Professional Documents
Culture Documents
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 2
Table of Contents
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 3
1 General references
This installation instruction contains important information which should be read and understood before
installation and start-up. For safe and reliable operation the whole of this guide should be considered
essential reading as safety and operational information is provided in all sections, not only in the "safety
references" section. Both the installer and person responsible for the on-going operation should read and
understand this guide. This guide should always be available at the installation site. This installation guide
refers to the PV module mounting system LORENTZ PM-1-X.
The total PV module area of the PV modules must not exceed 8.5 m² (91 ft²). The maximum width of the
PV modules, including the distances between the PV modules, must not exceed 5.2 m (205 inch) and the
height must not exceed 2 m (78 inch) with the combined maximum surface area of 8.5 m² (91 ft²). PV
modules certified to IEC 61215 or UL 1703 must be installed vertically. If the PV modules are not certified
to IEC 61215, UL 1703 then care should be taken to assess the suitability for mounting onto the sub-
structure of the PM-1-X.
The customer must consider the local weather conditions and the suitability of the PM-1-X to operate in
these conditions. The Pole Mount structure is designed to perform with a maximum wind speed of 130
km/h (81mph). The maximum ice thickness is 25.4 mm (1 inch) at maximum wind speed. Snow thickness
equivalence of the ice thickness will vary from 50 mm (2 inch) to 300 mm (12 inch) depending on local
conditions. Where modules are installed in non-equatorial regions then the tilt angle of the modules will
reduce the likelihood of high snow thickness. All warranty claims against LORENTZ are invalidated if the
PM-1-X is installed in inappropriate conditions.
Safe working
All local safety standards, health and safety assessments and good general working practices must be
considered before work begin to prevent accidents.
Consequences
If safety information and advice is not followed then there is a risk of personal injury, equipment damage
and loss of ability to make warranty claims.
V190701
V150703
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 4
Electrical safety
Electronic and electrical systems should only be worked on by qualified and experienced persons who
have been trained and hold the necessary permits, certificates and approvals to meet local codes, require-
ments and laws. Untrained and unqualified persons could cause damage to the equipment and increase
the risk of injury. Local rules, codes, requirements and laws must be met (for example the regulations of
Verband der Elektronik = VDE, Germany).
Inappropriate treatment
The safety of the systems can only be guaranteed when they are installed and operated within the guide-
lines and limits listed in the technical specifications
Qty. of PV Modules
Size 2 x 1 m 1 1 3 3 4 4
Foundation
Height [mm] 600
Height [inch] 23.6
D x D [mm] 800 x 800 800 x 800 1100 x 1100 1100 x 1100 1200 x 1200 1200 x 1200
D x D [inch] 31 x 31 31 x 31 43 x 43 43 x 43 47 x 47 47 x 47
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 5
US Market
Beam US Standard pipe Schedule 40
Cross section [inch] 2.5
Length [inch] for calculation of beam length A see formula chapter 5.3
Pole US Standard pipe schedule 40
Cross section [inch] 2.5 4
Length [inch] 75
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 6
3 Parts list
6 kits Pole Mount PM-1-x (x: 1 to 6) mounting structure without pole or beam
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 7
4 Foundation
Before installing the Pole Mount PM-1-x a suitable foundation is required. Close attention should be paid
that the mounting pole is a minimum 0.4 m into the foundation (more details in the following drawings)
The foundation specified has been designed to meet wind load requirements for the maximum PV mod-
ule surface area.
You should seek professional advice if you plan to use alternative foundation types or sizes. These draw-
ings are examples of a suitable foundation with concrete reinforcement.
Component no. 1
Foundation dimensions
Foundation
PM-1-
DxDxC
X
[mm/inch]
PM-1- 550x550x500
1 / 22x22x20
PM-1- 700x700 x500
2 / 28x28x20
PM-1- 775x775 x500
3 / 31x31x20
PM-1- 775x775 x500
4 / 31x31x20
PM-1- 925x925 x500
5 / 36,5x36,5x20
PM-1- 925x925 x500
6 / 36,5x36,5x20
Component no. 2
V190701
V150703
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 8
5 Mounting
The Pole Mount PM-1-x is designed to require minimum servicing or maintenance work. For safe and
reliable operation the system should be checked regularly.
We recommend that nuts, bolts and screws are checked for appropriate tightness 6
months after installation, and then every year.
All nuts, bolts and connection parts are stainless steel to strength class 70. If any parts are replaced they
should be replaced with parts of the same specification.
This manual is an installation guide and does not replace good engineering practice.
The local installer should check and verify the installation carefully.
Please use a torque wrench to ensure nuts and bolts are tightened correctly!
V190701
V150703
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 9
This rack is adjustable for different sizes of PV modules. To assemble the Pole Mount some dimensions
have to be calculated. Ascertain the right installation dimensions as follows:
Number of PV Modules = n =
L1 = n * w + ( n + 1 ) * 30mm = [mm]
L1 = n * w + ( n + 1 ) * 1.2inch = [inch]
L2 = L1 /2 = [mm/inch]
The measurement L3 is only for Pole Mount Systems with an uneven number of PV-Modules necessary.
L3 = w /2 = [mm/inch]
L1 is the total length of the beam. Take the steel marker and mark the position of L2 on the beam. The
Measurement L3 helps you to center the middle PV Module on the beam if your Pole Mount has an une-
ven number of PV Modules.
V190701
V150703
BERNT LORENTZ GmbH, Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germany, Tel.: +49 (0)4193 8806-700, www.lorentz.de
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice.
Pictures may differ from actual products depending on local market requirements and regulations
Page 10
Parts of the mounting system are very heavy so care must be taken during
handling, unpacking and installation. Appropriate safety equipment includ-
ing safety gloves and safety shoes must be worn at all times.
Please follow the steps below for the Installation of the LORENTZ Pole
Mount
3. Fix the Rack Head (2) with three screws M10x25 (3) to the Pole.
Please use a torque wrench (32Nm). The Rack Head for a 2.5
inch Pole looks different but can also be mounted with these in-
stallation manual.
2. Place the Rack Head (2) on the Pole (1) and adjust in to South.
The long axis of the Rack Head should be oriented to East/West
direction.
32 [Nm] ,
23,6 [lb-ft]
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
150703
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations
Page 11
Lightly
tighten
5. Place the Beam Support (4) under the Beam, insert the U-bolt
6. Slide the Beam symmetrical onto the Rack Head. Make sure the
(6) into the holes and through the Rack Head, connect washers
marked middle of the Beam is in the middle of the Rack Head.
10.5 (7) and Nuts M10 (8), tighten them lightly.
7. Place the second Beam Support under the Beam and mount it
as shown in the picture below.
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
150703
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations
Page 12
32 [Nm]
23.6 [lb-ft]
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
150703
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations
Page 13
Hammer blow
• Hold the PV Module Clips with the open side towards the Rail
and the PV Module. The flat side of the PV Module Clips must
touch the rail. Watch out that the PV Module frame and the Rail Attention:
are between the jaws of the PV Module Clips. Take a rubber For a Pole Mount PM-1-x with an uneven number
mallet and knock the PV Module Clips onto the Rail. of PV Modules you have to center the middle PV
Module over the Rack Head and not the Rail. Use
the mark L3 on the Beam.
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
150703
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations
Page 14
12. Hold the upper side of the PV Modules and loose the Nuts M10
of the Rack Head.
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
150703
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations
Page 15
13. Set the Tilt angle. Please have a look at Chapter 5.5 Adjustment
of the tilt angle.
32 [Nm]
23.6 [lb-ft]
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
150703
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations
Page 16
L3 is the measurement between the lower end of the Rail and the Pole. Please Measure from the edge
shown below edge on the Rail to the Pole.
The tilt adjustment for the northern hemisphere is shown below. (Adjust accordingly for southern hemi-
sphere):
BERNT LORENTZ GmbH & Co. KG Siebenstuecken 24, 24558 Henstedt-Ulzburg, Germanyl +49 (0)4193 7548-0, Fax -29, www.lorentz.de
V150813
All specifications and information are given with good intent, errors are possible and products may be subject to change without notice. Pictures may
differ from actual products depending on local market requirements and regulations