You are on page 1of 1

COST ESTIMATE FORM

Prepared by Vetted by Approved by

Facility PT Natgas Indonesia Date : March 10, 2020 Mohamad Syahmi Ken Tan Simon Sim

Project : As-Built 3D Modelling - Facilities, Equipments, Electrical and Pipelines


Modelling Reference :

No Item Material Qty Unit Unit Amount Remarks


Price (IDR) SGD
MATERIAL COST

1 Piping Modelling
Create Piping Specification 32 Sheet P&ID IDR 470,000.00 $ 1,457.69
Create Piping Catalog and Accessories 32 Sheet P&ID IDR 390,000.00 $ 1,209.57
Route Piping 32 Sheet P&ID IDR 750,000.00 $ 2,326.10
Equipment Modelling 32 Sheet P&ID IDR 450,000.00 $ 1,395.66

2 Civil Modelling 1 Lump Sum IDR 5,000,000.00 $ 484.60

3 Steel Structure Modelling 1 Lump Sum IDR 5,000,000.00 $ 484.60

4 Electrical Modelling
Main cable Tray 1 Lump Sum IDR 3,000,000.00 $ 290.76
Panel Box 1 Lump Sum IDR 1,000,000.00 $ 96.92
Lighting Poles 1 Lump Sum IDR 1,000,000.00 $ 96.92

5 Hydrant Piping Modelling 1 Lump Sum IDR 4,000,000.00 $ 387.68


Sub-Total $ 8,230.50

Total Cost: $ 8,230.50

Remarks: Reports/3D Modelling to be summitted are Cardworx (Cardworx 2017) Model that can be edited, and viewer Navisworx

ENG-FM-17-01

You might also like