MTHL Project Package 1 22-06-2020

Status of OSD Related Submissions

Submission Days
No. Contractor Letter No. Subject Note
Date passed
4 2629 MTHL/P1/LT-IHI/GC/LT/CON-0002629/2020 Submission of Method Statement for Paint Coating of OSD Girder Bridges at Fabrication Shop Superstructure 2020 Mar 19 95
Welding Procedure Qualification Record (IIA) for Fabrication of OSD Girder Bridges Superstructure (3rd
5 2630 MTHL/P1/LT-IHI/GC/LT/QAC-0002630/2020 2020 Mar 19 95
Submission)
6 2631 MTHL/P1/LT-IHI/GC/LT/QAC-0002631/2020 Submission of Colour Samples of Paint Coating System for OSD Girder Bridges-Superstructure 2020 Mar 19 95
Welding Procedure Qualification Record (TCT) for Fabrication of OSD Girder Bridges-Superstructure (2 nd
8 2654 MTHL/P1/LT-IHI/GC/LT/QAC-0002654/2020 2020 Mar 31 83
Submission)
Welding Procedure Qualification Record (SMSS) for Fabrication of OSD Girder Bridges-Superstructure (1st
9 2656 MTHL/P1/LT-IHI/GC/LT/QAC-0002656/2020 2020 Mar 31 83
Submission)
Welding Procedure Qualification Record (SMSS) for Fabrication of OSD Girder Bridges-Superstructure (2nd
10 2847 MTHL/P1/LT-IHI/GC/LT/QAC-0002847/2020 2020 May 11 42
Submission)
Welding Procedure Qualification Record (SMSS) for Fabrication of OSD Girder Bridges-Superstructure (3rd
11 2978 MTHL/P1/LT-IHI/GC/LT/QAC-0002978/2020 2020 Jun 06 16
Submission)
Submission of latest documents of Steel Manufacturer -M/s. China Steel Corporation, Taiwan for fabrication of
12 2675 MTHL/P1/LT-IHI/GC/LT/QAC-0002675/2020 2020 Apr 06 77
OSD Steel Superstructure (Re-submission)
Submission of Inspection Test Plan (ITP) and Quality Plan for Manufacturing and Transportation of Bearings
13 2682 MTHL/P1/LT-IHI/GC/LT/QAC-0002682/2020 2020 Apr 07 76
for OSD Bridges -Superstructure
18 2984 MTHL/P1/LT-IHI/GC/LT/QAC-0002984/2020 Submission of Inspection and Test Plan for Damper System to Orthotropic Steel Bridges -Superstructure 2020 Jun 06 16
Submission of additional QA documents of Paint Manufacturer(s) for fabrication of OSD for Steel Bridge-
19 2848 MTHL/P1/LT-IHI/GC/LT/QAC-0002848/2020 2020 May 11 42
Superstructure
Submission of Material Inspection Record of Steel Plates Lot 1 (MG M1-1) for Fabrication of OSD Girder
20 2071 MTHL/P1/LT-IHI/GC/LT/QAC-0002071/2019 2019 Nov 20 215
Bridge (P1-OS01-SG)-Superstructure
Submission of Material Inspection Reocrd of Steel Plates Lot 3 (MG M 1-3) for Fabrication of OSD Girder
21 2194 MTHL/P1/LT-IHI/GC/LT/QAC-0002194/2019 2019 Dec 20 185
Bridge (P1-OS01-SG) Superstructure
Submission of Material Inspection Record of steel Plates Lot 2 (MG M1-2) for Fabrication of OSD Girder
22 2195 MTHL/P1/LT-IHI/GC/LT/QAC-0002195/2019 2019 Dec 20 185
Bridge (P1-OS01-SG) Superstructure
Submission of Material Inspection Record of steel Plates Lot 4 (MG M1-4) for Fabrication of OSD Girder
23 2429 MTHL/P1/LT-IHI/GC/LT/QAC-0002429/2020 2020 Feb 13 130
Bridge (P1-OS01-SG) Superstructure
Submission of Material Inspection Record of Steel Plates Lot 4 (MG M1-5) for Fabrication of OSD Girder
24 2430 MTHL/P1/LT-IHI/GC/LT/QAC-0002430/2020 2020 Feb 13 130
Bridge (P1-OS01-SG) Superstructure
Submission of Material Inspection Record of steel Plates Lot 5 (MG M1-5) for Fabrication of OSD Girder
25 2493 MTHL/P1/LT-IHI/GC/LT/QAC-0002493/2020 2020 Feb 27 116
Brider (P1-OS01-NG) - Superstructure
Submission of Material Inspection Record of Steel Plates Lot 1 (MG M2-1) for Fabrication of OSD Girder
26 2621 MTHL/P1/LT-IHI/GC/LT/QAC-0002621/2020 2020 Mar 17 97
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 1 (MG M4-1) for Fabrication of OSD Girder
27 2667 MTHL/P1/LT-IHI/GC/LT/QAC-0002667/2020 2020 Apr 03 80
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of CHS Steel Pipes Lot 1 (CHS M4-1) for Fabrication of OSD Girder
28 2668 MTHL/P1/LT-IHI/GC/LT/QAC-0002668/2020 2020 Apr 03 80
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 2 (MG M2-2) for Fabrication of OSD Girder
29 2692 MTHL/P1/LT-IHI/GC/LT/QAC-0002692/2020 2020 Apr 08 75
Bridge (P1-OS02-NG)-Superstructure
Submission of Inspection Records for Fabrication and Trial Assembly of OSD Girder Bridge P1-OS01-NG Lot
30 2713 MTHL/P1/LT-IHI/GC/LT/QAC-0002713/2020 2020 Apr 10 73
2 (Segment 7~11) - Superstructure
Submission of Material Inspection Record of Paint (1st time delivery) at Fabrication shop for OSD Girder
31 2715 MTHL/P1/LT-IHI/GC/LT/QAC-0002715/2021 2020 Apr 10 73
Bridges (P1-OS01-NG / P1-OS04-NG / P1-OS02-SG)
Submission of Material Inspection Record of Steel Plates Lot 1 (MG M4-1) for Fabrication of OSD Girder Letter no, 2667 Reiissued by
32 2732 MTHL/P1/LT-IHI/GC/LT/QAC-0002732/2020 2020 Apr 16 67
Bridge (P1-OS04-NG)-Superstructure mistake
Submission of Material Inspection Record of CHS Steel Pipes Lot 1 (CHS M4-1) for Fabrication of OSD Girder Letter no, 2668 Reiissued by
33 2733 MTHL/P1/LT-IHI/GC/LT/QAC-0002733/2020 2020 Apr 16 67
Bridge (P1-OS04-NG)-Superstructure mistake
Submission of Material Inspection Record of Steel Plates U-rib Lot 1 (Urib M2-1) for Fabrication of OSD Girder
34 2734 MTHL/P1/LT-IHI/GC/LT/QAC-0002734/2020 2020 Apr 16 67
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 1 (MG M4-1) for Fabrication of OSD Girder
35 2735 MTHL/P1/LT-IHI/GC/LT/QAC-0002735/2020 2020 Apr 15 68
Bridge (P1-OS04-SG)-Superstructure
Submission of Material Inspection Record of CHS Steel Pipes Lot 1 (CHS M4-1) for Fabrication of OSD Girder
36 2736 MTHL/P1/LT-IHI/GC/LT/QAC-0002736/2020 2020 Apr 15 68
Bridge (P1-OS04-SG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 2 (MG M4-2) for Fabrication of OSD Girder
37 2749 MTHL/P1/LT-IHI/GC/LT/QAC-0002749/2020 2020 Apr 21 62
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates U-rib Lot 2 (Urib M2-2) for Fabrication of OSD Girder
38 2781 MTHL/P1/LT-IHI/GC/LT/QAC-0002781/2020 2020 Apr 28 55
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates U-rib Lot 3 (Urib M2-3) for Fabrication of OSD Girder
39 2782 MTHL/P1/LT-IHI/GC/LT/QAC-0002782/2020 2020 Apr 28 55
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of CHS Steel Pipes Lot 2 (CHS M2-2) for Fabrication of OSD Girder
40 2783 MTHL/P1/LT-IHI/GC/LT/QAC-0002783/2020 2020 Apr 28 55
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 3 (MG M2-3) for Fabrication of OSD Girder
41 2784 MTHL/P1/LT-IHI/GC/LT/QAC-0002784/2020 2020 Apr 28 55
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of CHS Steel Pipes Lot 1 (CHS M2-1) for Fabrication of OSD Girder
42 2785 MTHL/P1/LT-IHI/GC/LT/QAC-0002785/2020 2020 Apr 28 55
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates U-rib Lot 1 (Urib M4-1) for Fabrication of OSD Girder
43 2800 MTHL/P1/LT-IHI/GC/LT/QAC-0002800/2020 2020 Apr 30 53
Bridge (P1-OS04-NG)-Superstructure
Submission of Inspection Records for Fabrication and Trial Assembly of OSD Girder Bridge P1-OS01-SG
44 2855 MTHL/P1/LT-IHI/GC/LT/QAC-0002855/2020 2020 May 09 44
(South Girder) Lot 1 (Segment 1~6) - Superstructure
Submission of Inspection Records for Fabrication and Trial Assembly of OSD Girder Bridge P1-OS01-NG
45 2856 MTHL/P1/LT-IHI/GC/LT/QAC-0002856/2020 2020 May 09 44
(North Girder) Lot 3 (Segment 23~28) - Superstructure
Submission of Material Inspection Record of Steel Plates U-rib Lot 2 (Urib M4-2) for Fabrication of OSD Girder
46 2861 MTHL/P1/LT-IHI/GC/LT/QAC-0002861/2020 2020 May 09 44
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates U-rib Lot 3 (Urib M4-3) for Fabrication of OSD Girder
47 2893 MTHL/P1/LT-IHI/GC/LT/QAC-0002893/2020 2020 May 20 33
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 3 (MG M4-3) for Fabrication of OSD Girder
48 2894 MTHL/P1/LT-IHI/GC/LT/QAC-0002894/2020 2020 May 20 33
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Paint (1st & 2nd time delivery) at Fabrication shop for OSD
49 2915 MTHL/P1/LT-IHI/GC/LT/QAC-0002915/2020 2020 May 25 28
Girder Bridges (P1-OS01-SG / P1-OS04-SG / P1-OS03-SG)
Submission of Material Inspection Record of Steel Plates Lot 2 (MG M4-2) for Fabrication of OSD Girder
50 2916 MTHL/P1/LT-IHI/GC/LT/QAC-0002916/2020 2020 May 25 28
Bridge (P1-OS04-SG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 5 (MG M4-5) for Fabrication of OSD Girder
51 2966 MTHL/P1/LT-IHI/GC/LT/QAC-0002966/2020 2020 Jun 05 17
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 6 (MG M4-6) for Fabrication of OSD Girder
52 2967 MTHL/P1/LT-IHI/GC/LT/QAC-0002967/2020 2020 Jun 05 17
Bridge (P1-OS04-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 3 (MG M4-3) for Fabrication of OSD Girder
53 3052 MTHL/P1/LT-IHI/GC/LT/QAC-0003052/2020 2020 Jun 18 4
Bridge (P1-OS04-SG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 4 (MG M2-4) for Fabrication of OSD Girder
54 3051 MTHL/P1/LT-IHI/GC/LT/QAC-0003051/2020 2020 Jun 18 4
Bridge (P1-OS02-NG)-Superstructure
Submission of Material Inspection Record of Steel Plates Lot 5 (MG M2-5) for Fabrication of OSD Girder
55 3050 MTHL/P1/LT-IHI/GC/LT/QAC-0003050/2020 2020 Jun 18 4
Bridge (P1-OS02-NG)-Superstructure
Submission of Inspection Records for Fabrication and Trial Assembly of OSD Girder Bridge P1-OS01-NG
56 3054 MTHL/P1/LT-IHI/GC/LT/QAC-0003054/2020 2020 Jun 18 4
(North Girder) Lot 4 (Segment 18~23) - Superstructure