DETAIL OF QUANTITY FOR PIPE LAYING (JUAN)

S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
1   DISMANTLING OF ROAD                
1.1 8.5 (b), Dismantling Brick work, Tile Masonry or Tile                
HSR Lining and Tile Terracing. In cement

    3m wide road ( Pipeline 1)   105.85 3 0.15 47.633 Cum Cum Refer Drawing
5/10
    6m wide road ( Pipeline 1)   6 3 0.115 2.070 Cum Cum  

    15m wide road ( Pipeline 3)   15 4.53 0.115 7.814 Cum Cum  

    Sub Total         57.52 Cum Cum  

2   EARTHWORK EXCAVATION                

2.1 6.7, HSR Earthwork in excavation in foundations,               Refer Drawing


trenches, of under ground structures, sullage 1/23 & 5/23
drains, etc. and other similar works in ordinary
soil including dressing of bottom and sides, to
correct levels and templates, cutting of trees
and bushes, dewatering of rain water,
diversion of traffic, fixing and maintenance of
caution boards, and night signals, crossing over
trenches for access to houses, watching,
stacking of excavated soil, clear from the edge
of excavation, and subsequent filling, where
required around masonry, in 15 cm layers,
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
with compaction and disposal of surplus soil as
directed within a lead of 30 metres for depth
upto 2 metres below natural ground level.
                   

    Pipelaying P1   6 3.66 2.43 53.36 cum P%cum {( 1.23 +


6.09 )/2 = 3.66}
      3.4 2.89 1.66 16.31 cum P%cum {( 1.23 +
4.55 )/2 = 2.89}
      104.10 3 1.2 374.76 cum P%cum  

      6.5 2.235 1.005 14.60 cum P%cum {( 1.23 +


3.24 )/2 =
2.235}
    Pipelaying P2 - 230 1.755 0.525 211.92 cum P%cum {( 1.23 +
2.28 )/2 =
1.755}
    Pipelaying P3 - 190 2.06 0.83 324.86 cum P%cum {( 1.23 +
2.89 )/2 = 2.06}
    For Manhole M1 8 17.25 138 cum P%cum {( 1.23 +
2.89 )/2 = 2.06}
    Pipelaying P3         514.62 cum P%cum  

    For Manhole M2 1 17.25 17.25 cum P%cum  

    For Sluice Valve   4.92 4.92 2.32 56.16 cum P%cum {( 2.6 +
7.24 )/2 = 4.92}

    WING WALL 5 3.4 1.6 2.82 76.70 cum P%cum Refer "
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
    5 3.4 1.6 2.82 76.70 cum P%cum Annexure - J "

    5 1.7 1.5 2.82 35.96 cum P%cum

    5 1.7 1.5 2.82 35.96 cum P%cum

    5 1.73 1.35 2.82 32.93 cum P%cum

    5 1.73 1.35 2.82 32.93 cum P%cum

    Recharge Shaft 1   7.19 7.19 3 155.09 cum P%cum {( 4.19 +


10.19 )/2 =
7.19}
    Recharge Shaft 2   7.19 7.19 3 155.09 cum P%cum {( 4.19 +
10.19 )/2 =
7.19}
    Sub Total         2323.20 cum P%cum  
3   REHANDLING OF EARTH                

3.1 HSR Total Excavated earth         2323.20 cum P%cum  


    Deduction of earth                

    C.C Under pipe (P1) - 120 0.63 0.1 7.56 cum P%cum  

    For Pipe (P1) - (3.14 X 0.162 X 0.162 X 120 ) 9.89 cum P%cum  

    Sluice valve   (3.14 X 0.365 X 0.365 X 2.32 ) 0.97      

    C.C Under pipe (P2) - 230 0.63 0.1 14.49 cum P%cum  
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
    For Pipe (P2) - (3.14 X 0.162 X 0.162 X 230 ) 18.95 cum P%cum  

    C.C Under pipe (P3) - 190 0.63 0.1 11.97 cum P%cum  

    For Pipe (P3) - (3.14 X 0.162 X 0.162 X 190 ) 15.66 cum P%cum  

    Manhole of (P2) & (P3) 9 1.05 1.05 1.5 14.88 cum P%cum  

    Sub Total         2228.82 cum P%cum  

4   BRICKWORK                

4.1 11.4, HSR First class brick work laid in cement sand                
mortar 1:4 in foundation and plinth

    For Sluice Valve - 1.09 1.090 Cum Cum Refer "


Annexure -I"
    For Manhole wall M1 32 0.85 0.115 1.5 4.692 Cum Cum (8 Manhole X 4
Sides = 32 )
    For Manhole wall M2 4 0.85 0.115 1.5 0.587 Cum Cum (1 Manhole X 4
Sides = 4 )
    Recharge Shaft 1 4 2.69 0.345 6 22.273 Cum Cum  
    Recharge Shaft 2 4 2.69 0.345 6 22.273 Cum Cum  
    Sub Total         50.91 Cum Cum  

5   PLASTER                
5.1 15.5, HSR 12 mm thick cement plaster 1:4                
    For Manhole wall M1 32 0.85   1.5 40.800 Sqm Sqm (8 Manhole X 4
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
Sides = 32 )
    For Manhole wall M2 4 0.85   1.5 5.100 Sqm Sqm (1 Manhole X 4
Sides = 4 )
    Recharge Shaft 1 4 2.69   6 64.560 Sqm Sqm  
    Recharge Shaft 2 4 2.69   6 64.560 Sqm Sqm  
    Sub Total         175.02 Sqm Sqm  

6   CEMENT CONCRETE M-15 (1:2:4)                

6.1 10.41, HSR Cement Concrete 1:2:4 with stone aggregate 20               Refer Drawing
mm nominal size in foundation and plinth 5/23

    Below Pipeline P1                

    Pipeline (P1)   120 0.63 0.1 7.56 Cum Cum  

    Pipeline (P2)   230 0.63 0.1 14.49 Cum Cum  

    Pipeline (P3)   190 0.63 0.1 11.97 Cum Cum  

    Manhole   1.05 1.05 0.1 0.11 Cum Cum  

    For Wing Wall Base 5 0.869 4.345 Cum Cum Refer "
Annexure -J"
    Slab for outlet of wing wall 2 2 1.58 6.32 Cum Cum Refer "
Annexure -K"
    Sub Total         44.80 Cum Cum  
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
7   REINFORCED CEMENT CONCRETE 1:1.5:3                
(M-20)

7.1 10.65, HSR Design Mix cement concrete of grade M-20                


with minimum cement contents 300 kg/cum in
foundation and plinth

    For wing wall 5 3.331 16.655 Cum Cum Refer "


Annexure -J"
8   STEEL REINFORCEMENT                

8.1 18.22, HSR Fe-500 EQR TMT steel bars for bars RCC,            
works, where not including in the complete
rate of RCC including beading, binding and
placing in position complete.

    Wing Wall 5 ( 162.5 + 154.64 ) 16.33 Quintal Quintal Refer Table 2

9   MANHOLE COVER                

9.1 28.59, HSR Providing & fixing DUCTILE IRON DOUBLE                


SEAL MANHOLE COVERS AND FRAMES OF
610mm X 610mm with locking arrangement on
clear water tanks including cost of setting in
cement concrete 1:2:4 to correct alignment and
levels including carriage , loading , unloading
etc. complete in all respects to the satisfaction
of the Engineer - in - charge
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
    In Manhole M1         8 Each Each  

    In Manhole M2         1 Each Each  

    Sub Total         9.00 Each Each  

10   SLUICE VALVE                

10.1 N.S. Item 1 Sluice valve for 0.324 m dia         1 Each Each  

11   DWC HDPE PIPE                

11.1 N.S. Item Double Wall Corrugated High-density                


polyethylene Pipe of ɸ 0.324m

    Pipeline P1         120 Meter Meter  

    Pipeline P2 L.S.       230 Meter Meter  

    Pipeline P3         190 Meter Meter  

    Sub Total         540.00 Meter Meter  

12   WATER QUALITY SENSOR                


12.1 N.S. Item Water Quality Sensor         2 Each Each  
13   WATER LEVEL SENSOR                
13.1 N.S. Item Water level sensor         2 Each Each  
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
14   RESTORING OF ROAD                
14.1 24.38, HSR Restoring the road cut, in level with the                
existing road surface, including preparation of
subgrade laying and relaying of soling and
laying and consolidation of wearings coats to
water bound macadam specification, and
laying 20 mm thick premix carpet, on top
including cost of tack and seal coat complete in
all respect.
    6m wide road ( along Pipeline 1)   6 3   18.000 Sqm P%Sqm  

    15m wide road ( along Pipeline 3 )   15 4.53   67.950 Sqm P%Sqm  

    Sub Total         85.95 Sqm P%Sqm  

15   PIEZOMETER                

15.1 N.S. Item Piezometer with complete in all respect                


( including drilling, u-PVC pipe , MS Clamps,
PVC End cap )

    Piezometer 1a/1b - 60/30 meter length         4 Each Each  

16   FILTER MEDIA                

16.1 28.50 ( d), Bajri ( coarsed ) screened and washed graded                


HSR from 20 mm to 25 mm ( from ghaggar or
approved equivalent quarry)
S. Reference Description of Items No. Length Width H/D (m) Quantity UNIT For Remarks
No. No. (m) (m) Rate
    PIEZOMETER 1a 2 (3.14 X 0.2 X 0.2 X 60 ) - ( 3.14 X 6.59 Cum Cum  
0.15 X 0.15 X 60 )
    PIEZOMETER 1b 2 (3.14 X 0.2 X 0.2 X 30 ) - ( 3.14 X 3.30 Cum Cum  
0.15 X 0.15 X 30 )
    Sub Total         9.89 Cum Cum  

16.2 N.S. Item Supply, Installation and commissioning of         4.00 Each Each  
Acoustic Digital Water Level Recorder
17   OPERATION & MAINTENANCE                

17.1 N.S. Item Dashboard charges for Data in Piezometer 4 For 3 years 12 Year Year  

17.2 DC RATES Helper (Technician) (1 X 36) 36 Months Months  