” Barks Publica-


tions Inc., 1991, Chicago, IL

9-6 “Electrical Engineering Pocket Handbook,” Electrical


Apparatus Service Association, 1993, St. Louis, MO

9-7 Rob Gray, Washington State Energy Office, “Keep-


ing the Spark in Your Electrical Distribution System:
An Industrial Electrical Distribution Maintenance
Guidebook,” Bonneville Power Administration,
United States Department of Energy, PacifiCorp,
Portland General Electric, Tacoma Public Utilities,
October 1995.

9-8 “EASA Standards for the Repair of Electrical Appara-


tus,” The Electrical Apparatus Service Association, St.
Louis, MO

9-9 Institute of Electrical and Electronics Engineers, “IEEE


Std. 43-1974(R1991) IEEE Recommended Practice for
Testing Insulation Resistance of Rotating Machinery.”
(ANSI)

9-10 Institute of Electrical and Electronics Engineers, “IEEE


Std. 95-1977 (R1991) IEEE Recommended Practice for
Insulation Testing of Large AC Rotating Machinery with
High Direct Voltage.” (ANSI)

Preventative and Predictive Maintenance 9-13


9-11 National Electric Manufacturers Association, “NEMA
Std. MG 1-1993 (R3): Motors and Generators.” Virginia,
1995.

9-12 Howard W. Penrose, “Field Testing Electric Motors for


Inverter Application,” Transactions: Electrical Manu-
facturing & Coil Winding ’96, Electrical Manufacturing
& Coil Winding Association, Inc.

9-13 David E. Schump, “Predict Motor Failure with Insula-


tion Testing,” Plant Engineering, September 1996

9-14 Energy Management for Motor-Driven Systems


Appendix A
Motor Nameplate and Field Test Data Form
Employee Name ________________________ Facility/Location ________________________
Company ______________________________ Department _____________________________
Date ___________________________________ Process ________________________________

General Data Motor Operating Profile


Serving Electrical Utility _________________ Weekdays Wknd/Holiday
Energy Rate ($/kWh) ________________ Days/Year Days/Year
Hours 1st Shift ________ ________
Monthly Demand Charge ($/kW/mo.) _____
Per 2nd Shift ________ ________
Application _____________________________
Day 3rd Shift ________ ________
Type of equipment that motor drives
Annual Operating Time ______ hours/year
Coupling Type __________________________
Motor Type (Design A,B,C,D _____________ Type of load (Place an “X” by the most
AC,DC, etc.) appropriate type)
Motor Purchase Date / Age ______________ ____ 1. Load is quite steady, motor “On” during shift
____ 2. Load starts, stops, but is constant when “On”
Rewound _______________ ¨ Yes ¨ No
____ 3. Load starts, stops, and fluctuates when “On”
Motor Nameplate Data
Answer the following only if #2 or #3 above
1. Manufacturer ________________________ was selected:
2. Motor ID Number ____________________ % of time load is “on” ____%

3. Model _______________________________ Answer the following only if #3 was selected:


Estimate average load as a % of motor size____%
4. Serial Number _______________________
5. NEMA Design Type __________________
Measured Data
6. Size (hp) ____________________________ Supply Voltage
By Voltmeter
7. Enclosure Type ______________________
Line- Vab ________
8. Synchronous Speed (RPM) ___________ to- Vbc ________ Vavg ______
Line Vca ________
9. Full Load Speed (RPM) _______________
10. Voltage Rating ______________________ Input Amps
By Ampmeter
11. Frame Designation __________________ Aa __________
Ab __________ Aavg ______
12. Full Load Amperage _________________ Ac __________
13. Full Load Power Factor (%) __________
Power Factor (PF) _______________________
14. Full Load Efficiency (%) ______________ Input Power (kW) ________________________
15. Service Factor Rating ________________ If available. Otherwise equal to:
Vavg x A avg x PF x 3 / 1000
16. Temperature Rise ___________________
Motor Operating Speed _________________
17. Insulation Class _____________________ By Tachometer

18. kVA Code ___________________________ Driven Equipment Operating Speed ______

Motor Nameplate and Field Test Data Form A-1


A-2 Energy Management for Motor-Driven Systems
Appendix B
Average Efficiencies for Standard Efficiency
Motors at Various Load Points

Efficiencies for 900 rpm, Standard Efficiency Motors


Load Level In Percent
Motor ODP TEFC
Size 100 % 75% 50% 25% 100% 75% 50% 25%
10 87.2 87.6 86.3 78.3 86.8 87.6 86.8 77.3
15 87.8 88.8 88.2 79.6 87.5 88.7 88.1 79.1
20 88.2 89.2 88.0 81.8 89.2 89.9 89.2 82.6
25 88.6 89.2 88.0 83.0 89.7 90.3 89.1 78.6
30 89.9 90.7 90.2 84.5 89.6 90.5 86.5 84.1
40 91.0 91.8 91.7 86.2 90.5 91.4 85.5 85.0
50 90.8 91.9 91.1 87.1 90.2 91.0 90.2 84.9
75 91.7 92.4 92.1 86.5 91.6 91.8 91.0 87.0
100 92.2 92.2 91.8 85.8 92.4 92.5 92.0 83.6
125 92.9 92.3 91.7 86.9 93.0 93.1 92.1 87.9
150 93.3 93.1 92.6 89.5 93.0 93.4 92.5 NA
200 92.8 93.5 93.1 NA 93.7 94.1 93.4 NA
250 93.1 93.5 93.0 NA 91.7 94.8 94.5 NA
300 93.1 93.7 92.9 92.7 94.4 94.2 93.7 NA

Efficiencies for 1200 rpm, Standard Efficiency Motors


Load Level In Percent
Motor ODP TEFC
Size 100 % 75% 50% 25% 100% 75% 50% 25%
10 87.3 86.9 85.7 78.5 87.1 87.7 86.4 80.3
15 87.4 87.5 86.8 80.8 88.2 88.1 87.3 80.7
20 88.5 89.2 88.8 84.1 89.1 89.7 89.4 82.8
25 89.4 89.7 89.3 85.0 89.8 90.5 89.8 83.5
30 89.2 90.1 89.8 87.6 90.1 91.3 90.7 84.6
40 90.1 90.4 90.0 85.8 90.3 90.1 89.3 85.3
50 90.7 91.2 90.9 86.9 91.6 92.0 91.5 86.7
75 92.0 92.5 92.3 88.6 91.9 91.6 91.0 87.2
100 92.3 92.7 92.2 87.4 92.8 92.7 91.9 86.5
125 92.6 92.9 92.8 87.9 93.0 93.0 92.6 88.7
150 93.1 93.3 92.9 89.7 93.3 93.8 93.4 91.1
200 94.1 94.6 93.5 91.5 94.0 94.3 93.6 NA
250 93.5 94.4 94.0 91.9 94.6 94.5 94.0 NA
300 93.8 94.4 94.3 92.9 94.7 94.8 94.0 NA

Average Efficiencies for Standard Efficiency Motors at Various Load Points B-1
Efficiencies for 1800 rpm, Standard Efficiency Motors
Load Level In Percent
Motor ODP TEFC
Size 100 % 75% 50% 25% 100% 75% 50% 25%
10 86.3 86.8 85.9 80.0 87.0 88.4 87.7 80.0
15 88.0 89.0 88.5 82.6 88.2 89.3 88.4 80.7
20 88.6 89.2 88.9 83.3 89.6 90.8 90.0 83.4
25 89.5 90.6 90.0 86.6 90.0 90.9 90.3 83.4
30 89.7 91.0 90.9 87.3 90.6 91.6 91.0 85.6
40 90.1 90.0 89.0 86.3 90.7 90.5 89.2 84.2
50 90.4 90.8 90.3 88.1 91.6 91.8 91.1 86.3
75 91.7 92.4 92.0 87.7 92.2 92.5 91.3 87.1
100 92.2 92.8 92.3 89.2 92.3 92.1 91.4 85.5
125 92.8 93.2 92.7 90.7 92.6 92.3 91.3 84.0
150 93.3 93.3 93.0 89.2 93.3 93.1 92.2 86.7
200 93.4 93.8 93.3 90.7 94.2 94.0 93.1 87.8
250 93.9 94.4 94.0 92.6 93.8 94.2 93.5 89.4
300 94.0 94.5 94.2 93.4 94.5 94.4 93.3 89.9

Efficiencies for 3600 rpm, Standard Efficiency Motors


Load Level In Percent
Motor ODP TEFC
Size 100 % 75% 50% 25% 100% 75% 50% 25%
10 86.3 87.7 86.4 79.2 86.1 87.2 85.7 77.8
15 87.9 88.0 87.3 82.8 86.8 87.8 85.9 79.5
20 89.1 89.5 88.7 85.2 87.8 89.6 88.3 79.7
25 89.0 89.9 89.1 84.4 88.6 89.6 87.9 79.3
30 89.2 89.3 88.3 84.8 89.2 90.0 88.7 81.0
40 90.0 90.4 89.9 86.9 89.0 88.4 86.8 79.7
50 90.1 90.3 88.7 85.8 89.3 89.2 87.3 82.0
75 90.7 91.0 90.1 85.7 91.2 90.5 88.7 82.5
100 91.9 92.1 91.5 89.0 91.2 90.4 89.3 83.8
125 91.6 91.8 91.1 88.8 91.7 90.8 89.2 82.6
150 92.0 92.3 92.0 89.2 92.3 91.7 90.1 85.6
200 93.0 93.0 92.1 87.9 92.8 92.2 90.5 84.9
250 92.7 93.1 92.4 87.1 92.7 92.5 91.2 90.3
300 93.9 94.3 93.8 90.4 93.2 92.8 91.1 89.9

B-2 Energy Management for Motor-Driven Systems


Appendix C
Motor Energy Savings Calculation Form

Employee Name ______________________ Facility/Location ______________________


Company ____________________________ Department __________________________
Date ________________________________ Process ______________________________

Motor Nameplate & Operating Information Motor Load and Efficiency Determination
Manufacturer ________________________ Load ___________________________________
Input Power(kW) / [ Motor Size(hp) x 0.746 / Efficiency at
Motor ID Number______________________ Full Load ]
Size (hp) ____________________________ Motor Efficiency at Operating Load ________
Enclosure Type ______________________ (Interpolate from Appendix B)

Synchronous Speed (RPM) _____________


Full Load Speed (RPM)_________________
Full Load Amperage ___________________
Full Load Power Factor (%) _____________ Energy Savings and Value
Full Load Efficiency (%) ________________ kW saved ___________________________
Input Power - [ Load x hp x 0.746 / Efficiency of
Replacement Motor at Load Point ]

kWh saved ___________________________


kW saved x Annual Operating Hours
Utility Rates
Energy Rate ($/kWh) __________________
Monthly Demand Charge ($/kW/mo.) _____
Annual Operating Hours (hrs/yr.) ________

Total Annual Savings


Total Annual Savings $ __________________
(kW saved x 12 x Monthly Demand Charge) + (kWh saved
x Energy Rate)
Annual Energy Use and Cost
Input Power (kW) _____________________
Annual Energy Use ___________________
Input Power x Annual Operating Hours

Annual Energy Cost ___________________ Economic Justification


Annual Energy Use x Energy Rate Cost for Replacement Motor ______________
(or Incremental Cost for New Motor)
Annual DemandCost __________________
Input Power x Monthly Demand Charge x 12 Simple Payback (years) ___________________
( Cost for Replacement Motor + Installation Charge - Utility
Total Annual Cost ____________________ Rebate ) / Total Annual Savings
Annual Energy Cost + Annual Demand Cost

Motor Energy Savings Calculation Form C-1


C-2 Energy Management for Motor-Driven Systems
Appendix D
Power Factor Correction Capacitor Suppliers

ASC Industries Inc./ General Electric Company


Power Distribution Group Industry Sales and Services
8967 Pleasantwood Avenue NW Division
North Canton, OH 44720-0523 1 River Road
Phone: (216) 499-1210 Schenectady, NY 12345
Phone: (518) 385-2211
ASEA Brown boveri Inc./
ABB Power T & D Co., Inc. Graybar Electric Company, Inc.
630 Sentry Park 34 North Meramec Avenue
Blue Bell, PA 19422 PO Box 7231
Phone: (215) 834-7400 St. Louis, MO 63172-9910
Phone: (314) 727-3900
Aerovox Inc.
370 Faunce Corner Road North American Capacitor
North Dartmouth, MA 02747 Company
Phone: (508) 995-8000 7545 Rockville Road
PO Box 1284
Brush Fuses Inc. Indianapolis, IN 46206
800 Regency Drive Phone: (317) 273-0090
Glendale Heights, IL 60139-2286
Phone: (708) 894-2221 Plastic Capacitors, Inc.
2623 N. Pulaski Road
Commonwealth Sprague Chicago, IL 60639
Capacitor, Inc. Phone: (312) 489-2229
Brown Street
North Adams, MA 01247 Ronk Electrical Industries, Inc.
Phone: (413) 664-4466 PO Box 160
Nokomis, Il 62075-0160
Delta Start Inc. Phone: (217) 563-8333
3550 Mayflower Drive
PO Box 10429
Lynchburg, VA 24506-0429
Phone: (800) 368-3017

Power Factor Correction Capacitor Suppliers D-1


D-2 Energy Management for Motor-Driven Systems
Cover Art 11/7/03 9:56 AM Page 1

F OR A DDITIONAL I NFORMATION ,
P LEASE C ONTACT:

The OIT Information Clearinghouse


Phone: (800) 862-2086
Fax: (360) 586-8303

Please send any comments,


questions, or suggestions to
webmaster.oit@ee.doe.gov

Visit our home page at


www.oit.doe.gov.

Office of Industrial Technologies


Energy Efficiency
and Renewable Energy
U.S. Department of Energy
Washington, DC 20585

DOE/MC-10021
Reprinted February 2000

You might also like