The Core functions of the building branch can be translated into six basic procedures
namely;
`
1) PROCESSING CLIENT REQUESTS & APPLICATIONS FOR ANNUAL
ALLOCATIONS
Introduction
Identification of new project proposals for the forthcoming new Five Year Malaysia
Plan is normally carried out before the current Plan ends. Projects may also be
identified during Mid Term Review or come from ad hoc projects requested by the
State and Federal Government.
ACTION RESPONSIBILITY
1(A) Client Requests For Projects Which Have Not Been
Approved Yet
ACTION RESPONSIBILITY
5. Proceed to prepare proposals and consider the following SH
below:
(a) State Government Circular; and
(b) Discussions with the Clients to determine the requirement
and priority of projects. AIC
Introduction
Before projects can be implemented, siting approval must first be obtained from the
Stale Planning Authority (SPA). This procedure describes the process flow for Siting
Applications for JKR development projects only. This process (Appendix 3) is
applicable to all Divisions except for Bintulu Division whereby siting is submitted to
Bintulu Development Authority [BDA].
Development projects for other Ministries and Departments, the Client is responsible
to submit siting applications.
ACTION RESPONSIBILITY
1. Proceed to submit an application to Superintendent of DE
Land and Survey to identify & a suitable site for the
project.
Introduction
This procedure is to provide the information required for a Design Quality Plan for
State and Federal Building Projects costing RM 5.0 million and above which are
implemented using open tender.
ACTION RESPONSIBILITY
1. Prior to commencement of project implementation, SH/AIC
prepare a Design Quality Plan (Appendix 5) for the
approval of AD (B).
Introduction
This procedure describes separately the process flow to prepare Schematic Design
for development projects implemented as follows:
i) 4(A) Preparation of Schematic Design (In-house), and
ii) 4(B) Preparation of Schematic Design (Consultant)
ACTION RESPONSIBILITY
4(A) Preparation of Schematic Design (In-house)
2. Obtain a survey plan, location arid site plans from DL, AIC/DT
Client or Surveying Consultant, if relevant.
ACTION RESPONSIBILITY
3. Upon agreement, complete the Form For Proposed AIC
Appointment of Consultants (Appendix 10) and submit for
approval to SFS for State projects and KSU for Federal
projects.
Introduction
This procedure describes separately the process flow for preparation of Working
Drawings and Specifications for the development of projects implemented as follows:
i.) 5(A) Preparation of Working Drawings and Specification (In-house), and
ii.) 5(B) Preparation of Working Drawings and Specification (Consultant).
ACTION RESPONSIBILITY
5 (A) Preparation of Working Drawings and
Specifications In-house
Introduction
3. Arrange a date for site handing over to the Contractor and SO/PD
followed by the first Site Meeting.
Appendix 1
B UILD IN G B R AN C H C O R E P R O C E S S C H AR T
1 ) IN - H O US E
START
A. PLANNING STAGE
PQP NO
APPROVED
YES
2.1 COORDINATE WITH DESIGN TEAM (ARCH, C&S, M&E, QS, CLIENT)
IGN STAGE
START
CONSULTANT
NO
APPROVED
YES
1.3 SUBMIT NOMINATIONS TO SFS
NO
APPROVED
YES
1.4 ISSUE LETTERS OF APPOINTMENT
NO
B. SCHEMATIC DESIGN STAGE
APPROVED
YES
2.2 OBTAIN APPROVAL OF DESIGN FROM CLIENT
NO
APPROVED
YES
NO
APPROVED
YES
-
Appendix 2
ADEQUACY CHECKLIST FORM
PROJECT NAME
Please tick(√) if complete, if documents are not complete, please liaise with relevant client/authority or DE
Site Identification
To
(Section Head)
All documents are complete and I am ready to discuss implementation of project.
To:
A.I.C Name:
2. Applicant.....................................................................................................................................................
..................................................................................................
..................................................................................................
..................................................................................................
..................................................................................................
..................................................................................................
.....
..................................................................................................
..................................................................................................
..................................................................................................
..................................................................................................
..................................................................................................
.....
Signature:................................................................................Designation.................................................................
Date: 3 September 1 9 9 6
Appendix 5
Page 1/5
Project Name
Name of Client's
Representative
Tel. No. Fax. No.
2. PROJECT FINANCIAL DETAILS
Head:
Malaysia Plan No.
Subhead:
3. PROJECT SCOPE
(Attach or state works scope)
Location
Size of Site
Project Description
(such as space
requirement type of
building such as office,
school, etc.)
Appendix 5
Page 3/5
4. PROJECT TEAM
Mark as follows:
Responsibility "A" - Works scope implemented by PWD HQ
"B" - Works scope implemented by Consultant
Activities Responsibility
a) Surveying Works
b) Schematic Design Drawings
c) Basic Working Drawings & Building Specification
d) Soil Investigation
e) Working Drawings & Structural and Civil Specifications
f) Mechanical & Electrical Drawing and Specifications
g) Project Cost Estimate
h) Tender Documentation
i) Supervision & Contract Administration
Appendix 5
Page 4/5
5. PROJECT TEAM
Consultant
a) Architect
d) Quantity Surveyor
e) Other Contacts:
(other department/government
agencies)
Appendix 5
Page 5/5
Appendix 6
Page 1/2
SITE RECORD FORM
PROJECT NAME
Items Remarks
I. Location of Site
II. She and Zoning
III. Accessibility
IV. Natural Physical Features:
a) Topographical Features
b) Drainage Patterns
c) Vegetations/Trees
d) Rocks
e) Streams/Rivers/Ponds
V. Man-made Features:
a) Buildings/Other
Structures
b) Squarters
c) Local Characteristics
Appendix 6
Page2/2
Items Remarks
VI. Circulation
a) Vehicle Traffic
b) Pedestrian Movement
VII. Utilities:
a) Electricity
b) Sewer/Discharge Point
c) Water
d) Telephone
Prepared By:
(Name: ) Date
Appendix 7
Page1/2
Appendix 7
Page1/2
PUBLIC WORKS DEPARTMENT- SARAWAK
PWD142A
a
b
c
d
-
e
f
g
h
Electrlcal Installation
and D items done by the DepartmentInsert T for items included in Main Tender, X for items tendered
14 Site Works
15 Surface Drainage
16 Road: and Paths
17 Fencing and Gates
18
19
20
21
22
23
24 Advertisements All-in Unit Rates
2s Supervision Area-Ft. Sup. Cost/Ft. Sup.
Total (Buildings & Services) RM
FEESPROFESSIONAL
26 RM Quantity
27 Surveyor
28 Designation Date
29 Engineer/
30 Architect
31 Date
32 Director
of
33 Public Works
Total Cost of Project RM Date
Appendix 7
Page2/2
The following abbreviations shall be used in completing the 'Brief descriptions of Buildings':
AC - Asbestos Clay T - Clay Tiles P&P. - Precast Concrete T&G - Tongued and
Cement Post and Panel Grooved Board
Al - Aluminum Conc. - Concrete Pqt. - Parquet TSW. - Timber frame
Bk - Brick Conc. T - Concrete Tiles screen wall
BUF - Built-up CR. - Cement QT. - Quarry Tiles TT. - Terrazzo Tiles
roofing-felt Rendering R.C. - Reinforce Concrete Tz - In- situ Terrazzo
BUP - Built-up GCI - Galvanized S. - Stone VT. - Vinyl Tiles
roofing plastic Corrugated Iron
St - Steel W.Bd - Weather Boarding
C.Bk - Cement Brick LAC. - Light-weight T. - Timber WCR. - Waterproof
Asbestos Cement Rendering
Cement TF. - Timber Flooring
CCR - Colored MSW. - Metal Name
Cement screen wall
Rendering
CHB - Cement Hollow MT. - Mosaic Tiles
Block
Both the base material and the finish shall be given in the case of floors and flat roofs, thus:
Conc. /VT RC/WCR.
The standard of the building relates to the general standard of finishes rather than to construction and shall be given as one of the
categories:
Prestige, high, normal, low
8. All prime cost and Provisional Sums shall be listed in the space provided, or on the attach sheet, and in the case of “Revised” and
“As Completed" Detailed Abstracts, figures as allowed and as actually expended shall be shown
9. Where Quantity Surveyor is employed on a project, all Detailed Abstracts shall be prepared by him.
10. The C.E.B. / electrical authority shall be consulted by the Architect/Engineer before costs are inserted in the Detailed Abstract.
11. The amount of Professional fees for each Consultant Shall be inserted in the space provided, the total amount being placed in the
'Cost" column.
L - C 3 l 7 8 PNMB, Kch.
Appendix 8
Page1/6
Appendix 8
Page2/6
Appendix 8
Page3/6
Appendix 8
Page4/6
Appendix 8
Page5/6
Appendix 8
Page 6/6
Appendix 9
Appendix 10
Page 1/4
PROJECT TITLE
BUDGET INFORMATION
Appendix 10
Page 2/4
(Appendix A)
CONSULTANT REQUIRED
ARCHITECT
(Please tick where appropriate)
CIVIL & STRUCTURAL
MECHANICAL & ELECTRICAL
QUANTITY SURVEYOR
LAND SURVEYOR
OTHERS
(Name eg. Geological Surveyor)
RECOMMENDED CONSULTANTS
* APPOINTMENT OF CONSULTANTS
(CONSULTANT BRIEF REPORT)
CONSULTANT’S BACKGROUND
Other
Architect Q.S. Civil Eng Mech Eng Elect Eng (Surveyor
etc)
Cont Period
Head Subhead Estimates Total Provision RM
Tender Valid Until
Provision for Construction RM
Cost RM Date of Possession of Site Expected Date of Completion
1
PRELIMINARIES --
Basic Unit Rates
2 MAIN WORKS DRG. NOS.
-
Volume-Ft. Cu. Cost/Ft. Cu. Area-Ft. Sup. Cost/Ft. Sup.
a
b
c
d
e
f
g
h
Electrlcal Installation
tendered and D items done by the DepartmentInsert T for items included in Main Tender, X for items
27 RM Quantity
28 Surveyor
29 Designation Date
30 Engineer/
31 Architect
32 Date
33 Director
of
Total Cost of Project RM
Public Works
Savings RM Date
Appendix 17
Page 2/2
NOTES ON COMPILING AND SUBMITTING DETAILED ABSTRACTS
12. (a) The Plan Area snail be measured to the outside face
at the walls on each Moor plan, viz., Ground floor,
First Floor. etc.
The following abbreviations shall be used in completing the 'Brief descriptions of Buildings':
AC - Asbestos Clay T - Clay Tiles P&P. - Precast Concrete T&G - Tongued and
Cement Post and Panel Grooved Board
Al - Aluminum Conc. - Concrete Pqt. - Parquet TSW. - Timber frame
Bk - Brick Conc. T - Concrete Tiles screen wall
BUF - Built-up CR. - Cement QT. - Quarry Tiles TT. - Terrazzo Tiles
roofing-felt Rendering R.C. - Reinforce Concrete Tz - In- situ Terrazzo
BUP - Built-up GCI - Galvanized S. - Stone VT. - Vinyl Tiles
roofing plastic Corrugated Iron
St - Steel W.Bd - Weather Boarding
C.Bk - Cement Brick LAC. - Light-weight T. - Timber WCR. - Waterproof
Asbestos Cement Rendering
Cement TF. - Timber Flooring
CCR - Colored MSW. - Metal Name
Cement screen wall
Rendering
CHB - Cement Hollow MT. - Mosaic Tiles
Block
Both the base material and the finish shall be given in the case of floors and flat roofs, thus:
Conc. /VT RC/WCR.
The standard of the building relates to the general standard of finishes rather than to construction and shall be given as one of the
categories:
Prestige, high, normal, low
12. All prime cost and Provisional Sums shall be listed in the space provided, or on the attach sheet, and in the case of “Revised” and
“As Completed" Detailed Abstracts, figures as allowed and as actually expended shall be shown
13. Where Quantity Surveyor is employed on a project, all Detailed Abstracts shall be prepared by him.
14. The C.E.B. / electrical authority shall be consulted by the Architect/Engineer before costs are inserted in the Detailed Abstract.
15. The amount of Professional fees for each Consultant Shall be inserted in the space provided, the total amount being placed in the
'Cost" column.
L - C 3 l 7 8 PNMB, Kch.
GUIDELINE FOR OPERATIONAL PROCEDURES FOR BUILDING PROJECTS
– POST CONTRACT STAGE
ACTION RESPONSIBILITY
3. Arrange a date for site handing over to the Contractor and SO/PD
followed by the first Site Meeting.
10. Ensure that safety and health requirement are compiled with SO/PD
in accordance with the Occupational Safety and Health Act
during all stages of the construction.
ACTION RESPONSIBILITY
11. Process and prepare the following where relevant, among SO/PD
others:
a) Interim Certificates
e) Extension of Time
a) Certificate of Non-Completion
If the Contractor fails to complete the construction works SO / PD
by the Date of Completion or any extended date fixed,
prepare for Certificate of Non-Completion to the
Contractor. (Refer to Procedure JKR-CP-PM-04 Item
7.3)
b) Notice of Default
If the Contractor without reasonable cause wholly
suspends the carrying out of the works before SO / PD
completion date or fails to proceed regularly and
diligently with the works or has abandoned the contract,
proceed to give the Contractor notice specifying the
default (Refer to Procedure JKR-CP PM-04 Item 7.5)
Appendix 17
PUBLIC WORKS DEPARTMENT- SARAWAK
PWD142B
Cont Period
Head Subhead Estimates Total Provision RM
Tender Valid Until
Provision for Construction RM
Cost RM Date of Possession of Site Expected Date of Completion
1
PRELIMINARIES --
Basic Unit Rates
2 MAIN WORKS DRG. NOS.
-
Volume-Ft. Cu. Cost/Ft. Cu. Area-Ft. Sup. Cost/Ft. Sup.
a
b
c
d
e
f
g
h
Electrlcal Installation
tendered and D items done by the DepartmentInsert T for items included in Main Tender, X for items
27 RM Quantity
28 Surveyor
29 Designation Date
30 Engineer/
31 Architect
32 Date
33 Director
of
Total Cost of Project RM
Public Works
Savings RM Date
Appendix 17
Page 2/2
NOTES ON COMPILING AND SUBMITTING DETAILED ABSTRACTS
18. (a) The Plan Area snail be measured to the outside face
at the walls on each Moor plan, viz., Ground floor,
First Floor. etc.
The following abbreviations shall be used in completing the 'Brief descriptions of Buildings':
AC - Asbestos Clay T - Clay Tiles P&P. - Precast Concrete T&G - Tongued and
Cement Post and Panel Grooved Board
Al - Aluminum Conc. - Concrete Pqt. - Parquet TSW. - Timber frame
Bk - Brick Conc. T - Concrete Tiles screen wall
BUF - Built-up CR. - Cement QT. - Quarry Tiles TT. - Terrazzo Tiles
roofing-felt Rendering R.C. - Reinforce Concrete Tz - In- situ Terrazzo
BUP - Built-up GCI - Galvanized S. - Stone VT. - Vinyl Tiles
roofing plastic Corrugated Iron
St - Steel W.Bd - Weather Boarding
C.Bk - Cement Brick LAC. - Light-weight T. - Timber WCR. - Waterproof
Asbestos Cement Rendering
Cement TF. - Timber Flooring
CCR - Colored MSW. - Metal Name
Cement screen wall
Rendering
CHB - Cement Hollow MT. - Mosaic Tiles
Block
Both the base material and the finish shall be given in the case of floors and flat roofs, thus:
Conc. /VT RC/WCR.
The standard of the building relates to the general standard of finishes rather than to construction and shall be given as one of the
categories:
Prestige, high, normal, low
16. All prime cost and Provisional Sums shall be listed in the space provided, or on the attach sheet, and in the case of “Revised” and
“As Completed" Detailed Abstracts, figures as allowed and as actually expended shall be shown
17. Where Quantity Surveyor is employed on a project, all Detailed Abstracts shall be prepared by him.
18. The C.E.B. / electrical authority shall be consulted by the Architect/Engineer before costs are inserted in the Detailed Abstract.
19. The amount of Professional fees for each Consultant Shall be inserted in the space provided, the total amount being placed in the
'Cost" column.
L - C 3 l 7 8 PNMB, Kch.
Appendix 18
Page 1/3
SITE DIARY
FOR CONTRACT WORKS
Contract No ……………………………..
………………………………………………………….
Appendix 18
Page 2/3
1. This diary is to be entered up daily by the P.W.D. site representative, from the
commencement of the project to its final completion.
2. The following details are to be entered daily under the headings given:
Materials delivered or required
(a) Brief note of principal materials delivered.
(b) Any shortage of materials on site.
Works carried out
Brief note of principal works carved out, sufficient to show state of progress.
Visits by supervisory staff
(a) Name or title of visitor
(b) Time of visit
Instructions given to Contractor
3. Instructions re standard of work, rectification required.
4. Instructions re variations required (Engineer to be given full details to
e n a b l e him to confirm in writing to the Contractor).
Miscellaneous
(a) Any records required by Engineer, such as details of excavation depths,
etc. (N.B. Blank pages at end of diary are to be used for this if more
convenient)
(b) Details of any tests carried out, such as on drains, etc.
(c) Brief notes of any accidents, strikes or other occurrences affecting the
works
3. All concrete test cubes taken are to be recorded in the schedule at the end of
the diary Test results may be recorded later if required.
4. All piles driven are to be recorded in the schedule at the end of diary.
5. The blank pages at the end of the diary are to be used for all records, sketches,
etc. for which the daly pages are inadequate. Such entries are to be dated and
made in order.
Appendix 18
Page 3/3
Weather (stating severity and time of rain)
………………………………………………
Extent to which work interrupted by
weather……………………………………………
Number of men employed on site:
Nominated Sub-
Main Contractor
Contractor
Coolies…………………… Painter……………………. Electricians……………….
Steel benders…………...... Drivers/plant operators…… Flat roofing……………
Masons…………………….. Foreman & clerks………… Tile paving……………….
Carpenters……………….....
Plumbers…………………...
Glaziers…………………….
Miscellaneous: