Kalsel-1 CFPP Monthly Schedule 2018-2019

The document is a schedule for the Kalsel-1 CFPP power plant project in Indonesia from February 2018 through May 2019. It includes key milestones and test dates for various units and systems, including commissioning tests for the boiler, turbine, emissions systems and others. Major activities scheduled include initial coal firing and steam blowing in August 2018, emission testing in October 2018, and completion of testing by May 2019.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
286 views1 page

Kalsel-1 CFPP Monthly Schedule 2018-2019

The document is a schedule for the Kalsel-1 CFPP power plant project in Indonesia from February 2018 through May 2019. It includes key milestones and test dates for various units and systems, including commissioning tests for the boiler, turbine, emissions systems and others. Major activities scheduled include initial coal firing and steam blowing in August 2018, emission testing in October 2018, and completion of testing by May 2019.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
  • Complex System Diagram: Showcases a detailed system diagram, possibly illustrating interconnections or processes with numerous nodes connected by lines.

28-Feb-18 IKAL_I-18 - Kalsel-1 CFPP (Indonesia) Level 3 Rev.

1 Monthly Updated Schedule_20180228EPC)_Full 2

2018 2019
February March April May June July August September October November December January February March April May

15-Mar-18 29-Mar-18 02-Apr-18 22-Apr-18 26-Apr-18 06-May-18 07-May-18 27-May-18 31-May-18 21-Jun-18 25-Jun-18 07-Jul-18 21-Jul-18 01-Aug-18 10-Aug-18 19-Aug-18 22-Aug-18 02-Sep-18 04-Sep-18 29-Sep-18 03-Oct-18 22-Oct-18 22-Oct-18 13-Nov-18 17-Dec-18 02-Jan-19 02-Jan-19 18-Jan-19 19-Jan-19 05-Feb-19 11-Feb-19 15-Apr-19 21-Apr-19 01-May-19 07-May-19
02-Feb-18 09-Feb-18 13-Feb-18 13-Feb-18 17-Feb-18 12-Feb-18 13-Feb-18 10-Jun-18 14-Jun-18 05-Jul-18 09-Jul-18 16-May-18 30-May-18 19-Jun-18 28-Jun-18 17-Jun-18 20-Jun-18 01-Jul-18 03-Jul-18 17-Aug-18 21-Aug-18 08-Sep-18 08-Sep-18 29-Sep-18 02-Nov-18 18-Nov-18 18-Nov-18 04-Dec-18 05-Dec-18 22-Dec-18 28-Dec-18 01-Mar-19 07-Mar-19 17-Mar-19 23-Mar-19

[Unit 1] - 6.9kV Power WWT System Motor No- RWT System Motor No- Agiator Test for WWT [Unit 2] - EHC Oil Pump [Unit 2] - EHC Oil System [Unit 2] - LV SWGR & MCC [Unit 2] - Bag Filter Interlock [Unit 2] - Closed Cooling [Unit 2] - Air Line Blowing [Unit 2] - Air & Gas Damper [Unit 2] - Boiler FO Initial [Unit 2] - Steam Blowing [Unit 2] - Initial Coal Firing [Unit 2] - AVR offline Test [Unit 2] - Sootblower Actual [Unit 2] - Emissiong Test [Unit 2] - PT Instrument
Receiving Load Test Load Test Clarifier Motor No- Load Test Test Test (B/F & AHS Bldg) Test Water Line Flushing Test Firing Out Test Removal

17-Feb-18 11-Mar-18 15-Mar-18 04-Apr-18 10-Apr-18 30-Apr-18 01-May-18 13-May-18 19-May-18 01-Jun-18 20-Jun-18 05-Jul-18 09-Jul-18 22-Jul-18 23-Jul-18 05-Aug-18 06-Aug-18 23-Aug-18 01-Sep-18 12-Sep-18 21-Sep-18 04-Oct-18 05-Oct-18 22-Oct-18 27-Oct-18 06-Nov-18 15-Nov-18 26-Nov-18 30-Nov-18 18-Dec-18 01-Jan-19 12-Jan-19 12-Jan-19 28-Jan-19 06-Feb-19 22-Apr-19 07-May-19
31-Jan-18 10-Jan-18 14-Jan-18 20-Mar-18 26-Mar-18 16-Feb-18 17-Feb-18 17-Feb-18 23-Feb-18 15-Jun-18 04-Jul-18 24-Apr-18 28-Apr-18 06-Jun-18 07-Jun-18 20-Jun-18 21-Jun-18 21-Jun-18 30-Jun-18 27-Jul-18 05-Aug-18 22-Aug-18 23-Aug-18 08-Sep-18 13-Sep-18 02-Oct-18 11-Oct-18 24-Oct-18 28-Oct-18 03-Nov-18 17-Nov-18 28-Nov-18 28-Nov-18 15-Dec-18 24-Dec-18 08-Mar-19 23-Mar-19

[Unit 1] - Backfeed Power [Unit 2] - IPB Test [Unit 2] - DC & UPS System Agitator Test for RWT Chemical Dosing Test for [Unit 2] - EHC Oil Line [Unit 1] - Condensate [Unit 2] - ACW PP Motor [Unit 2] - Chemical Dosing [Unit 2] - Closed Cooling [Unit 2] - Condensate [Unit 2] - Draft System Test [Unit 2] - Boiler Refractory [Unit 2] - Coal Receiving [Unit 2] - Fly Ash Handling [Unit 2] - Bed Ash Removal [Unit 2] - Steam Admission [Unit 2] - FWH System Test [Unit 2] - Performance
Unit #1 Test Conc. Tank Demi. System Flushing System Test Flushing & N… No- Load Test System Flushing Water System Test System Test (Load Test) Dry Out from Owner No-Load Test System Test for Unit #2 Guarantees Test

28-Feb-18 03-Mar-18 16-Mar-18 17-Mar-18 31-Mar-18 01-Apr-18 18-Apr-18 24-Apr-18 05-May-18 05-May-18 22-May-18 31-May-18 12-Jun-18 12-Jun-18 10-Jul-18 14-Jul-18 24-Jul-18 30-Jul-18 17-Aug-18 18-Aug-18 02-Sep-18 22-Sep-18 06-Oct-18 07-Oct-18 28-Oct-18 11-Nov-18 30-Nov-18 04-Dec-18 18-Dec-18 23-Dec-18 02-Jan-19 11-Jan-19 20-Jan-19 21-Jan-19 06-Feb-19 13-Feb-19 15-Apr-19 21-Apr-19 08-May-19 15-May-19
27-Jan-18 28-Jan-18 15-Jan-18 16-Jan-18 16-Mar-18 17-Mar-18 07-Feb-18 13-Feb-18 11-Feb-18 11-Feb-18 05-Jun-18 14-Jun-18 23-Mar-18 23-Mar-18 29-Apr-18 03-May-18 08-Jun-18 14-Jun-18 15-Jun-18 16-Jun-18 22-Jul-18 11-Aug-18 24-Aug-18 25-Aug-18 14-Sep-18 28-Sep-18 24-Oct-18 28-Oct-18 03-Nov-18 08-Nov-18 18-Nov-18 27-Nov-18 06-Dec-18 07-Dec-18 24-Dec-18 31-Dec-18 01-Mar-19 07-Mar-19 24-Mar-19 31-Mar-19

[Unit 1] - Fire Fighting [Unit 2] - IPB Sealing Test [Unit 2] - F/F System Ready Chemical Dosing System WWT Clarifier Ready [Unit 2] - TBN Oil Pump Demi. Water Transfer [Unit 1] - Condensate [Unit 2] - ACW Line [Unit 2] - CCW PP Motor [Unit 2] - Feedwater System [Unit 2] - Boiler Air Balance [Unit 2] - Refractory [Unit 2] - Bed Ash Handling [Unit 2] - Temporary Piping [Unit 2] - Water & Steam [Unit 2] - Exciter / Electrical [Unit 1] - NDC Test [Unit 2] - PT Instrument [Unit 2] - NDC Test
Pump Test Completed for Batter Room Test for RWT System Motor No- Load Test System Test System Test Flushing No- Load Test Test Test Inspection No- Load Test Restoration Purity Control Test Installation

04-Mar-18 08-Mar-18 02-Apr-18 03-Apr-18 22-Apr-18 23-Apr-18 08-May-18 17-May-18 27-May-18 31-May-18 22-Jun-18 31-Jul-18 11-Aug-18 23-Aug-18 02-Sep-18 04-Sep-18 21-Sep-18 30-Sep-18 11-Oct-18 20-Oct-18 01-Nov-18 10-Nov-18 25-Nov-18 29-Nov-18 18-Dec-18 01-Jan-19 13-Jan-19 13-Jan-19 13-Feb-19 13-Feb-19 15-May-19 15-May-19
29-Jan-18 30-Jan-18 18-Mar-18 19-Mar-18 22-Apr-18 23-Apr-18 18-Feb-18 27-Feb-18 10-Jun-18 14-Jun-18 09-Jun-18 18-Jul-18 29-Jun-18 11-Jul-18 19-Aug-18 21-Aug-18 09-Aug-18 18-Aug-18 29-Aug-18 07-Sep-18 27-Sep-18 06-Oct-18 19-Oct-18 23-Oct-18 03-Nov-18 17-Nov-18 29-Nov-18 29-Nov-18 31-Dec-18 31-Dec-18 31-Mar-19 31-Mar-19

[Unit 1] - TR Area FF Spray [Unit 2] - VAC System [Unit 2] - F/F System Ready RWT Clarifirer System Test [Unit 2] - TBN Lube Oil [Unit 2] - BFP LO Flushing [Unit 2] - Bag Filter Pulse [Unit 2] - Draft System [Unit 2] - Flame Scanner [Unit 2] - CEMS Test [Unit 2] - MV SWGR Test [Unit 2] - Ash Crusher No- [Unit 2] - Lime Stone [Unit 2] - TBN initial Rolling [Unit 1] - COD of Unit#1 [Unit 2] - COD of Un
Test Ready for Battery Room for Each Panel Room Flushing Preparation Air Test Interlock Test Test (CHS Bldg) Load Test Feeding System Test

28-Feb-18 01-Mar-18 30-Mar-18 05-Apr-18 14-Apr-18 15-Apr-18 29-Apr-18 29-Apr-18 20-May-18 22-May-18 02-Jun-18 03-Jun-18 18-Jun-18 20-Jun-18 13-Jul-18 19-Jul-18 31-Jul-18 05-Aug-18 20-Aug-18 21-Aug-18 04-Sep-18 04-Sep-18 21-Sep-18 30-Sep-18 11-Oct-18 13-Oct-18 28-Oct-18 29-Oct-18 21-Nov-18 25-Nov-18 05-Dec-18 09-Dec-18 18-Dec-18 01-Jan-19 14-Jan-19 15-Jan-19 30-Jan-19 05-Feb-19 14-Feb-19 23-Feb-19 06-May-19 15-May-19
26-Jan-18 26-Jan-18 30-Mar-18 05-Apr-18 09-Mar-18 10-Mar-18 15-Feb-18 15-Feb-18 28-Feb-18 02-Mar-18 23-Mar-18 24-Mar-18 21-May-18 23-May-18 03-Jul-18 09-Jul-18 15-Jun-18 20-Jun-18 03-Sep-18 04-Sep-18 12-Jul-18 12-Jul-18 09-Aug-18 18-Aug-18 29-Aug-18 31-Aug-18 14-Sep-18 15-Sep-18 19-Oct-18 23-Oct-18 22-Oct-18 26-Oct-18 03-Nov-18 17-Nov-18 30-Nov-18 01-Dec-18 17-Dec-18 23-Dec-18 01-Jan-19 10-Jan-19 22-Mar-19 31-Mar-19

[Unit 1] - Fire Fighting [Unit 2] - Backfeed Power [Unit 1] - ACW PP Motor RWT Clarifier Ready Multi-Cell Filter Test [Unit 1] - Chemical Dosing [Unit 1] - Draft System [Unit 2] - ID Fan Lube Oil [Unit 2] - Aux Cooling Water [Unit 2] - Turning Gear [Unit 2] - Smoke Air Leak [Unit 2] - MFT Interlock Test [Unit 2] - BLR Blowdown [Unit 2] - Temporary Piping [Unit 2] - Fly Ash Blower [Unit 2] - Coal Crusher [Unit 2] - Fly Ash [Unit 2] - TBN Stretch-out [Unit 1] - PT Instrument [Unit 1] - Reliability Run [Unit 2] - Reliability Run
Pump Motor No- Load Test SWYD No- Load Test System Flushing Interlock Test Flushing System Test Motor No- Load Test Test System Test Restoration Test Motor No- Load Test Recirculation System Test Check Removal Test Test

11-Apr-18 13-Apr-18 30-Apr-18 01-May-18 25-May-18 25-May-18 04-Jun-18 18-Jun-18 10-Jul-18 19-Jul-18 01-Aug-18 03-Aug-18 22-Aug-18 24-Aug-18 07-Sep-18 11-Sep-18 22-Sep-18 25-Sep-18 08-Oct-18 12-Oct-18 23-Oct-18 23-Oct-18 18-Nov-18 07-Dec-18 19-Dec-18 23-Dec-18 16-Jan-19 17-Jan-19
06-Mar-18 08-Mar-18 16-Feb-18 17-Feb-18 05-Mar-18 05-Mar-18 25-Mar-18 08-Apr-18 29-Apr-18 08-May-18 19-Jul-18 21-Jul-18 05-Sep-18 07-Sep-18 22-Jul-18 26-Jul-18 07-Aug-18 10-Aug-18 26-Aug-18 30-Aug-18 09-Sep-18 09-Sep-18 14-Oct-18 02-Nov-18 04-Nov-18 08-Nov-18 02-Dec-18 03-Dec-18

[Unit 1] - Cooling Tower Fan Raw Water Intake Pump DCS ready [Unit 1] - Chemical Dosing [Unit 1] - Feedwater System [Unit 2] - BFP Motor No- [Unit 2] - Turning Gear Test [Unit 2] - Condensate [Unit 1] - Aux. Steam [Unit 2] - Boiler Vent & [Unit 2] - Boiler Chemical [Unit 2] - Sand Handling [Unit 2] - Aux. Steam [Unit 2] - TBN / Generator
Test Test System Test Test Load Test System Test Flushing & N… System Control Valve Test Drain MOV Test Cleaning System Test System Control Valve Test No-load Test

30-Mar-18 02-Apr-18 13-Apr-18 27-Apr-18 08-May-18 21-May-18 01-Jun-18 09-Aug-18 26-Aug-18 04-Sep-18 19-Sep-18 23-Sep-18 12-Oct-18 10-Nov-18 25-Nov-18 14-Dec-18 24-Dec-18 24-Dec-18 22-Jan-19 22-Jan-19
13-Mar-18 16-Mar-18 13-Apr-18 27-Apr-18 18-Feb-18 03-Mar-18 15-Jun-18 23-Aug-18 12-Aug-18 21-Aug-18 04-Aug-18 08-Aug-18 30-Aug-18 28-Sep-18 19-Oct-18 07-Nov-18 09-Nov-18 09-Nov-18 08-Dec-18 08-Dec-18

[Unit 1] - EHC Oil Pump [Unit 2] - LV SWGR & MCC WWT System Test [Unit 2] - TBN Lube Oil [Unit 2] - Loop Seal HP [Unit 2] - Burner Adjstment [Unit 2] - Temporary Piping [Unit 2] - Limestone [Unit 2] - Aux. Steam [Unit 2] - Mechanical
Motor No- Load Test Test ( WT Building) Flushing Blower System Test Installation Handling System Test Function Test Completion

09-Apr-18 10-Apr-18 29-Apr-18 29-Apr-18 23-May-18 24-May-18 13-Jun-18 22-Jun-18 07-Jul-18 08-Jul-18 23-Jul-18 29-Jul-18 10-Aug-18 19-Aug-18 31-Aug-18 06-Sep-18 21-Sep-18 23-Sep-18 09-Oct-18 20-Oct-18 11-Nov-18 20-Nov-18 08-Dec-18 12-Dec-18 26-Dec-18 29-Dec-18 22-Jan-19 23-Jan-19
04-Mar-18 05-Mar-18 15-Feb-18 15-Feb-18 03-Mar-18 04-Mar-18 24-Mar-18 02-Apr-18 24-May-18 25-May-18 13-Jul-18 19-Jul-18 24-Aug-18 02-Sep-18 14-Jul-18 20-Jul-18 12-Aug-18 14-Aug-18 26-Aug-18 06-Sep-18 07-Oct-18 16-Oct-18 03-Nov-18 07-Nov-18 11-Nov-18 14-Nov-18 08-Dec-18 09-Dec-18

[Unit 1] - Cooling Tower Fan Raw Water Intake Motor Potable Water System [Unit 1] - Closed Cooling [Unit 1] - Draft System Test [Unit 2] - SA Fan Lube Oil [Unit 2] - TBN Lube Oil Test [Unit 2] - CEP Motor No- [Unit 1] - Vacuum Pump [Unit 2] - Burner System [Unit 2] - LV SWGR & MCC [Unit 2] - Sand Silo Sand [Unit 2] - Bypass System [Unit 2] - GEN First
Motor No- Load Test No- Load Test Motor No- Load Test Water System Test (Load Test) Flushing Load Test System Test Test Test (CHS Elec Bldg) Receiving Valve Test Synchro.

08-Apr-18 08-Apr-18 24-Apr-18 25-Apr-18 09-May-18 09-May-18 25-May-18 31-May-18 13-Jun-18 15-Jun-18 09-Jul-18 10-Jul-18 02-Aug-18 11-Aug-18 22-Aug-18 05-Sep-18 16-Sep-18 18-Sep-18 01-Oct-18 07-Oct-18 21-Oct-18 21-Oct-18 06-Nov-18 12-Nov-18 25-Nov-18 29-Nov-18 15-Dec-18 16-Dec-18 02-Jan-19 03-Jan-19 24-Jan-19 13-Apr-19
03-Mar-18 03-Mar-18 24-Apr-18 25-Apr-18 23-Feb-18 23-Feb-18 05-Mar-18 11-Mar-18 10-May-18 12-May-18 26-May-18 27-May-18 23-Jul-18 01-Aug-18 07-Jul-18 21-Jul-18 13-Aug-18 15-Aug-18 19-Aug-18 25-Aug-18 07-Sep-18 07-Sep-18 23-Sep-18 29-Sep-18 12-Oct-18 16-Oct-18 01-Nov-18 02-Nov-18 16-Nov-18 17-Nov-18 10-Dec-18 27-Feb-19

[Unit 1] - Fire Fighting [Unit 2] - VAC System Filtered Water Storage Tank Potable Water System Test [Unit 1] - Loop Seal HP [Unit 1] - Boiler Air Balance [Unit 2] - SA Fan System [Unit 2] - Pre-boiler Line [Unit 2] - CW Line Flushing [Unit 2] - Ignitoer & Burner [Unit 2] - Overall Check [Unit 1] - Sootblower Actual [Unit 2] - Coal Conveyor-1 [Unit 2] - Process Aux. [Unit 2] - Bypass System [Unit 2] - Commissioing Test
Ready for Cooling Twer Ready for Each Panel Ro… Ready Blower Motor Solo Run Test Test Test Chemical Cleaning Test Test No- Load Test Steam Line Flushing Cold Function Test (Functional Test)

13-Apr-18 27-Apr-18 23-May-18 24-May-18 16-Jun-18 26-Jun-18 06-Jul-18 07-Jul-18 23-Jul-18 01-Aug-18 12-Aug-18 21-Aug-18 09-Sep-18 10-Sep-18 04-Oct-18 08-Oct-18 21-Oct-18 21-Oct-18 01-Dec-18 20-Dec-18 30-Dec-18 03-Jan-19 13-Jan-19 16-Jan-19
13-Apr-18 27-Apr-18 03-Mar-18 04-Mar-18 13-May-18 23-May-18 01-Jun-18 02-Jun-18 13-Jul-18 22-Jul-18 02-Aug-18 11-Aug-18 03-Aug-18 04-Aug-18 21-Aug-18 25-Aug-18 07-Sep-18 07-Sep-18 29-Oct-18 17-Nov-18 13-Nov-18 17-Nov-18 29-Nov-18 02-Dec-18

[Unit 2] - LV SWGR & MCC Filtered W/S PP Motor No- [Unit 1] - Loop Seal HP [Unit 2] - Cooling Tower Fan [Unit 2] - ID Fan System [Unit 2] - PA Fan System [Unit 1] - Process Aux. [Unit 2] - Lime Stone Blower [Unit 2] - Insulation [Unit 2] - Fly Ash Handling [Unit 2] - Condenser [Unit 2] - HP & LP FWH
(CCB) Test Load Test Blower System Test Motor No- Load Test Test Test Steam Line Flushing Test Completed (Boiler / Pipin… System Test Vacuum Up Test Shell Side Flushing

13-Apr-18 27-Apr-18 23-May-18 11-Jun-18 23-Jun-18 28-Jun-18 11-Jul-18 15-Jul-18 30-Jul-18 01-Aug-18 19-Aug-18 21-Aug-18 12-Sep-18 15-Sep-18 30-Sep-18 03-Oct-18 17-Oct-18 21-Oct-18 01-Nov-18 05-Nov-18 30-Nov-18 09-Dec-18 24-Dec-18 27-Dec-18 13-Jan-19 27-Jan-19
13-Apr-18 27-Apr-18 03-Mar-18 22-Mar-18 03-Apr-18 08-Apr-18 28-May-18 01-Jun-18 20-Jul-18 22-Jul-18 09-Aug-18 11-Aug-18 09-Aug-18 12-Aug-18 17-Aug-18 20-Aug-18 03-Sep-18 07-Sep-18 27-Sep-18 01-Oct-18 17-Oct-18 26-Oct-18 09-Nov-18 12-Nov-18 30-Nov-18 14-Dec-18

[Unit 2] - MV SWGR (CCB) Demi. Water Treatment Compressed Air System [Unit 1] - Boiler Vent & [Unit 2] - SA Fan Motor Solo [Unit 2] - Loop Seal HP [Unit 2] - CWP Motor No- [Unit 2] - Lime Stone Blower [Unit 2] - Boiler Chemical [Unit 2] - Coal Truck Scale [Unit 2] - Coal Conveyor-1 [Unit 2] - Boiler Pressure [Unit 2] - FWH Vent & Drain
Test System Test Test Drain MOV Test Run Test Blower Motor Solo Run Test Load Test No- Load Test Cleaning Preparation Test Load Test Raising Test System Test

04-Apr-18 08-Apr-18 23-Apr-18 28-Apr-18 25-May-18 25-May-18 11-Jun-18 11-Jun-18 28-Jun-18 29-Jun-18 11-Jul-18 22-Jul-18 02-Aug-18 08-Aug-18 19-Aug-18 19-Aug-18 08-Sep-18 12-Sep-18 01-Oct-18 20-Oct-18 30-Oct-18 08-Nov-18 10-Dec-18 19-Dec-18 28-Dec-18 01-Jan-19 14-Jan-19 20-Jan-19
12-Mar-18 16-Mar-18 18-Mar-18 23-Mar-18 05-Mar-18 05-Mar-18 22-Mar-18 22-Mar-18 05-Jun-18 06-Jun-18 28-May-18 08-Jun-18 23-Jul-18 29-Jul-18 11-Jul-18 11-Jul-18 24-Jul-18 28-Jul-18 19-Aug-18 07-Sep-18 16-Sep-18 25-Sep-18 27-Oct-18 05-Nov-18 13-Nov-18 17-Nov-18 01-Dec-18 07-Dec-18

[Unit 1] - TBN Oil Pump [Unit 1] - Aux Cooling Water Filtered Water Supply Pump Demi Water Make-up PP [Unit 1] - Turning Gear [Unit 1] - Burner System [Unit 2] - PA Fan Lube Oil [Unit 2] - Completion of Flue [Unit 1] - Coal Crusher [Unit 2] - Sootblower Dry [Unit 1] - FWH System Test [Unit 2] - Coal Crusher Test [Unit 2] - Boiler Safety Valve [Unit 1] - Emissiong Test
Motor No- Load Test System Test Test Motor No- Load Test Motor No- Load Test Test Flushing Gas Duct Construction Motor No- Load Test Test Poping Test

16-Apr-18 22-Apr-18 19-May-18 21-May-18 06-Jun-18 15-Jun-18 29-Jun-18 01-Jul-18 20-Jul-18 22-Jul-18 09-Aug-18 11-Aug-18 05-Sep-18 14-Sep-18 27-Sep-18 01-Oct-18 27-Oct-18 09-Nov-18 25-Nov-18 15-Dec-18 28-Dec-18 01-Jan-19 14-Jan-19 20-Jan-19
11-Mar-18 17-Mar-18 24-Feb-18 26-Feb-18 10-Apr-18 19-Apr-18 09-Apr-18 11-Apr-18 10-Jul-18 12-Jul-18 30-Jul-18 01-Aug-18 19-Jul-18 28-Jul-18 15-Aug-18 19-Aug-18 29-Sep-18 12-Oct-18 12-Oct-18 01-Nov-18 13-Nov-18 17-Nov-18 01-Dec-18 07-Dec-18

[Unit 1] - ACW Line DWT System Motor No- [Unit 2] - TR Protection Test [Unit 1] - Air Line Blowing [Unit 2] - ID Fan Motor Solo [Unit 2] - PA Fan Motor Solo [Unit 1] - Coal Conveyor-1 [Unit 1] - Condenser [Unit 2] Sampling System [Unit 2] - Coal Storage [Unit 2] - TBN Valve Test [Unit 1] - PT Instrument
Flushing Load Test Run Test Run Test Load Test Vacuum Up Test Test Shed Stacking Test Installation

30-Mar-18 08-Apr-18 28-Apr-18 04-May-18 19-May-18 19-May-18 16-Jun-18 16-Jun-18 02-Jul-18 06-Jul-18 27-Jul-18 29-Jul-18 14-Aug-18 17-Sep-18 03-Oct-18 03-Oct-18 19-Oct-18 20-Oct-18 18-Dec-18 01-Jan-19 21-Jan-19 05-Feb-19
07-Mar-18 16-Mar-18 31-Mar-18 06-Apr-18 25-Feb-18 25-Feb-18 30-Apr-18 30-Apr-18 19-May-18 23-May-18 18-Jun-18 20-Jun-18 01-Jul-18 04-Aug-18 20-Aug-18 20-Aug-18 05-Sep-18 06-Sep-18 03-Nov-18 17-Nov-18 08-Dec-18 23-Dec-18

[Unit 1] - TBN Lube Oil [Unit 1] - ID Fan Lube Oil Demi. Water Storage Tank [Unit 2] - Back Energizing [Unit 1] - Air & Gas Damper [Unit 2] - Bag Filter [Unit 1] - Steam Blowing [Unit 1] - Initial Coal Firing [Unit 1] - AVR offline Test [Unit 2] - Coal FDR & [Unit 1] - Performance
Flushing Preparation Flushing Ready Unit #2 Test Installation Completed Out Tripper Test Guarantees Test

28-Feb-18 07-Jun-18 17-Jun-18 18-Jun-18 05-Jul-18 05-Jul-18 24-Jul-18 24-Jul-18 07-Aug-18 21-Aug-18 31-Aug-18 04-Sep-18 18-Sep-18 23-Sep-18 03-Oct-18 12-Oct-18 21-Oct-18 22-Oct-18 28-Dec-18 01-Jan-19
01-Mar-18 08-Jun-18 01-May-18 02-May-18 31-May-18 31-May-18 10-Jun-18 10-Jun-18 22-Jun-18 06-Jul-18 14-Jul-18 18-Jul-18 05-Aug-18 10-Aug-18 20-Aug-18 29-Aug-18 07-Sep-18 08-Sep-18 13-Nov-18 17-Nov-18

[Unit 1] - Communication [Unit 2] - 6.9kV Power [Unit 2] - Fire Fighting [Unit 1] - Boiler FO Initial [Unit 2] - Chemical Dosing [Unit 1] - Coal Conveyor-1 [Unit 1] - Temporary Piping [Unit 1] - Water & Steam [Unit 1] - Exciter / Electrical [Unit 2] - SH Temperature
System Receiving Ready for Cooling Twer Firing System Test No- Load Test Restoration Purity Control Test Control Test

23-Apr-18 27-Apr-18 12-May-18 14-May-18 01-Jun-18 03-Jun-18 18-Jun-18 22-Jun-18 08-Jul-18 10-Jul-18 24-Jul-18 29-Jul-18 08-Aug-18 12-Aug-18 23-Aug-18 01-Sep-18 26-Sep-18 26-Sep-18 13-Oct-18 13-Oct-18 18-Dec-18 27-Dec-18
06-Apr-18 10-Apr-18 18-Apr-18 20-Apr-18 05-Apr-18 07-Apr-18 29-Mar-18 02-Apr-18 03-Jun-18 05-Jun-18 10-Jun-18 15-Jun-18 29-Jun-18 03-Jul-18 09-Jul-18 18-Jul-18 11-Aug-18 11-Aug-18 30-Aug-18 30-Aug-18 03-Nov-18 12-Nov-18

[Unit 1] - EHC Oil System [Unit 1] - SA Fan Motor Solo [Unit 2] - GCB Test Air Dryer Test [Unit 2] - Cooling Tower Fan [Unit 1] - Boiler Refractory [Unit 1] - Coal Truck Scale [Unit 1] - LV SWGR & MCC [Unit 1] - Aux. Steam [Unit 1] - Steam Admission [Unit 2] - Bed Material
Test Run Test Test Dry Out Test Test (CHS Elec Bldg) Function Test for Unit #1 System Test

03-Apr-18 22-Apr-18 12-May-18 18-May-18 29-May-18 29-May-18 14-Jun-18 17-Jun-18 29-Jun-18 03-Jul-18 14-Jul-18 16-Jul-18 30-Jul-18 13-Aug-18 23-Aug-18 27-Aug-18 18-Sep-18 02-Oct-18 14-Oct-18 17-Oct-18 28-Dec-18 01-Jan-19
17-Mar-18 05-Apr-18 22-Apr-18 28-Apr-18 25-Apr-18 25-Apr-18 25-Mar-18 28-Mar-18 19-Apr-18 23-Apr-18 31-May-18 02-Jun-18 16-Jun-18 30-Jun-18 14-Jul-18 18-Jul-18 05-Aug-18 19-Aug-18 31-Aug-18 03-Sep-18 13-Nov-18 17-Nov-18

[Unit 1] - EHC Oil Line [Unit 1] - PA Fan Lube Oil [Unit 2] - Fire Fighting Air Compressor MTR Test [Unit 1] - CEP Motor No- [Unit 1] - BLR Blowdown [Unit 1] - Refractory [Unit 1] - Coal Storage [Unit 1] - Fly Ash [Unit 1] - HP & LP FWH [Unit 2] - Bed Material
Flushing Flushing Pump Motor No- Load Test Load Test System Test Inspection Shed Stacking Test Recirculation System Test Shell Side Flushing Feeding to Boiler

05-May-18 11-May-18 30-May-18 31-May-18 23-Jun-18 25-Jun-18 25-Jul-18 25-Jul-18 13-Aug-18 22-Aug-18 02-Sep-18 05-Sep-18 18-Sep-18 02-Oct-18 17-Oct-18 18-Oct-18 05-Dec-18 20-Dec-18 30-Dec-18 31-Dec-18
11-Apr-18 17-Apr-18 26-Apr-18 27-Apr-18 15-May-18 17-May-18 11-Jun-18 11-Jun-18 29-Jun-18 08-Jul-18 27-Jul-18 30-Jul-18 05-Aug-18 19-Aug-18 03-Sep-18 04-Sep-18 29-Oct-18 13-Nov-18 16-Nov-18 17-Nov-18

[Unit 1] - SA Fan Lube Oil [Unit 2] - Fire Fighting [Unit 1] - CW Line Flushing [Unit 1] - Boiler Chemical [Unit 1] - MV SWGR Test [Unit 1] - Bed Ash Handling [Unit 1] - Coal FDR & [Unit 1] - TBN / Generator [Unit 2] - Bed Ash Handling [Unit 2] - Coal Silo Coal
Flushing Pump Test Cleaning (CHS Bldg) No- Load Test Tripper Test No-load Test System Test Receiving

01-Jun-18 02-Jun-18 26-Jun-18 03-Jul-18 30-Jul-18 31-Jul-18 28-Aug-18 31-Aug-18 18-Sep-18 27-Sep-18 07-Oct-18 08-Oct-18 23-Oct-18 23-Oct-18 15-Dec-18 16-Dec-18
28-Apr-18 29-Apr-18 18-May-18 25-May-18 16-Jun-18 17-Jun-18 27-Jul-18 30-Jul-18 05-Aug-18 14-Aug-18 18-Aug-18 19-Aug-18 09-Sep-18 09-Sep-18 08-Nov-18 09-Nov-18

[Unit 2] - TR Area FF Spray [Unit 1] - Circulating Water [Unit 1] - Temporary Piping [Unit 1] - Fly Ash Handling [Unit 1] - Bed Material [Unit 1] - Bypass System [Unit 1] - Mechanical [Unit 2] - Limestone Silo
Test System Test Restoration No-Load Test System Test Cold Function Test Completion Receiving

28-May-18 01-Jun-18 19-Jun-18 22-Jun-18 03-Jul-18 05-Jul-18 23-Jul-18 23-Jul-18 13-Aug-18 22-Aug-18 18-Sep-18 02-Oct-18 23-Oct-18 24-Oct-18 26-Dec-18 26-Dec-18
21-Apr-18 01-May-18 11-May-18 14-May-18 21-Apr-18 23-Apr-18 09-Jun-18 09-Jun-18 04-Jul-18 13-Jul-18 05-Aug-18 19-Aug-18 09-Sep-18 10-Sep-18 09-Nov-18 09-Nov-18

[Unit 1] - SA Fan System [Unit 1] - CWP Motor No- [Unit 1] - BFP Motor No- [Unit 1] - Overall Check [Unit 1] - Coal Receiving [Unit 1] - Lime Stone [Unit 1] - GEN First [Unit 2] - Vacuum Pump No-
Test Load Test Load Test from Owner Feeding System Test Synchro. Load Test

25-May-18 02-Jul-18 23-Jul-18 23-Jul-18 26-Aug-18 14-Sep-18 24-Sep-18 27-Sep-18 14-Oct-18 14-Oct-18 27-Dec-18 29-Dec-18
13-Mar-18 20-Apr-18 09-Jun-18 09-Jun-18 21-Jul-18 09-Aug-18 11-Aug-18 14-Aug-18 31-Aug-18 31-Aug-18 10-Nov-18 12-Nov-18

[Unit 1] - BFP LO Flushing [Unit 1] - Insulation [Unit 1] - Sand Handling [Unit 1] - Boiler Pressure [Unit 1] - TBN initial Rolling [Unit 2] - Vacuum Pump
Completed (Boiler / Pipin… System Test Raising Test System Test

27-May-18 11-Jun-18 03-Jul-18 09-Jul-18 19-Jul-18 23-Jul-18 26-Aug-18 14-Sep-18 25-Sep-18 27-Sep-18 15-Oct-18 29-Oct-18 28-Dec-18 01-Jan-19
08-Apr-18 23-Apr-18 21-May-18 27-May-18 05-Jun-18 09-Jun-18 21-Jul-18 09-Aug-18 12-Aug-18 14-Aug-18 01-Sep-18 15-Sep-18 23-Nov-18 27-Nov-18

[Unit 1] - Pre-boiler Line [Unit 1] - Ignitoer & Burner [Unit 1] - Boiler Chemical [Unit 1] - Limestone [Unit 1] - TBN Gland Seal [Unit 1] - FWH Vent & Drain [Unit 2] - TBN Drain System
Chemical Cleaning Test Cleaning Preparation Handling System Test Steam System Test System Test Test

19-May-18 28-May-18 08-Jun-18 12-Jun-18 23-Jun-18 02-Jul-18 14-Jul-18 23-Jul-18 25-Aug-18 27-Aug-18 28-Sep-18 02-Oct-18 15-Oct-18 16-Oct-18 23-Dec-18 25-Dec-18
21-Apr-18 30-Apr-18 02-May-18 12-May-18 11-May-18 20-May-18 31-May-18 09-Jun-18 15-Jul-18 17-Jul-18 15-Aug-18 19-Aug-18 01-Sep-18 02-Sep-18 09-Nov-18 11-Nov-18

[Unit 1] - FO Storage Tank [Unit 1] - PA Fan System [Unit 1] - MFT Interlock Test [Unit 1] - CEMS Test [Unit 1] - Ash Crusher No- [Unit 1] - TBN Valve Test [Unit 1] - TBN Stretch-out [Unit 2] - TBN Gland Seal

1. This commissioning sequence is filtered from SRP


Cleaning & Filling Test Load Test Check Steam System Test

20-May-18 22-May-18 05-Jun-18 07-Jun-18 20-Jun-18 24-Jun-18 15-Jul-18 13-Aug-18 25-Aug-18 27-Aug-18 23-Sep-18 02-Oct-18 28-Dec-18 01-Jan-19
07-Apr-18 09-Apr-18 29-Apr-18 01-May-18 23-May-18 27-May-18 01-Jun-18 30-Jun-18 24-Jul-18 26-Jul-18 10-Aug-18 19-Aug-18 23-Nov-18 27-Nov-18

[Unit 1] - ID Fan Motor Solo


Run Test
[Unit 1] - PA Fan Motor Solo
Run Test
[Unit 1] - Lime Stone Blower
Test
[Unit 1] - Temporary Piping
Installation
[Unit 1] - Fly Ash Blower
Test
[Unit 1] - Generator
Protection Test
[Unit 2] - Vibration
Monitoring System Test 2. TPI appreciate if HGU could updates this every
week.
14-May-18 21-Aug-18 15-Sep-18 24-Sep-18 03-Oct-18 12-Oct-18 23-Dec-18 01-Jan-19
29-May-18 05-Sep-18 29-Jul-18 07-Aug-18 20-Aug-18 29-Aug-18 18-Nov-18 27-Nov-18

[Unit 2] - Communication [Unit 1] - Coal Crusher Test [Unit 1] - TBN Protection [Unit 2] - TBN Protection
System System Test System Test

07-Mar-18 03-Aug-18 26-Aug-18 08-Sep-18 19-Sep-18 26-Sep-18 08-Oct-18 12-Oct-18 13-Dec-18 22-Dec-18
02-Feb-18 01-Jul-18 01-Jul-18 14-Jul-18 16-Aug-18 23-Aug-18 25-Aug-18 29-Aug-18 08-Nov-18 17-Nov-18

[Unit 1] - Fire Fighting & [Unit 1] Sampling System [Unit 2] - Circulating Water [Unit 1] - Vibration [Unit 2] - Generator
Alarm System Test System Test Monitoring System Test Protection Test

29-May-18 02-Jun-18 17-Jun-18 19-Jun-18 03-Jul-18 22-Jul-18 21-Sep-18 26-Sep-18 08-Oct-18 12-Oct-18 23-Dec-18 29-Dec-18
01-May-18 05-May-18 20-May-18 22-May-18 21-May-18 09-Jun-18 05-Aug-18 10-Aug-18 25-Aug-18 29-Aug-18 09-Nov-18 15-Nov-18

[Unit 1] - FO Supply Pump [Unit 1] - Lime Stone Blower [Unit 1] - Sootblower Dry [Unit 1] - Coal Distribution [Unit 1] - TBN Drain System [Unit 2] - Coal Distribution
Motor No- Load Test No- Load Test Test Con. No-Load Test Test Conveyoy Load Test

03-Jun-18 07-Jun-18 23-Jun-18 02-Jul-18 28-Sep-18 02-Oct-18 18-Dec-18 22-Dec-18


06-May-18 10-May-18 11-May-18 20-May-18 15-Aug-18 19-Aug-18 04-Nov-18 08-Nov-18

[Unit 1] - Burner Adjstment [Unit 1] - Flame Scanner [Unit 1] - Boiler Safety Valve [Unit 2] - Coal Distribution
Test Poping Test Con. No-Load Test

03-Jun-18 12-Jun-18 23-Jun-18 05-Jul-18 28-Sep-18 02-Oct-18 20-Dec-18 29-Dec-18


06-May-18 15-May-18 11-May-18 23-May-18 15-Aug-18 19-Aug-18 06-Nov-18 15-Nov-18

[Unit 1] - FO System [Unit 1] - Bag Filter Pulse [Unit 1] - Bed Material [Unit 2] - Coal Conveyor-2
Flushing Air Test Feeding to Boiler Load Test

23-May-18 27-May-18 13-Jun-18 22-Jun-18 18-Sep-18 02-Oct-18 15-Dec-18 19-Dec-18


10-Apr-18 20-Apr-18 16-May-18 25-May-18 05-Aug-18 19-Aug-18 01-Nov-18 05-Nov-18

[Unit 1] - ID Fan System [Unit 1] - FO Supply System [Unit 1] - Bed Ash Removal [Unit 2] - Coal Conveyor-2
Test Test System Test No- Load Test

24-May-18 24-May-18 13-Jun-18 22-Jun-18 28-Sep-18 02-Oct-18 25-Oct-18 13-Jan-19


08-Apr-18 08-Apr-18 01-May-18 10-May-18 15-Aug-18 19-Aug-18 11-Sep-18 30-Nov-18

[Unit 1] - Bag Filter [Unit 1] - Bag Filter Interlock [Unit 1] - SH Temperature [Unit 1] - Commissioing Test
Installation Completed Test Control Test (Functional Test)

05-Jun-18 01-Nov-18
02-May-18 28-Sep-18

[Unit 2] - Fire Fighting &


Alarm System

01-Jun-18 01-Jun-18 18-Jun-18 27-Jun-18 27-Sep-18 03-Oct-18


09-Apr-18 09-Apr-18 26-May-18 04-Jun-18 11-Aug-18 17-Aug-18

[Unit 1] - Smoke Air Leak [Unit 1] - TBN Lube Oil Test [Unit 1] - Coal Distribution
Test Conveyoy Load Test

31-May-18 31-May-18 30-Jun-18 02-Jul-18 19-Sep-18 23-Sep-18 05-Oct-18 06-Oct-18


08-Apr-18 08-Apr-18 07-Jun-18 09-Jun-18 03-Aug-18 07-Aug-18 18-Aug-18 19-Aug-18

[Unit 1] - Completion of Flue [Unit 1] - Turning Gear Test [Unit 1] - Coal Conveyor-2 [Unit 1] - Coal Silo Coal
Gas Duct Construction No- Load Test Receiving

02-Jun-18 05-Jun-18 25-Sep-18 04-Oct-18


20-Mar-18 23-Mar-18 08-Aug-18 17-Aug-18

[Unit 1] - Closed Cooling [Unit 1] - Coal Conveyor-2


Water Line Flushing Load Test

31-May-18 01-Jun-18 20-Sep-18 20-Sep-18


18-Mar-18 19-Mar-18 11-Aug-18 11-Aug-18

[Unit 1] - CCW PP Motor [Unit 1] - Vacuum Pump No-


No- Load Test Load Test

09-Apr-18 17-Jun-18 15-Sep-18 19-Sep-18 03-Oct-18 06-Oct-18


17-Mar-18 25-May-18 10-Aug-18 14-Aug-18 14-Aug-18 17-Aug-18

[Unit 1] - TBN Lube Oil [Unit 1] - Sand Silo Sand [Unit 1] - Bypass System
Flushing Receiving Valve Test

13-May-18 27-May-18 15-Sep-18 16-Sep-18


31-Mar-18 14-Apr-18 10-Aug-18 11-Aug-18

[Unit 1] - LV SWGR & MCC [Unit 1] - Limestone Silo


Test (B/F & AHS Bldg) Receiving

01-Sep-18 20-Sep-18
31-Jul-18 19-Aug-18

[Unit 1] - Fly Ash Handling


System Test

06-Sep-18 25-Sep-18
31-Jul-18 19-Aug-18

[Unit 1] - Bed Ash Handling


System Test

Non-driving, non-critical
Actual Work
Remaining Work Driving, non-critical
Critical Remaining Work Critical
Milestone
Summary Data Date Line

28-Feb-18
IKAL_I-18 - Kalsel-1 CFPP (Indonesia) Level 3 Rev.1 Monthly Updated Schedule_20180228EPC)_Full