1 Access road
a) 8000mm ± 500mm (wide)
b) (Premix/Crusher Run*)
MJ
c) Catered for double axle trucks carrying
60 tons transformer c/w method
statement (as per sample)
2 Internal road
a) In front of transformer bay - 8000mm ±
500mm (wide)
b) In front of loading bay - 6000mm ±
500mm (wide)
c) Others - 3000mm ± 500mm (wide)
MJ
d) (Premix/Reinforced Concrete)
e) Catered for double axle trucks carrying
60 tons transformer c/w method
statement (as per sample)
f) To conduct coring test min. 2 location (in
front of loading bay and transformer bay)
Page 1 of 6
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
6 Sewerage system
a) (Centralize/Individual)**
MJ
b) Culverts & sump (standalone PPU)**
c) Heavy Duty FRP Grating at all crossings
7 Water supply
(Domestic connection/ Rain water harvesting MJ
system/Tube well)**
Lebar: ± 1.0mm
Panjang: ± 10mm
Page 2 of 6
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
12 a) Main signboard MN
b) TNB Careline
Location: at PPU wall facing MN
the main road
c) Danger sign
Location: at all four (4) sides MN
Signage
of perimeter fencing
d) No entry sign
Location: at all four (4) sides MN
of perimeter fencing
e) Safety Excellence
Management System (SEMS) MN
symbol
14 Site Clearing MN
* Developer shall provide an undertaking letter for provision of premix upon the completion of the development
**As per local authorities’ approval
Page 3 of 6
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
b) Removable handrail –
900mm high 75mmØ stainless MJ
steel
MJ
nosing tiles
4 a) Apron
Visual inspection - no cracks
Cement render finishes
b) Ramp MN
Visual inspection - no cracks
V-shaped Groove line
Yellow and black demarcation lines
6 Cable entry 11 kV
a) 24 Nos of ducting HDPE PN10 200mm Ø
b) 1000mm extended beyond perimeter MJ
fencing c/w endcap
c) 1000mm cable landing before ramp
Page 4 of 6
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Page 5 of 6
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 6 of 6
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
3. a) Room signage MN
Signage
b) Danger sign MN
c) No entry sign MN
4. a) 5000 x 2500mm(h) ± 5%
Removable fencing hot
dipped galvanised iron frame
Outdoor type
MJ
with hot dipped galvanised
anti-climb, anti-cut mesh
Mesh size: 12.5 x 75 x 4mm Ø
Page 1 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Ventilation system
Mechanical ventilation connected MJ
to fire alarm panel
10. Lighting -
Electrical fittings (incl. Testing &
Switches
a) 1 Nos Weatherproof switches
b) 1 Nos 20 Amps power point MJ
c) 1 Nos 3 phase 20 Amps
power point
Syste
ng
Page 2 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Page 3 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
3. a) Room signage MN
Signage
b) Danger sign MN
c) No entry sign MN
4. a) 5000 x 2500mm(h) ± 5%
Removable fencing hot
dipped galvanised iron frame
Outdoor type
MJ
with hot dipped galvanised
anti-climb, anti-cut mesh
Mesh size: 12.5 x 75 x 4mm Ø
Page 4 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Ventilation system
Mechanical ventilation connected MJ
to fire alarm panel
10. Lighting -
Electrical fittings (incl. Testing
Switches
a) 1 Nos Weatherproof switches
b) 1 Nos 20 Amps power point MJ
c) 1 Nos 3 phase 20 Amps
power point
Page 5 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Page 6 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
3. a) Room signage MN
Signage
b) Danger sign MN
c) No entry sign MN
4. a) 5000 x 2500mm(h) ± 5%
Removable fencing hot
dipped galvanised iron frame
Outdoor type
MJ
with hot dipped galvanised
anti-climb, anti-cut mesh
Mesh size: 12.5 x 75 x 4mm Ø
Page 7 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Ventilation system
Mechanical ventilation connected MJ
to fire alarm panel
10. Lighting -
Electrical fittings (incl. Testing
Switches
a) 1 Nos Weatherproof switches
b) 1 Nos 20 Amps power point MJ
c) 1 Nos 3 phase 20 Amps
power point
Page 8 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Page 9 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
3. a) Room signage MN
Signage
b) Danger sign MN
c) No entry sign MN
4. a) 5000 x 2500mm(h) ± 5%
Removable fencing hot dipped
galvanised iron frame with hot
Outdoor type
MJ
dipped galvanised anti-climb,
anti-cut mesh
Mesh size: 12.5 x 75 x 4mm Ø
Page 10 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Ventilation system
Mechanical ventilation connected MJ
to fire alarm panel
10. Lighting -
Electrical fittings (incl. Testing
Switches
a) 1 Nos Weatherproof switches
b) 1 Nos 20 Amps power point MJ
c) 1 Nos 3 phase 20 Amps
power point
Page 11 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Page 12 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
3. a) Room signage MN
Signage
b) Danger sign MN
c) No entry sign MN
4. a) 5000 x 2500mm(h) ± 5%
Removable fencing hot dipped
galvanised iron frame with hot
Outdoor type
MJ
dipped galvanised anti-climb,
anti-cut mesh
Mesh size: 12.5 x 75 x 4mm Ø
Page 13 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Ventilation system
Mechanical ventilation MJ
connected to fire alarm panel
10. Lighting -
Electrical fittings (incl. Testing
Switches
a) 1 Nos Weatherproof switches
b) 1 Nos 20 Amps power point MJ
c) 1 Nos 3 phase 20 Amps power
point
Page 14 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Page 15 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 16 of 16
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
skirting
c) Danger signage MJ
d) No Entry signage MJ
e) Room signage MJ
skirting
c) Danger signage MJ
d) No Entry signage MJ
e) Room signage MJ
3 a) Cable trench
6mm thick reinforced chequered MJ
Structural & finishes
b) Cable entry 33 kV
24 Nos of ducting HDPE PN10
150mm Ø c/w endcap
1000mm cable landing before 30° MJ
inclination ramp with smooth
landing
Page 1 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
c) Cable entry 11 kV
24 Nos of ducting HDPE PN10
200mm Ø c/w endcap
MJ
1000mm cable landing before 30°
inclination ramp with smooth
landing
Page 2 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
*Demarcation line– wall (Red & White – 50mm) & floor (Yellow - 100mm with 200mm spacing diagonals at 45°)
**Underside of chequered plate to be welded with 25 x 25mm mild steel angle iron stopper
***To be witnessed and verified by TNB during construction
ψ MSB shall be located at next to cable cellar main entrance
Page 3 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 4 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
c) Danger signage MN
d) No entry signage MN
e) Room signage MN
3 a) Floor hardener
MJ
Structural &
Page 1 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
c) Wall finishes
2100mm (h) TNB grey gloss
paints - ICI or equivalent
MN
Above 2100mm (h), white
emulsion paint – ICI or
equivalent
f) LVAC slot
1000 (l) x 500 (w) ± 5%
6mm thick reinforced
chequered plate c/w lifting MJ
hooks** and 6mm x 50mm
exposed copper tape at
opening
Page 2 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Commissioning)
MN
Testing &
Page 3 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
Commissioning)
tape at 33 kV slot
8 a) "UTAMAKAN KESELAMATAN"
sign – green colour (letter), MJ
Signage
Safety
white (background)
Page 4 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 5 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Room signage MN
MN
protector (outside the room)
c) Danger signage MN
d) No entry signage MN
e) Room signage MN
3. a) Floor hardener/
MJ
Design load: 10kN/m
d) Wall finishes
2100mm (h) TNB grey gloss MN
paints - ICI or equivalent
Page 1 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
h) Ceiling
MN
Reinforced concrete roof slab
Page 2 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
ing)
Fire
MN
Laminated Schematic Diagram
DB / Sub-DB
Commissioning)
(incl. Testing &
Page 3 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
8. a) "UTAMAKAN KESELAMATAN"
sign – green colour (lettering) white MN
Signage
Safety
(background)
Page 4 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 5 of 5
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
d) Room signage MN
MN
protector
c) Danger signage MN
d) No entry signage MN
e) Room signage MN
3. a) Floor finish
MJ
Acid resistant floor tiles
b) Wall finish
2100mm (h) acid resistant tiles
Structural & Finishes
c) 200mm x 500mm ± 5%
Slot covered with c/w 6mm
MJ
thick reinforced chequered
plate c/w lifting hooks**
Page 1 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
f) Ceiling
MJ
Reinforced concrete roof slab
Page 2 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
b) Earth bar MJ
Page 3 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 4 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
c) Danger signage MN
d) No entry signage MN
e) Room signage MN
b) Floor hardener MN
c) Floor finish
Green epoxy paint
MN
(Nippon EA-4 Evergreen
Structural & Finishes
1461)
e) Wall finishes
2100mm (h) white
MN
emulsion paint – ICI or
equivalent
f) Ceiling – reinforced
MN
concrete roof slab
Page 1 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
g) (Ventilation
block/aluminium lourves)
c/w stainless steel anti- MJ
vermin netting fixed on
both sides
Page 2 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
extinguishers c/w
MJ
demarcation line*,
labelling/tag & BOMBA
certificates
*Demarcation line– wall (Red & White – 50mm) & floor (Yellow - 100mm with 200mm spacing diagonals at 45°)
**Underside of chequered plate to be welded with 25 x 25mm mild steel angle iron stopper
Page 3 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA
completion date.
Page 4 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
5. Room sign MJ
8. Switches MJ
Page 1 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
6. Room sign MN
e) Fan (wall) MN
Page 2 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
1. Roof finishes –
MJ
0.48mm thick clip-lock metal decking
OTHERS
1. Warranty of building/equipments in
MJ
condition construction work in progress
Page 3 of 4
APDV-5005-PSI PRECOMMISSIONING, INSPECTION AND TESTING (PIAT) CHECKLIST
RESULT
DATE:
CONCLUSION:
COMMENT :
AUDITED BY
NAME : SIGNATURE :
VERIFIED BY
NAME : SIGNATURE & DATE :
Note : Project Manager is required to scan & email this page to Project Design, Asset Development Unit within 5 days of SCA