1 AOC MEETING MINUTES


CISPDR: CAIBIN, RAUL, TITO
AOC: DIEGO, MARIO

1. delivery schedule about GEO works


No. REPORT SUBMISSION SCHEDULE
1 Informe de Mecánica de Suelos L/T SSFD-TAR CELEC comments for LAB test work of test pit
Modification about SPT, MARIO CONFIRM 10/2
Preliminary version B with complementary SPT until
approval of lab tests work for complementary test pits
from CELEC: 2020/10/05
Lab tests proposal: 2020/10/02
2 Informe de Mecánica de Suelos L/T TAR-CUY CELEC comments for LAB test work of test pit
Modification about SPT, MARIO CONFIRM 10/2
Preliminary version B with complementary SPT until
approval of lab tests work for complementary test pits
from CELEC: 2020/10/05
Lab tests proposal: 2020/10/02
3 Informe de Mecánica de Suelos L/T LOR-OSO CELEC comments for LAB test work of test pit
Modification about SPT, MARIO CONFIRM 10/2
Preliminary version B with complementary SPT until
approval of lab tests work for complementary test pits
from CELEC: 2020/10/05
Lab tests proposal: 2020/10/02
4 Informe de Mecánica de Suelos L/T SSFD-PAM CELEC comments for LAB test work of test pit
No. REPORT SUBMISSION SCHEDULE
Modification about SPT, MARIO CONFIRM 10/2
There is no SPT work, previous soil mechanical and
geotechnical reports are still valid until approval of lab
tests work for complementary test pits from CELEC.
Lab tests proposal: 2020/10/02
5 Informe de Mecánica de Suelos L/T SSFD-EPF No comment from CELEC MARIO CONFIRM 10/2
Preliminary version B, no complementary SPT work
until Secoya variant: 2020/10/09
Final version: 2020/10/16
6 Informe de Mecánica de Suelos L/T EPF-CPT No comment from CELEC, MARIO CONFIRM 10/2
Preliminary version B with complementary SPT:
2020/10/09
Final version: 2020/10/16
7 Informe con estudio de materiales y diseño de hormigones L/T SSFD-TAR MARIO CONFIRM 10/2
2020/10/06
8 Informe con estudio de materiales y diseño de hormigones L/T TAR-CUY MARIO CONFIRM 10/2
2020/10/06
9 Informe con estudio de materiales y diseño de hormigones L/T LOR-OSO MARIO CONFIRM 10/2
2020/10/06
10 Informe con estudio de materiales y diseño de hormigones L/T SSFD-PAM MARIO CONFIRM 10/2
2020/10/06
11 Informe con estudio de materiales y diseño de hormigones L/T SSFD-EPF MARIO CONFIRM 10/2
2020/10/06
12 Informe con estudio de materiales y diseño de hormigones L/T EPF-CPT MARIO CONFIRM 10/2
No. REPORT SUBMISSION SCHEDULE
2020/10/06
13 Informe con resultados de Estudios Geotécnicos de L/T SSFD-TAR Safety factor
2020/10/07
14 Informe con resultados de Estudios Geotécnicos de L/T TAR-CUY Safety factor
2020/10/07
15 Informe con resultados de Estudios Geotécnicos de L/T LOR-OSO Safety factor
2020/10/07
16 Informe con resultados de Estudios Geotécnicos de L/T SSFD-PAM N/A
17 Informe con resultados de Estudios Geotécnicos de L/T SSFD-EPF Safety factor
2020/10/19
18 Informe con resultados de Estudios Geotécnicos de L/T EPF-CPT Safety factor
2020/10/19
19 Resistivity Measurement results SSFD-TAR 2020/10/06
20 Resistivity Measurement results TAR-CUY 2020/10/06
21 Resistivity Measurement results LOR-OSO 2020/10/03
22 Resistivity Measurement results SSFD-PAM 2020/10/03
23 Resistivity Measurement results SSFD-EPF 2020/10/09
24 Resistivity Measurement results EPF-CPT 2020/10/09
25 Profile drawing of L/T SSFD-TAR 2020/10/07
26 Profile drawing of L/T TAR-CUY 2020/10/07
27 Profile drawing of L/T LOR-OSO 2020/10/07
28 Profile drawing of L/T SSFD-PAM N/A
29 Profile drawing of L/T SSFD-EPF With the corresponding Geotechnical report
30 Profile drawing of L/T EPF-CPT With the corresponding Geotechnical report
2. TEST PIT for northern bank lines
10/2 AOC provide proposal of LAB TEST working amount for test pits for SSFD-TAR, TAR-CUY, LOR-OSO and SSFD-PAM.
10/5 meeting with FERNANDO about the proposal. (RAUL, TITO, FERNANDO, MARIO)
Bryan Moya is checking the proposals (sent by AOC on 2020/10/05 in the morning) and will prepare an answer. During the meeting with Fernando Vásquez, he
mentioned that he has not received lab tests proposals.

3. safety factor for GEO reports


Safety factor for all of foundations design of LEO and HUGO
10/5 meeting with FERNANDO about the safety factor and criteria of foundation design (RAUL, TITO, LEO, FERNANDO, HUGO, MARIO)
10/2 meeting AOC and CISPDR

4. site work schedule for SECOYA


CELEC requirement and human resource for topographic profile drawing (RAUL, TITO)
10/3 9:30pm meeting about schedule (RAUL, TITO, MARIO)
AOC cannot prepare a detailed schedule until information for stakeout and geotechnical studies is received, (detailed scope, tower coordinates and geotechnical plan),
however a preliminary version with general information has been prepared by CISPDR.