Project Logo Project Name : BURJ ALFARDAN (OFFICE TOWER) Project

No. : P-377 Location: LUSAIL


Client Project Manager/ Consultant Contractor

SEQUENCE OF OPERATION OF EMERGENCY GENERATOR


(Black out test procedure)

Loss of Kahramaa Power: Emergency generator is given a signal to start by receipt of a start
signal from the Automatic transfer switch voltage sensing or a remote device through Totalizing
panel. On receipt of the signal, all the 3 generator set automatically starts and accelerates to
the rated frequency and builds up to the rated voltage, operates to connect load. Starting from
1-5Sec all the 3 DG set will be synchronized based on the connected load. Details of Generator
stability timing and Synchronization timing along with breaker positions are shown on the
annexure 1.
Return of Kahramaa Power: When all the of the system star signals are removed, the load will
be transferred back to the Kharamaa supply, the generator set(s) operates at no load for a cool
down period. When the cooldown period has been completed, the generator set(s) shuts down.
If start signal is received during cooldown period, the system immediately re-transfers to
generator set power, as described in “Loss of Kahramaa Power”.

In Normal Mode
Supply and exhaust fan shall be working on low speed. Space temperature is provided in the
room, If the temperature inside the generator room reaches more than 60 degree (irrespective
of generator working condition) then supply & exhaust fan will run at high speed.
In Fire mode:
Fire condition outside the room in Building: Supply & exhaust fan will be working at high speed.
Fire condition inside the room: Foam system sequence will be initiated until the foam is
released * All the ventilation fan will be switch off. Generator will be switched off in fire
condition by Fire alarm. Foam panel will shut down the ventilation fan during fire mode. The
system will resume to normal condition when the maintenance team reset the foam panel
manually.
Project Logo Project Name : BURJ ALFARDAN (OFFICE TOWER) Project No. : P-377 Location: LUSAIL
Client Project Manager/ Consultant Contractor
Engine monitoring and generator
time synchronization Breakers load running hours
stability time
G1 G2 G3 G1 G2 G3 G1 G2 G3 T.Panel ATS panel
0s start start start
8s available available available done done done close close close close 1s
9s available available available done done done close close close close close
10s available available available done done done close close close close close load > 900 KVA
T available available available done done out close close open close close 630 KVA > load
available available cooling 360s done done out close close open close close
T+ 360 s available available rest done done out close close open close close
T1 available available start done done out close close open close close +8 hours
T1+8s available available available done done done close close close close close
T1+9s available Cooling 360s available done out done close open close close close
T1+369s available rest available done out done close open close close close
T2 available start available done out done close open close close close +8 hours
T2+8s available available available done done done close close close close close
T2+9s Cooling 360s available available done out done open close close close close
T2+369s rest available available out done done open close close close close
T rest available available out done done open close close close close 210 KVA > load
rest available cooling 360s out done out open close open close close
T+ 360 s rest available rest out done out open close open close close
T1 start available rest out done out open close open close close +8 hours
T1+8s available available rest done done out close close Open close close
T1+9s available Cooling 360s rest done out out close open open close close
T1+369s available rest rest done out out close open open close close
Project Logo Project Name : BURJ ALFARDAN (OFFICE TOWER) Project No. : P-377 Location: LUSAIL
Client Project Manager/ Consultant Contractor
T2 available rest start done out out close open open close close +8 hours
T2+8s available rest available done out done close open close close close
T2+9s Cooling 360s rest available out out done open open close close close
T2+369s rest rest available out out done open open close close close
T start rest available out out done close open close close close 420 KVA < load<900KVA
T+ 8 s available rest available done out done close open close close close
T1 available start available done out done close open close close close +8 hours
T1 +8 s available available available done done done close close close close close
T1 +9 s cooling 360s available available out done done open close close close close
T1+360 s rest available available out done done open close close close close
T2 start available available out done done open close close close close +8 hours
T2 +8 s available available available done done done close close close close close
T2 +9 s available available cooling 360s done done out close close open close close
T2+360 s available available rest done done out close close open close close
T3 available available available done done done close close close close close load > 900 KVA