You are on page 1of 107

ENI - IRAQ

ZUBAIR OIL FIELD DEVELOPMENT PROJECT

DOCUMENT LIST
(Existing DGS Modifications - WO 0 General)

B.S.
EX-CO 07 07/15/2014 Final Issue T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 06 05/18/2014 Final Issue T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 05 04/28/2014 Issued for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 04 04/09/2014 Issued for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 03 01/11/2014 Issued for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 02 08/12/2013 Issued for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 01 25/11/2013 Issued for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-CO 00 16/11/2013 Issued for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-DE 05 09/28/2013 Re-issue for Approval T.M. Kim K.U. Son J.H. Lee A.Quaranta
Chung
B.S.
EX-DE 04 03/04/2013 Re-issue for Approval S.Y. Kim C.Y. Seo J.H. Lee Chung A.Quaranta
B.S.
EX-DE 03 01/10/2013 Re-issue for Approval S.Y. Kim C.Y. Seo J.H. Lee Chung A.Quaranta
B.S.
EX-DE 02 11/08/2012 Re-issue for Approval Negusanti V J.H. Lee J.H. Lee Chung A.Quaranta
B.S.
EX-DE 01 09/28/2012 Re-issue for Approval Negusanti V J.H. Lee J.H. Lee Chung A.Quaranta
B.S.
EX-DE 00 09/19/2012 Issue for Approval Negusanti V J.H. Lee J.H. Lee Chung A.Quaranta
Validity Rev.
Status Number Prepared Checked Approved Contractor Company
Date Description
by by by Approval Approval
Revision index
Company logo and business name Project name Company Identification

ZUBAIR OIL FIELD 00250600DGED0002M


eni iraq b.v. DEVELOPMENT
Job N.

Contractor logo and business name Contractor Identification

P12020G0002M
STX Heavy Industries Co. Ltd.
Contract N.
Vendor logo and business name Vendor Identification

Order N.

Facility Name Location Scale Sheet of Sheets


ZUBAIR FIELD - GENERAL ONSHORE 1 of 4
Document Title Supersedes N.

DOCUMENT LIST Superseded by N.


(Existing DGS Modifications - WO 0 General) Plant area Plant unit

File N° 00250600DGED0002M_EXCO07_04.xls

This document is property of eni iraq b.v.


It shall neither be shown to Third Parties, nor used for purposes other than those for which it has been sent.
Logo and business name of Company Document Contractor Document Revision Index
document Owner Identification Identification Validity Sheet of sheets
Rev. N.
Staus
00250600DGED0002M P12020G0002M EX-CO 07 2 of 4

REVISION HISTORY

Rev. Date No. of


sheets Description

EX-DE 00 09/19/2012 3 Issue for Approval


EX-DE 01 09/28/2012 3 Re-issue for Approval
EX-DE 02 11/08/2012 5 Re-issue for Approval
EX-DE 03 01/10/2013 7 Re-issue for Approval
EX-DE 04 03/04/2013 5 Re-issue for Approval
EX-DE 05 09/28/2013 4 Re-issue for Approval
EX-CO 00 16/11/2013 4 Issued for Approval
EX-CO 01 25/11/2013 4 Issued for Approval
EX-CO 02 08/12/2013 4 Issued for Approval
EX-CO 03 01/11/2014 4 Issued for Approval
EX-CO 04 04/09/2014 4 Issued for Approval
EX-CO 05 04/28/2014 4 Issued for Approval
EX-CO 06 04/28/2014 4 Final Issue
EX-CO 07 07/15/2014 4 Final Issue
COMPANY DOCUMENT ID OWNER DOCUMENT ID Rev. Index Sheet of sheets
LOGO AND BUSINESS NAME OF DOCUMENT OWNER
Validity status Rev. No.
00250600DGED0002M P12020G0002M 3 of 4
EX-CO 07

ENI E&P DOCUMENT ID REVISION INDEX

FACILITY

SUBFACILITY

PHASE

DISCIPLINE

TYPE & SUBTYPE

SEQUENTIAL NUMNER

VALIDITY STATUS

REVISION NUMBER
ENI E&P
ID DOCUMENT TITLE CONTRACT DISCIPLINE CONTRACTOR DOCUMENT ID DOCUMENT TITLE FUNTIONAL UNIT ISSUE DATE DOCUMENT SIZE N° SHEET NOTES FROM FEED
CODE
(SEE 27605)

1 CA11 Civil and Architectural 002506 00 D A DQ 0035M P12020A0035M SYMBOLS - REFERENCE AND MISCELLANEOUS (ADDENDUM) EX-CO 01 210 18-10-2012 A4
2 CA11 Civil and Architectural 002506 00 D A DQ 0033M P12020A0033M ANCHOR BOLTS (ADDENDUM) EX-CO 00 210 18-10-2012 A1
3 CA11 Civil and Architectural 002506 00 D A DQ 0034M P12020A0034M GENERAL STEEL CONSTRUCTION NOTES (ADDENDUM) EX-CO 00 210 18-10-2012 A1
4 CA11 Civil and Architectural 002506 00 D A DQ 0032M P12020A0032M TYPICAL DRAWING FOR ROADS AND PAVING AND MISCELLANEOUS DETAILS (ADDENDUM) EX-CO 00 210 18-10-2012 A3
5 CA03 Civil and Architectural 002506 00 D A ST 0054M P12020A0054M DESIGN LOADS AND LOADS COMBINATION (ADDENDUM) EX-CO 00 210 18-10-2012 A1
6 CB06 Civil and Architectural 002506 00 D A SG 0049M P12020A0049M GENERAL SPECIFICATION FOR ERECTION OF STEEL STRUCTURES (ADDENDUM) EX-CO 00 210 18-10-2012 A4
7 CB06 Civil and Architectural 002506 00 D A SG 0053M P12020A0053M GENERAL SPECIFICATION FOR CIVIL AND STRUCTURAL DESIGN CRITERIA (ADDENDUM) EX-CO 00 210 18-10-2012 A4
8 CA11 Civil and Architectural 002506 00 D A DB 0060M P12020A0060M GENERAL CONCRETE NOTES (ADDENDUM) EX-CO 00 210 18-10-2012 A4
9 CA03 Civil and Architectural 002506 00 D A ST 0052M P12020A0052M REINFORCED CONCRETE AND FOUNDATIONS DESIGN CRITERIA (ADDENDUM) EX-CO 00 210 18-10-2012 A1
10 CB06 Civil and Architectural 002506 00 D A ST 0055M P12020A0055M STEEL STRUCTURE DESIGN CRITERIA (ADDENDUM) EX-CO 00 210 18-10-2012 A4
11 CA11 Civil and Architectural 002506 00 D A DQ 0030M P12020A0030M TYPICAL DRAWING FOR CABLE TRENCH AND DUCT BANK EX-DE 00 210 11-02-2013 A4
11 CA11 Civil and Architectural 002506 00 D A DQ 0030M P12020A0030M TYPICAL DRAWING FOR CABLE TRENCH AND DUCT BANK EX-CO 00 210 11-02-2013 A4
12 CA11 Civil and Architectural 002506 00 D A DQ 0058M P12020A0058M TYPICAL DRAWING FOR EQUIPMENT FOUNDATION (ADDENDUM) EX-CO 00 210 21-11-2012 A1
13 CA11 Civil and Architectural 002506 00 D A DQ 0056M P12020A0056M TYPICAL DRAWING FOR FENCING AND GATES (ADDENDUM) EX-CO 01 210 22-11-2012 A1
14 CA11 Civil and Architectural 002506 00 D A DQ 0057M P12020A0057M TYPICAL DRAWING FOR SHELTERS/SUNSHADES (ADDENDUM) EX-CO 01 210 21-11-2012 A1
15 CA09 Civil and Architectural 002506 00 D A SS 5001M P12020A5001M GENERAL SPECIFICATION FOR GEOTECHNICAL SURVEY (ADDENDUM) EX-CO 00 210 14-11-2012 A1
16 CA03 Civil and Architectural 002506 00 D A SG 0042M P12020A0042M GENERAL SPECIFICATION FOR CONCRETE WORKS (ADDENDUM) EX-CO 00 210 22-10-2012 A4
17 CA03 Civil and Architectural 002506 00 D A SG 0051M P12020A0051M GENERAL SPECIFICATION FOR DEMOLITION WORKS (ADDENDUM) EX-CO 00 210 21-11-2012 A4
18 CA03 Civil and Architectural 002506 00 D A SG 0045M P12020A0045M GENERAL SPECIFICATION FOR EMBEDMENTS (ADDENDUM) EX-CO 00 210 22-11-2012 A4
19 CA03 Civil and Architectural 002506 00 D A SG 0046M P12020A0046M GENERAL SPECIFICATION FOR GROUTING AND LEVELLING (ADDENDUM) EX-CO 00 210 22-11-2012 A4
20 CA03 Civil and Architectural 002506 00 D A SG 0043M P12020A0043M GENERAL SPECIFICATION FOR ROAD WORKS (ADDENDUM) EX-CO 00 210 22-10-2012 A4
21 CA03 Civil and Architectural 002506 00 D A SG 0041M P12020A0041M GENERAL SPECIFICATION FOR SITE PREPARATION/EARTHWORKS (ADDENDUM) EX-CO 02 210 14-01-2013 A4
22 CB06 Civil and Architectural 002506 00 D A SG 0044M P12020A0044M GENERAL SPECIFICATION FOR STEEL WORKS (ADDENDUM) EX-CO 01 210 21-11-2012 A4
25 CA03 Civil and Architectural 002506 00 D A SG 0050M P12020A0050M CIVIL AND STRUCTURAL BASIS OF DESIGN (ADDENDUM) EX-CO 00 210 18-10-2012 A4
26 CA03 Civil and Architectural 002506 00 D A SG 0048M P12020A0048M GENERAL SPECIFICATION FOR GRATINGS (ADDENDUM) EX-CO 01 210 21-11-2012 A4
27 CA03 Civil and Architectural 002506 00 D A SG 0047M P12020A0047M GENERAL SPECIFICATION FOR SEWERS AND DRAINS (ADDENDUM) EX-CO 00 210 21-11-2012 A4
28 CA11 Civil and Architectural 002506 00 D A DQ 0039M P12020A0039M GRATING CLAMPS (ADDENDUM) EX-CO 01 210 22-11-2012 A4
29 CA11 Civil and Architectural 002506 00 D A DQ 0038M P12020A0038M HANDRAILS (ADDENDUM) EX-CO 01 210 22-11-2012 A1
30 CA04 Civil and Architectural 002506 00 D A GC 0061M P12020A0061M REQUIRED TECHNICAL DOCUMENTATION FOR SKIDDED CABINS (DDS) EX-CO 01 210 17-12-2012 A1
31 CA11 Civil and Architectural 002506 00 D A DQ 0040M P12020A0040M SAFETY CLOSURE FOR LADDERS (ADDENDUM) EX-CO 01 210 22-11-2012 A4
32 CA11 Civil and Architectural 002506 00 D A DQ 0037M P12020A0037M STAIRS (ADDENDUM) EX-CO 01 210 22-11-2012 A1
33 CA11 Civil and Architectural 002506 00 D A DQ 0059M P12020A0059M TYPICAL DRAWING FOR SWALES CUT (ADDENDUM) EX-CO 00 210 21-11-2012 A1
34 CA11 Civil and Architectural 002506 00 D A DQ 0036M P12020A0036M VERTICAL LADDERS (ADDENDUM) EX-CO 01 210 22-11-2012 A1
37 CA09 Civil and Architectural 002506 00 D A RS 5011M P12020A5011M SITE SURVEY AND SOIL INVESTIGATION REPORT EX-DE 00 210 08-02-2013 A4
37 CA09 Civil and Architectural 002506 00 D A RS 5011M P12020A5011M SITE SURVEY AND SOIL INVESTIGATION REPORT EX-CO 00 210 08-02-2013 A4
38 CA15 Civil and Architectural 002506 00 D A RS 5012M P12020A5012M STUDY ON PILE BEARING CAPACITY AND FOUNDATION TYPE ANALYSIS EX-DE 00 210 08-02-2013 A4
38 CA15 Civil and Architectural 002506 00 D A RS 5012M P12020A5012M STUDY ON PILE BEARING CAPACITY AND FOUNDATION TYPE ANALYSIS EX-CO 01 210 08-02-2013 A4
39 K52 Electrical 002506 00 D E GB 0036M P12020E0036M INSPECTION DATASHEET FOR DIESEL GENERATOR EX-CO 00 210 26-11-2012 A4
40 K26 Electrical 002506 00 D E ST 0089M P12020E0089M TECHNICAL SPECIFICATION FOR ASYNCHRONOUS MOTORS (ADDENDUM) EX-CO 00 210 04-02-2013 A4
41 K17 Electrical 002506 00 D E ST 0025M P12020E0025M TECHNICAL SPECIFICATION FOR DIESEL GENERATOR EX-DE 00 210 12-10-2012 A4
41 K17 Electrical 002506 00 D E ST 0025M P12020E0025M TECHNICAL SPECIFICATION FOR DIESEL GENERATOR EX-CO 00 210 12-10-2012 A4
42 K27 Electrical 002506 00 D E ST 0091M P12020E0091M TECHNICAL SPECIFICATION FOR ELECTRICAL BULK AND EARTHING MATERIAL (ADDENDUM) EX-CO 03 210 20-02-2013 A4
43 K19 Electrical 002506 00 D E ST 0088M P12020E0088M TECHNICAL SPECIFICATION FOR ELECTRICAL SYSTEM IN PACKAGE UNIT (ADDENDUM) EX-CO 00 210 23-02-2013 A4
44 K50 Electrical 002506 03 D E SF 5358M P12020E5358M MATERIAL REQUISITION FOR DIESEL GENERATOR EX-CO 00 210 26/11/2012 A4
45 K52 Electrical 002506 00 D E GB 0038M P12020E0038M INSPECTION DATASHEET FOR 230V AC UPS EX-CO 00 210 26-11-2012 A4
46 K53 Electrical 002506 00 D E GC 0061M P12020E0061M REQUIRED DOCUMENT DATASHEET FOR 230V AC UPS EX-CO 00 210 26-11-2012 A4
47 K19 Electrical 002506 00 D E ST 0007M P12020E0007M TECHNICAL SPECIFICATION FOR 230V AC UPS EX-DE 00 210 04-02-2013 A4
47 K19 Electrical 002506 00 D E ST 0007M P12020E0007M TECHNICAL SPECIFICATION FOR 230V AC UPS EX-CO 00 210 04-02-2013 A4
48 K52 Electrical 002506 00 D E GB 0040M P12020E0040M INSPECTION DATA SHEET FOR LIGHTING PANEL EX-CO 00 210 26-11-2012 A4
49 K52 Electrical 002506 00 D E GB 0039M P12020E0039M INSPECTION DATASHEET FOR POWER AND CONTROL CABLE EX-CO 00 210 26-11-2012 A4
50 K53 Electrical 002506 00 D E GC 0063M P12020E0063M REQUIRED DOCUMENT DATA SHEET FOR LIGHTING PANEL EX-CO 00 210 26-11-2012 A4
51 K53 Electrical 002506 00 D E GC 0059M P12020E0059M REQUIRED DOCUMENT DATASHEET FOR DIESEL GENERATOR EX-CO 00 210 26-11-2012 A4
52 K53 Electrical 002506 00 D E GC 0062M P12020E0062M REQUIRED DOCUMENT DATASHEET FOR POWER AND CONTROL CABLE EX-CO 00 210 26-11-2012 A4
53 K32 Electrical 002506 00 D E ST 0028M P12020E0028M TECHNICAL SPECIFICATION FOR LIGHTING PANEL EX-DE 00 210 04-02-2013 A4
53 K32 Electrical 002506 00 D E ST 0028M P12020E0028M TECHNICAL SPECIFICATION FOR LIGHTING PANEL EX-CO 00 210 04-02-2013 A4
54 K15 Electrical 002506 00 D E ST 0090M P12020E0090M TECHNICAL SPECIFICATION FOR POWER AND CONTROL CABLE (ADDENDUM) EX-CO 00 210 20-02-2013 A4
55 K52 Electrical 002506 00 D E GB 0037M P12020E0037M INSPECTION DATASHEET FOR LOW VOLTAGE SWITCHGEAR EX-CO 00 210 26-11-2012 A4
56 K53 Electrical 002506 00 D E GC 0060M P12020E0060M REQUIRED DOCUMENT DATASHEET FOR LOW VOLTAGE SWITCHGEAR EX-CO 00 210 26-11-2012 A4
57 K12 Electrical 002506 00 D E ST 0087M P12020E0087M TECHNICAL SPECIFICATION FOR LOW VOLTAGE SWITCHGEAR (ADDENDUM) EX-CO 00 210 04-02-2013 A4
58 K52 Electrical 002506 00 D E GB 0035M P12020E0035M INSPECTION DATASHEET FOR POWER TRANSFORMER EX-CO 00 210 26-11-2012 A4
59 K53 Electrical 002506 00 D E GC 0058M P12020E0058M REQUIRED DOCUMENT DATASHEET FOR POWER TRANSFORMER EX-CO 00 210 26-11-2012 A4
60 K12 Electrical 002506 00 D E ST 0086M P12020E0086M TECHNICAL SPECIFICATION FOR POWER TRANSFORMER (ADDENDUM) EX-CO 00 210 04-02-2013 A4
61 K52 Electrical 002506 00 D E GB 0034M P12020E0034M INSPECTION DATASHEET FOR MEDIUM VOLTAGE SWITCHGEAR EX-CO 00 210 26-11-2012 A4
62 K52 Electrical 002506 00 D E GB 0083M P12020E0083M INSPECTION DATASHEET FOR 110V DC BATTERY CHARGER EX-CO 00 210 26-11-2012 A4
63 K53 Electrical 002506 00 D E GC 0057M P12020E0057M REQUIRED DOCUMENT DATASHEET FOR MEDIUM VOLTAGE SWITCHGEAR EX-CO 00 210 26-11-2012 A4
64 K53 Electrical 002506 00 D E GC 0084M P12020E0084M REQUIRED DOCUMENT DATASHEET FOR 110V DC BATTERY CHARGER EX-CO 00 210 26-11-2012 A4
65 K19 Electrical 002506 00 D E ST 0008M P12020E0008M TECHNICAL SPECIFICATION FOR 110 VDC BATTERY CHARGER EX-DE 210 27/03/2013 A4
65 K19 Electrical 002506 00 D E ST 0008M P12020E0008M TECHNICAL SPECIFICATION FOR 110 VDC BATTERY CHARGER EX-CO 210 27/03/2013 A4
66 K50 Electrical 002506 00 D E SF 5353M P12020E5353M MATERIAL REQUISITION FOR 230V AC UPS EX-CO 00 210 29-03-2013 A4
67 K50 Electrical 002506 03 D E EP 5350M P12020E5350M MATERIAL REQUISITION FOR 6.6KV SWITCHGEAR EX-CO 00 210 29-03-2013 A4
68 K50 Electrical 002506 03 D E SF 5357M P12020E5357M MATERIAL REQUISITION FOR BULK MATERIAL EX-CO 210 22-01-2013 A4
69 K50 Electrical 002506 00 D E SF 5355M P12020E5355M MATERIAL REQUISITION FOR LIGHTING PANEL EX-CO 00 210 20-04-2013 A4
70 K50 Electrical 002506 00 D E SF 5356M P12020E5356M MATERIAL REQUISITION FOR LIGHTING SYSTEM MATERIAL EX-CO 00 210 20-04-2013 A4
71 K50 Electrical 002506 00 D E SF 5352M P12020E5352M MATERIAL REQUISITION FOR LOW VOLTAGE SWITCHGEAR EX-CO 00 210 20-04-2013 A4
72 K50 Electrical 002506 00 D E SF 5354M P12020E5354M MATERIAL REQUISITION FOR POWER AND CONTROL CABLE EX-CO 00 210 20-04-2013 A4
73 K50 Electrical 002506 00 D E SF 5351M P12020E5351M MATERIAL REQUISITION FOR POWER TRANSFORMER EX-CO 00 210 20-04-2013 A4
74 K12 Electrical 002506 00 D E ST 0006M P12020E0006M TECHNICAL SPECIFICATION FOR MEDIUM VOLTAGE SWITCHGEAR EX-DE 00 210 20-12-2012 A4
74 K12 Electrical 002506 00 D E ST 0006M P12020E0006M TECHNICAL SPECIFICATION FOR MEDIUM VOLTAGE SWITCHGEAR EX-CO 01 210 20-12-2012 A4
75 K52 Electrical 002506 00 D E GB 0047M P12020E0047M INSPECTION DATA SHEET FOR DC UPS (ADDENDUM) EX-CO 00 210 26-11-2012 A4
76 K53 Electrical 002506 00 D E GC 0048M P12020E0048M REQUIRED DOCUMENTATION DATA SHEET FOR DC UPS (ADDENDUM) EX-CO 00 210 26-11-2012 A4
77 AB05 Interdisciplinary and Miscellaneous 002506 00 D G PG 0001M P12020G0001M DOCUMENT AND ITEM MANAGEMENT PROCEDURE EX-DE 210 20-04-2013 A4
77 AB05 Interdisciplinary and Miscellaneous 002506 00 D G PG 0001M P12020G0001M DOCUMENT AND ITEM MANAGEMENT PROCEDURE EX-CO 00 210 20-04-2013 A4
78 N/A Interdisciplinary and Miscellaneous 002506 00 D G PT 0007M P12020G0007M ENGINEERING EXECUTION PLAN EX-DE 01 210 05-11-2012 A4
78 N/A Interdisciplinary and Miscellaneous 002506 00 D G PT 0007M P12020G0007M ENGINEERING EXECUTION PLAN EX-CO 00 210 05-11-2012 A4
79 AB06 Interdisciplinary and Miscellaneous 002506 00 D G PL 0014M P12020G0014M FOUR (4) WEEKS LOOK AHEAD SCHEDULE EX-DE 210 21-12-2012 A4
79 AB06 Interdisciplinary and Miscellaneous 002506 00 D G PL 0014M P12020G0014M FOUR (4) WEEKS LOOK AHEAD SCHEDULE EX-CO 210 21-12-2012 A4
80 AB06 Interdisciplinary and Miscellaneous 002506 00 D G PL 0013M P12020G0013M LEVEL 2 PROJECT SCHEDULE FOR WORK ORDER 1,2,3 EX-DE 210 26-10-2012 A4
80 AB06 Interdisciplinary and Miscellaneous 002506 00 D G PL 0013M P12020G0013M LEVEL 2 PROJECT SCHEDULE FOR WORK ORDER 1,2,3 EX-CO 210 26-10-2012 A4
81 AA11 Logistic 002506 00 D H PF 0008M P12020H0008M PROCUREMENT EXECUTION PLAN EX-DE 210 15-10-2012 A4
81 AA11 Logistic 002506 00 D H PF 0008M P12020H0008M PROCUREMENT EXECUTION PLAN EX-CO 00 210 15-10-2012 A4
82 AA11 Logistic 002506 00 D H RV 1001M P12020H1001M PROCUREMT STATUS REPORT EX-DE 210 15-10-2012 A4
82 AA11 Logistic 002506 00 D H RV 1001M P12020H1001M PROCUREMT STATUS REPORT EX-CO 210 15-10-2012 A4
83 N/A Interdisciplinary and Miscellaneous 002506 00 D G RG 0032M P12020G0032M PROGRESS S-CURVE EX-DE 210 15-10-2012 A4
83 N/A Interdisciplinary and Miscellaneous 002506 00 D G RG 0032M P12020G0032M PROGRESS S-CURVE EX-CO 210 15-10-2012 A4
84 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0002M P12020G0002M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 0 - GENERAL) EX-DE 04 210 22-01-2013 A4
84 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0002M P12020G0002M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 0 - GENERAL) EX-CO 05 210 22-01-2013 A4
85 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0003M P12020G0003M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 1 - DRY TO WET CONVERSION OF EXISTING TRAINS) EX-DE 04 210 22-01-2013 A4
85 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0003M P12020G0003M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 1 - DRY TO WET CONVERSION OF EXISTING TRAINS) EX-CO 05 210 22-01-2013 A4
86 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0004M P12020G0004M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 2 - WATER INJECTION REFURBISHMENT) EX-DE 04 210 22-01-2013 A4
86 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0004M P12020G0004M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 2 - WATER INJECTION REFURBISHMENT) EX-CO 05 210 22-01-2013 A4
87 N/A Interdisciplinary and Miscellaneous 002506 00 D G PP 0019M P12020G0019M PROJECT ORGANIZATION CHART EX-DE 210 20-04-2013 A4
87 N/A Interdisciplinary and Miscellaneous 002506 00 D G PP 0019M P12020G0019M PROJECT ORGANIZATION CHART EX-CO 210 20-04-2013 A4
88 N/A Interdisciplinary and Miscellaneous 002506 00 D G RG 0031M P12020G0031M VALUE OF WORK DONE (VOWD) EX-DE 210 28-09-2012 A4
88 N/A Interdisciplinary and Miscellaneous 002506 00 D G RG 0031M P12020G0031M VALUE OF WORK DONE (VOWD) EX-CO 210 28-09-2012 A4
89 N/A Interdisciplinary and Miscellaneous 002506 00 D G PG 0012M P12020G0012M VALUE OF WORK DONE PROCEDURE EX-DE 01 210 28-09-2012 A4
89 N/A Interdisciplinary and Miscellaneous 002506 00 D G PG 0012M P12020G0012M VALUE OF WORK DONE PROCEDURE EX-CO 00 210 28-09-2012 A4
90 N/A Interdisciplinary and Miscellaneous 002506 00 D G ST 0010M P12020G0010M DRY TO WET SHELTER TECHNICAL SPECIFICATION (BROWNFIELD) EX-DE 210 31-01-2013 A4
90 N/A Interdisciplinary and Miscellaneous 002506 00 D G ST 0010M P12020G0010M DRY TO WET SHELTER TECHNICAL SPECIFICATION (BROWNFIELD) EX-CO 210 31-01-2013 A4
91 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0005M P12020G0005M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 3 - OIL FISCAL METERING INSTALLATION) EX-DE 03 210 22-01-2013 A4
91 AB02 Interdisciplinary and Miscellaneous 002506 00 D G ED 0005M P12020G0005M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 3 - OIL FISCAL METERING INSTALLATION) EX-CO 05 210 22-01-2013 A4
92 AA01 Interdisciplinary and Miscellaneous 002506 00 D G SG 0001M P12020G0001M SITE & CLIMATIC CONDITIONS (ADDENDUM) EX-CO 00 210 20-04-2013 A4
93 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3007M P12020F3007M FIRE PREVENTION & PROTECTION EX-DE 00 210 28-09-2012 A4
93 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3007M P12020F3007M FIRE PREVENTION & PROTECTION EX-CO 02 210 28-09-2012 A4
94 R07 HSE (Health Safety & Environment) 002506 00 D F PV 3008M P12020F3008M FIRST AID EX-DE 01 210 29-10-2012 A4
94 R07 HSE (Health Safety & Environment) 002506 00 D F PV 3008M P12020F3008M FIRST AID EX-CO 210 29-10-2012 A4
95 XA01 HSE (Health Safety & Environment) 002506 00 D F PA 0026M P12020F0026M HEALTH SAFETY AND ENVIRONMENT (HSE) PLAN EX-DE 04 210 20-12-2012 A4
95 XA01 HSE (Health Safety & Environment) 002506 00 D F PA 0026M P12020F0026M HEALTH SAFETY AND ENVIRONMENT (HSE) PLAN EX-CO 00 210 20-12-2012 A4
96 R07 HSE (Health Safety & Environment) 002506 00 D F PG 3002M P12020F3002M HSE INDUCTION & TRAINING EX-DE 00 210 29-10-2012 A4
96 R07 HSE (Health Safety & Environment) 002506 00 D F PG 3002M P12020F3002M HSE INDUCTION & TRAINING EX-CO 00 210 29-10-2012 A4
97 R07 HSE (Health Safety & Environment) 002506 00 D F RS 3003M P12020F3003M INCIDENT REPORTING & INVESTIGATION EX-DE 01 210 29-10-2012 A4
97 R07 HSE (Health Safety & Environment) 002506 00 D F RS 3003M P12020F3003M INCIDENT REPORTING & INVESTIGATION EX-CO 02 210 29-10-2012 A4
98 R29 HSE (Health Safety & Environment) 002506 00 D F PG 3005M P12020F3005M LOCK OUT & TAG OUT (LOTO) EX-DE 00 210 29-10-2012 A4
98 R29 HSE (Health Safety & Environment) 002506 00 D F PG 3005M P12020F3005M LOCK OUT & TAG OUT (LOTO) EX-CO 02 210 29-10-2012 A4
99 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3010M P12020F3010M BRIDGING DOCUMENT & STX PERMIT TO WORK PROCEDURE EX-DE 00 210 29-10-2012 A4
99 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3010M P12020F3010M BRIDGING DOCUMENT & STX PERMIT TO WORK PROCEDURE EX-CO 01 210 29-10-2012 A4
100 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3009M P12020F3009M PERSONAL PROTECTIVE EQUIPMENT PROCEDURE EX-DE 00 210 29-10-2012 A4
100 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3009M P12020F3009M PERSONAL PROTECTIVE EQUIPMENT PROCEDURE EX-CO 01 210 29-10-2012 A4
101 XA18 HSE (Health Safety & Environment) 002506 00 D F RZ 3006M P12020F3006M RISK ASSESSMENT EX-DE 02 210 29-10-2012 A4
101 XA18 HSE (Health Safety & Environment) 002506 00 D F RZ 3006M P12020F3006M RISK ASSESSMENT EX-CO 00 210 29-10-2012 A4
102 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3011M P12020F3011M ROAD AND TRAFFIC SAFETY PROCEDURE EX-DE 02 210 29-10-2012 A4
102 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3011M P12020F3011M ROAD AND TRAFFIC SAFETY PROCEDURE EX-CO 01 210 29-10-2012 A4
103 R28 HSE (Health Safety & Environment) 002506 00 D F PG 3004M P12020F3004M SIMOPS PLAN EX-DE 02 210 29-10-2012 A4
103 R28 HSE (Health Safety & Environment) 002506 00 D F PG 3004M P12020F3004M SIMOPS PLAN EX-CO 210 29-10-2012 A4
104 R06 HSE (Health Safety & Environment) 002506 00 D F PA 3001M P12020F3001M SUB-CONTRACTOR SAFETY PROCEDURE EX-DE 02 210 29-10-2012 A4
104 R06 HSE (Health Safety & Environment) 002506 00 D F PA 3001M P12020F3001M SUB-CONTRACTOR SAFETY PROCEDURE EX-CO 02 210 29-10-2012 A4
105 XA07 HSE (Health Safety & Environment) 002506 00 D F PV 3012M P12020F3012M WASTE MANAGEMENT EX-DE 02 210 29-10-2012 A4
105 XA07 HSE (Health Safety & Environment) 002506 00 D F PV 3012M P12020F3012M WASTE MANAGEMENT EX-CO 01 210 29-10-2012 A4
106 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3019M P12020F3019M CONFINED SPACE ENTRY EX-DE 01 210 22-10-2012 A4
106 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3019M P12020F3019M CONFINED SPACE ENTRY EX-CO 00 210 22-10-2012 A4
107 XB10 HSE (Health Safety & Environment) 002506 00 D F PV 3013M P12020F3013M EVACUATION & EMERGENCY PLAN EX-DE 02 210 19-02-2013 A4
107 XB10 HSE (Health Safety & Environment) 002506 00 D F PV 3013M P12020F3013M EVACUATION & EMERGENCY PLAN EX-CO 210 19-02-2013 A4
108 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3017M P12020F3017M EXCAVATION & BACKFILLING PROCEDURE EX-DE 00 210 27-02-2013 A4
108 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3017M P12020F3017M EXCAVATION & BACKFILLING PROCEDURE EX-CO 02 210 27-02-2013 A4
109 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3021M P12020F3021M FLAMMABLE & COMBUSTIBLE LIQUIDS EX-DE 01 210 22-10-2012 A4
109 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3021M P12020F3021M FLAMMABLE & COMBUSTIBLE LIQUIDS EX-CO 00 210 22-10-2012 A4
110 R07 HSE (Health Safety & Environment) 002506 00 D F PV 3015M P12020F3015M HSE AUDIT & INSPECTION EX-DE 210 15-10-2012 A4
110 R07 HSE (Health Safety & Environment) 002506 00 D F PV 3015M P12020F3015M HSE AUDIT & INSPECTION EX-CO 02 210 15-10-2012 A4
111 R28 HSE (Health Safety & Environment) 002506 00 D F PV 3014M P12020F3014M HSE COMMUNICATION & MEETING EX-DE 00 210 15-10-2012 A4
111 R28 HSE (Health Safety & Environment) 002506 00 D F PV 3014M P12020F3014M HSE COMMUNICATION & MEETING EX-CO 00 210 15-10-2012 A4
112 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3018M P12020F3018M RIGGING AND LIFTING PROCEDURE EX-DE 00 210 22-10-2012 A4
112 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3018M P12020F3018M RIGGING AND LIFTING PROCEDURE EX-CO 02 210 22-10-2012 A4
113 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3020M P12020F3020M RIGGING EX-DE 210 22-10-2012 A4
113 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3020M P12020F3020M RIGGING EX-CO 210 22-10-2012 A4
114 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3016M P12020F3016M SCAFFOLDING AND PORTABLE LADDERS PROCEDURE EX-DE 00 210 15-10-2012 A4
114 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3016M P12020F3016M SCAFFOLDING AND PORTABLE LADDERS PROCEDURE EX-CO 02 210 15-10-2012 A4
115 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3022M P12020F3022M SITE SECURITY CONTROL EX-DE 02 210 01-02-2013 A4
115 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3022M P12020F3022M SITE SECURITY CONTROL EX-CO 03 210 01-02-2013 A4
116 XA29 HSE (Health Safety & Environment) 002506 00 D F PU 0034M P12020F0034M HAZOP PROCEDURE EX-DE 00 210 24-12-2012 A4
116 XA29 HSE (Health Safety & Environment) 002506 00 D F PU 0034M P12020F0034M HAZOP PROCEDURE EX-CO 02 210 24-12-2012 A4
117 XA21 HSE (Health Safety & Environment) 002506 00 D F PU 0035M P12020F0035M SIL ASSESMENT PROCEDURE EX-DE 01 210 11-02-2013 A4
117 XA21 HSE (Health Safety & Environment) 002506 00 D F PU 0035M P12020F0035M SIL ASSESMENT PROCEDURE EX-CO 00 210 11-02-2013 A4
118 XB03 HSE (Health Safety & Environment) 002506 00 D F ST 0023M P12020F0023M MOBILE FIRE EXTINGUISHER AND SAFETY EQUIPMENT SPECIFICATION EX-DE 00 210 30-10-2012 A4
118 XB03 HSE (Health Safety & Environment) 002506 00 D F ST 0023M P12020F0023M MOBILE FIRE EXTINGUISHER AND SAFETY EQUIPMENT SPECIFICATION EX-CO 00 210 30-10-2012 A4
119 XA03 HSE (Health Safety & Environment) 002506 00 D F PU 0014M P12020F0014M HAZARDOUS AREA CLASSIFICATION PHILOSOPHY (ADDENDUM) EX-CO 00 210 20-02-2013 A4
120 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0070M P12020I0070M FIBER OPTIC CABLES REQUIRED DOCUMENT DATASHEET (RDDS) EX-CO 00 210 01-12-2012 A4
121 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0067M P12020I0067M FIBER OPTIC CABLES INSPECTION DATASHEET (IDS) EX-CO 00 210 01-12-2012 A4
122 HB03 Instrumentation, Control and Automation 002506 00 D I SH 0043M P12020I0043M FUNCTIONAL SPECIFICATION FOR UCP PACKAGE (ADDENDUM) EX-CO 00 210 08-02-2013 A4
123 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0037M P12020I0037M INSTRUMENTATION AND CONTROL BASIS OF DESIGN (ADDENDUM) EX-CO 00 210 18-10-2012 A4
124 HA13 Instrumentation, Control and Automation 002506 00 D I ST 0050M P12020I0050M SAFETY AND CONTROL PANEL TECHNICAL SPECIFICATION (BROWNFIELD) (ADDENDUM) EX-CO 00 210 08-02-2013 A4
125 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0061M P12020I0061M TECHNICAL SPECIFICATION FOR FIBER OPTIC CABLES EX-DE 00 210 08-02-2013 A4
125 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0061M P12020I0061M TECHNICAL SPECIFICATION FOR FIBER OPTIC CABLES EX-CO 210 08-02-2013 A4
126 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0044M P12020I0044M TECHNICAL SPECIFICATION FOR INSTRUMENT CABLES (ADDENDUM) EX-CO 00 210 08-02-2013 A4
127 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0049M P12020I0049M TECHNICAL SPECIFICATION FOR JUNCTION BOXES (ADDENDUM) EX-CO 00 210 08-02-2013 A4
128 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0069M P12020I0069M INSTRUMENT CABLES REQUIRED DOCUMENT DATASHEET (RDDS) EX-CO 00 210 01-12-2012 A4
129 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0066M P12020I0066M INSTRUMENT CABLES INSPECTION DATASHEET (IDS) EX-CO 00 210 01-12-2012 A4
130 HA50 Instrumentation, Control and Automation 002506 00 D I SF 0027M P12020I0027M MATERIAL REQUISITION FOR FIBER OPTIC CABLES EX-CO 210 05/04/2013 A4
131 HA50 Instrumentation, Control and Automation 002506 00 D I SF 0026M P12020I0026M MATERIAL REQUISITION FOR INSTRUMENT CABLES EX-CO 00 210 05/04/2013 A4
132 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0191M P12020I0191M GENERAL SPECIFICATION FOR CHOKE VALVES (ADDENDUM) EX-CO 00 210 04/01/2013 A4
133 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0039M P12020I0039M GENERAL SPECIFICATION FOR SAFETY VALVES AND RUPTURE DISKS (ADDENDUM) EX-CO 00 210 15-01-2013 A4
134 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0038M P12020I0038M TECHNICAL SPECIFICATION FOR ELECTRIC ACTUATORS (ADDENDUM) EX-CO 00 210 08-02-2013 A4
135 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0040M P12020I0040M TECHNICAL SPECIFICATION FOR PNEUMATIC ACTUATORS (ADDENDUM) EX-CO 00 210 08-02-2013 A4
136 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0072M P12020I0072M FIRE & GAS DETECTION SYSTEM REQUIRED DOCUMENT DATASHEET (RDDS) EX-CO 00 210 01-12-2012 A4
137 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0068M P12020I0068M FIRE & GAS DETECTION SYSTEM INSPECTION DATASHEET (IDS) EX-CO 00 210 01-12-2012 A4
138 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0071M P12020I0071M F&G DETECTORS REQUIRED DOCUMENT DATASHEET (RDDS) EX-CO 00 210 01-12-2012 A4
139 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0009M P12020I0009M F&G DETECTORS INSPECTION DATASHEET (IDS) EX-CO 00 210 01-12-2012 A4
140 HA13 Instrumentation, Control and Automation 002506 00 D I ST 0042M P12020I0042M TECHNICAL SPECIFICATION FOR FIRE & GAS DETECTION SYSTEM (ADDENDUM) EX-CO 00 210 08-02-2013 A4
141 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0062M P12020I0062M TECHNICAL SPECIFICATION FOR BULK MATERIAL EX-DE 00 210 11-01-2013 A4
141 HA09 Instrumentation, Control and Automation 002506 00 D I ST 0062M P12020I0062M TECHNICAL SPECIFICATION FOR BULK MATERIAL EX-CO 00 210 11-01-2013 A4
143 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0002M P12020I0002M FIELD INSTRUMENTS INSPECTION DATASHEET (IDS) EX-CO 00 210 24-11-2012 A4
144 HA50 Instrumentation, Control and Automation 002506 11 D I EJ 5229M P12020I5229M MATERIAL REQUISITION FOR F&G DETECTORS EX-CO 00 210 01-02-2013 A4
150 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0015M P12020I0015M CONTROL VALVE DOCUMENT DATASHEET (DDS) EX-CO 00 210 24-11-2012 A4
151 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0006M P12020I0006M CONTROL VALVE INSPECTION DATASHEET (IDS) EX-CO 00 210 24-11-2012 A4
152 HA50 Instrumentation, Control and Automation 002506 03 D I EJ 5409M P12020I5409M MATERIAL REQUISITION FOR SAFETY AND CONTROL SYSTEM EX-CO 00 210 01-02-2013 A4
153 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0017M P12020I0017M MOTORIZED OPERATED VALVE DOCUMENT DATASHEET (DDS) EX-CO 00 210 24-11-2012 A4
154 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0008M P12020I0008M MOTORIZED OPERATED VALVE INSPECTION DATASHEET (IDS) EX-CO 00 210 24-11-2012 A4
155 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0016M P12020I0016M PRESSURE SAFETY VALVE DOCUMENT DATASHEET (DDS) EX-CO 00 210 24-11-2012 A4
156 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0007M P12020I0007M PRESSURE SAFETY VALVE INSPECTION DATASHEET (IDS) EX-CO 00 210 24-11-2012 A4
157 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0014M P12020I0014M SHUT OFF VALVE DOCUMENT DATASHEET (DDS) EX-CO 00 210 01-12-2012 A4
158 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0005M P12020I0005M SHUT OFF VALVE INSPECTION DATASHEET (IDS) EX-CO 00 210 01-12-2012 A4
162 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0011M P12020I0011M FIELD INSTRUMENTS DOCUMENT DATASHEET (DDS) EX-CO 00 210 24-11-2012 A4
163 HA58 Instrumentation, Control and Automation 002506 00 D I SF 5006M P12020I5006M DRY TO WET - FINAL TEST CERTIFICATE/QUALITY STATEMENT EX-DE 210 As-built A4
163 HA58 Instrumentation, Control and Automation 002506 00 D I SF 5006M P12020I5006M DRY TO WET - FINAL TEST CERTIFICATE/QUALITY STATEMENT EX-CO 210 As-built A4
165 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0052M P12020I0052M INSTRUMENTATION AND CONTROL PHILOSOPHY (ADDENDUM) EX-CO 00 210 08-02-2013 A4
166 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0051M P12020I0051M INSTRUMENTATION AND CONTROL SYSTEM DESIGN CRITERIA FOR PACKAGES (ADDENDUM) EX-CO 00 210 18-10-2012 A4
167 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0089M P12020I0089M GENERAL SPECIFICATION FOR CONTROL VALVES (ADDENDUM) EX-CO 00 210 15-01-2013 A4
168 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0056M P12020I0056M GENERAL SPECIFICATION FOR LEVEL INSTRUMENTS (ADDENDUM) EX-CO 00 210 15-01-2013 A4
169 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0090M P12020I0090M SAFETY AND CONTROL SYSTEM IDS (BROWNFIELD) (ADDENDUM) EX-CO 01 210 15-01-2013 A4
170 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0053M P12020I0053M GENERAL SPECIFICATION FOR FLOW INSTRUMENTS (ADDENDUM) EX-CO 00 210 15-01-2013 A4
171 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0055M P12020I0055M GENERAL SPECIFICATION FOR PRESSURE INSTRUMENTS (ADDENDUM) EX-CO 00 210 15-01-2013 A4
172 HA01 Instrumentation, Control and Automation 002506 00 D I SG 0054M P12020I0054M GENERAL SPECIFICATION FOR TEMPERATURE INSTRUMENTS (ADDENDUM) EX-CO 00 210 15-01-2013 A4
173 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0094M P12020I0094M ON-OFF VALVES DOCUMENT DATASHEET (DDS) (BROWNFIELD) (ADDENDUM) EX-CO 00 210 01-12-2012 A4
174 HA52 Instrumentation, Control and Automation 002506 00 D I GB 0091M P12020I0091M ON-OFF VALVES INSPECTION DATASHEET (IDS) (BROWNFIELD) (ADDENDUM) EX-CO 00 210 01-12-2012 A4
175 HA04 Instrumentation, Control and Automation 002506 00 D I GC 0093M P12020I0093M SAFETY AND CONTROL SYSTEM DOCUMENT DATASHEET (DDS) (BROWNFIELD) (ADDENDUM) EX-CO 02 210 15-01-2013 A4
176 F01 Machinery 002506 00 D M SG 0003M P12020M0003M BASIS OF DESIGN FOR MACHINERY AND PACKAGES (ADDENDUM) EX-CO 00 210 06-12-2012 A4
177 F12 Machinery 002506 00 D M GB 0005M P12020M0005M INSPECTION DATA SHEET (IDS) FOR CENTRIFUGAL PUMPS WITH ELECTRIC MOTOR DRIVER (ADDENDUM) EX-CO 01 210 28-11-2012 A4
178 F22 Machinery 002506 00 D M GC 0001M P12020M0001M REQUIRED DOCUMENT DATA SHEET (RDDS) FOR CENTRIFUGAL PUMPS - ELECTRIC MOTOR WITH VSD EX-CO 00 210 20-04-2013 A4
179 F22 Machinery 002506 00 D M GC 0004M P12020M0004M REQUIRED DOCUMENT DATA SHEET (RDDS) FOR CENTRIFUGAL PUMPS - FIXED SPEED ELECTRIC MOTOR (ADDENDUM) EX-CO 01 210 25-03-2013 A4
180 F01 Machinery 002506 00 D M ST 0032M P12020M0032M TECHNICAL SPECIFICATION FOR CENTRIFUGAL PUMPS (ADDENDUM) EX-CO 00 210 27-02-2013 A4
181 EC02 Corrosion and materials selection 002506 00 D X RV 0001M P12020X0001M MATERIAL SELECTION REPORT (BROWNFIELD) (ADDENDUM) EX-CO 00 210 06-12-2012 A4
182 F01 Mechanical Equipment 002506 00 D V SG 0004M P12020V0004M BASIS OF DESIGN FOR STATIC EQUIPMENTS AND HEAT EXCHANGER (ADDENDUM) EX-CO 00 210 20-04-2013 A4
183 F12 Mechanical Equipment 002506 00 D V GB 0005M P12020V0005M INSPECTION DATA SHEET (IDS) FOR PRESSURE VESSELS (ADDENDUM) EX-CO 01 210 28-11-2012 A4
184 EA01 Mechanical Equipment 002506 00 D V ST 0010M P12020V0010M TECHNICAL SPECIFICATION FOR PRESSURE VESSELS (ADDENDUM) EX-CO 00 210 18-10-2012 A4
185 EA04 Mechanical Equipment 002506 00 D V GC 0003M P12020V0003M REQUIRED DOCUMENT DATA SHEET (RDDS) FOR LARGE WELDED STORAGE TANK EX-CO 00 210 28-02-2013 A4
186 EB18 Mechanical Equipment 002506 00 D V GB 0002M P12020V0002M INSPECTION DATA SHEET (IDS) FOR LARGE WELDED STORAGE TANK EX-CO 00 210 08-11-2012 A4
187 F01 Mechanical Equipment 002506 00 D V ST 0006M P12020V0006M TECHNICAL SPECIFICATION FOR LARGE WELDED STORAGE TANK (ADDENDUM) EX-CO 00 210 08-11-2012 A4
189 EA04 Mechanical Equipment 002506 00 D V GC 0007M P12020V0007M REQUIRED DOCUMENT DATA SHEET (RDDS) FOR PRESSURE VESSELS (ADDENDUM) EX-CO 01 210 20-04-2013 A4
190 EB18 Mechanical Equipment 002506 00 D V GB 0009M P12020V0009M INSPECTION DATA SHEET (IDS) FOR PLATE&FRAME HEAT EXCHANGERS (ADDENDUM) EX-CO 01 210 28-11-2012 A4
191 EB05 Mechanical Equipment 002506 00 D V GC 0008M P12020V0008M REQUIRED DOCUMENT DATA SHEET (RDDS) FOR PRESSURE PLATE&FRAME HEAT EXCHANGERS (ADDENDUM) EX-CO 01 210 20-04-2013 A4
192 EB01 Mechanical Equipment 002506 00 D V ST 0011M P12020V0011M TECHNICAL SPECIFICATION FOR PLATE&FRAME HEAT EXCHANGERS (ADDENDUM) EX-CO 00 210 18-10-2012 A4
193 DB02 Plant layout and Piping 002506 00 D T ST 0008M P12020T0008M SPECIFICATION FOR PIPING CLASSIFICATION AND MATERIAL (ADDENDUM) EX-CO 00 210 18-10-2012 A4
194 DB01 Plant layout and Piping 002506 00 D T SG 0006M P12020T0006M SPECIFICATION FOR PIPING STRESS ANALYSIS (ADDENDUM) EX-CO 00 210 27-02-2013 A4
195 DB03 Plant layout and Piping 002506 00 D T GB 0052M P12020T0052M BALL VALVES INSPECTION DATA SHEET EX-CO 00 210 18-10-2012 A4
196 DB03 Plant layout and Piping 002506 00 D T GB 0054M P12020T0054M CHECKS VALVE INSPECTION DATA SHEET EX-CO 00 210 18-10-2012 A4
197 DB03 Plant layout and Piping 002506 00 D T GB 0033M P12020T0033M GATE VALVES INSPECTION DATA SHEET EX-CO 00 210 18-10-2012 A4
198 DB03 Plant layout and Piping 002506 00 D T GB 0051M P12020T0051M GLOBE VALVE INSPECTION DATA SHEET EX-CO 00 210 18-10-2012 A4
199 DB01 Plant layout and Piping 002506 00 D T SG 0007M P12020T0007M PIPING BASIS OF DESIGN (ADDENDUM) EX-CO 02 210 14-11-2012 A4
200 DB03 Plant layout and Piping 002506 00 D T GC 0053M P12020T0053M PLANT VALVES REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 18-10-2012 A4
201 DC03 Plant layout and Piping 002506 00 D T SG 0003M P12020T0003M SPECIFICATION FOR EXTERNAL COATING OF BELOW GROUND ON-PLOT PIPING (ADDENDUM) EX-CO 00 210 14-11-2012 A4
202 EC18 Plant layout and Piping 002506 00 D T SG 0002M P12020T0002M SPECIFICATION FOR SHOP AND FIELD PAINTING OF ABOVE GROUND STEEL SURFACES (ADDENDUM) EX-CO 00 210 27-02-2013 A4
203 DC02 Plant layout and Piping 002506 00 D T SG 0004M P12020T0004M THERMAL INSULATION SPECIFICATION FOR HOT SERVICE (ADDENDUM) EX-CO 00 210 27-02-2013 A4
204 DB03 Plant layout and Piping 002506 00 D T GB 0055M P12020T0055M BUTTERFLY VALVES INSPECTION DATA SHEET EX-CO 00 210 18-10-2012 A4
205 DB03 Plant layout and Piping 002506 00 D T GB 0047M P12020T0047M PLANT PIPE INSPECTION DATA SHEET EX-CO 00 210 22-11-2012 A4
206 DB03 Plant layout and Piping 002506 00 D T GC 0048M P12020T0048M PLANT PIPE REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 22-11-2012 A4
207 DB03 Plant layout and Piping 002506 00 D T GB 0032M P12020T0032M PLANT FITTINGS INSPECTION DATA SHEET EX-CO 00 210 22-11-2012 A4
208 DB03 Plant layout and Piping 002506 00 D T GC 0031M P12020T0031M PLANT FITTINGS REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 22-11-2012 A4
209 DB03 Plant layout and Piping 002506 00 D T GB 0049M P12020T0049M PLANT FLANGES INSPECTION DATA SHEET EX-CO 00 210 22-11-2012 A4
210 DB03 Plant layout and Piping 002506 00 D T GC 0050M P12020T0050M PLANT FLANGES REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 22-11-2012 A4
212 DB02 Plant layout and Piping 002506 00 D T SG 0005M P12020T0005M PIPING GENERAL WELDING SPECIFICATION (ADDENDUM) EX-CO 00 210 17-11-2012 A4
213 EC20 Plant layout and Piping 002506 00 D T SG 0001M P12020T0001M SPECIFICATION FOR FIELD REPAIR OF SHOP APPLIED COATINGS (ADDENDUM) EX-CO 00 210 05-04-2013 A4
214 N/A Plant layout and Piping 002506 00 D T QR 5016M P12020T5016M 3D MODEL REVIEW PROCEDURE EX-DE 00 210 08-11-2012 A4
214 N/A Plant layout and Piping 002506 00 D T QR 5016M P12020T5016M 3D MODEL REVIEW PROCEDURE EX-CO 01 210 08-11-2012 A4
215 B02 Process 002506 00 D P RB 0100M P12020P0100M ISOLATION PHILOSOPHY (ADDENDUM) EX-CO 00 210 22-11-2012 A4
218 B11 Process 002506 00 D P FM 0005M P12020P0005M ZUBAIR FIELD - LEGENDA & SYMBOLS P&ID EX-DE 00 210 05-11-2012 A4 00250600BPFM08030-CD-FE-03
218 B11 Process 002506 00 D P FM 0005M P12020P0005M ZUBAIR FIELD - LEGENDA & SYMBOLS P&ID EX-CO 03 210 05-11-2012 A4 00250600BPFM08030-CD-FE-03
219 Q06 Quality Assurance and Control 002506 00 D B QR 2002M P12020B2002M CORRECTIVE AND PREVENTIVE ACTION PROCEDURE EX-DE 02 210 25-10-2012 A1
219 Q06 Quality Assurance and Control 002506 00 D B QR 2002M P12020B2002M CORRECTIVE AND PREVENTIVE ACTION PROCEDURE EX-CO 00 210 25-10-2012 A1
220 Q06 Quality Assurance and Control 002506 00 D B QR 2001M P12020B2001M SITE DOCUMENT CONTROL PROCEDURE EX-DE 04 210 07-01-2013 A4
220 Q06 Quality Assurance and Control 002506 00 D B QR 2001M P12020B2001M SITE DOCUMENT CONTROL PROCEDURE EX-CO 00 210 07-01-2013 A4
221 Q06 Quality Assurance and Control 002506 00 D B QR 2005M P12020B2005M MATERIAL IDENTIFICATION AND TRACEABILITY PROCEDURE EX-DE 02 210 07-01-2013 A4
221 Q06 Quality Assurance and Control 002506 00 D B QR 2005M P12020B2005M MATERIAL IDENTIFICATION AND TRACEABILITY PROCEDURE EX-CO 01 210 07-01-2013 A4
222 Q06 Quality Assurance and Control 002506 00 D B QR 2003M P12020B2003M MEASURING AND TEST EQUIPMENT CONTROL PROCEDURE EX-DE 04 210 10-12-2012 A4
222 Q06 Quality Assurance and Control 002506 00 D B QR 2003M P12020B2003M MEASURING AND TEST EQUIPMENT CONTROL PROCEDURE EX-CO 00 210 10-12-2012 A4
223 Q01 Quality Assurance and Control 002506 00 D B QA 0024M P12020B0024M PROJECT QUALITY PLAN EX-DE 06 210 19-02-2013 A4
223 Q01 Quality Assurance and Control 002506 00 D B QA 0024M P12020B0024M PROJECT QUALITY PLAN EX-CO 00 210 19-02-2013 A4
224 Q04 Quality Assurance and Control 002506 00 D B QA 0021M P12020B0021M QUALITY ASSURANCE and QUALITY CONTROL EX-DE 210 20-04-2013 A4
224 Q04 Quality Assurance and Control 002506 00 D B QA 0021M P12020B0021M QUALITY ASSURANCE and QUALITY CONTROL EX-CO 210 20-04-2013 A4
226 Q06 Quality Assurance and Control 002506 00 D B QR 2004M P12020B2004M MATERIAL RECEIVING INSPECTION PROCEDURE EX-DE 02 210 07-01-2013 A4
226 Q06 Quality Assurance and Control 002506 00 D B QR 2004M P12020B2004M MATERIAL RECEIVING INSPECTION PROCEDURE EX-CO 02 210 07-01-2013 A4
227 R08 Quality Assurance and Control 002506 00 D B QR 2012M P12020B2012M DYE PENETRANT PROCEDURE EX-DE 01 210 20-04-2013 A4
227 R08 Quality Assurance and Control 002506 00 D B QR 2012M P12020B2012M DYE PENETRANT PROCEDURE EX-CO 00 210 20-04-2013 A4
230 R08 Quality Assurance and Control 002506 00 D B QR 2019M P12020B2019M HARDNESS TEST PROCEDURE EX-DE 01 210 07-01-2013 A4
230 R08 Quality Assurance and Control 002506 00 D B QR 2019M P12020B2019M HARDNESS TEST PROCEDURE EX-CO 00 210 07-01-2013 A4
231 R03 Quality Assurance and Control 002506 00 D B QR 2006M P12020B2006M IMS AUDIT PROCEDURE EX-DE 02 210 07-01-2013 A4
231 R03 Quality Assurance and Control 002506 00 D B QR 2006M P12020B2006M IMS AUDIT PROCEDURE EX-CO 00 210 07-01-2013 A4
232 R08 Quality Assurance and Control 002506 00 D B QR 2010M P12020B2010M MAGNETIC PARTICLE PROCEDURE EX-DE 01 210 20-04-2013 A4
232 R08 Quality Assurance and Control 002506 00 D B QR 2010M P12020B2010M MAGNETIC PARTICLE PROCEDURE EX-CO 00 210 20-04-2013 A4
234 Q06 Quality Assurance and Control 002506 00 D B QN 2020M P12020B2020M NON-CONFORMANCE PROCEDURE EX-DE 04 210 07-01-2013 A4
234 Q06 Quality Assurance and Control 002506 00 D B QN 2020M P12020B2020M NON-CONFORMANCE PROCEDURE EX-CO 00 210 07-01-2013 A4
235 R08 Quality Assurance and Control 002506 00 D B QR 2008M P12020B2008M PIPING PRESSURE TEST PROCEDURE EX-DE 210 17-10-2012 A4
235 R08 Quality Assurance and Control 002506 00 D B QR 2008M P12020B2008M PIPING PRESSURE TEST PROCEDURE EX-CO 210 17-10-2012 A4
236 R11 Quality Assurance and Control 002506 00 D B QR 2018M P12020B2018M POSITIVE MATERIAL IDENTIFICATION PROCEDURE EX-DE 01 210 07-01-2013 A4
236 R11 Quality Assurance and Control 002506 00 D B QR 2018M P12020B2018M POSITIVE MATERIAL IDENTIFICATION PROCEDURE EX-CO 00 210 07-01-2013 A4
237 R08 Quality Assurance and Control 002506 00 D B QR 2009M P12020B2009M RADIOGRAPHY (RT) PROCEDURE EX-DE 00 210 20-04-2013 A4
237 R08 Quality Assurance and Control 002506 00 D B QR 2009M P12020B2009M RADIOGRAPHY (RT) PROCEDURE EX-CO 00 210 20-04-2013 A4
238 R08 Quality Assurance and Control 002506 00 D B QR 2014M P12020B2014M ULTRASONIC PROCEDURE EX-DE 02 210 20-04-2013 A4
238 R08 Quality Assurance and Control 002506 00 D B QR 2014M P12020B2014M ULTRASONIC PROCEDURE EX-CO 00 210 20-04-2013 A4
240 R08 Quality Assurance and Control 002506 00 D B QR 2016M P12020B2016M VISUAL INSPECTION PROCEDURE EX-DE 04 210 07-01-2013 A4
240 R08 Quality Assurance and Control 002506 00 D B QR 2016M P12020B2016M VISUAL INSPECTION PROCEDURE EX-CO 00 210 07-01-2013 A4
242 R13 Quality Assurance and Control 002506 00 D B QR 2007M P12020B2007M WELDER QUALIFICATION PROCEDURE EX-DE 01 210 15-01-2013 A4
242 R13 Quality Assurance and Control 002506 00 D B QR 2007M P12020B2007M WELDER QUALIFICATION PROCEDURE EX-CO 00 210 15-01-2013 A4
243 R06 Interdisciplinary and Miscellaneous 002506 00 D G PT 1007M P12020G1007M ENGINEERING EXECUTION PLAN for Work Order 4 EX-DE 210 07-11-2012 A4
243 R06 Interdisciplinary and Miscellaneous 002506 00 D G PT 1007M P12020G1007M ENGINEERING EXECUTION PLAN for Work Order 4 EX-CO 210 07-11-2012 A4
244 R06 Interdisciplinary and Miscellaneous 002506 00 D G PP 1006M P12020G1006M OVERALL EXECUTION PLAN for Work Order No.4 EX-DE 210 07-11-2012 A4
244 R06 Interdisciplinary and Miscellaneous 002506 00 D G PP 1006M P12020G1006M OVERALL EXECUTION PLAN for Work Order No.4 EX-CO 210 07-11-2012 A4
246 R29 Interdisciplinary and Miscellaneous 002506 00 B G SG 0011M P12020G0011M BASIC ENGINEERING DESIGN BASIS (ADDENDUM) EX-CO 04 210 20-04-2013 A4
254 HA53 Instrumentation, Control and Automation 002506 00 D I DR 5062M P12020I5062M SUPPLIERS DRAWINGS FOR VALVES AND IN-LINE INSTRUMENTS EX-DE 210 03/05/2013 A4
254 HA53 Instrumentation, Control and Automation 002506 00 D I DR 5062M P12020I5062M SUPPLIERS DRAWINGS FOR VALVES AND IN-LINE INSTRUMENTS EX-CO 210 03/05/2013 A4
255 HA54 Instrumentation, Control and Automation 002506 00 D I DR 5063M P12020I5063M SUPPLIERS DRAWINGS FOR SYSTEMS/ ANALYSERS AND INSTRUMENTS EX-DE 210 03/05/2013 A4
255 HA54 Instrumentation, Control and Automation 002506 00 D I DR 5063M P12020I5063M SUPPLIERS DRAWINGS FOR SYSTEMS/ ANALYSERS AND INSTRUMENTS EX-CO 210 03/05/2013 A4
266 Q06 Quality Assurance and Control 002506 00 D B QR 2022M P12020B2022M NOTIFICATION OF INSPECTION (NOI) EX-DE 210 20-04-2013 A4
266 Q06 Quality Assurance and Control 002506 00 D B QR 2022M P12020B2022M NOTIFICATION OF INSPECTION (NOI) EX-CO 210 20-04-2013 A4
267 P02 Quality Assurance and Control 002506 00 D B PS 4004M P12020B4004M VESSEL PRESSURE TEST PROCEDURE EX-DE 210 20-04-2013 A4
267 P02 Quality Assurance and Control 002506 00 D B PS 4004M P12020B4004M VESSEL PRESSURE TEST PROCEDURE EX-CO 210 20-04-2013 A4
268 XA20 HSE (Health Safety & Environment) 002506 00 D F PV 4005M P12020F4005M HAZARDOUS MATERIALS REGISTER EX-DE 210 20-04-2013 A4
268 XA20 HSE (Health Safety & Environment) 002506 00 D F PV 4005M P12020F4005M HAZARDOUS MATERIALS REGISTER EX-CO 210 20-04-2013 A4
269 Q06 Quality Assurance and Control 002506 00 D B QB 4006M P12020B4006M I&TP FOR CONCRETE MIX DESIGN EX-DE 01 210 12-01-2013 A4
269 Q06 Quality Assurance and Control 002506 00 D B QB 4006M P12020B4006M I&TP FOR CONCRETE MIX DESIGN EX-CO 00 210 12-01-2013 A4
270 Q06 Quality Assurance and Control 002506 00 D B QB 4007M P12020B4007M I&TP FOR EARTH WORK EX-DE 210 12-01-2013 A4
270 Q06 Quality Assurance and Control 002506 00 D B QB 4007M P12020B4007M I&TP FOR EARTH WORK EX-CO 210 12-01-2013 A4
271 Q06 Quality Assurance and Control 002506 00 D B QB 4008M P12020B4008M I&TP FOR BLINDING,CONCRETING,COATING FOUNDATION AND BACKFILLING EX-DE 210 20-04-2013 A4
271 Q06 Quality Assurance and Control 002506 00 D B QB 4008M P12020B4008M I&TP FOR BLINDING,CONCRETING,COATING FOUNDATION AND BACKFILLING EX-CO 210 20-04-2013 A4
272 Q06 Quality Assurance and Control 002506 00 D B QB 4009M P12020B4009M I&TP FOR INSITU CAST CONCRETE EX-DE 01 210 04-01-2013 A4
272 Q06 Quality Assurance and Control 002506 00 D B QB 4009M P12020B4009M I&TP FOR INSITU CAST CONCRETE EX-CO 00 210 04-01-2013 A4
273 Q06 Quality Assurance and Control 002506 00 D B QB 4010M P12020B4010M I&TP FOR PRECAST CONCRETE EX-DE 02 210 12-01-2013 A4
273 Q06 Quality Assurance and Control 002506 00 D B QB 4010M P12020B4010M I&TP FOR PRECAST CONCRETE EX-CO 00 210 12-01-2013 A4
274 Q06 Quality Assurance and Control 002506 00 D B QB 4011M P12020B4011M I&TP FOR ASPHALT ROADS WORK EX-DE 02 210 12-01-2013 A4
274 Q06 Quality Assurance and Control 002506 00 D B QB 4011M P12020B4011M I&TP FOR ASPHALT ROADS WORK EX-CO 00 210 12-01-2013 A4
275 Q06 Quality Assurance and Control 002506 00 D B QB 4012M P12020B4012M I&TP FOR UNDERGROUND PIPE & BACK FILLING EX-DE 02 210 12-01-2013 A4
275 Q06 Quality Assurance and Control 002506 00 D B QB 4012M P12020B4012M I&TP FOR UNDERGROUND PIPE & BACK FILLING EX-CO 00 210 12-01-2013 A4
276 Q06 Quality Assurance and Control 002506 00 D B QB 4013M P12020B4013M I&TP FOR CONCRETE PAVING EX-DE 04 210 19-02-2013 A4
276 Q06 Quality Assurance and Control 002506 00 D B QB 4013M P12020B4013M I&TP FOR CONCRETE PAVING EX-CO 00 210 19-02-2013 A4
277 Q06 Quality Assurance and Control 002506 00 D B QB 4014M P12020B4014M I&TP FOR STRUCTURAL STEEL PREFABRICATION EX-DE 04 210 12-01-2013 A4
277 Q06 Quality Assurance and Control 002506 00 D B QB 4014M P12020B4014M I&TP FOR STRUCTURAL STEEL PREFABRICATION EX-CO 00 210 12-01-2013 A4
278 Q06 Quality Assurance and Control 002506 00 D B QB 4015M P12020B4015M I&TP FOR STRUCTURAL STEEL ERECTION EX-DE 01 210 12-01-2013 A4
278 Q06 Quality Assurance and Control 002506 00 D B QB 4015M P12020B4015M I&TP FOR STRUCTURAL STEEL ERECTION EX-CO 00 210 12-01-2013 A4
280 Q06 Quality Assurance and Control 002506 00 D B QB 4017M P12020B4017M I&TP FOR PSV VALVES INSTALLATION EX-DE 210 20-04-2013 A4
280 Q06 Quality Assurance and Control 002506 00 D B QB 4017M P12020B4017M I&TP FOR PSV VALVES INSTALLATION EX-CO 210 20-04-2013 A4
281 Q06 Quality Assurance and Control 002506 00 D B QB 4018M P12020B4018M I&TP FOR STATIC EQUIPMENT EX-DE 210 12-01-2013 A4
281 Q06 Quality Assurance and Control 002506 00 D B QB 4018M P12020B4018M I&TP FOR STATIC EQUIPMENT EX-CO 210 12-01-2013 A4
282 Q06 Quality Assurance and Control 002506 00 D B QB 4019M P12020B4019M I&TP FOR ROTATING EQUIPMENT EX-DE 210 12-01-2013 A4
282 Q06 Quality Assurance and Control 002506 00 D B QB 4019M P12020B4019M I&TP FOR ROTATING EQUIPMENT EX-CO 210 12-01-2013 A4
283 Q06 Quality Assurance and Control 002506 00 D B QB 4020M P12020B4020M I&TP FOR PIPING PREFABRICATION AND ERECTION EX-DE 02 210 12-01-2013 A4
283 Q06 Quality Assurance and Control 002506 00 D B QB 4020M P12020B4020M I&TP FOR PIPING PREFABRICATION AND ERECTION EX-CO 00 210 12-01-2013 A4
284 Q06 Quality Assurance and Control 002506 00 D B QB 4021M P12020B4021M I&TP ABOVEGROUND PIPING PRESSURE TEST EX-DE 210 20-04-2013 A4
284 Q06 Quality Assurance and Control 002506 00 D B QB 4021M P12020B4021M I&TP ABOVEGROUND PIPING PRESSURE TEST EX-CO 210 20-04-2013 A4
285 Q06 Quality Assurance and Control 002506 00 D B QB 4022M P12020B4022M I&TP UNDERGROUND PIPING PRESSURE TEST EX-DE 210 20-04-2013 A4
285 Q06 Quality Assurance and Control 002506 00 D B QB 4022M P12020B4022M I&TP UNDERGROUND PIPING PRESSURE TEST EX-CO 210 20-04-2013 A4
286 Q06 Quality Assurance and Control 002506 00 D B QB 4023M P12020B4023M I&TP FOR GENERATORS INSTALLATION EX-DE 03 210 12-01-2013 A4
286 Q06 Quality Assurance and Control 002506 00 D B QB 4023M P12020B4023M I&TP FOR GENERATORS INSTALLATION EX-CO 00 210 12-01-2013 A4
287 Q06 Quality Assurance and Control 002506 00 D B QB 4024M P12020B4024M I&TP FOR BATTERIES, BATTERY CHARGER AND UPS INSTALLATION EX-DE 01 210 12-01-2013 A4
287 Q06 Quality Assurance and Control 002506 00 D B QB 4024M P12020B4024M I&TP FOR BATTERIES, BATTERY CHARGER AND UPS INSTALLATION EX-CO 00 210 12-01-2013 A4
288 Q06 Quality Assurance and Control 002506 00 D B QB 4025M P12020B4025M I&TP FOR POWER AND CONTROL CABLE INSTALLATION EX-DE 02 210 12-01-2013 A4
288 Q06 Quality Assurance and Control 002506 00 D B QB 4025M P12020B4025M I&TP FOR POWER AND CONTROL CABLE INSTALLATION EX-CO 00 210 12-01-2013 A4
289 Q06 Quality Assurance and Control 002506 00 D B QB 4026M P12020B4026M I&TP FOR LIGHTING SYSTEM INSTALLATION EX-DE 02 210 12-01-2013 A4
289 Q06 Quality Assurance and Control 002506 00 D B QB 4026M P12020B4026M I&TP FOR LIGHTING SYSTEM INSTALLATION EX-CO 00 210 12-01-2013 A4
290 Q06 Quality Assurance and Control 002506 00 D B QB 4027M P12020B4027M I&TP FOR EARTHING & LIGHTING PROTECTION SYSTEM INSTALLATION EX-DE 02 210 12-01-2013 A4
290 Q06 Quality Assurance and Control 002506 00 D B QB 4027M P12020B4027M I&TP FOR EARTHING & LIGHTING PROTECTION SYSTEM INSTALLATION EX-CO 00 210 12-01-2013 A4
291 Q06 Quality Assurance and Control 002506 00 D B QB 4028M P12020B4028M I&TP FOR LOW AND HIGH VOLTAGE MOTOR INSTALLATION EX-DE 03 210 15-02-2013 A4
291 Q06 Quality Assurance and Control 002506 00 D B QB 4028M P12020B4028M I&TP FOR LOW AND HIGH VOLTAGE MOTOR INSTALLATION EX-CO 00 210 15-02-2013 A4
292 Q06 Quality Assurance and Control 002506 00 D B QB 4029M P12020B4029M I&TP FOR POWER TRANSFORMER INSTALLATION EX-DE 02 210 12-01-2013 A4
292 Q06 Quality Assurance and Control 002506 00 D B QB 4029M P12020B4029M I&TP FOR POWER TRANSFORMER INSTALLATION EX-CO 210 12-01-2013 A4
293 Q06 Quality Assurance and Control 002506 00 D B QB 4030M P12020B4030M I&TP FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION EX-DE 02 210 12-01-2013 A4
293 Q06 Quality Assurance and Control 002506 00 D B QB 4030M P12020B4030M I&TP FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION EX-CO 00 210 12-01-2013 A4
294 Q06 Quality Assurance and Control 002506 00 D B QB 4031M P12020B4031M I&TP FOR SMALL POWER DISTRIBUTION EQUIPMENT EX-DE 03 210 12-01-2013 A4
294 Q06 Quality Assurance and Control 002506 00 D B QB 4031M P12020B4031M I&TP FOR SMALL POWER DISTRIBUTION EQUIPMENT EX-CO 00 210 12-01-2013 A4
295 Q06 Quality Assurance and Control 002506 00 D B QB 4032M P12020B4032M I&TP FOR CABLE RACKS, TRAYS AND CONDUIT INSTALLATION EX-DE 01 210 12-01-2013 A4
295 Q06 Quality Assurance and Control 002506 00 D B QB 4032M P12020B4032M I&TP FOR CABLE RACKS, TRAYS AND CONDUIT INSTALLATION EX-CO 00 210 12-01-2013 A4
296 Q06 Quality Assurance and Control 002506 00 D B QB 4033M P12020B4033M I&TP FOR GLANDING & TERMINATION OF POWER AND CONTROL CABLES INSTALLATION EX-DE 04 210 19-02-2013 A4
296 Q06 Quality Assurance and Control 002506 00 D B QB 4033M P12020B4033M I&TP FOR GLANDING & TERMINATION OF POWER AND CONTROL CABLES INSTALLATION EX-CO 00 210 19-02-2013 A4
297 Q06 Quality Assurance and Control 002506 00 D B QB 4034M P12020B4034M I&TP FOR MOTOR OPERATE VALVE INSTALLATION EX-DE 210 20-04-2013 A4
297 Q06 Quality Assurance and Control 002506 00 D B QB 4034M P12020B4034M I&TP FOR MOTOR OPERATE VALVE INSTALLATION EX-CO 210 20-04-2013 A4
298 Q06 Quality Assurance and Control 002506 00 D B QB 4035M P12020B4035M I&TP FOR NEUTRAL EARTH RESISTORS INSTALLATION EX-DE 01 210 12-01-2013 A4
298 Q06 Quality Assurance and Control 002506 00 D B QB 4035M P12020B4035M I&TP FOR NEUTRAL EARTH RESISTORS INSTALLATION EX-CO 00 210 12-01-2013 A4
299 Q06 Quality Assurance and Control 002506 00 D B QB 4036M P12020B4036M I&TP FOR ELECTRICAL HEAT TRACING INSTALLATION EX-DE 210 12-01-2013 A4
299 Q06 Quality Assurance and Control 002506 00 D B QB 4036M P12020B4036M I&TP FOR ELECTRICAL HEAT TRACING INSTALLATION EX-CO 210 12-01-2013 A4
300 Q06 Quality Assurance and Control 002506 00 D B QB 4037M P12020B4037M I&TP FOR BRAZING OF CABLE CONNECTIONS EX-DE 210 20-04-2013 A4
300 Q06 Quality Assurance and Control 002506 00 D B QB 4037M P12020B4037M I&TP FOR BRAZING OF CABLE CONNECTIONS EX-CO 210 20-04-2013 A4
301 Q06 Quality Assurance and Control 002506 00 D B QB 4038M P12020B4038M I&TP FOR FIELD MOUNTED INSTRUMENTS EX-DE 210 20-04-2013 A4
301 Q06 Quality Assurance and Control 002506 00 D B QB 4038M P12020B4038M I&TP FOR FIELD MOUNTED INSTRUMENTS EX-CO 210 20-04-2013 A4
302 Q06 Quality Assurance and Control 002506 00 D B QB 4039M P12020B4039M I&TP FOR INSTRUMENT CABLES INSTALLATION EX-DE 03 210 19-02-2013 A4
302 Q06 Quality Assurance and Control 002506 00 D B QB 4039M P12020B4039M I&TP FOR INSTRUMENT CABLES INSTALLATION EX-CO 00 210 19-02-2013 A4
303 Q06 Quality Assurance and Control 002506 00 D B QB 4040M P12020B4040M I&TP FOR INSTRUMENT INTERFACE PANELS & JUNCTION BOX INSTALLATION EX-DE 02 210 12-01-2013 A4
303 Q06 Quality Assurance and Control 002506 00 D B QB 4040M P12020B4040M I&TP FOR INSTRUMENT INTERFACE PANELS & JUNCTION BOX INSTALLATION EX-CO 00 210 12-01-2013 A4
304 Q06 Quality Assurance and Control 002506 00 D B QB 4041M P12020B4041M I&TP FOR INSTRUMENT PANELS, CONSOLE & DESKS INSTALLATION EX-DE 03 210 12-01-2013 A4
304 Q06 Quality Assurance and Control 002506 00 D B QB 4041M P12020B4041M I&TP FOR INSTRUMENT PANELS, CONSOLE & DESKS INSTALLATION EX-CO 00 210 12-01-2013 A4
305 Q06 Quality Assurance and Control 002506 00 D B QB 4042M P12020B4042M I&TP FOR FIBER OPTIC CABLES INSTALLATION EX-DE 02 210 12-01-2013 A4
305 Q06 Quality Assurance and Control 002506 00 D B QB 4042M P12020B4042M I&TP FOR FIBER OPTIC CABLES INSTALLATION EX-CO 00 210 12-01-2013 A4
306 Q06 Quality Assurance and Control 002506 00 D B QB 4043M P12020B4043M I&TP FOR FIRE & GAS DETECTION SYSTEM INSTALLATION EX-DE 03 210 19-02-2013 A4
306 Q06 Quality Assurance and Control 002506 00 D B QB 4043M P12020B4043M I&TP FOR FIRE & GAS DETECTION SYSTEM INSTALLATION EX-CO 00 210 19-02-2013 A4
307 Q06 Quality Assurance and Control 002506 00 D B QB 4044M P12020B4044M I&TP FOR INSTRUMENT CALIBRATION EX-DE 210 20-04-2013 A4
307 Q06 Quality Assurance and Control 002506 00 D B QB 4044M P12020B4044M I&TP FOR INSTRUMENT CALIBRATION EX-CO 210 20-04-2013 A4
308 Q06 Quality Assurance and Control 002506 00 D B QB 4045M P12020B4045M I&TP FOR INSTRUMENT LOOP CONTINUITY CHECK EX-DE 04 210 12-01-2013 A4
308 Q06 Quality Assurance and Control 002506 00 D B QB 4045M P12020B4045M I&TP FOR INSTRUMENT LOOP CONTINUITY CHECK EX-CO 00 210 12-01-2013 A4
309 Q06 Quality Assurance and Control 002506 00 D B QB 4046M P12020B4046M I&TP FOR PIPELINE INSTALLATION EX-DE 210 20-04-2013 A4
309 Q06 Quality Assurance and Control 002506 00 D B QB 4046M P12020B4046M I&TP FOR PIPELINE INSTALLATION EX-CO 210 20-04-2013 A4
310 Q06 Quality Assurance and Control 002506 00 D B QB 4047M P12020B4047M I&TP FOR CLEANING, GAUGING, HYDROTESTING,DEWATERING, DRYING & PURGING OF PIPELINE EX-DE 210 20-04-2013 A4
310 Q06 Quality Assurance and Control 002506 00 D B QB 4047M P12020B4047M I&TP FOR CLEANING, GAUGING, HYDROTESTING,DEWATERING, DRYING & PURGING OF PIPELINE EX-CO 210 20-04-2013 A4
311 Q06 Quality Assurance and Control 002506 00 D B QB 4048M P12020B4048M I&TP FOR PAINTING OF STEEL STRUCTURE EX-DE 210 20-04-2013 A4
311 Q06 Quality Assurance and Control 002506 00 D B QB 4048M P12020B4048M I&TP FOR PAINTING OF STEEL STRUCTURE EX-CO 210 20-04-2013 A4
312 Q06 Quality Assurance and Control 002506 00 D B QB 4049M P12020B4049M I&TP FOR PAINTING OF PIPING EX-DE 210 20-04-2013 A4
312 Q06 Quality Assurance and Control 002506 00 D B QB 4049M P12020B4049M I&TP FOR PAINTING OF PIPING EX-CO 210 20-04-2013 A4
313 N/A Quality Assurance and Control 002506 00 D B PV 4050M P12020B4050M STORAGE-CONTROL & DISTRIBUTION OF WELDING MATERIALS AT SITE EX-DE 00 210 10-01-2013 A4
313 N/A Quality Assurance and Control 002506 00 D B PV 4050M P12020B4050M STORAGE-CONTROL & DISTRIBUTION OF WELDING MATERIALS AT SITE EX-CO 00 210 10-01-2013 A4
314 N/A Quality Assurance and Control 002506 00 D B PS 4051M P12020B4051M WELDING MAP & WELDS RECORDING PROCEDURE EX-DE 01 210 20-04-2013 A4
314 N/A Quality Assurance and Control 002506 00 D B PS 4051M P12020B4051M WELDING MAP & WELDS RECORDING PROCEDURE EX-CO 00 210 20-04-2013 A4
316 N/A Quality Assurance and Control 002506 00 D B PC 4053M P12020B4053M STEEL STRUCTURE FABRICATION / INSTALLATION PROCEDURE EX-DE 01 210 09-01-2013 A4
316 N/A Quality Assurance and Control 002506 00 D B PC 4053M P12020B4053M STEEL STRUCTURE FABRICATION / INSTALLATION PROCEDURE EX-CO 00 210 09-01-2013 A4
317 N/A Quality Assurance and Control 002506 00 D B PC 4054M P12020B4054M STATIC EQUIPMENTS INSTALLATION PROCEDURE EX-DE 210 14-01-2013 A4
317 N/A Quality Assurance and Control 002506 00 D B PC 4054M P12020B4054M STATIC EQUIPMENTS INSTALLATION PROCEDURE EX-CO 210 14-01-2013 A4
318 N/A Quality Assurance and Control 002506 00 D B PC 4055M P12020B4055M ROTATING EQUIPMENTS INSTALLATION PROCEDURE EX-DE 210 14-01-2013 A4
318 N/A Quality Assurance and Control 002506 00 D B PC 4055M P12020B4055M ROTATING EQUIPMENTS INSTALLATION PROCEDURE EX-CO 210 14-01-2013 A4
319 N/A Quality Assurance and Control 002506 00 D B PF 4056M P12020B4056M PRESERVATION AND STORAGE OF PROJECT MATERIALS EX-DE 02 210 27-02-2013 A4
319 N/A Quality Assurance and Control 002506 00 D B PF 4056M P12020B4056M PRESERVATION AND STORAGE OF PROJECT MATERIALS EX-CO 00 210 27-02-2013 A4
320 N/A Quality Assurance and Control 002506 00 D B PC 4057M P12020B4057M GROUTING PROCEDURE EX-DE 01 210 09-01-2013 A4
320 N/A Quality Assurance and Control 002506 00 D B PC 4057M P12020B4057M GROUTING PROCEDURE EX-CO 00 210 09-01-2013 A4
321 N/A Quality Assurance and Control 002506 00 D B PC 4058M P12020B4058M PIPING - SANDBLASTING AND PAINTING PROCEDURE EX-DE 210 04-02-2013 A4
321 N/A Quality Assurance and Control 002506 00 D B PC 4058M P12020B4058M PIPING - SANDBLASTING AND PAINTING PROCEDURE EX-CO 210 04-02-2013 A4
322 N/A Quality Assurance and Control 002506 00 D B PC 4059M P12020B4059M STEEL STRUCTURE - SAND BLASTING AND PAINTING PROCEDURE EX-DE 00 210 04-02-2013 A4
322 N/A Quality Assurance and Control 002506 00 D B PC 4059M P12020B4059M STEEL STRUCTURE - SAND BLASTING AND PAINTING PROCEDURE EX-CO 00 210 04-02-2013 A4
323 N/A Quality Assurance and Control 002506 00 D B PV 4060M P12020B4060M PAINTING REPAIR PROCEDURE EX-DE 01 210 04-02-2013 A4
323 N/A Quality Assurance and Control 002506 00 D B PV 4060M P12020B4060M PAINTING REPAIR PROCEDURE EX-CO 00 210 04-02-2013 A4
324 N/A Quality Assurance and Control 002506 00 D B PC 4061M P12020B4061M UNDERGROUND ELECTRICAL / INSTRUMENT CABLE INSTALLATION PROCEDURE EX-DE 01 210 20-02-2013 A4
324 N/A Quality Assurance and Control 002506 00 D B PC 4061M P12020B4061M UNDERGROUND ELECTRICAL / INSTRUMENT CABLE INSTALLATION PROCEDURE EX-CO 00 210 20-02-2013 A4
325 N/A Quality Assurance and Control 002506 00 D B PC 4062M P12020B4062M ELECTRICAL / INSTRUMENT CABLE TRAYS- CONDUITS INSTALLATION PROCEDURE EX-DE 210 20-04-2013 A4
325 N/A Quality Assurance and Control 002506 00 D B PC 4062M P12020B4062M ELECTRICAL / INSTRUMENT CABLE TRAYS- CONDUITS INSTALLATION PROCEDURE EX-CO 210 20-04-2013 A4
326 N/A Quality Assurance and Control 002506 00 D B PC 4063M P12020B4063M JUNCTION BOX INSTALLATION PROCEDURE EX-DE 00 210 20-02-2013 A4
326 N/A Quality Assurance and Control 002506 00 D B PC 4063M P12020B4063M JUNCTION BOX INSTALLATION PROCEDURE EX-CO 00 210 20-02-2013 A4
327 N/A Quality Assurance and Control 002506 00 D B PV 4064M P12020B4064M INSTRUMENT CALIBRATION PROCEDURE EX-DE 01 210 20-02-2013 A4
327 N/A Quality Assurance and Control 002506 00 D B PV 4064M P12020B4064M INSTRUMENT CALIBRATION PROCEDURE EX-CO 00 210 20-02-2013 A4
328 N/A Quality Assurance and Control 002506 00 D B PV 4065M P12020B4065M PSV CALIBRATION PROCEDURE EX-DE 01 210 20-02-2013 A4
328 N/A Quality Assurance and Control 002506 00 D B PV 4065M P12020B4065M PSV CALIBRATION PROCEDURE EX-CO 00 210 20-02-2013 A4
329 N/A Quality Assurance and Control 002506 00 D B PC 4066M P12020B4066M PIPING PREFABRICATION & ERECTION PROCEDURE EX-DE 02 210 28-01-2013 A4
329 N/A Quality Assurance and Control 002506 00 D B PC 4066M P12020B4066M PIPING PREFABRICATION & ERECTION PROCEDURE EX-CO 00 210 28-01-2013 A4
330 N/A Quality Assurance and Control 002506 00 D B PC 4067M P12020B4067M UNDERGROUND PIPE INSTALLATION PROCEDURE EX-DE 01 210 04-02-2013 A4
330 N/A Quality Assurance and Control 002506 00 D B PC 4067M P12020B4067M UNDERGROUND PIPE INSTALLATION PROCEDURE EX-CO 00 210 04-02-2013 A4
331 N/A Quality Assurance and Control 002506 00 D B PC 4068M P12020B4068M TIE-IN INSTALLATION PROCEDURE EX-DE 210 20-04-2013 A4
331 N/A Quality Assurance and Control 002506 00 D B PC 4068M P12020B4068M TIE-IN INSTALLATION PROCEDURE EX-CO 210 20-04-2013 A4
332 N/A Quality Assurance and Control 002506 00 D B PS 4069M P12020B4069M TECHNICAL SURVEY PROCEDURE EX-DE 210 20-04-2013 A4
332 N/A Quality Assurance and Control 002506 00 D B PS 4069M P12020B4069M TECHNICAL SURVEY PROCEDURE EX-CO 210 20-04-2013 A4
333 N/A Quality Assurance and Control 002506 00 D B PC 4070M P12020B4070M PRE-CAST AND IN SITU CONCRETE PROCEDURE EX-DE 210 11-01-2013 A4
333 N/A Quality Assurance and Control 002506 00 D B PC 4070M P12020B4070M PRE-CAST AND IN SITU CONCRETE PROCEDURE EX-CO 00 210 11-01-2013 A4
334 N/A Quality Assurance and Control 002506 00 D B PC 4071M P12020B4071M CIVIL WORK PROCEDURE EX-DE 210 19-02-2013 A4
334 N/A Quality Assurance and Control 002506 00 D B PC 4071M P12020B4071M CIVIL WORK PROCEDURE EX-CO 00 210 19-02-2013 A4
335 N/A Quality Assurance and Control 002506 00 D B PC 4072M P12020B4072M WELDING BOOK INCLUDING WPS & PQR,s EX-DE 210 20-04-2013 A4
335 N/A Quality Assurance and Control 002506 00 D B PC 4072M P12020B4072M WELDING BOOK INCLUDING WPS & PQR,s EX-CO 210 20-04-2013 A4
336 N/A Quality Assurance and Control 002506 00 D B PC 4073M P12020B4073M CONSTRUCTION OF ROADS PROCEDURE EX-DE 00 210 19-02-2013 A4
336 N/A Quality Assurance and Control 002506 00 D B PC 4073M P12020B4073M CONSTRUCTION OF ROADS PROCEDURE EX-CO 00 210 19-02-2013 A4
338 N/A HSE (Health Safety & Environment) 002506 00 D F PA 4075M P12020F4075M HEALTH MANAGEMENT PLAN EX-DE 00 210 20-04-2013 A4
338 N/A HSE (Health Safety & Environment) 002506 00 D F PA 4075M P12020F4075M HEALTH MANAGEMENT PLAN EX-CO 00 210 20-04-2013 A4
339 N/A HSE (Health Safety & Environment) 002506 00 D F PA 4076M P12020F4076M HSE REPORTING PLAN EX-DE 210 20-04-2013 A4
339 N/A HSE (Health Safety & Environment) 002506 00 D F PA 4076M P12020F4076M HSE REPORTING PLAN EX-CO 210 20-04-2013 A4
340 N/A HSE (Health Safety & Environment) 002506 00 D F MO 4077M P12020F4077M PROJECT TRAINING PROGRAMME EX-DE 210 20-04-2013 A4
340 N/A HSE (Health Safety & Environment) 002506 00 D F MO 4077M P12020F4077M PROJECT TRAINING PROGRAMME EX-CO 210 20-04-2013 A4
341 N/A HSE (Health Safety & Environment) 002506 00 D F MS 4078M P12020F4078M HSE BRIDGING DOCUMENT EX-DE 210 20-04-2013 A4
341 N/A HSE (Health Safety & Environment) 002506 00 D F MS 4078M P12020F4078M HSE BRIDGING DOCUMENT EX-CO 210 20-04-2013 A4
342 N/A HSE (Health Safety & Environment) 002506 00 D F EA 4079M P12020F4079M LIST OF FIRE PROTECTION EQUIPMENT EX-DE 210 20-04-2013 A4
342 N/A HSE (Health Safety & Environment) 002506 00 D F EA 4079M P12020F4079M LIST OF FIRE PROTECTION EQUIPMENT EX-CO 210 20-04-2013 A4
343 N/A HSE (Health Safety & Environment) 002506 00 D F RS 4080M P12020F4080M HSE CLOSE-OUT REPORT EX-DE 210 20-04-2013 A4
343 N/A HSE (Health Safety & Environment) 002506 00 D F RS 4080M P12020F4080M HSE CLOSE-OUT REPORT EX-CO 210 20-04-2013 A4
360 K50 Electrical 002506 00 D E SF 5366M P12020E5366M MATERIAL REQUISITION FOR CATHODIC PROTECTION SYSTEM EX-CO 00 210 29-03-2013 A4
364 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5007M P12020I5007M MATERIAL REQUISITIONS FOR ORIFICE PLATE & RESTRICTION ORIFICE EX-CO 00 210 01-02-2013 A4
365 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5008M P12020I5008M MATERIAL REQUISITIONS FOR FLOW TRANSMITTER (DP) EX-CO 00 210 01-02-2013 A4
366 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5009M P12020I5009M MATERIAL REQUISITIONS FOR LEVEL GAUGE EX-CO 00 210 01-02-2013 A4
367 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5010M P12020I5010M MATERIAL REQUISITIONS FOR LEVEL TRANSMITTER EX-CO 00 210 01-02-2013 A4
368 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5011M P12020I5011M MATERIAL REQUISITIONS FOR LEVEL SWITCH EX-CO 00 210 01-02-2013 A4
369 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5012M P12020I5012M MATERIAL REQUISITIONS FOR PRESSURE TRANSMITTER EX-CO 00 210 01-02-2013 A4
370 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5013M P12020I5013M MATERIAL REQUISITIONS FOR PRESSURE GAUGE EX-CO 00 210 01-02-2013 A4
371 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5014M P12020I5014M MATERIAL REQUISITIONS FOR TEMPERATURE TRANSMITTER EX-CO 00 210 01-02-2013 A4
372 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5015M P12020I5015M MATERIAL REQUISITIONS FOR TEMPERATURE GAUGE EX-CO 00 210 01-02-2013 A4
373 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5016M P12020I5016M MATERIAL REQUISITIONS FOR ANALYZER EX-CO 00 210 01-02-2013 A4
374 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5017M P12020I5017M MATERIAL REQUISITIONS FOR PNEUMATIC CONTROL VALVE EX-CO 00 210 01-02-2013 A4
375 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5018M P12020I5018M MATERIAL REQUISITIONS FOR PRESSURE SAFETY VALVE EX-CO 00 210 01-02-2013 A4
376 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5019M P12020I5019M MATERIAL REQUISITIONS FOR ON-OFF VALVE EX-CO 00 210 01-02-2013 A4
377 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5020M P12020I5020M MATERIAL REQUISITIONS FOR BULK MATERIAL EX-CO 00 210 12/04/2013 A4
378 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5021M P12020I5021M MATERIAL REQUISITIONS FOR JUNCTION BOX EX-CO 00 210 12/04/2013 A4
380 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5023M P12020I5023M MATERIAL REQUISITIONS FOR ULTRASONIC FLOWMETER (316SS/CS) EX-CO 00 210 04-02-2013 A4
382 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5025M P12020I5025M MATERIAL REQUISITIONS FOR PRESSURE SWITCH EX-CO 00 210 01-02-2013 A4
384 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5027M P12020I5027M MATERIAL REQUISITIONS FOR MOTOR OPERATED VALVE EX-CO 00 210 01-02-2013 A4
386 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5029M P12020I5029M MATERIAL REQUISITIONS FOR LOCAL EQUIPMENT ROOM EX-CO 00 210 01-02-2013 A4
416 DB17 Plant layout and Piping 002506 00 D T SF 5001M P12020T5001M PIPING MATERIAL REQUISITION FOR SMLS CARBON STEEL PIPE EX-CO 00 210 29-03-2013 A4
417 DB17 Plant layout and Piping 002506 00 D T SF 5002M P12020T5002M PIPING MATERIAL REQUISITION FOR SMLS STAINLESS STEEL PIPE EX-CO 00 210 29-03-2013 A4
418 DB17 Plant layout and Piping 002506 00 D T SF 5004M P12020T5004M PIPING MATERIAL REQUISITION FOR FORGED FITTING EX-CO 00 210 29-03-2013 A4
419 DB17 Plant layout and Piping 002506 00 D T SF 5005M P12020T5005M PIPING MATERIAL REQUISITION FOR BUTT-WELDING FITTING EX-CO 00 210 29-03-2013 A4
420 DB17 Plant layout and Piping 002506 00 D T SF 5006M P12020T5006M PIPING MATERIAL REQUISITION FOR FLANGE EX-CO 00 210 29-03-2013 A4
421 DB17 Plant layout and Piping 002506 00 D T SF 5007M P12020T5007M PIPING MATERIAL REQUISITION FOR GASKET EX-CO 00 210 29-03-2013 A4
422 DB17 Plant layout and Piping 002506 00 D T SF 5009M P12020T5009M PIPING MATERIAL REQUISITION FOR FORGED VALVE EX-CO 00 210 29-03-2013 A4
423 DB17 Plant layout and Piping 002506 00 D T SF 5010M P12020T5010M PIPING MATERIAL REQUISITION FOR CASTING VALVE EX-CO 00 210 29-03-2013 A4
424 DB17 Plant layout and Piping 002506 00 D T SF 5011M P12020T5011M PIPING MATERIAL REQUISITION FOR BALL VALVE EX-CO 00 210 29-03-2013 A4
425 DB17 Plant layout and Piping 002506 00 D T SF 5012M P12020T5012M PIPING MATERIAL REQUISITION FOR BUTTERFLY VALVE EX-CO 00 210 29-03-2013 A4
426 DB17 Plant layout and Piping 002506 00 D T SF 5050M P12020T5050M PIPING MATERIAL REQUISITION FOR WO#3 PIPING EX-CO 00 210 29-03-2013 A4
428 DB17 Plant layout and Piping 002506 00 D T SF 5008M P12020T5008M PIPING MATERIAL REQUISITION FOR BOLT/NUTS EX-CO 00 210 29-03-2013 A4
429 DB17 Plant layout and Piping 002506 00 D T SF 5014M P12020T5014M PIPING MATERIAL REQUISITION FOR STRAINER EX-CO 00 210 29-03-2013 A4
431 N/A Interdisciplinary and Miscellaneous 002506 00 D G PL 0016M P12020G0016M LEVEL 3 PROJECT SCHEDULE FOR WORK ORDER 1,2,3 EX-DE 210 20-04-2013 A4
431 N/A Interdisciplinary and Miscellaneous 002506 00 D G PL 0016M P12020G0016M LEVEL 3 PROJECT SCHEDULE FOR WORK ORDER 1,2,3 EX-CO 210 20-04-2013 A4
432 N/A Interdisciplinary and Miscellaneous 002506 00 D G PL 0015M P12020G0015M LEVEL 4 PROJECT SCHEDULE FOR WORK ORDER 1,2,3 EX-DE 210 20-04-2013 A4
432 N/A Interdisciplinary and Miscellaneous 002506 00 D G PL 0015M P12020G0015M LEVEL 4 PROJECT SCHEDULE FOR WORK ORDER 1,2,3 EX-CO 210 20-04-2013 A4
433 R13 Quality Assurance and Control 002506 00 D B QB 2023M P12020B2023M GENERAL WELDING PROCEDURE EX-DE 210 18-01-2013 A4
433 R13 Quality Assurance and Control 002506 00 D B QB 2023M P12020B2023M GENERAL WELDING PROCEDURE EX-CO 210 18-01-2013 A4
434 R13 Quality Assurance and Control 002506 00 D B QB 2024M P12020B2024M WELDING REPAIR PROCEDURE EX-DE 210 18-01-2013 A4
434 R13 Quality Assurance and Control 002506 00 D B QB 2024M P12020B2024M WELDING REPAIR PROCEDURE EX-CO 210 18-01-2013 A4
435 K02 Electrical 002506 00 D E FU 0142M P12020E0142M ELECTRICAL SYMBOLS AND LEGEND EX-DE 00 210 20-12-2012 A4
435 K02 Electrical 002506 00 D E FU 0142M P12020E0142M ELECTRICAL SYMBOLS AND LEGEND EX-CO 02 210 20-12-2012 A4
436 N/A Construction and erection/installation 002506 00 D J PC 0009M P12020J0009M CONSTRUCTION EXECUTION PLAN EX-DE 00 210 04-12-2012 A3
436 N/A Construction and erection/installation 002506 00 D J PC 0009M P12020J0009M CONSTRUCTION EXECUTION PLAN EX-CO 01 210 04-12-2012 A3
437 N/A Interdisciplinary and Miscellaneous 002506 00 D G ED 0006M P12020G0006M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 4 - FIRE FIGHTING SYSTEM) EX-DE 05 210 18-02-2013 A4
437 N/A Interdisciplinary and Miscellaneous 002506 00 D G ED 0006M P12020G0006M DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 4 - FIRE FIGHTING SYSTEM) EX-CO 01 210 18-02-2013 A4
438 N/A HSE (Health Safety & Environment) 002506 00 D F RB 0040M P12020F0040M LOSS PREVENTION & ENVIRONMENT PHILOSOPHY (Adeendum) EX-DE 210 04-01-2013 A4
438 N/A HSE (Health Safety & Environment) 002506 00 D F RB 0040M P12020F0040M LOSS PREVENTION & ENVIRONMENT PHILOSOPHY (Adeendum) EX-CO 210 04-01-2013 A4
439 N/A Quality Assurance and Control 002506 00 D B QB 2008M P12020B2008M PIPING PRESSURE TEST PROCEDURE EX-DE 210 15-01-2013 A4
439 N/A Quality Assurance and Control 002506 00 D B QB 2008M P12020B2008M PIPING PRESSURE TEST PROCEDURE EX-CO 210 15-01-2013 A4
440 N/A Quality Assurance and Control 002506 00 D B QB 4081M P12020B4081M INSPECTION AND TEST PLAN FOR VESSEL INSTALLATION EX-DE 210 18-01-2013 A4
440 N/A Quality Assurance and Control 002506 00 D B QB 4081M P12020B4081M INSPECTION AND TEST PLAN FOR VESSEL INSTALLATION EX-CO 210 18-01-2013 A4
441 N/A Quality Assurance and Control 002506 00 D B QB 4082M P12020B4082M INSPECTION AND TEST PLAN FOR HEAT EXCHANGER INSTALLATION EX-DE 210 18-01-2013 A4
441 N/A Quality Assurance and Control 002506 00 D B QB 4082M P12020B4082M INSPECTION AND TEST PLAN FOR HEAT EXCHANGER INSTALLATION EX-CO 210 18-01-2013 A4
442 N/A Quality Assurance and Control 002506 00 D B QB 4083M P12020B4083M INSPECTION AND TEST PLAN FOR FILTER INSTALLATION EX-DE 210 18-01-2013 A4
442 N/A Quality Assurance and Control 002506 00 D B QB 4083M P12020B4083M INSPECTION AND TEST PLAN FOR FILTER INSTALLATION EX-CO 210 18-01-2013 A4
443 N/A Quality Assurance and Control 002506 00 D B QB 4084M P12020B4084M INSPECTION AND TEST PLAN FOR SKID & PACKAGE INSTALLATION EX-DE 210 18-01-2013 A4
443 N/A Quality Assurance and Control 002506 00 D B QB 4084M P12020B4084M INSPECTION AND TEST PLAN FOR SKID & PACKAGE INSTALLATION EX-CO 210 18-01-2013 A4
444 N/A Quality Assurance and Control 002506 00 D B QB 4085M P12020B4085M INSPECTION AND TEST PLAN FOR PUMP INSTALLATION EX-DE 210 18-01-2013 A4
444 N/A Quality Assurance and Control 002506 00 D B QB 4085M P12020B4085M INSPECTION AND TEST PLAN FOR PUMP INSTALLATION EX-CO 210 18-01-2013 A4
445 N/A Quality Assurance and Control 002506 00 D B QB 4086M P12020B4086M INSPECTION AND TEST PLAN FOR COMPRESSOR INSTALLATION EX-DE 210 18-01-2013 A4
445 N/A Quality Assurance and Control 002506 00 D B QB 4086M P12020B4086M INSPECTION AND TEST PLAN FOR COMPRESSOR INSTALLATION EX-CO 210 18-01-2013 A4
446 N/A Quality Assurance and Control 002506 00 D B QB 4087M P12020B4087M INSPECTION AND TEST PLAN FOR BLOWER INSTALLATION EX-DE 210 18-01-2013 A4
446 N/A Quality Assurance and Control 002506 00 D B QB 4087M P12020B4087M INSPECTION AND TEST PLAN FOR BLOWER INSTALLATION EX-CO 210 18-01-2013 A4
447 EC02 Corrosion and materials selection 002506 00 D X RV 0002M P12020X0002M Material Selection Report for Produced Water Treatment Package EX-DE 210 05-04-2013 A4
447 EC02 Corrosion and materials selection 002506 00 D X RV 0002M P12020X0002M Material Selection Report for Produced Water Treatment Package EX-CO 210 05-04-2013 A4
448 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5071M P12020I5071M MATERIAL REQUISITIONS FOR LIMIT SWITCH EX-CO 00 210 01-02-2013 A4
449 N/A Plant layout and Piping 002506 00 D T GB 5070M P12020T5070M PLANT GASKETS INSPECTION DATA SHEET EX-CO 00 210 28-01-2013 A4
450 N/A Plant layout and Piping 002506 00 D T GB 5069M P12020T5069M PLANT STUD BOLTS AND NUTS INSPECTION DATA SHEET EX-CO 00 210 28-01-2013 A4
451 N/A Plant layout and Piping 002506 00 D T GB 5071M P12020T5071M PLANT STRAINERS INSPECTION DATA SHEET EX-CO 00 210 28-01-2013 A4
452 N/A Plant layout and Piping 002506 00 D T GC 5073M P12020T5073M PLANT GASKETS REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 28-01-2013 A4
453 N/A Plant layout and Piping 002506 00 D T GC 5072M P12020T5072M PLANT STUD BOLTS AND NUTS REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 28-01-2013 A4
454 N/A Plant layout and Piping 002506 00 D T GC 5074M P12020T5074M PLANT STRAINERS REQUIRED DOCUMENT DATA SHEET EX-CO 00 210 28/01/2013 A4
455 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5031M P12020I5031M MATERIAL REQUISTIONS FOR SIGNAL CONVERTER EX-CO 00 210 04/02/2013 A4
456 N/A Logistic 002506 00 D H RV 1001M P12020H1001M PROCUREMENT STATUS REPORT A EX-DE 210 Every week A4
456 N/A Logistic 002506 00 D H RV 1001M P12020H1001M PROCUREMENT STATUS REPORT A EX-CO 210 Every week A4
457 N/A Logistic 002506 00 D H RV 1002M P12020H1002M PROCUREMENT STATUS REPORT B EX-DE 210 Every week A4
457 N/A Logistic 002506 00 D H RV 1002M P12020H1002M PROCUREMENT STATUS REPORT B EX-CO 210 Every week A4
460 HA44 Instrumentation, Control and Automation 002506 01 D I EI 0092M P12020I0092M TYPICAL LOOP WIRING (BROWNFIELD) EX-DE 210 12/04/2013 A4
460 HA44 Instrumentation, Control and Automation 002506 01 D I EI 0092M P12020I0092M TYPICAL LOOP WIRING (BROWNFIELD) EX-CO 210 12/04/2013 A4
461 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5072M P12020I5072M MATERIAL REQUISITIONS FOR CORROSION COUPON EX-CO 00 210 12/04/2013 A4
462 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5073M P12020I5073M MATERIAL REQUISITIONS FOR MIXING VALVE EX-CO 00 210 26/04/2013 A4 00250600DISF5073M
463 HA42 Instrumentation, Control and Automation 002506 00 D I DQ 5074M P12020I5074M INSTRUMENT TYPICAL INSTALLATION DETAIL DRAWING EX-DE 00 210 01/04/2013 A4
463 HA42 Instrumentation, Control and Automation 002506 00 D I DQ 5074M P12020I5074M INSTRUMENT TYPICAL INSTALLATION DETAIL DRAWING EX-CO 01 210 01/04/2013 A4
464 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5075M P12020I5075M MATERIAL REQUISITIONS FOR CHOKE VALVE EX-CO 00 210 26/04/2013 A4
465 HA50 Instrumentation, Control and Automation 002506 00 D I DQ 5076M P12020I5076M TYPICAL INSTRUMENT ELECTRICAL HOOK-UP DRAWINGS EX-DE 00 210 26/04/2013 A4
465 HA50 Instrumentation, Control and Automation 002506 00 D I DQ 5076M P12020I5076M TYPICAL INSTRUMENT ELECTRICAL HOOK-UP DRAWINGS EX-CO 02 210 26/04/2013 A4
466 HA04 Instrumentation, Control and Automation 002506 00 D I GA 5077M P12020I5077M DATA SHEET FOR INSTRUMENT CABLE EX-DE 01 210 17/04/2013 A4
466 HA04 Instrumentation, Control and Automation 002506 00 D I GA 5077M P12020I5077M DATA SHEET FOR INSTRUMENT CABLE EX-CO 04 210 17/04/2013 A4
468 N/A Quality Assurance and Control 002506 00 D B QR 2023M P12020B2023M Shop Notification of Inspection EX-DE 210 15/04/2013 A4
468 N/A Quality Assurance and Control 002506 00 D B QR 2023M P12020B2023M Shop Notification of Inspection EX-CO 210 15/04/2013 A4
469 DB11 Plant layout and Piping 002506 00 D T DQ 5075M P12020T5075M TYPICAL SUPPORTS FOR PIPING AND EQUIPMENT EX-DE 210 28-01-2013 A4
469 DB11 Plant layout and Piping 002506 00 D T DQ 5075M P12020T5075M TYPICAL SUPPORTS FOR PIPING AND EQUIPMENT EX-CO 00 210 28-01-2013 A4
470 N/A HSE (Health Safety & Environment) 002506 00 D F ST 0041M P12020F0041M FIREPROOFING SPECIFICATION EX-DE 00 210 20-04-2013 A4
470 N/A HSE (Health Safety & Environment) 002506 00 D F ST 0041M P12020F0041M FIREPROOFING SPECIFICATION EX-CO 00 210 20-04-2013 A4
471 N/A Quality Assurance and Control 002506 00 D B PC 4081M P12020E4081M PROCEDURE FOR EARTHING & LIGHTNING SYSTEM INSTALLATION EX-DE 01 210 30/05/2013 A4
471 N/A Quality Assurance and Control 002506 00 D B PC 4081M P12020E4081M PROCEDURE FOR EARTHING & LIGHTNING SYSTEM INSTALLATION EX-CO 00 210 30/05/2013 A4
472 N/A Electrical 002506 00 D E PC 4082M P12020E4082M PROCEDURE FOR LIGHTING SYSTEM INSTALLATION EX-DE 210 20/08/2013 A4
472 N/A Electrical 002506 00 D E PC 4082M P12020E4082M PROCEDURE FOR LIGHTING SYSTEM INSTALLATION EX-CO 210 20/08/2013 A4
473 N/A Quality Assurance and Control 002506 00 D B PC 4083M P12020E4083M PROCEDURE FOR ELECTRICAL & INSTRUMENT EQUIPMENT INSTALLATION EX-DE 01 210 30/05/2013 A4
473 N/A Quality Assurance and Control 002506 00 D B PC 4083M P12020E4083M PROCEDURE FOR ELECTRICAL & INSTRUMENT EQUIPMENT INSTALLATION EX-CO 00 210 30/05/2013 A4
474 N/A Electrical 002506 00 D E PC 4084M P12020E4084M PROCEDURE FOR FIBER OPTICAL CABLE EX-DE 210 30/05/2013 A4
474 N/A Electrical 002506 00 D E PC 4084M P12020E4084M PROCEDURE FOR FIBER OPTICAL CABLE EX-CO 210 30/05/2013 A4
475 N/A Quality Assurance and Control 002506 00 D B PC 4085M P12020E4085M PROCEDURE FOR FIRE & GAS DETECTION SYSTEM EX-DE 00 210 30/05/2013 A4
475 N/A Quality Assurance and Control 002506 00 D B PC 4085M P12020E4085M PROCEDURE FOR FIRE & GAS DETECTION SYSTEM EX-CO 00 210 30/05/2013 A4
476 N/A Quality Assurance and Control 002506 00 D B PC 4087M P12020E4087M PROCEDURE FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION EX-DE 00 210 25/06/2013 A4
476 N/A Quality Assurance and Control 002506 00 D B PC 4087M P12020E4087M PROCEDURE FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION EX-CO 00 210 25/06/2013 A4
477 N/A Electrical 002506 00 D E PC 4602M P12020E4602M METHOD STATEMENT OF UNDER & ABOVE GROUND ELECTRICAL & INSTRUMENT CABLE INSTALLATION EX-DE 00 210 20/08/2013 A4
477 N/A Electrical 002506 00 D E PC 4602M P12020E4602M METHOD STATEMENT OF UNDER & ABOVE GROUND ELECTRICAL & INSTRUMENT CABLE INSTALLATION EX-CO 00 210 20/08/2013 A4
478 N/A Electrical 002506 00 D E PC 4600M P12020E4600M METHOD STATEMENT OF EARTHING WORK EX-DE 01 210 05/08/2013 A4
478 N/A Electrical 002506 00 D E PC 4600M P12020E4600M METHOD STATEMENT OF EARTHING WORK EX-CO 00 210 05/08/2013 A4
479 N/A Electrical 002506 00 D E PC 4601M P12020E4601M METHOD STATEMENT OF CATHODIC PROTECTION SYSTEM INSTALLATION WORK EX-DE 01 210 05/08/2013 A4
479 N/A Electrical 002506 00 D E PC 4601M P12020E4601M METHOD STATEMENT OF CATHODIC PROTECTION SYSTEM INSTALLATION WORK EX-CO 00 210 05/08/2013 A4
480 N/A Electrical 002506 00 D B PC 4083M P12020E4604M METHOD STATEMENT OF ELECTRICAL EQUIPMENT INSTALLATION WORK EX-DE 01 210 15/09/2013 A4
480 N/A Electrical 002506 00 D B PC 4083M P12020E4604M METHOD STATEMENT OF ELECTRICAL EQUIPMENT INSTALLATION WORK EX-CO 00 210 15/09/2013 A4
481 N/A Electrical 002506 00 D E PC 4603M P12020E4603M METHOD STATEMENT OF CABLE RACEWAY INSTALLATION WORK EX-DE 210 15/09/2013 A4
481 N/A Electrical 002506 00 D E PC 4603M P12020E4603M METHOD STATEMENT OF CABLE RACEWAY INSTALLATION WORK EX-CO 210 15/09/2013 A4
482 N/A Electrical 002506 00 D E PC 4605M P12020E4605M METHOD STATEMENT OF CABLING & WIRING WORK EX-DE 210 15/09/2013 A4
482 N/A Electrical 002506 00 D E PC 4605M P12020E4605M METHOD STATEMENT OF CABLING & WIRING WORK EX-CO 210 15/09/2013 A4
483 N/A Electrical 002506 00 D E PC 4606M P12020E4606M METHOD STATEMENT OF LIGHTING INSTALLATION WORK EX-DE 210 15/09/2013 A4
483 N/A Electrical 002506 00 D E PC 4606M P12020E4606M METHOD STATEMENT OF LIGHTING INSTALLATION WORK EX-CO 210 15/09/2013 A4
484 N/A Electrical 002506 00 D E PC 4607M P12020E4607M METHOD STATEMENT OF INSTRUMENT INSTALLATION WORK EX-DE 210 30/09/2013 A4
484 N/A Electrical 002506 00 D E PC 4607M P12020E4607M METHOD STATEMENT OF INSTRUMENT INSTALLATION WORK EX-CO 210 30/09/2013 A4
485 N/A Electrical 002506 00 D E PC 4608M P12020E4608M METHOD STATEMENT OF IMPULSE TUBING WORK EX-DE 210 30/09/2013 A4
485 N/A Electrical 002506 00 D E PC 4608M P12020E4608M METHOD STATEMENT OF IMPULSE TUBING WORK EX-CO 210 30/09/2013 A4
486 N/A Electrical 002506 00 D E PC 4609M P12020E4609M METHOD STATEMENT OF FIRE & GAS DETECTION INSTALLATION WORK EX-DE 210 30/09/2013 A4
486 N/A Electrical 002506 00 D E PC 4609M P12020E4609M METHOD STATEMENT OF FIRE & GAS DETECTION INSTALLATION WORK EX-CO 210 30/09/2013 A4
487 N/A Quality Assurance and Control 002506 00 D B PC 4086M P12020B4086M PROCEDURE FOR INSULATION INSTALLATION EX-DE 00 210 24/05/2013 A4
487 N/A Quality Assurance and Control 002506 00 D B PC 4086M P12020B4086M PROCEDURE FOR INSULATION INSTALLATION EX-CO 00 210 24/05/2013 A4
488 N/A Quality Assurance and Control 002506 00 D B PC 4400M P12020B4400M PROCEDURE FOR HYDROSTATIC TEST EX-DE 00 210 30/09/2013 A4 deleted by eni instruction
488 N/A Quality Assurance and Control 002506 00 D B PC 4400M P12020B4400M PROCEDURE FOR HYDROSTATIC TEST EX-CO 210 30/09/2013 A4 deleted by eni instruction
489 N/A Quality Assurance and Control 002506 00 D B PC 4401M P12020B4401M PROCEDURE FOR PRE-COMMISSIONING EX-DE 210 31/10/2013 A4 deleted by eni instruction
489 N/A Quality Assurance and Control 002506 00 D B PC 4401M P12020B4401M PROCEDURE FOR PRE-COMMISSIONING EX-CO 210 31/10/2013 A4 deleted by eni instruction
490 N/A Plant layout and Piping 002506 00 D T PC 4202M P12020T4202M METHOD STATEMENT FOR STEEL PIPE INSTALLATION EX-DE 01 210 20/06/2013 A4
490 N/A Plant layout and Piping 002506 00 D T PC 4202M P12020T4202M METHOD STATEMENT FOR STEEL PIPE INSTALLATION EX-CO 00 210 20/06/2013 A4
491 N/A Civil and Architectural 002509 01 D A PC 4101M P12020A4101M METHOD STATEMENT FOR STEEL STRUCTURE ERECTION EX-DE 210 21/06/2013 A4
491 N/A Civil and Architectural 002509 01 D A PC 4101M P12020A4101M METHOD STATEMENT FOR STEEL STRUCTURE ERECTION EX-CO 210 21/06/2013 A4
492 N/A Quality Assurance and Control 002510 01 D J PC 4402M P12020J4402M METHOD STATEMENT FOR DESALTER / DEHYDRATOR - ZUBAIR MISHRIF EX-DE 210 15/09/2013 A4
492 N/A Quality Assurance and Control 002510 01 D J PC 4402M P12020J4402M METHOD STATEMENT FOR DESALTER / DEHYDRATOR - ZUBAIR MISHRIF EX-CO 210 15/09/2013 A4
493 N/A Quality Assurance and Control 002512 01 D J PC 4403M P12020J4403M METHOD STATEMENT FOR DESALTER / DEHYDRATOR - HAMMAR MISHRIF EX-DE 210 15/09/2013 A4
493 N/A Quality Assurance and Control 002512 01 D J PC 4403M P12020J4403M METHOD STATEMENT FOR DESALTER / DEHYDRATOR - HAMMAR MISHRIF EX-CO 210 15/09/2013 A4
494 N/A Quality Assurance and Control 002510 01 D J PC 4404M P12020J4404M METHOD STATEMENT FOR WATER TANK ERECTION - ZUBAIR MISHRIF EX-DE 210 30/08/2013 A4
494 N/A Quality Assurance and Control 002510 01 D J PC 4404M P12020J4404M METHOD STATEMENT FOR WATER TANK ERECTION - ZUBAIR MISHRIF EX-CO 210 30/08/2013 A4
495 N/A Quality Assurance and Control 002512 01 D J PC 4405M P12020J4405M METHOD STATEMENT FOR WATER TANK ERECTION - HAMMAR MISHRIF EX-DE 210 30/08/2013 A4
495 N/A Quality Assurance and Control 002512 01 D J PC 4405M P12020J4405M METHOD STATEMENT FOR WATER TANK ERECTION - HAMMAR MISHRIF EX-CO 210 30/08/2013 A4
496 N/A Plant layout and Piping 002506 00 D T PC METHOD STATEMENT FOR HYDROSTATIC TEST OF NORTH SATELLITE EX-DE 210 30/09/2013 A4
496 N/A Plant layout and Piping 002506 00 D T PC METHOD STATEMENT FOR HYDROSTATIC TEST OF NORTH SATELLITE EX-CO 210 30/09/2013 A4
497 N/A Plant layout and Piping 002506 00 D T PC 4501M P12020T4501M METHOD STATEMENT FOR HYDROSTATIC TEST OF LOWER MIDDLE SATELLITE EX-DE 210 30/09/2013 A4
497 N/A Plant layout and Piping 002506 00 D T PC 4501M P12020T4501M METHOD STATEMENT FOR HYDROSTATIC TEST OF LOWER MIDDLE SATELLITE EX-CO 210 30/09/2013 A4
498 N/A Plant layout and Piping 002506 00 D T PC 4502M P12020T4502M METHOD STATEMENT FOR HYDROSTATIC TEST OF SOUTH SATELLITE EX-DE 210 30/09/2013 A4
498 N/A Plant layout and Piping 002506 00 D T PC 4502M P12020T4502M METHOD STATEMENT FOR HYDROSTATIC TEST OF SOUTH SATELLITE EX-CO 210 30/09/2013 A4
499 N/A Plant layout and Piping 002506 00 D T PC 4503M P12020T4503M METHOD STATEMENT FOR TIE-IN - ZUBAIR MISHRIF EX-DE 210 30/08/2013 A4
499 N/A Plant layout and Piping 002506 00 D T PC 4503M P12020T4503M METHOD STATEMENT FOR TIE-IN - ZUBAIR MISHRIF EX-CO 210 30/08/2013 A4
500 N/A Plant layout and Piping 002506 00 D T PC 4504M P12020T4504M METHOD STATEMENT FOR TIE-IN - HAMMAR MISHRIF EX-DE 210 30/08/2013 A4
500 N/A Plant layout and Piping 002506 00 D T PC 4504M P12020T4504M METHOD STATEMENT FOR TIE-IN - HAMMAR MISHRIF EX-CO 210 30/08/2013 A4
501 N/A Plant layout and Piping 002506 00 D T PC 4505M P12020T4505M METHOD STATEMENT FOR HYDROTEST OF TIE-IN - ZUBAIR MISHRIF EX-DE 210 30/09/2013 A4
501 N/A Plant layout and Piping 002506 00 D T PC 4505M P12020T4505M METHOD STATEMENT FOR HYDROTEST OF TIE-IN - ZUBAIR MISHRIF EX-CO 210 30/09/2013 A4
502 N/A Plant layout and Piping 002506 00 D T PC 4506M P12020T4506M METHOD STATEMENT FOR HYDROTEST OF TIE-IN - HAMMAR MISHRIF EX-DE 210 30/09/2013 A4
502 N/A Plant layout and Piping 002506 00 D T PC 4506M P12020T4506M METHOD STATEMENT FOR HYDROTEST OF TIE-IN - HAMMAR MISHRIF EX-CO 210 30/09/2013 A4
503 N/A Quality Assurance and Control 002506 00 D J PC 4406M P12020J4406M METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - ZUBAIR MISHRIF EX-DE 210 30/09/2013 A4
503 N/A Quality Assurance and Control 002506 00 D J PC 4406M P12020J4406M METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - ZUBAIR MISHRIF EX-CO 210 30/09/2013 A4
504 N/A Quality Assurance and Control 002506 00 D J PC 4407M P12020J4407M METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - HAMMAR MISHRIF EX-DE 210 30/09/2013 A4
504 N/A Quality Assurance and Control 002506 00 D J PC 4407M P12020J4407M METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - HAMMAR MISHRIF EX-CO 210 30/09/2013 A4
505 N/A Quality Assurance and Control 002506 00 D J PC 4408M P12020J4408M METHOD STATEMENT FOR PGI EQUIPMENT - HAMMAR MISHRIF EX-DE 210 30/09/2013 A4
505 N/A Quality Assurance and Control 002506 00 D J PC 4408M P12020J4408M METHOD STATEMENT FOR PGI EQUIPMENT - HAMMAR MISHRIF EX-CO 210 30/09/2013 A4
506 N/A Quality Assurance and Control 002506 00 D J PC 4409M P12020J4409M METHOD STATEMENT FOR PGI EQUIPMENT - ZUBAIR MISHRIF EX-DE 210 30/09/2013 A4
506 N/A Quality Assurance and Control 002506 00 D J PC 4409M P12020J4409M METHOD STATEMENT FOR PGI EQUIPMENT - ZUBAIR MISHRIF EX-CO 210 30/09/2013 A4
507 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3023M 12020F3023M CONTROL AND USE OF PLANTS AND EQUIPMENT PROCEDURE EX-DE 00 210 30/10/2013 A4
507 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3023M 12020F3023M CONTROL AND USE OF PLANTS AND EQUIPMENT PROCEDURE EX-CO 00 210 30/10/2013 A4
508 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3024M 12020F3024M COMPRESSED GAS CYLINDER STORAGE, TRANSPORTATION AND USE PROCEDURE EX-DE 00 210 30/10/2013 A4
508 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3024M 12020F3024M COMPRESSED GAS CYLINDER STORAGE, TRANSPORTATION AND USE PROCEDURE EX-CO 00 210 30/10/2013 A4
509 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3025M 12020F3025M HAND AND POWER TOOLS PROCEDURE EX-DE 00 210 30/10/2013 A4
509 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3025M 12020F3025M HAND AND POWER TOOLS PROCEDURE EX-CO 00 210 30/10/2013 A4
510 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3026M 12020F3026M HAZARD COMMUNICATION (COSHH) PROCEDURE EX-DE 00 210 30/10/2013 A4
510 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3026M 12020F3026M HAZARD COMMUNICATION (COSHH) PROCEDURE EX-CO 00 210 30/10/2013 A4
511 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3027M 12020F3027M HEARING CONSERVATION PROCEDURE EX-DE 00 210 30/10/2013 A4
511 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3027M 12020F3027M HEARING CONSERVATION PROCEDURE EX-CO 00 210 30/10/2013 A4
512 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3028M 12020F3028M HEAT-COLD STRESS PROCEDURE EX-DE 00 210 30/10/2013 A4
512 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3028M 12020F3028M HEAT-COLD STRESS PROCEDURE EX-CO 00 210 30/10/2013 A4
513 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3029M 12020F3029M HOUSEKEEPING PROCEDURE EX-DE 00 210 30/10/2013 A4
513 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3029M 12020F3029M HOUSEKEEPING PROCEDURE EX-CO 00 210 30/10/2013 A4
514 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3030M 12020F3030M MANUAL HANDLING PROCEDURE EX-DE 00 210 30/10/2013 A4
514 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3030M 12020F3030M MANUAL HANDLING PROCEDURE EX-CO 00 210 30/10/2013 A4
515 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3031M 12020F3031M MATERIAL SAFETY DATA AND HAZARD ASSESSMENT PROCEDURE EX-DE 00 210 30/10/2013 A4
515 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3031M 12020F3031M MATERIAL SAFETY DATA AND HAZARD ASSESSMENT PROCEDURE EX-CO 00 210 30/10/2013 A4
516 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3032M 12020F3032M TEMPORARY ELECTRICS PROCEDURE EX-DE 00 210 30/10/2013 A4
516 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3032M 12020F3032M TEMPORARY ELECTRICS PROCEDURE EX-CO 00 210 30/10/2013 A4
517 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3033M 12020F3033M TOOLBOX TALKS PROCEDURE EX-DE 00 210 30/10/2013 A4
517 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3033M 12020F3033M TOOLBOX TALKS PROCEDURE EX-CO 00 210 30/10/2013 A4
518 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3034M 12020F3034M WARNING SIGNS AND BARRIERS PROCEDURE EX-DE 00 210 30/10/2013 A4
518 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3034M 12020F3034M WARNING SIGNS AND BARRIERS PROCEDURE EX-CO 00 210 30/10/2013 A4
519 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3035M 12020F3035M WORKING AT HEIGHT PROCEDURE EX-DE 00 210 30/10/2013 A4
519 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3035M 12020F3035M WORKING AT HEIGHT PROCEDURE EX-CO 00 210 30/10/2013 A4
520 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5078M P12020I5078M MATERIAL REQUISITIONS FOR LOCAL CONTROLLER EX-CO 00 210 A4 moved to WO#2
521 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5079M P12020I5079M MATERIAL REQUISITIONS FOR LOCAL CONTROL PANEL EX-CO 00 210 A4
522 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5076M P12020I5076M MATERIAL REQUISITIONS FOR SIGHT GLASS EX-CO 00 210 A4
523 R06 HSE (Health Safety & Environment) 002506 00 D V SF 7900M 12020V7900M MATERIAL REQUISION FOR FIRE EXTINGUISHER EX-CO 00 210 A4
524 N/A Quality Assurance and Control 002506 00 D B QR 4088M P12020B4088M BITUMEN EMULSION PROTECTIVE COATING DATA SHEET EX-DE 00 210 A4
524 N/A Quality Assurance and Control 002506 00 D B QR 4088M P12020B4088M BITUMEN EMULSION PROTECTIVE COATING DATA SHEET EX-CO 00 210 A4
525 N/A Quality Assurance and Control 002506 00 D B QR 4089M P12020B4089M CONTROL OF MEASURING EQUIPMENT EX-DE 210 A4
525 N/A Quality Assurance and Control 002506 00 D B QR 4089M P12020B4089M CONTROL OF MEASURING EQUIPMENT EX-CO 210 A4
526 N/A Quality Assurance and Control 002506 00 D B QR 4090M P12020B4090M CURING COMPOUND DATA SHEET EX-DE 00 210 A4
526 N/A Quality Assurance and Control 002506 00 D B QR 4090M P12020B4090M CURING COMPOUND DATA SHEET EX-CO 00 210 A4
527 N/A Quality Assurance and Control 002506 00 D B QR 4091M P12020B4091M FOSROC NITOSEAL PU 40 POLYURETHANE SEALANT DATA SHEET EX-DE 00 210 A4
527 N/A Quality Assurance and Control 002506 00 D B QR 4091M P12020B4091M FOSROC NITOSEAL PU 40 POLYURETHANE SEALANT DATA SHEET EX-CO 00 210 A4
528 N/A Quality Assurance and Control 002506 00 D B QR 4092M P12020B4092M GROUTING FOR THE PEDESTAL AND ANCHOR BOLTS DATA SHEET EX-DE 210 A4
528 N/A Quality Assurance and Control 002506 00 D B QR 4092M P12020B4092M GROUTING FOR THE PEDESTAL AND ANCHOR BOLTS DATA SHEET EX-CO 210 A4
529 N/A Quality Assurance and Control 002506 00 D B QB 4093M P12020B4093M INSPECTION AND TESTING PROCEDURE EX-DE 210 A4
529 N/A Quality Assurance and Control 002506 00 D B QB 4093M P12020B4093M INSPECTION AND TESTING PROCEDURE EX-CO 210 A4
530 N/A Quality Assurance and Control 002506 00 D B QB 4094M P12020B4094M INSPECTION AND TEST PLAN FOR BLINDING CONCRETE EX-DE 210 A4
530 N/A Quality Assurance and Control 002506 00 D B QB 4094M P12020B4094M INSPECTION AND TEST PLAN FOR BLINDING CONCRETE EX-CO 210 A4
531 N/A Quality Assurance and Control 002506 00 D B QB 4095M P12020B4095M INSPECTION AND TEST PLAN FOR EARTHWORKS FOR UNDERGROUND SERVICE EX-DE 00 210 A4
531 N/A Quality Assurance and Control 002506 00 D B QB 4095M P12020B4095M INSPECTION AND TEST PLAN FOR EARTHWORKS FOR UNDERGROUND SERVICE EX-CO 00 210 A4
532 N/A Quality Assurance and Control 002506 00 D B QB 4096M P12020B4096M INSPECTION AND TEST PLAN FOR ROADS CONSTRUCTION EX-DE 00 210 A4
532 N/A Quality Assurance and Control 002506 00 D B QB 4096M P12020B4096M INSPECTION AND TEST PLAN FOR ROADS CONSTRUCTION EX-CO 00 210 A4
533 N/A Quality Assurance and Control 002506 00 D B QR 4097M P12020B4097M MATERIAL CONTROL AT SITE PROCEDURE EX-DE 00 210 A4 deleted by eni instruction
533 N/A Quality Assurance and Control 002506 00 D B QR 4097M P12020B4097M MATERIAL CONTROL AT SITE PROCEDURE EX-CO 210 A4 deleted by eni instruction
534 N/A Quality Assurance and Control 002506 00 D B QR 4098M P12020B4098M PAINTING AND TOUCH UP PROCEDURE EX-DE 01 210 A4
534 N/A Quality Assurance and Control 002506 00 D B QR 4098M P12020B4098M PAINTING AND TOUCH UP PROCEDURE EX-CO 00 210 A4
535 N/A Quality Assurance and Control 002506 00 D B QR 4099M P12020B4099M PROCEDURE FOR COORDINATION AT CONSTRUCTION SITES EX-DE 00 210 A4
535 N/A Quality Assurance and Control 002506 00 D B QR 4099M P12020B4099M PROCEDURE FOR COORDINATION AT CONSTRUCTION SITES EX-CO 00 210 A4
536 N/A Quality Assurance and Control 002506 00 D B QR 4800M P12020B4800M PROCEDURE FOR STORAGE, HANDLING AND ISSUANCE OF WELDING CONSUMABLES EX-DE 00 210 A4 deleted by eni instruction
536 N/A Quality Assurance and Control 002506 00 D B QR 4800M P12020B4800M PROCEDURE FOR STORAGE, HANDLING AND ISSUANCE OF WELDING CONSUMABLES EX-CO 210 A4 deleted by eni instruction
537 N/A Quality Assurance and Control 002506 00 D B QR 4801M P12020B4801M PROTECTIVE EPOXY RESIN COATING DATA SHEET EX-DE 00 210 A4 deleted by eni instruction
537 N/A Quality Assurance and Control 002506 00 D B QR 4801M P12020B4801M PROTECTIVE EPOXY RESIN COATING DATA SHEET EX-CO 210 A4 deleted by eni instruction
538 N/A Quality Assurance and Control 002506 00 D B QR 4802M P12020B4802M READ BOAD-SBR CHEMICAL ADDITIVES FOR CEMENT EX-DE 00 210 A4
538 N/A Quality Assurance and Control 002506 00 D B QR 4802M P12020B4802M READ BOAD-SBR CHEMICAL ADDITIVES FOR CEMENT EX-CO 00 210 A4
539 N/A Quality Assurance and Control 002506 00 D B QR 4803M P12020B4803M RECEIVING & INSPECTION MATERALS - I&TP EX-DE 00 210 A4 deleted by eni instruction
539 N/A Quality Assurance and Control 002506 00 D B QR 4803M P12020B4803M RECEIVING & INSPECTION MATERALS - I&TP EX-CO 210 A4 deleted by eni instruction
540 N/A Quality Assurance and Control 002506 00 D B QR 4804M P12020B4804M SITE QUERY AND DEVIATION REQUEST EX-DE 00 210 A4
540 N/A Quality Assurance and Control 002506 00 D B QR 4804M P12020B4804M SITE QUERY AND DEVIATION REQUEST EX-CO 00 210 A4
541 N/A Quality Assurance and Control 002506 00 D B QR 4805M P12020B4805M SUBCONTRACTORS CONTROL PROCEDURE EX-DE 210 A4
541 N/A Quality Assurance and Control 002506 00 D B QR 4805M P12020B4805M SUBCONTRACTORS CONTROL PROCEDURE EX-CO 210 A4
542 N/A Quality Assurance and Control 002506 00 D B QR 4806M P12020B4806M VISUAL INSPECTION EX-DE 00 210 A4 deleted by eni instruction
542 N/A Quality Assurance and Control 002506 00 D B QR 4806M P12020B4806M VISUAL INSPECTION EX-CO 210 A4 deleted by eni instruction
543 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3036M P12020B3036M AERIAL WORK PLATFORMS PROCEDURE EX-DE 00 210 A4
543 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3036M P12020B3036M AERIAL WORK PLATFORMS PROCEDURE EX-CO 00 210 A4
544 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3037M P12020B3037M CAMP MANAGEMENT PLAN EX-DE 01 210 A4
544 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3037M P12020B3037M CAMP MANAGEMENT PLAN EX-CO 00 210 A4
545 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3038M P12020B3038M ELECTRICAL SAFETY PROCEDURE EX-DE 00 210 A4
545 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3038M P12020B3038M ELECTRICAL SAFETY PROCEDURE EX-CO 00 210 A4
546 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3039M P12020B3039M ENERGY ISOLATION PROCESS PROCEDURE EX-DE 00 210 A4
546 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3039M P12020B3039M ENERGY ISOLATION PROCESS PROCEDURE EX-CO 00 210 A4
547 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3040M P12020B3040M ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN EX-DE 00 210 A4
547 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3040M P12020B3040M ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN EX-CO 00 210 A4
548 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3041M P12020B3041M FOOD SAFETY AND CATERING PROCEDURE EX-DE 00 210 A4
548 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3041M P12020B3041M FOOD SAFETY AND CATERING PROCEDURE EX-CO 00 210 A4
549 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3042M P12020B3042M HSE STATISTICS REPORTING PROCEDURE EX-DE 00 210 A4
549 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3042M P12020B3042M HSE STATISTICS REPORTING PROCEDURE EX-CO 00 210 A4
550 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3043M P12020B3043M MANAGEMENT OF CHANGE (MOC) PROCEDURE EX-DE 00 210 A4
550 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3043M P12020B3043M MANAGEMENT OF CHANGE (MOC) PROCEDURE EX-CO 00 210 A4
551 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3044M P12020B3044M NIGHT WORKS PROCEDURE EX-DE 00 210 A4
551 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3044M P12020B3044M NIGHT WORKS PROCEDURE EX-CO 00 210 A4
552 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3045M P12020B3045M PNEUMATIC TESTING PROCEDURE EX-DE 00 210 A4
552 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3045M P12020B3045M PNEUMATIC TESTING PROCEDURE EX-CO 00 210 A4
553 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3046M P12020B3046M RADIOGRAPHY PLAN EX-DE 01 210 A4
553 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3046M P12020B3046M RADIOGRAPHY PLAN EX-CO 00 210 A4
554 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3047M P12020B3047M SIMULTANEOUS OPERATIONS (SIMOPS) PROCEDURE EX-DE 00 210 A4
554 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3047M P12020B3047M SIMULTANEOUS OPERATIONS (SIMOPS) PROCEDURE EX-CO 00 210 A4
555 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3048M P12020B3048M SPILL RESPONSE PROCEDURE EX-DE 00 210 A4
555 R06 HSE (Health Safety & Environment) 002506 00 D F PV 3048M P12020B3048M SPILL RESPONSE PROCEDURE EX-CO 00 210 A4
556 N/A Plant layout and Piping 002506 00 D T PC 1001M P12020T1001M METHOD STATEMENT FOR PIPING SHOP FABRICATION EX-DE 01 210 A4
556 N/A Plant layout and Piping 002506 00 D T PC 1001M P12020T1001M METHOD STATEMENT FOR PIPING SHOP FABRICATION EX-CO 00 210 A4
557 N/A Quality Assurance and Control 002506 00 D B QR 3049M P12020B3049M PAINTING – DATA SHEET FOR ZINC PRIMER (ORGANIC) EX-DE 210 A4
557 N/A Quality Assurance and Control 002506 00 D B QR 3049M P12020B3049M PAINTING – DATA SHEET FOR ZINC PRIMER (ORGANIC) EX-CO 210 A4
558 N/A Quality Assurance and Control 002506 00 D B QR 3050M P12020B3050M PAINTING – DATA SHEET FOR EPOXY PHENOLIC EX-DE 210 A4
558 N/A Quality Assurance and Control 002506 00 D B QR 3050M P12020B3050M PAINTING – DATA SHEET FOR EPOXY PHENOLIC EX-CO 210 A4
559 N/A Quality Assurance and Control 002506 00 D B QR 3051M P12020B3051M PAINTING – DATA SHEET FOR POLYURETHANE TOPCOAT EX-DE 210 A4
559 N/A Quality Assurance and Control 002506 00 D B QR 3051M P12020B3051M PAINTING – DATA SHEET FOR POLYURETHANE TOPCOAT EX-CO 210 A4
560 N/A Quality Assurance and Control 002506 00 D B PV 3052M P12020B3052M GENERAL MAGNETIC PARTICLE TESTING PROCEDURE For Al-bilal EX-DE 00 210 A4
560 N/A Quality Assurance and Control 002506 00 D B PV 3052M P12020B3052M GENERAL MAGNETIC PARTICLE TESTING PROCEDURE For Al-bilal EX-CO 00 210 A4
561 N/A Quality Assurance and Control 002506 00 D B QR 3053M P12020B3053M PAINTING – DATA SHEET FOR EPOXY MODIFIED EX-DE 210 A4
561 N/A Quality Assurance and Control 002506 00 D B QR 3053M P12020B3053M PAINTING – DATA SHEET FOR EPOXY MODIFIED EX-CO 210 A4
562 N/A Quality Assurance and Control 002506 00 D B PV 3054M P12020B3054M GENERAL LIQUID PENETRANT TESTING PROCEDURE For Al-bilal EX-DE 00 210 A4
562 N/A Quality Assurance and Control 002506 00 D B PV 3054M P12020B3054M GENERAL LIQUID PENETRANT TESTING PROCEDURE For Al-bilal EX-CO 00 210 A4
563 N/A Quality Assurance and Control 002506 00 D B QR 3055M P12020B3055M PAINTING – DATA SHEET FOR EPOXY UNDERCOAT EX-DE 210 A4
563 N/A Quality Assurance and Control 002506 00 D B QR 3055M P12020B3055M PAINTING – DATA SHEET FOR EPOXY UNDERCOAT EX-CO 210 A4
564 N/A Quality Assurance and Control 002506 00 D B QR 3056M P12020B3056M PAINTING – DATA SHEET FOR EPOXY PRIMER EX-DE 210 A4
564 N/A Quality Assurance and Control 002506 00 D B QR 3056M P12020B3056M PAINTING – DATA SHEET FOR EPOXY PRIMER EX-CO 210 A4
565 N/A Quality Assurance and Control 002506 00 D B QR 3057M P12020B3057M PAINTING – DATA SHEET FOR ZINC PRIMER (INORGANIC) EX-DE 210 A4
565 N/A Quality Assurance and Control 002506 00 D B QR 3057M P12020B3057M PAINTING – DATA SHEET FOR ZINC PRIMER (INORGANIC) EX-CO 210 A4
566 N/A Quality Assurance and Control 002506 00 D B PV 3058M P12020B3058M GENERAL RADIOGRAPHIC TESTING PROCEDURE For Al-bilal EX-DE 00 210 A4
566 N/A Quality Assurance and Control 002506 00 D B PV 3058M P12020B3058M GENERAL RADIOGRAPHIC TESTING PROCEDURE For Al-bilal EX-CO 00 210 A4
567 N/A Quality Assurance and Control 002506 00 D B QR 3059M P12020B3059M PAINTING – DATA SHEET FOR SILICONE EX-DE 210 A4
567 N/A Quality Assurance and Control 002506 00 D B QR 3059M P12020B3059M PAINTING – DATA SHEET FOR SILICONE EX-CO 210 A4
568 N/A Quality Assurance and Control 002506 00 D B QR 3060M P12020B3060M PAINTING – DATA SHEET FOR WATER TREATED TANK (EXTERNAL) EX-DE 210 A4
568 N/A Quality Assurance and Control 002506 00 D B QR 3060M P12020B3060M PAINTING – DATA SHEET FOR WATER TREATED TANK (EXTERNAL) EX-CO 210 A4
569 N/A Quality Assurance and Control 002506 00 D B PV 3061M P12020B3061M GENERAL ULTRASONIC TESTING PROCEDURE For Al-bilal EX-DE 00 210 A4
569 N/A Quality Assurance and Control 002506 00 D B PV 3061M P12020B3061M GENERAL ULTRASONIC TESTING PROCEDURE For Al-bilal EX-CO 00 210 A4
570 N/A Quality Assurance and Control 002506 00 D B PV 3062M P12020B3062M WELDING VISUAL INSPECTION PROCEDURE For Al-bilal EX-DE 00 210 A4
570 N/A Quality Assurance and Control 002506 00 D B PV 3062M P12020B3062M WELDING VISUAL INSPECTION PROCEDURE For Al-bilal EX-CO 00 210 A4
571 HA50 Instrumentation, Control and Automation 002506 00 D I SF 5081M P12020I5081M MATERIAL REQUISITIONS FOR SELF REGULATING VALVE EX-CO 00 210 A4 moved to WO#1
572 HA50 Civil and Architectural 002506 00 D A DB 9801M P12020A9801M MINOR FOUNDATION & STRUCTURAL DETAILS FOR MISCELLANEOUS ITEMS EX-DE 00 210 A4
572 HA50 Civil and Architectural 002506 00 D A DB 9801M P12020A9801M MINOR FOUNDATION & STRUCTURAL DETAILS FOR MISCELLANEOUS ITEMS EX-CO 01 210 A4
573 HA50 Civil and Architectural 002506 00 D A CC 9802M P12020A9802M CALCULATION REPORT FOR MISCELLANEOUS ITEMS EX-DE 00 210 A4
573 HA50 Civil and Architectural 002506 00 D A CC 9802M P12020A9802M CALCULATION REPORT FOR MISCELLANEOUS ITEMS EX-CO 01 210 A4
574 N/A Quality Assurance and Control 002506 00 D B PV 3063M P12020B3063M NDT PROCEDURE EX-DE 210 A4
574 N/A Quality Assurance and Control 002506 00 D B PV 3063M P12020B3063M NDT PROCEDURE EX-CO 210 A4
575 N/A Quality Assurance and Control 002506 00 D B SS 3064M P12020B3064M INSPECTION AND TEST PLAN FOR NDT EX-DE 210 A4
575 N/A Quality Assurance and Control 002506 00 D B SS 3064M P12020B3064M INSPECTION AND TEST PLAN FOR NDT EX-CO 210 A4
576 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3065M P12020B3065M Journey Management Procedure EX-DE 00 210 A4
576 N/A HSE (Health Safety & Environment) 002506 00 D F PV 3065M P12020B3065M Journey Management Procedure EX-CO 00 210 A4
577 N/A Quality Assurance and Control 002512 00 D B QR 8000M P12020B8000M HAMMAR MISHRIF - HYDROTEST PACKAGE FOR LP Flaring System (SS 2006;PKG-001) EX-DE 210 A4
577 N/A Quality Assurance and Control 002512 00 D B QR 8000M P12020B8000M HAMMAR MISHRIF - HYDROTEST PACKAGE FOR LP Flaring System (SS 2006;PKG-001) EX-CO 210 A4
578 N/A Quality Assurance and Control 002506 00 D B QR 8001M P12020B8001M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-03 ;PKG No.002) EX-DE 210 A4
578 N/A Quality Assurance and Control 002506 00 D B QR 8001M P12020B8001M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-03 ;PKG No.002) EX-CO 210 A4
579 N/A Quality Assurance and Control 002506 00 D B QR 8002M P12020B8002M HYDROTEST PACKAGE FOR Dehydrator Unit (SS-2001/CO-01; PKG No. 003) EX-DE 210 A4
579 N/A Quality Assurance and Control 002506 00 D B QR 8002M P12020B8002M HYDROTEST PACKAGE FOR Dehydrator Unit (SS-2001/CO-01; PKG No. 003) EX-CO 210 A4
580 N/A Quality Assurance and Control 002506 00 D B QR 8003M P12020B8003M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-04;PKG No.004) EX-DE 210 A4
580 N/A Quality Assurance and Control 002506 00 D B QR 8003M P12020B8003M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-04;PKG No.004) EX-CO 210 A4
581 N/A Quality Assurance and Control 002506 00 D B QR 8004M P12020B8004M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CO-06;PKG No. 005) EX-DE 210 A4
581 N/A Quality Assurance and Control 002506 00 D B QR 8004M P12020B8004M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CO-06;PKG No. 005) EX-CO 210 A4
582 N/A Quality Assurance and Control 002506 00 D B QR 8005M P12020B8005M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-01;PKG No. 006) EX-DE 210 A4
582 N/A Quality Assurance and Control 002506 00 D B QR 8005M P12020B8005M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-01;PKG No. 006) EX-CO 210 A4
583 N/A Quality Assurance and Control 002506 00 D B QR 8006M P12020B8006M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-03; PKG No. 007) EX-DE 210 A4
583 N/A Quality Assurance and Control 002506 00 D B QR 8006M P12020B8006M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-03; PKG No. 007) EX-CO 210 A4
584 N/A Quality Assurance and Control 002506 00 D B QR 8007M P12020B8007M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-05;PKG No. 008) EX-DE 210 A4
584 N/A Quality Assurance and Control 002506 00 D B QR 8007M P12020B8007M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-05;PKG No. 008) EX-CO 210 A4
585 N/A Quality Assurance and Control 002506 00 D B QR 8008M P12020B8008M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-06 ;PKG No.009) EX-DE 210 A4
585 N/A Quality Assurance and Control 002506 00 D B QR 8008M P12020B8008M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-06 ;PKG No.009) EX-CO 210 A4
586 N/A Quality Assurance and Control 002506 00 D B QR 8009M P12020B8009M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CD-08 ;PKG No.010) EX-DE 210 A4
586 N/A Quality Assurance and Control 002506 00 D B QR 8009M P12020B8009M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CD-08 ;PKG No.010) EX-CO 210 A4
587 N/A Quality Assurance and Control 002506 00 D B QR 8010M P12020B8010M HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-02 ;PKG No.011) EX-DE 210 A4
587 N/A Quality Assurance and Control 002506 00 D B QR 8010M P12020B8010M HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-02 ;PKG No.011) EX-CO 210 A4
588 N/A Quality Assurance and Control 002506 00 D B QR 8011M P12020B8011M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-07 ;PKG No.012) EX-DE 210 A4
588 N/A Quality Assurance and Control 002506 00 D B QR 8011M P12020B8011M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-07 ;PKG No.012) EX-CO 210 A4
589 N/A Quality Assurance and Control 002506 00 D B QR 8012M P12020B8012M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-01;PKG No.013) EX-DE 210 A4
589 N/A Quality Assurance and Control 002506 00 D B QR 8012M P12020B8012M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-01;PKG No.013) EX-CO 210 A4
590 N/A Quality Assurance and Control 002506 00 D B QR 8013M P12020B8013M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-04;PKG No. 014) EX-DE 210 A4
590 N/A Quality Assurance and Control 002506 00 D B QR 8013M P12020B8013M HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-04;PKG No. 014) EX-CO 210 A4
591 N/A Quality Assurance and Control 002506 00 D B QR 8014M P12020B8014M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-02;PKG No.015) EX-DE 210 A4
591 N/A Quality Assurance and Control 002506 00 D B QR 8014M P12020B8014M HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-02;PKG No.015) EX-CO 210 A4
592 N/A Quality Assurance and Control 002506 00 D B QR 8015M P12020B8015M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-010 ;PKG No.016) EX-DE 210 A4
592 N/A Quality Assurance and Control 002506 00 D B QR 8015M P12020B8015M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-010 ;PKG No.016) EX-CO 210 A4
593 N/A Quality Assurance and Control 002506 00 D B QR 8016M P12020B8016M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/IW-01;PKG No.017) EX-DE 210 A4
593 N/A Quality Assurance and Control 002506 00 D B QR 8016M P12020B8016M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/IW-01;PKG No.017) EX-CO 210 A4
594 N/A Quality Assurance and Control 002506 00 D B QR 8017M P12020B8017M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-08;PKG No.018) EX-DE 210 A4
594 N/A Quality Assurance and Control 002506 00 D B QR 8017M P12020B8017M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-08;PKG No.018) EX-CO 210 A4
595 N/A Quality Assurance and Control 002506 00 D B QR 8018M P12020B8018M HYDROTEST PACKAGE FOR Instrument Air System (SS 3002/IA-01;PKG No.019) EX-DE 210 A4
595 N/A Quality Assurance and Control 002506 00 D B QR 8018M P12020B8018M HYDROTEST PACKAGE FOR Instrument Air System (SS 3002/IA-01;PKG No.019) EX-CO 210 A4
596 N/A Quality Assurance and Control 002506 00 D B QR 8019M P12020B8019M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-07;PKG No.020) EX-DE 210 A4
596 N/A Quality Assurance and Control 002506 00 D B QR 8019M P12020B8019M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-07;PKG No.020) EX-CO 210 A4
597 N/A Quality Assurance and Control 002506 00 D B QR 8020M P12020B8020M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-09 ;PKG No.021) EX-DE 210 A4
597 N/A Quality Assurance and Control 002506 00 D B QR 8020M P12020B8020M HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-09 ;PKG No.021) EX-CO 210 A4
598 N/A Quality Assurance and Control 002506 00 D B QR 8021M P12020B8021M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-02;PKG No.022) EX-DE 210 A4
598 N/A Quality Assurance and Control 002506 00 D B QR 8021M P12020B8021M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-02;PKG No.022) EX-CO 210 A4
599 N/A Quality Assurance and Control 002506 00 D B QR 8022M P12020B8022M HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-01 ;PKG No.023) EX-DE 210 A4
599 N/A Quality Assurance and Control 002506 00 D B QR 8022M P12020B8022M HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-01 ;PKG No.023) EX-CO 210 A4
600 N/A Quality Assurance and Control 002506 00 D B QR 8023M P12020B8023M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-03;PKG No.024) EX-DE 210 A4
600 N/A Quality Assurance and Control 002506 00 D B QR 8023M P12020B8023M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-03;PKG No.024) EX-CO 210 A4
601 N/A Quality Assurance and Control 002506 00 D B QR 8024M P12020B8024M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-01;PKG No.025) EX-DE 210 A4
601 N/A Quality Assurance and Control 002506 00 D B QR 8024M P12020B8024M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-01;PKG No.025) EX-CO 210 A4
602 N/A Quality Assurance and Control 002506 00 D B QR 8025M P12020B8025M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-02;PKG No.026) EX-DE 210 A4
602 N/A Quality Assurance and Control 002506 00 D B QR 8025M P12020B8025M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-02;PKG No.026) EX-CO 210 A4
603 N/A Quality Assurance and Control 002506 00 D B QR 8026M P12020B8026M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-03;PKG No.027) EX-DE 210 A4
603 N/A Quality Assurance and Control 002506 00 D B QR 8026M P12020B8026M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-03;PKG No.027) EX-CO 210 A4
604 N/A Quality Assurance and Control 002506 00 D B QR 8027M P12020B8027M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/SL-01;PKG No.028) EX-DE 210 A4
604 N/A Quality Assurance and Control 002506 00 D B QR 8027M P12020B8027M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/SL-01;PKG No.028) EX-CO 210 A4
605 N/A Quality Assurance and Control 002506 00 D B QR 8028M P12020B8028M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/UN-01;PKG No.029) EX-DE 210 A4
605 N/A Quality Assurance and Control 002506 00 D B QR 8028M P12020B8028M HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/UN-01;PKG No.029) EX-CO 210 A4
606 N/A Quality Assurance and Control 002506 00 D B QR 8029M P12020B8029M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-01;PKG No.030) EX-DE 210 A4
606 N/A Quality Assurance and Control 002506 00 D B QR 8029M P12020B8029M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-01;PKG No.030) EX-CO 210 A4
607 N/A Quality Assurance and Control 002506 00 D B QR 8030M P12020B8030M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-02;PKG No.031) EX-DE 210 A4
607 N/A Quality Assurance and Control 002506 00 D B QR 8030M P12020B8030M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-02;PKG No.031) EX-CO 210 A4
608 N/A Quality Assurance and Control 002506 00 D B QR 8031M P12020B8031M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-03;PKG No.032) EX-DE 210 A4
608 N/A Quality Assurance and Control 002506 00 D B QR 8031M P12020B8031M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-03;PKG No.032) EX-CO 210 A4
609 N/A Quality Assurance and Control 002506 00 D B QR 8032M P12020B8032M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-04;PKG No.033) EX-DE 210 A4
609 N/A Quality Assurance and Control 002506 00 D B QR 8032M P12020B8032M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-04;PKG No.033) EX-CO 210 A4
610 N/A Quality Assurance and Control 002506 00 D B QR 8033M P12020B8033M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-05;PKG No.034) EX-DE 210 A4
610 N/A Quality Assurance and Control 002506 00 D B QR 8033M P12020B8033M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-05;PKG No.034) EX-CO 210 A4
611 N/A Quality Assurance and Control 002506 00 D B QR 8034M P12020B8034M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-06;PKG No.035) EX-DE 210 A4
611 N/A Quality Assurance and Control 002506 00 D B QR 8034M P12020B8034M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-06;PKG No.035) EX-CO 210 A4
612 N/A Quality Assurance and Control 002506 00 D B QR 8035M P12020B8035M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-07;PKG No.036) EX-DE 210 A4
612 N/A Quality Assurance and Control 002506 00 D B QR 8035M P12020B8035M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-07;PKG No.036) EX-CO 210 A4
613 N/A Quality Assurance and Control 002506 00 D B QR 8036M P12020B8036M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-08;PKG No.037) EX-DE 210 A4
613 N/A Quality Assurance and Control 002506 00 D B QR 8036M P12020B8036M HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-08;PKG No.037) EX-CO 210 A4
614 N/A Quality Assurance and Control 002506 00 D B QR 8037M P12020B8037M HYDROTEST PACKAGE FOR Wash Water Pump/Economizer(SS 3001/IW-02;PKG No.038) EX-DE 210 A4
614 N/A Quality Assurance and Control 002506 00 D B QR 8037M P12020B8037M HYDROTEST PACKAGE FOR Wash Water Pump/Economizer(SS 3001/IW-02;PKG No.038) EX-CO 210 A4
615 N/A Quality Assurance and Control 002506 00 D B QR 8038M P12020B8038M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-04;PKG No.039) EX-DE 210 A4
615 N/A Quality Assurance and Control 002506 00 D B QR 8038M P12020B8038M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-04;PKG No.039) EX-CO 210 A4
616 N/A Quality Assurance and Control 002506 00 D B QR 8039M P12020B8039M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-05;PKG No.040) EX-DE 210 A4
616 N/A Quality Assurance and Control 002506 00 D B QR 8039M P12020B8039M HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-05;PKG No.040) EX-CO 210 A4
617 N/A Quality Assurance and Control 002506 00 D B QR 8040M P12020B8040M BUTT AND/OR FILLET WELD- PIPE TO PIPE, PIPE TO PUP AND PIPE TO FITTINGS PIPING WELDING (WPS NO: AD-SS-02 Rev.00) EX-DE 00 210 A4
617 N/A Quality Assurance and Control 002506 00 D B QR 8040M P12020B8040M BUTT AND/OR FILLET WELD- PIPE TO PIPE, PIPE TO PUP AND PIPE TO FITTINGS PIPING WELDING (WPS NO: AD-SS-02 Rev.00) EX-CO 00 210 A4
618 N/A Quality Assurance and Control 002506 00 D B QR 8041M P12020B8041M HYDROTEST PACKAGE FOR Treated Water Tank (Tank No.002510015550TA001) EX-DE 210 A4
618 N/A Quality Assurance and Control 002506 00 D B QR 8041M P12020B8041M HYDROTEST PACKAGE FOR Treated Water Tank (Tank No.002510015550TA001) EX-CO 210 A4
619 N/A Quality Assurance and Control 002506 00 D B QR 8042M P12020B8042M HYDROTEST PACKAGE FOR Treated Water Tank (Tank No..002512015550TA001) EX-DE 210 A4
619 N/A Quality Assurance and Control 002506 00 D B QR 8042M P12020B8042M HYDROTEST PACKAGE FOR Treated Water Tank (Tank No..002512015550TA001) EX-CO 210 A4
620 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9000M P12020W9000M PUNCH LIST FOR WO#1 EX-DE 210 A4 moved to WO#1
620 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9000M P12020W9000M PUNCH LIST FOR WO#1 EX-CO 210 A4 moved to WO#1
621 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9001M P12020W9001M PUNCH LIST FOR WO#2 EX-DE 210 A4 moved to WO#2
621 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9001M P12020W9001M PUNCH LIST FOR WO#2 EX-CO 210 A4 moved to WO#2
622 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9002M P12020W9002M PUNCH LIST FOR WO#3 EX-DE 210 A4 moved to WO#3
622 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9002M P12020W9002M PUNCH LIST FOR WO#3 EX-CO 210 A4 moved to WO#3
623 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9003M P12020W9003M PUNCH LIST FOR WO#4 EX-DE 210 A4 moved to WO#4
623 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9003M P12020W9003M PUNCH LIST FOR WO#4 EX-CO 210 A4 moved to WO#4
624 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9004M P12020W9004M CHEMICAL LOADING PROCEDURE - anti-scaling EX-DE 210 A4 deleted by eni instruction
624 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9004M P12020W9004M CHEMICAL LOADING PROCEDURE - anti-scaling EX-CO 210 A4 deleted by eni instruction
625 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9005M P12020W9005M CHEMICAL LOADING PROCEDURE - Corrosion Inhibitor EX-DE 210 A4 deleted by eni instruction
625 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9005M P12020W9005M CHEMICAL LOADING PROCEDURE - Corrosion Inhibitor EX-CO 210 A4 deleted by eni instruction
626 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9006M P12020W9006M CHEMICAL LOADING PROCEDURE - Demulsfier EX-DE 210 A4 deleted by eni instruction
626 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9006M P12020W9006M CHEMICAL LOADING PROCEDURE - Demulsfier EX-CO 210 A4 deleted by eni instruction
627 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9007M P12020W9007M CHEMICAL LOADING PROCEDURE - DIESEL EX-DE 210 A4 deleted by eni instruction
627 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9007M P12020W9007M CHEMICAL LOADING PROCEDURE - DIESEL EX-CO 210 A4 deleted by eni instruction
628 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9009M P12020W9009M COMMISSIONING PERMIT TO WORK (PTW) PROCEDURE EX-DE 210 A4 deleted by eni instruction
628 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9009M P12020W9009M COMMISSIONING PERMIT TO WORK (PTW) PROCEDURE EX-CO 210 A4 deleted by eni instruction
629 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9010M P12020W9010M COMMISSIONING PROCEDURE EX-DE 00 210 A4 moved to WO#1
629 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9010M P12020W9010M COMMISSIONING PROCEDURE EX-CO 210 A4 moved to WO#1
630 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9011M P12020W9011M COMMISSIONING TEAM ORGANIZATION CHART EX-DE 01 210 A4 moved to WO#1
630 N/A Precommissioning,commissioning and test run 002506 00 D W PP 9011M P12020W9011M COMMISSIONING TEAM ORGANIZATION CHART EX-CO 210 A4 moved to WO#1
631 N/A Precommissioning,commissioning and test run 002506 00 D W EA 9012M P12020W9012M COMMISSIONING TOOLS & EQUIPMENTS LIST EX-DE 210 A4
631 N/A Precommissioning,commissioning and test run 002506 00 D W EA 9012M P12020W9012M COMMISSIONING TOOLS & EQUIPMENTS LIST EX-CO 210 A4
632 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9013M P12020W9013M GENERAL LEAK TESTING & INERTING PROCEDURE EX-DE 00 210 A4
632 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9013M P12020W9013M GENERAL LEAK TESTING & INERTING PROCEDURE EX-CO 210 A4
633 N/A Precommissioning,commissioning and test run 002506 00 D W QE 9014M P12020W9014M HANDOVER CERTIFICATES READY FOR COMMISSIONING AND READY FOR STARTUP EX-DE 210 A4
633 N/A Precommissioning,commissioning and test run 002506 00 D W QE 9014M P12020W9014M HANDOVER CERTIFICATES READY FOR COMMISSIONING AND READY FOR STARTUP EX-CO 210 A4
634 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9015M P12020W9015M ISOLATION POINTS MANAGEMENT EX-DE 00 210 A4
634 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9015M P12020W9015M ISOLATION POINTS MANAGEMENT EX-CO 210 A4
635 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9016M P12020W9016M OPERATIONAL TEST LIST EX-DE 00 210 A4 deleted by eni instruction
635 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9016M P12020W9016M OPERATIONAL TEST LIST EX-CO 210 A4 deleted by eni instruction
636 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9017M P12020W9017M OTP (Operational Test Procedure) of Corrosion Inhibitor Injection Unit. EX-DE 210 A4 deleted by eni instruction
636 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9017M P12020W9017M OTP (Operational Test Procedure) of Corrosion Inhibitor Injection Unit. EX-CO 210 A4 deleted by eni instruction
637 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9018M P12020W9018M OTP (Operational Test Procedure) of Dehydrator Package. EX-DE 210 A4 moved to WO#1
637 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9018M P12020W9018M OTP (Operational Test Procedure) of Dehydrator Package. EX-CO 210 A4 moved to WO#1
638 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9019M P12020W9019M OTP (Operational Test Procedure) of Desalter Package. EX-DE 210 A4 deleted by eni instruction
638 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9019M P12020W9019M OTP (Operational Test Procedure) of Desalter Package. EX-CO 210 A4 deleted by eni instruction
639 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9020M P12020W9020M OTP (Operational Test Procedure) of Emulsifier Inhibitor Injection Unit. EX-DE 210 A4 deleted by eni instruction
639 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9020M P12020W9020M OTP (Operational Test Procedure) of Emulsifier Inhibitor Injection Unit. EX-CO 210 A4 deleted by eni instruction
640 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9021M P12020W9021M OTP (Operational Test Procedure) of Oil Pump. EX-DE 210 A4 moved to WO#1
640 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9021M P12020W9021M OTP (Operational Test Procedure) of Oil Pump. EX-CO 210 A4 moved to WO#1
641 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9023M P12020W9023M OTP (Operational Test Procedure) of Pack-up IA Compressor EX-DE 210 A4 moved to WO#3
641 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9023M P12020W9023M OTP (Operational Test Procedure) of Pack-up IA Compressor EX-CO 210 A4 moved to WO#3
642 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9024M P12020W9024M OTP (Operational Test Procedure) of Recycled Water Pump Motor EX-DE 210 A4 deleted by eni instruction
642 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9024M P12020W9024M OTP (Operational Test Procedure) of Recycled Water Pump Motor EX-CO 210 A4 deleted by eni instruction
643 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9025M P12020W9025M OTP (Operational Test Procedure) of Scale Inhibitor Injection Unit EX-DE 210 A4 deleted by eni instruction
643 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9025M P12020W9025M OTP (Operational Test Procedure) of Scale Inhibitor Injection Unit EX-CO 210 A4 deleted by eni instruction
644 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9026M P12020W9026M OTP (Operational Test Procedure) of Wash Water Pump Motor EX-DE 210 A4 deleted by eni instruction
644 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9026M P12020W9026M OTP (Operational Test Procedure) of Wash Water Pump Motor EX-CO 210 A4 deleted by eni instruction
645 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9027M P12020W9027M OTP (Operational Test Procedure) of Produced Water Treatment Package EX-DE 210 A4 moved to WO#1
645 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9027M P12020W9027M OTP (Operational Test Procedure) of Produced Water Treatment Package EX-CO 210 A4 moved to WO#1
646 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9028M P12020W9028M OTP (Operational Test Procedure) of Produced Water Treatment Drain Pit Pumps EX-DE 210 A4 deleted by eni instruction
646 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9028M P12020W9028M OTP (Operational Test Procedure) of Produced Water Treatment Drain Pit Pumps EX-CO 210 A4 deleted by eni instruction
647 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9029M P12020W9029M PRE-COMMISSIONING PROCEDURE (CHECK LISTS & STATIC TEST SHEETS) EX-DE 00 210 A4
647 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9029M P12020W9029M PRE-COMMISSIONING PROCEDURE (CHECK LISTS & STATIC TEST SHEETS) EX-CO 210 A4
648 N/A Precommissioning,commissioning and test run 002506 00 D W EA 9030M P12020W9030M PRE-COMMISSIONING TEMPORARY TOOLS & EQUIPMENT LIST EX-DE 210 A4 deleted by eni instruction
648 N/A Precommissioning,commissioning and test run 002506 00 D W EA 9030M P12020W9030M PRE-COMMISSIONING TEMPORARY TOOLS & EQUIPMENT LIST EX-CO 210 A4 deleted by eni instruction
649 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9031M P12020W9031M PROCEDURE OF COMMISSIONING WITNESS BY COMPANY EX-DE 00 210 A4 deleted by eni instruction
649 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9031M P12020W9031M PROCEDURE OF COMMISSIONING WITNESS BY COMPANY EX-CO 210 A4 deleted by eni instruction
650 N/A Precommissioning,commissioning and test run 002506 00 D W PG 9032M P12020W9032M PUNCH LIST MANAGEMENT PROCEDURE EX-DE 00 210 A4
650 N/A Precommissioning,commissioning and test run 002506 00 D W PG 9032M P12020W9032M PUNCH LIST MANAGEMENT PROCEDURE EX-CO 210 A4
651 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9033M P12020W9033M SITE PRE-COMMISSIONING WITNESS BY COMMISSIONING EX-DE 210 A4 deleted by eni instruction
651 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9033M P12020W9033M SITE PRE-COMMISSIONING WITNESS BY COMMISSIONING EX-CO 210 A4 deleted by eni instruction
652 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9034M P12020W9034M STARTUP ISOLATING LIST EX-DE 210 A4 moved to WO#1
652 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9034M P12020W9034M STARTUP ISOLATING LIST EX-CO 210 A4 moved to WO#1
653 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9035M P12020W9035M STARTUP SEQUENCE EX-DE 210 A4 deleted by eni instruction
653 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9035M P12020W9035M STARTUP SEQUENCE EX-CO 210 A4 deleted by eni instruction
654 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9036M P12020W9036M SUBSYSTEM IDENTIFICATION LIST EX-DE 01 210 A4 moved to WO#1
654 N/A Precommissioning,commissioning and test run 002506 00 D W PC 9036M P12020W9036M SUBSYSTEM IDENTIFICATION LIST EX-CO 210 A4 moved to WO#1
655 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9037M P12020W9037M SWITCHING PROCEDURE FOR ENERGISATION OF EMERGENCY SWITCHBOARDS EX-DE 210 A4
655 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9037M P12020W9037M SWITCHING PROCEDURE FOR ENERGISATION OF EMERGENCY SWITCHBOARDS EX-CO 210 A4
656 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9038M P12020W9038M TRAINING PLAN FOR OPERATION EX-DE 00 210 A4
656 N/A Precommissioning,commissioning and test run 002506 00 D W QR 9038M P12020W9038M TRAINING PLAN FOR OPERATION EX-CO 210 A4
657 N/A Quality Assurance and Control 002506 00 D J PV 4416M P12020J4416M SAND BLAST AND PAINTING PROCEDURE AT SITE EX-DE 01 210 A4
657 N/A Quality Assurance and Control 002506 00 D J PV 4416M P12020J4416M SAND BLAST AND PAINTING PROCEDURE AT SITE EX-CO 00 210 A4
658 N/A Quality Assurance and Control 002506 00 D J PC 4418M P12020J4418M PAINTING METHOD OF STATEMENT FOR TREATED WATER TANK EX-DE 00 210 A4
658 N/A Quality Assurance and Control 002506 00 D J PC 4418M P12020J4418M PAINTING METHOD OF STATEMENT FOR TREATED WATER TANK EX-CO 00 210 A4
659 N/A Precommissioning,commissioning and test run 002506 00 C W QR 9040M P12020W9040M FLUSHING PROCEDURE EX-DE 210 A4
659 N/A Precommissioning,commissioning and test run 002506 00 C W QR 9040M P12020W9040M FLUSHING PROCEDURE EX-CO 01 210 A4
660 N/A Civil and Architectural 002506 00 D A DQ 0061M P12020A0061M TYPICAL DRAWINGS FOR UNDERGROUND PIPING EX-DE 00 210 A4
660 N/A Civil and Architectural 002506 00 D A DQ 0061M P12020A0061M TYPICAL DRAWINGS FOR UNDERGROUND PIPING EX-CO 01 210 A4
661 N/A Civil and Architectural 002506 00 D A RS 4003M P12020A4003M TOPOGRAPHIC SURVEY REPORT EX-DE 00 210 A4
661 N/A Civil and Architectural 002506 00 D A RS 4003M P12020A4003M TOPOGRAPHIC SURVEY REPORT EX-CO 00 210 A4
662 N/A Quality Assurance and Control 002506 00 D B PC 4200M P12020B4200M METHOD STATEMENT of UNDERGROUND PIPE INSTALLATION EX-DE 00 210 A4
662 N/A Quality Assurance and Control 002506 00 D B PC 4200M P12020B4200M METHOD STATEMENT of UNDERGROUND PIPE INSTALLATION EX-CO 210 A4
663 N/A Quality Assurance and Control 002506 00 D B PV 4421M P12020B4421M WELDING PROCEDURE SPECIFICATION FOR EMC(EM-CS-04) EX-DE 00 210 A4
663 N/A Quality Assurance and Control 002506 00 D B PV 4421M P12020B4421M WELDING PROCEDURE SPECIFICATION FOR EMC(EM-CS-04) EX-CO 210 A4
664 N/A Quality Assurance and Control 002506 00 D B QB 2021M P12020B2021M Field Inspection And Test Procedure/Plan (Itp) EX-DE 00 210 A4
664 N/A Quality Assurance and Control 002506 00 D B QB 2021M P12020B2021M Field Inspection And Test Procedure/Plan (Itp) EX-CO 210 A4
665 N/A Quality Assurance and Control 002506 00 D B QB 2022M P12020B2022M SITE NOTIFICATION OF INSPECTION PROCEDURE EX-DE 00 210 A4
665 N/A Quality Assurance and Control 002506 00 D B QB 2022M P12020B2022M SITE NOTIFICATION OF INSPECTION PROCEDURE EX-CO 00 210 A4
666 N/A Quality Assurance and Control 002506 00 D B QB 2025M P12020B2025M INSPECTION AND TEST PROCEDURE FOR WATER STORAGE TANK EX-DE 01 210 A4
666 N/A Quality Assurance and Control 002506 00 D B QB 2025M P12020B2025M INSPECTION AND TEST PROCEDURE FOR WATER STORAGE TANK EX-CO 210 A4
667 N/A Quality Assurance and Control 002506 00 D B QB 4072M P12020B4072M WELDING BOOK OF SITE WPS/PQR,s EX-DE 00 210 A4
667 N/A Quality Assurance and Control 002506 00 D B QB 4072M P12020B4072M WELDING BOOK OF SITE WPS/PQR,s EX-CO 01 210 A4
668 N/A Quality Assurance and Control 002506 00 D B QB 4088M P12020B4088M INSPECTION AND TEST PLAN FOR STORAGE TANK EX-DE 01 210 A4
668 N/A Quality Assurance and Control 002506 00 D B QB 4088M P12020B4088M INSPECTION AND TEST PLAN FOR STORAGE TANK EX-CO 210 A4
669 N/A Quality Assurance and Control 002506 00 D B QR 2017M P12020B2017M Visual Inspection Procedure for Structure Welds EX-DE 03 210 A4
669 N/A Quality Assurance and Control 002506 00 D B QR 2017M P12020B2017M Visual Inspection Procedure for Structure Welds EX-CO 00 210 A4
670 N/A Quality Assurance and Control 002506 00 D B QR 3063M P12020B3063M INSPECTION AND TEST PLAN FOR SITE ERECTION OF BRIDGE CRANE EX-DE 00 210 A4
670 N/A Quality Assurance and Control 002506 00 D B QR 3063M P12020B3063M INSPECTION AND TEST PLAN FOR SITE ERECTION OF BRIDGE CRANE EX-CO 00 210 A4
671 N/A Quality Assurance and Control 002506 00 D B QR 3064M P12020B3064M INSPECTION AND TEST PLAN FOR GATCH PAVING EX-DE 00 210 A4
671 N/A Quality Assurance and Control 002506 00 D B QR 3064M P12020B3064M INSPECTION AND TEST PLAN FOR GATCH PAVING EX-CO 00 210 A4
672 N/A Electrical 002506 00 D E PC 4610M P12020E4610M METHOD STATEMENT FOR 6.6 kV MAIN CABLE ROUTING WORK EX-DE 00 210 A4
672 N/A Electrical 002506 00 D E PC 4610M P12020E4610M METHOD STATEMENT FOR 6.6 kV MAIN CABLE ROUTING WORK EX-CO 00 210 A4
673 N/A Plant layout and Piping 002506 00 D T PC 4500M P12020T4500M METHOD STATEMENT FOR HYDROSTATIC TEST EX-DE 210 30/09/2013 A4
673 N/A Plant layout and Piping 002506 00 D T PC 4500M P12020T4500M METHOD STATEMENT FOR HYDROSTATIC TEST EX-CO 210 30/09/2013 A4
674 F12 Machinery 002506 00 C M GB 0017M P12020M0017M INSPECTION DATA SHEET (IDS) FOR DIAPHRAGM PUMP EX-CO 00 555 22/07/2013 A4
675 F22 Machinery 002506 00 C M GC 0018M P12020M0018M REQUIRED DOCUMENT DATA SHEET (RDDS) FOR DIAPHRAGM PUMP EX-CO 00 555 22/07/2013 A4
676 N/A Quality Assurance and Control 002506 00 D B GB 7000M P12020B7000M DATA SHEET FOR FIRE PROOFING MATERIAL EX-DE 00 210 A4
676 N/A Quality Assurance and Control 002506 00 D B GB 7000M P12020B7000M DATA SHEET FOR FIRE PROOFING MATERIAL EX-CO 210 A4
677 F22 Machinery 002506 00 D J PC 6000M P12020J6000M METHOD OF STATEMENT FOR DISMANTLING EXISTING ACCESS PLATFORM AT UPPER MIDDLE SATELLITE EX-DE 00 210 A4 moved to WO#2
677 F22 Machinery 002506 00 D J PC 6000M P12020J6000M METHOD OF STATEMENT FOR DISMANTLING EXISTING ACCESS PLATFORM AT UPPER MIDDLE SATELLITE EX-CO 210 A4 moved to WO#2
678 N/A Precommissioning,commissioning and test run 002506 00 D W PG 9039M P12020W9039M START-UP PROCEDURE (DRY TO WET) EX-DE 00 210 A4 moved to WO#1
678 N/A Precommissioning,commissioning and test run 002506 00 D W PG 9039M P12020W9039M START-UP PROCEDURE (DRY TO WET) EX-CO 210 A4 moved to WO#1
ID

1
2
3
4
5
6
7
8
9
10
11
11
12
13
14
15
16
17
18
19
20
21
22
25
26
27
28
29
30
31
32
33
34
37
37
38
38
39
40
41
41
42
43
44
45
46
47
47
48
49
50
51
52
53
53
54
55
56
57
58
59
60
61
62
63
64
65
65
66
67
68
69
70
71
72
73
74
74
75
76
77
77
78
78
79
79
80
80
81
81
82
82
83
83
84
84
85
85
86
86
87
87
88
88
89
89
90
90
91
91
92
93
93
94
94
95
95
96
96
97
97
98
98
99
99
100
100
101
101
102
102
103
103
104
104
105
105
106
106
107
107
108
108
109
109
110
110
111
111
112
112
113
113
114
114
115
115
116
116
117
117
118
118
119
120
121
122
123
124
125
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
141
143
144
150
151
152
153
154
155
156
157
158
162
163
163
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
212
213
214
214
215
218
218
219
219
220
220
221
221
222
222
223
223
224
224
226
226
227
227
230
230
231
231
232
232
234
234
235
235
236
236
237
237
238
238
240
240
242
242
243
243
244
244
246
254
254
255
255
266
266
267
267
268
268
269
269
270
270
271
271
272
272
273
273
274
274
275
275
276
276
277
277
278
278
280
280
281
281
282
282
283
283
284
284
285
285
286
286
287
287
288
288
289
289
290
290
291
291
292
292
293
293
294
294
295
295
296
296
297
297
298
298
299
299
300
300
301
301
302
302
303
303
304
304
305
305
306
306
307
307
308
308
309
309
310
310
311
311
312
312
313
313
314
314
316
316
317
317
318
318
319
319
320
320
321
321
322
322
323
323
324
324
325
325
326
326
327
327
328
328
329
329
330
330
331
331
332
332
333
333
334
334
335
335
336
336
338
338
339
339
340
340
341
341
342
342
343
343
360
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
380
382
384
386
416
417
418
419
420
421
422
423
424
425
426
428
429
431
431
432
432
433
433
434
434
435
435
436
436
437
437
438
438
439
439
440
440
441
441
442
442
443
443
444
444
445
445
446
446
447
447
448
449
450
451
452
453
454
455
456
456
457
457
460
460
461
462
463
463
464
465
465
466
466
468
468
469
469
470
470
471
471
472
472
473
473
474
474
475
475
476
476
477
477
478
478
479
479
480
480
481
481
482
482
483
483
484
484
485
485
486
486
487
487
488
488
489
489
490
490
491
491
492
492
493
493
494
494
495
495
496
496
497
497
498
498
499
499
500
500
501
501
502
502
503
503
504
504
505
505
506
506
507
507
508
508
509
509
510
510
511
511
512
512
513
513
514
514
515
515
516
516
517
517
518
518
519
519
520
521
522
523
524
524
525
525
526
526
527
527
528
528
529
529
530
530
531
531
532
532
533
533
534
534
535
535
536
536
537
537
538
538
539
539
540
540
541
541
542
542
543
543
544
544
545
545
546
546
547
547
548
548
549
549
550
550
551
551
552
552
553
553
554
554
555
555
556
556
557
557
558
558
559
559
560
560
561
561
562
562
563
563
564
564
565
565
566
566
567
567
568
568
569
569
570
570
571
572
572
573
573
574
574
575
575
576
576
577
577
578
578
579
579
580
580
581
581
582
582
583
583
584
584
585
585
586
586
587
587
588
588
589
589
590
590
591
591
592
592
593
593
594
594
595
595
596
596
597
597
598
598
599
599
600
600
601
601
602
602
603
603
604
604
605
605
606
606
607
607
608
608
609
609
610
610
611
611
612
612
613
613
614
614
615
615
616
616
617
617
618
618
619
619
620
620
621
621
622
622
623
623
624
624
625
625
626
626
627
627
628
628
629
629
630
630
631
631
632
632
633
633
634
634
635
635
636
636
637
637
638
638
639
639
640
640
641
641
642
642
643
643
644
644
645
645
646
646
647
647
648
648
649
649
650
650
651
651
652
652
653
653
654
654
655
655
656
656
657
657
658
658
659
659
660
660
661
661
662
662
663
663
664
664
665
665
666
666
667
667
668
668
669
669
670
670
671
671
672
672
673
673
674
675
676
676
677
677
678
678
Title

SYMBOLS - REFERENCE AND MISCELLANEOUS (ADDENDUM)


ANCHOR BOLTS (ADDENDUM)
GENERAL STEEL CONSTRUCTION NOTES (ADDENDUM)
TYPICAL DRAWING FOR ROADS AND PAVING AND MISCELLANEOUS DETAILS (ADDENDUM)
DESIGN LOADS AND LOADS COMBINATION (ADDENDUM)
GENERAL SPECIFICATION FOR ERECTION OF STEEL STRUCTURES (ADDENDUM)
GENERAL SPECIFICATION FOR CIVIL AND STRUCTURAL DESIGN CRITERIA (ADDENDUM)
GENERAL CONCRETE NOTES (ADDENDUM)
REINFORCED CONCRETE AND FOUNDATIONS DESIGN CRITERIA (ADDENDUM)
STEEL STRUCTURE DESIGN CRITERIA (ADDENDUM)
TYPICAL DRAWING FOR CABLE TRENCH AND DUCT BANK
TYPICAL DRAWING FOR CABLE TRENCH AND DUCT BANK
TYPICAL DRAWING FOR EQUIPMENT FOUNDATION (ADDENDUM)
TYPICAL DRAWING FOR FENCING AND GATES (ADDENDUM)
TYPICAL DRAWING FOR SHELTERS/SUNSHADES (ADDENDUM)
GENERAL SPECIFICATION FOR GEOTECHNICAL SURVEY (ADDENDUM)
GENERAL SPECIFICATION FOR CONCRETE WORKS (ADDENDUM)
GENERAL SPECIFICATION FOR DEMOLITION WORKS (ADDENDUM)
GENERAL SPECIFICATION FOR EMBEDMENTS (ADDENDUM)
GENERAL SPECIFICATION FOR GROUTING AND LEVELLING (ADDENDUM)
GENERAL SPECIFICATION FOR ROAD WORKS (ADDENDUM)
GENERAL SPECIFICATION FOR SITE PREPARATION/EARTHWORKS (ADDENDUM)
GENERAL SPECIFICATION FOR STEEL WORKS (ADDENDUM)
CIVIL AND STRUCTURAL BASIS OF DESIGN (ADDENDUM)
GENERAL SPECIFICATION FOR GRATINGS (ADDENDUM)
GENERAL SPECIFICATION FOR SEWERS AND DRAINS (ADDENDUM)
GRATING CLAMPS (ADDENDUM)
HANDRAILS (ADDENDUM)
REQUIRED TECHNICAL DOCUMENTATION FOR SKIDDED CABINS (DDS)
SAFETY CLOSURE FOR LADDERS (ADDENDUM)
STAIRS (ADDENDUM)
TYPICAL DRAWING FOR SWALES CUT (ADDENDUM)
VERTICAL LADDERS (ADDENDUM)
SITE SURVEY AND SOIL INVESTIGATION REPORT
SITE SURVEY AND SOIL INVESTIGATION REPORT
STUDY ON PILE BEARING CAPACITY AND FOUNDATION TYPE ANALYSIS
STUDY ON PILE BEARING CAPACITY AND FOUNDATION TYPE ANALYSIS
INSPECTION DATASHEET FOR DIESEL GENERATOR
TECHNICAL SPECIFICATION FOR ASYNCHRONOUS MOTORS (ADDENDUM)
TECHNICAL SPECIFICATION FOR DIESEL GENERATOR
TECHNICAL SPECIFICATION FOR DIESEL GENERATOR
TECHNICAL SPECIFICATION FOR ELECTRICAL BULK AND EARTHING MATERIAL (ADDENDUM)
TECHNICAL SPECIFICATION FOR ELECTRICAL SYSTEM IN PACKAGE UNIT (ADDENDUM)
MATERIAL REQUISITION FOR DIESEL GENERATOR
INSPECTION DATASHEET FOR 230V AC UPS
REQUIRED DOCUMENT DATASHEET FOR 230V AC UPS
TECHNICAL SPECIFICATION FOR 230V AC UPS
TECHNICAL SPECIFICATION FOR 230V AC UPS
INSPECTION DATA SHEET FOR LIGHTING PANEL
INSPECTION DATASHEET FOR POWER AND CONTROL CABLE
REQUIRED DOCUMENT DATA SHEET FOR LIGHTING PANEL
REQUIRED DOCUMENT DATASHEET FOR DIESEL GENERATOR
REQUIRED DOCUMENT DATASHEET FOR POWER AND CONTROL CABLE
TECHNICAL SPECIFICATION FOR LIGHTING PANEL
TECHNICAL SPECIFICATION FOR LIGHTING PANEL
TECHNICAL SPECIFICATION FOR POWER AND CONTROL CABLE (ADDENDUM)
INSPECTION DATASHEET FOR LOW VOLTAGE SWITCHGEAR
REQUIRED DOCUMENT DATASHEET FOR LOW VOLTAGE SWITCHGEAR
TECHNICAL SPECIFICATION FOR LOW VOLTAGE SWITCHGEAR (ADDENDUM)
INSPECTION DATASHEET FOR POWER TRANSFORMER
REQUIRED DOCUMENT DATASHEET FOR POWER TRANSFORMER
TECHNICAL SPECIFICATION FOR POWER TRANSFORMER (ADDENDUM)
INSPECTION DATASHEET FOR MEDIUM VOLTAGE SWITCHGEAR
INSPECTION DATASHEET FOR 110V DC BATTERY CHARGER
REQUIRED DOCUMENT DATASHEET FOR MEDIUM VOLTAGE SWITCHGEAR
REQUIRED DOCUMENT DATASHEET FOR 110V DC BATTERY CHARGER
TECHNICAL SPECIFICATION FOR 110 VDC BATTERY CHARGER
TECHNICAL SPECIFICATION FOR 110 VDC BATTERY CHARGER
MATERIAL REQUISITION FOR 230V AC UPS
MATERIAL REQUISITION FOR 6.6KV SWITCHGEAR
MATERIAL REQUISITION FOR BULK MATERIAL
MATERIAL REQUISITION FOR LIGHTING PANEL
MATERIAL REQUISITION FOR LIGHTING SYSTEM MATERIAL
MATERIAL REQUISITION FOR LOW VOLTAGE SWITCHGEAR
MATERIAL REQUISITION FOR POWER AND CONTROL CABLE
MATERIAL REQUISITION FOR POWER TRANSFORMER
TECHNICAL SPECIFICATION FOR MEDIUM VOLTAGE SWITCHGEAR
TECHNICAL SPECIFICATION FOR MEDIUM VOLTAGE SWITCHGEAR
INSPECTION DATA SHEET FOR DC UPS (ADDENDUM)
REQUIRED DOCUMENTATION DATA SHEET FOR DC UPS (ADDENDUM)
DOCUMENT AND ITEM MANAGEMENT PROCEDURE
DOCUMENT AND ITEM MANAGEMENT PROCEDURE
ENGINEERING EXECUTION PLAN
ENGINEERING EXECUTION PLAN
FOUR (4) WEEKS LOOK AHEAD SCHEDULE
FOUR (4) WEEKS LOOK AHEAD SCHEDULE
LEVEL 2 PROJECT SCHEDULE FOR WORK ORDER 1,2,3
LEVEL 2 PROJECT SCHEDULE FOR WORK ORDER 1,2,3
PROCUREMENT EXECUTION PLAN
PROCUREMENT EXECUTION PLAN
PROCUREMT STATUS REPORT
PROCUREMT STATUS REPORT
PROGRESS S-CURVE
PROGRESS S-CURVE
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 0 - GENERAL)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 0 - GENERAL)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 1 - DRY TO WET CONVERSION OF EXISTING TRAINS)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 1 - DRY TO WET CONVERSION OF EXISTING TRAINS)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 2 - WATER INJECTION REFURBISHMENT)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 2 - WATER INJECTION REFURBISHMENT)
PROJECT ORGANIZATION CHART
PROJECT ORGANIZATION CHART
VALUE OF WORK DONE (VOWD)
VALUE OF WORK DONE (VOWD)
VALUE OF WORK DONE PROCEDURE
VALUE OF WORK DONE PROCEDURE
DRY TO WET SHELTER TECHNICAL SPECIFICATION (BROWNFIELD)
DRY TO WET SHELTER TECHNICAL SPECIFICATION (BROWNFIELD)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 3 - OIL FISCAL METERING INSTALLATION)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 3 - OIL FISCAL METERING INSTALLATION)
SITE & CLIMATIC CONDITIONS (ADDENDUM)
FIRE PREVENTION & PROTECTION
FIRE PREVENTION & PROTECTION
FIRST AID
FIRST AID
HEALTH SAFETY AND ENVIRONMENT (HSE) PLAN
HEALTH SAFETY AND ENVIRONMENT (HSE) PLAN
HSE INDUCTION & TRAINING
HSE INDUCTION & TRAINING
INCIDENT REPORTING & INVESTIGATION
INCIDENT REPORTING & INVESTIGATION
LOCK OUT & TAG OUT (LOTO)
LOCK OUT & TAG OUT (LOTO)
BRIDGING DOCUMENT & STX PERMIT TO WORK PROCEDURE
BRIDGING DOCUMENT & STX PERMIT TO WORK PROCEDURE
PERSONAL PROTECTIVE EQUIPMENT PROCEDURE
PERSONAL PROTECTIVE EQUIPMENT PROCEDURE
RISK ASSESSMENT
RISK ASSESSMENT
ROAD AND TRAFFIC SAFETY PROCEDURE
ROAD AND TRAFFIC SAFETY PROCEDURE
SIMOPS PLAN
SIMOPS PLAN
SUB-CONTRACTOR SAFETY PROCEDURE
SUB-CONTRACTOR SAFETY PROCEDURE
WASTE MANAGEMENT
WASTE MANAGEMENT
CONFINED SPACE ENTRY
CONFINED SPACE ENTRY
EVACUATION & EMERGENCY PLAN
EVACUATION & EMERGENCY PLAN
EXCAVATION & BACKFILLING PROCEDURE
EXCAVATION & BACKFILLING PROCEDURE
FLAMMABLE & COMBUSTIBLE LIQUIDS
FLAMMABLE & COMBUSTIBLE LIQUIDS
HSE AUDIT & INSPECTION
HSE AUDIT & INSPECTION
HSE COMMUNICATION & MEETING
HSE COMMUNICATION & MEETING
RIGGING AND LIFTING PROCEDURE
RIGGING AND LIFTING PROCEDURE
RIGGING
RIGGING
SCAFFOLDING AND PORTABLE LADDERS PROCEDURE
SCAFFOLDING AND PORTABLE LADDERS PROCEDURE
SITE SECURITY CONTROL
SITE SECURITY CONTROL
HAZOP PROCEDURE
HAZOP PROCEDURE
SIL ASSESMENT PROCEDURE
SIL ASSESMENT PROCEDURE
MOBILE FIRE EXTINGUISHER AND SAFETY EQUIPMENT SPECIFICATION
MOBILE FIRE EXTINGUISHER AND SAFETY EQUIPMENT SPECIFICATION
HAZARDOUS AREA CLASSIFICATION PHILOSOPHY (ADDENDUM)
FIBER OPTIC CABLES REQUIRED DOCUMENT DATASHEET (RDDS)
FIBER OPTIC CABLES INSPECTION DATASHEET (IDS)
FUNCTIONAL SPECIFICATION FOR UCP PACKAGE (ADDENDUM)
INSTRUMENTATION AND CONTROL BASIS OF DESIGN (ADDENDUM)
SAFETY AND CONTROL PANEL TECHNICAL SPECIFICATION (BROWNFIELD) (ADDENDUM)
TECHNICAL SPECIFICATION FOR FIBER OPTIC CABLES
TECHNICAL SPECIFICATION FOR FIBER OPTIC CABLES
TECHNICAL SPECIFICATION FOR INSTRUMENT CABLES (ADDENDUM)
TECHNICAL SPECIFICATION FOR JUNCTION BOXES (ADDENDUM)
INSTRUMENT CABLES REQUIRED DOCUMENT DATASHEET (RDDS)
INSTRUMENT CABLES INSPECTION DATASHEET (IDS)
MATERIAL REQUISITION FOR FIBER OPTIC CABLES
MATERIAL REQUISITION FOR INSTRUMENT CABLES
GENERAL SPECIFICATION FOR CHOKE VALVES (ADDENDUM)
GENERAL SPECIFICATION FOR SAFETY VALVES AND RUPTURE DISKS (ADDENDUM)
TECHNICAL SPECIFICATION FOR ELECTRIC ACTUATORS (ADDENDUM)
TECHNICAL SPECIFICATION FOR PNEUMATIC ACTUATORS (ADDENDUM)
FIRE & GAS DETECTION SYSTEM REQUIRED DOCUMENT DATASHEET (RDDS)
FIRE & GAS DETECTION SYSTEM INSPECTION DATASHEET (IDS)
F&G DETECTORS REQUIRED DOCUMENT DATASHEET (RDDS)
F&G DETECTORS INSPECTION DATASHEET (IDS)
TECHNICAL SPECIFICATION FOR FIRE & GAS DETECTION SYSTEM (ADDENDUM)
TECHNICAL SPECIFICATION FOR BULK MATERIAL
TECHNICAL SPECIFICATION FOR BULK MATERIAL
FIELD INSTRUMENTS INSPECTION DATASHEET (IDS)
MATERIAL REQUISITION FOR F&G DETECTORS
CONTROL VALVE DOCUMENT DATASHEET (DDS)
CONTROL VALVE INSPECTION DATASHEET (IDS)
MATERIAL REQUISITION FOR SAFETY AND CONTROL SYSTEM
MOTORIZED OPERATED VALVE DOCUMENT DATASHEET (DDS)
MOTORIZED OPERATED VALVE INSPECTION DATASHEET (IDS)
PRESSURE SAFETY VALVE DOCUMENT DATASHEET (DDS)
PRESSURE SAFETY VALVE INSPECTION DATASHEET (IDS)
SHUT OFF VALVE DOCUMENT DATASHEET (DDS)
SHUT OFF VALVE INSPECTION DATASHEET (IDS)
FIELD INSTRUMENTS DOCUMENT DATASHEET (DDS)
DRY TO WET - FINAL TEST CERTIFICATE/QUALITY STATEMENT
DRY TO WET - FINAL TEST CERTIFICATE/QUALITY STATEMENT
INSTRUMENTATION AND CONTROL PHILOSOPHY (ADDENDUM)
INSTRUMENTATION AND CONTROL SYSTEM DESIGN CRITERIA FOR PACKAGES (ADDENDUM)
GENERAL SPECIFICATION FOR CONTROL VALVES (ADDENDUM)
GENERAL SPECIFICATION FOR LEVEL INSTRUMENTS (ADDENDUM)
SAFETY AND CONTROL SYSTEM IDS (BROWNFIELD) (ADDENDUM)
GENERAL SPECIFICATION FOR FLOW INSTRUMENTS (ADDENDUM)
GENERAL SPECIFICATION FOR PRESSURE INSTRUMENTS (ADDENDUM)
GENERAL SPECIFICATION FOR TEMPERATURE INSTRUMENTS (ADDENDUM)
ON-OFF VALVES DOCUMENT DATASHEET (DDS) (BROWNFIELD) (ADDENDUM)
ON-OFF VALVES INSPECTION DATASHEET (IDS) (BROWNFIELD) (ADDENDUM)
SAFETY AND CONTROL SYSTEM DOCUMENT DATASHEET (DDS) (BROWNFIELD) (ADDENDUM)
BASIS OF DESIGN FOR MACHINERY AND PACKAGES (ADDENDUM)
INSPECTION DATA SHEET (IDS) FOR CENTRIFUGAL PUMPS WITH ELECTRIC MOTOR DRIVER (ADDENDUM)
REQUIRED DOCUMENT DATA SHEET (RDDS) FOR CENTRIFUGAL PUMPS - ELECTRIC MOTOR WITH VSD
REQUIRED DOCUMENT DATA SHEET (RDDS) FOR CENTRIFUGAL PUMPS - FIXED SPEED ELECTRIC MOTOR (ADDENDUM)
TECHNICAL SPECIFICATION FOR CENTRIFUGAL PUMPS (ADDENDUM)
MATERIAL SELECTION REPORT (BROWNFIELD) (ADDENDUM)
BASIS OF DESIGN FOR STATIC EQUIPMENTS AND HEAT EXCHANGER (ADDENDUM)
INSPECTION DATA SHEET (IDS) FOR PRESSURE VESSELS (ADDENDUM)
TECHNICAL SPECIFICATION FOR PRESSURE VESSELS (ADDENDUM)
REQUIRED DOCUMENT DATA SHEET (RDDS) FOR LARGE WELDED STORAGE TANK
INSPECTION DATA SHEET (IDS) FOR LARGE WELDED STORAGE TANK
TECHNICAL SPECIFICATION FOR LARGE WELDED STORAGE TANK (ADDENDUM)
REQUIRED DOCUMENT DATA SHEET (RDDS) FOR PRESSURE VESSELS (ADDENDUM)
INSPECTION DATA SHEET (IDS) FOR PLATE&FRAME HEAT EXCHANGERS (ADDENDUM)
REQUIRED DOCUMENT DATA SHEET (RDDS) FOR PRESSURE PLATE&FRAME HEAT EXCHANGERS (ADDENDUM)
TECHNICAL SPECIFICATION FOR PLATE&FRAME HEAT EXCHANGERS (ADDENDUM)
SPECIFICATION FOR PIPING CLASSIFICATION AND MATERIAL (ADDENDUM)
SPECIFICATION FOR PIPING STRESS ANALYSIS (ADDENDUM)
BALL VALVES INSPECTION DATA SHEET
CHECKS VALVE INSPECTION DATA SHEET
GATE VALVES INSPECTION DATA SHEET
GLOBE VALVE INSPECTION DATA SHEET
PIPING BASIS OF DESIGN (ADDENDUM)
PLANT VALVES REQUIRED DOCUMENT DATA SHEET
SPECIFICATION FOR EXTERNAL COATING OF BELOW GROUND ON-PLOT PIPING (ADDENDUM)
SPECIFICATION FOR SHOP AND FIELD PAINTING OF ABOVE GROUND STEEL SURFACES (ADDENDUM)
THERMAL INSULATION SPECIFICATION FOR HOT SERVICE (ADDENDUM)
BUTTERFLY VALVES INSPECTION DATA SHEET
PLANT PIPE INSPECTION DATA SHEET
PLANT PIPE REQUIRED DOCUMENT DATA SHEET
PLANT FITTINGS INSPECTION DATA SHEET
PLANT FITTINGS REQUIRED DOCUMENT DATA SHEET
PLANT FLANGES INSPECTION DATA SHEET
PLANT FLANGES REQUIRED DOCUMENT DATA SHEET
PIPING GENERAL WELDING SPECIFICATION (ADDENDUM)
SPECIFICATION FOR FIELD REPAIR OF SHOP APPLIED COATINGS (ADDENDUM)
3D MODEL REVIEW PROCEDURE
3D MODEL REVIEW PROCEDURE
ISOLATION PHILOSOPHY (ADDENDUM)
ZUBAIR FIELD - LEGENDA & SYMBOLS P&ID
ZUBAIR FIELD - LEGENDA & SYMBOLS P&ID
CORRECTIVE AND PREVENTIVE ACTION PROCEDURE
CORRECTIVE AND PREVENTIVE ACTION PROCEDURE
SITE DOCUMENT CONTROL PROCEDURE
SITE DOCUMENT CONTROL PROCEDURE
MATERIAL IDENTIFICATION AND TRACEABILITY PROCEDURE
MATERIAL IDENTIFICATION AND TRACEABILITY PROCEDURE
MEASURING AND TEST EQUIPMENT CONTROL PROCEDURE
MEASURING AND TEST EQUIPMENT CONTROL PROCEDURE
PROJECT QUALITY PLAN
PROJECT QUALITY PLAN
QUALITY ASSURANCE and QUALITY CONTROL
QUALITY ASSURANCE and QUALITY CONTROL
MATERIAL RECEIVING INSPECTION PROCEDURE
MATERIAL RECEIVING INSPECTION PROCEDURE
DYE PENETRANT PROCEDURE
DYE PENETRANT PROCEDURE
HARDNESS TEST PROCEDURE
HARDNESS TEST PROCEDURE
IMS AUDIT PROCEDURE
IMS AUDIT PROCEDURE
MAGNETIC PARTICLE PROCEDURE
MAGNETIC PARTICLE PROCEDURE
NON-CONFORMANCE PROCEDURE
NON-CONFORMANCE PROCEDURE
PIPING PRESSURE TEST PROCEDURE
PIPING PRESSURE TEST PROCEDURE
POSITIVE MATERIAL IDENTIFICATION PROCEDURE
POSITIVE MATERIAL IDENTIFICATION PROCEDURE
RADIOGRAPHY (RT) PROCEDURE
RADIOGRAPHY (RT) PROCEDURE
ULTRASONIC PROCEDURE
ULTRASONIC PROCEDURE
VISUAL INSPECTION PROCEDURE
VISUAL INSPECTION PROCEDURE
WELDER QUALIFICATION PROCEDURE
WELDER QUALIFICATION PROCEDURE
ENGINEERING EXECUTION PLAN for Work Order 4
ENGINEERING EXECUTION PLAN for Work Order 4
OVERALL EXECUTION PLAN for Work Order No.4
OVERALL EXECUTION PLAN for Work Order No.4
BASIC ENGINEERING DESIGN BASIS (ADDENDUM)
SUPPLIERS DRAWINGS FOR VALVES AND IN-LINE INSTRUMENTS
SUPPLIERS DRAWINGS FOR VALVES AND IN-LINE INSTRUMENTS
SUPPLIERS DRAWINGS FOR SYSTEMS/ ANALYSERS AND INSTRUMENTS
SUPPLIERS DRAWINGS FOR SYSTEMS/ ANALYSERS AND INSTRUMENTS
NOTIFICATION OF INSPECTION (NOI)
NOTIFICATION OF INSPECTION (NOI)
VESSEL PRESSURE TEST PROCEDURE
VESSEL PRESSURE TEST PROCEDURE
HAZARDOUS MATERIALS REGISTER
HAZARDOUS MATERIALS REGISTER
I&TP FOR CONCRETE MIX DESIGN
I&TP FOR CONCRETE MIX DESIGN
I&TP FOR EARTH WORK
I&TP FOR EARTH WORK
I&TP FOR BLINDING,CONCRETING,COATING FOUNDATION AND BACKFILLING
I&TP FOR BLINDING,CONCRETING,COATING FOUNDATION AND BACKFILLING
I&TP FOR INSITU CAST CONCRETE
I&TP FOR INSITU CAST CONCRETE
I&TP FOR PRECAST CONCRETE
I&TP FOR PRECAST CONCRETE
I&TP FOR ASPHALT ROADS WORK
I&TP FOR ASPHALT ROADS WORK
I&TP FOR UNDERGROUND PIPE & BACK FILLING
I&TP FOR UNDERGROUND PIPE & BACK FILLING
I&TP FOR CONCRETE PAVING
I&TP FOR CONCRETE PAVING
I&TP FOR STRUCTURAL STEEL PREFABRICATION
I&TP FOR STRUCTURAL STEEL PREFABRICATION
I&TP FOR STRUCTURAL STEEL ERECTION
I&TP FOR STRUCTURAL STEEL ERECTION
I&TP FOR PSV VALVES INSTALLATION
I&TP FOR PSV VALVES INSTALLATION
I&TP FOR STATIC EQUIPMENT
I&TP FOR STATIC EQUIPMENT
I&TP FOR ROTATING EQUIPMENT
I&TP FOR ROTATING EQUIPMENT
I&TP FOR PIPING PREFABRICATION AND ERECTION
I&TP FOR PIPING PREFABRICATION AND ERECTION
I&TP ABOVEGROUND PIPING PRESSURE TEST
I&TP ABOVEGROUND PIPING PRESSURE TEST
I&TP UNDERGROUND PIPING PRESSURE TEST
I&TP UNDERGROUND PIPING PRESSURE TEST
I&TP FOR GENERATORS INSTALLATION
I&TP FOR GENERATORS INSTALLATION
I&TP FOR BATTERIES, BATTERY CHARGER AND UPS INSTALLATION
I&TP FOR BATTERIES, BATTERY CHARGER AND UPS INSTALLATION
I&TP FOR POWER AND CONTROL CABLE INSTALLATION
I&TP FOR POWER AND CONTROL CABLE INSTALLATION
I&TP FOR LIGHTING SYSTEM INSTALLATION
I&TP FOR LIGHTING SYSTEM INSTALLATION
I&TP FOR EARTHING & LIGHTING PROTECTION SYSTEM INSTALLATION
I&TP FOR EARTHING & LIGHTING PROTECTION SYSTEM INSTALLATION
I&TP FOR LOW AND HIGH VOLTAGE MOTOR INSTALLATION
I&TP FOR LOW AND HIGH VOLTAGE MOTOR INSTALLATION
I&TP FOR POWER TRANSFORMER INSTALLATION
I&TP FOR POWER TRANSFORMER INSTALLATION
I&TP FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
I&TP FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
I&TP FOR SMALL POWER DISTRIBUTION EQUIPMENT
I&TP FOR SMALL POWER DISTRIBUTION EQUIPMENT
I&TP FOR CABLE RACKS, TRAYS AND CONDUIT INSTALLATION
I&TP FOR CABLE RACKS, TRAYS AND CONDUIT INSTALLATION
I&TP FOR GLANDING & TERMINATION OF POWER AND CONTROL CABLES INSTALLATION
I&TP FOR GLANDING & TERMINATION OF POWER AND CONTROL CABLES INSTALLATION
I&TP FOR MOTOR OPERATE VALVE INSTALLATION
I&TP FOR MOTOR OPERATE VALVE INSTALLATION
I&TP FOR NEUTRAL EARTH RESISTORS INSTALLATION
I&TP FOR NEUTRAL EARTH RESISTORS INSTALLATION
I&TP FOR ELECTRICAL HEAT TRACING INSTALLATION
I&TP FOR ELECTRICAL HEAT TRACING INSTALLATION
I&TP FOR BRAZING OF CABLE CONNECTIONS
I&TP FOR BRAZING OF CABLE CONNECTIONS
I&TP FOR FIELD MOUNTED INSTRUMENTS
I&TP FOR FIELD MOUNTED INSTRUMENTS
I&TP FOR INSTRUMENT CABLES INSTALLATION
I&TP FOR INSTRUMENT CABLES INSTALLATION
I&TP FOR INSTRUMENT INTERFACE PANELS & JUNCTION BOX INSTALLATION
I&TP FOR INSTRUMENT INTERFACE PANELS & JUNCTION BOX INSTALLATION
I&TP FOR INSTRUMENT PANELS, CONSOLE & DESKS INSTALLATION
I&TP FOR INSTRUMENT PANELS, CONSOLE & DESKS INSTALLATION
I&TP FOR FIBER OPTIC CABLES INSTALLATION
I&TP FOR FIBER OPTIC CABLES INSTALLATION
I&TP FOR FIRE & GAS DETECTION SYSTEM INSTALLATION
I&TP FOR FIRE & GAS DETECTION SYSTEM INSTALLATION
I&TP FOR INSTRUMENT CALIBRATION
I&TP FOR INSTRUMENT CALIBRATION
I&TP FOR INSTRUMENT LOOP CONTINUITY CHECK
I&TP FOR INSTRUMENT LOOP CONTINUITY CHECK
I&TP FOR PIPELINE INSTALLATION
I&TP FOR PIPELINE INSTALLATION
I&TP FOR CLEANING, GAUGING, HYDROTESTING,DEWATERING, DRYING & PURGING OF PIPELINE
I&TP FOR CLEANING, GAUGING, HYDROTESTING,DEWATERING, DRYING & PURGING OF PIPELINE
I&TP FOR PAINTING OF STEEL STRUCTURE
I&TP FOR PAINTING OF STEEL STRUCTURE
I&TP FOR PAINTING OF PIPING
I&TP FOR PAINTING OF PIPING
STORAGE-CONTROL & DISTRIBUTION OF WELDING MATERIALS AT SITE
STORAGE-CONTROL & DISTRIBUTION OF WELDING MATERIALS AT SITE
WELDING MAP & WELDS RECORDING PROCEDURE
WELDING MAP & WELDS RECORDING PROCEDURE
STEEL STRUCTURE FABRICATION / INSTALLATION PROCEDURE
STEEL STRUCTURE FABRICATION / INSTALLATION PROCEDURE
STATIC EQUIPMENTS INSTALLATION PROCEDURE
STATIC EQUIPMENTS INSTALLATION PROCEDURE
ROTATING EQUIPMENTS INSTALLATION PROCEDURE
ROTATING EQUIPMENTS INSTALLATION PROCEDURE
PRESERVATION AND STORAGE OF PROJECT MATERIALS
PRESERVATION AND STORAGE OF PROJECT MATERIALS
GROUTING PROCEDURE
GROUTING PROCEDURE
PIPING - SANDBLASTING AND PAINTING PROCEDURE
PIPING - SANDBLASTING AND PAINTING PROCEDURE
STEEL STRUCTURE - SAND BLASTING AND PAINTING PROCEDURE
STEEL STRUCTURE - SAND BLASTING AND PAINTING PROCEDURE
PAINTING REPAIR PROCEDURE
PAINTING REPAIR PROCEDURE
UNDERGROUND ELECTRICAL / INSTRUMENT CABLE INSTALLATION PROCEDURE
UNDERGROUND ELECTRICAL / INSTRUMENT CABLE INSTALLATION PROCEDURE
ELECTRICAL / INSTRUMENT CABLE TRAYS- CONDUITS INSTALLATION PROCEDURE
ELECTRICAL / INSTRUMENT CABLE TRAYS- CONDUITS INSTALLATION PROCEDURE
JUNCTION BOX INSTALLATION PROCEDURE
JUNCTION BOX INSTALLATION PROCEDURE
INSTRUMENT CALIBRATION PROCEDURE
INSTRUMENT CALIBRATION PROCEDURE
PSV CALIBRATION PROCEDURE
PSV CALIBRATION PROCEDURE
PIPING PREFABRICATION & ERECTION PROCEDURE
PIPING PREFABRICATION & ERECTION PROCEDURE
UNDERGROUND PIPE INSTALLATION PROCEDURE
UNDERGROUND PIPE INSTALLATION PROCEDURE
TIE-IN INSTALLATION PROCEDURE
TIE-IN INSTALLATION PROCEDURE
TECHNICAL SURVEY PROCEDURE
TECHNICAL SURVEY PROCEDURE
PRE-CAST AND IN SITU CONCRETE PROCEDURE
PRE-CAST AND IN SITU CONCRETE PROCEDURE
CIVIL WORK PROCEDURE
CIVIL WORK PROCEDURE
WELDING BOOK INCLUDING WPS & PQR,s
WELDING BOOK INCLUDING WPS & PQR,s
CONSTRUCTION OF ROADS PROCEDURE
CONSTRUCTION OF ROADS PROCEDURE
HEALTH MANAGEMENT PLAN
HEALTH MANAGEMENT PLAN
HSE REPORTING PLAN
HSE REPORTING PLAN
PROJECT TRAINING PROGRAMME
PROJECT TRAINING PROGRAMME
HSE BRIDGING DOCUMENT
HSE BRIDGING DOCUMENT
LIST OF FIRE PROTECTION EQUIPMENT
LIST OF FIRE PROTECTION EQUIPMENT
HSE CLOSE-OUT REPORT
HSE CLOSE-OUT REPORT
MATERIAL REQUISITION FOR CATHODIC PROTECTION SYSTEM
MATERIAL REQUISITIONS FOR ORIFICE PLATE & RESTRICTION ORIFICE
MATERIAL REQUISITIONS FOR FLOW TRANSMITTER (DP)
MATERIAL REQUISITIONS FOR LEVEL GAUGE
MATERIAL REQUISITIONS FOR LEVEL TRANSMITTER
MATERIAL REQUISITIONS FOR LEVEL SWITCH
MATERIAL REQUISITIONS FOR PRESSURE TRANSMITTER
MATERIAL REQUISITIONS FOR PRESSURE GAUGE
MATERIAL REQUISITIONS FOR TEMPERATURE TRANSMITTER
MATERIAL REQUISITIONS FOR TEMPERATURE GAUGE
MATERIAL REQUISITIONS FOR ANALYZER
MATERIAL REQUISITIONS FOR PNEUMATIC CONTROL VALVE
MATERIAL REQUISITIONS FOR PRESSURE SAFETY VALVE
MATERIAL REQUISITIONS FOR ON-OFF VALVE
MATERIAL REQUISITIONS FOR BULK MATERIAL
MATERIAL REQUISITIONS FOR JUNCTION BOX
MATERIAL REQUISITIONS FOR ULTRASONIC FLOWMETER (316SS/CS)
MATERIAL REQUISITIONS FOR PRESSURE SWITCH
MATERIAL REQUISITIONS FOR MOTOR OPERATED VALVE
MATERIAL REQUISITIONS FOR LOCAL EQUIPMENT ROOM
PIPING MATERIAL REQUISITION FOR SMLS CARBON STEEL PIPE
PIPING MATERIAL REQUISITION FOR SMLS STAINLESS STEEL PIPE
PIPING MATERIAL REQUISITION FOR FORGED FITTING
PIPING MATERIAL REQUISITION FOR BUTT-WELDING FITTING
PIPING MATERIAL REQUISITION FOR FLANGE
PIPING MATERIAL REQUISITION FOR GASKET
PIPING MATERIAL REQUISITION FOR FORGED VALVE
PIPING MATERIAL REQUISITION FOR CASTING VALVE
PIPING MATERIAL REQUISITION FOR BALL VALVE
PIPING MATERIAL REQUISITION FOR BUTTERFLY VALVE
PIPING MATERIAL REQUISITION FOR WO#3 PIPING
PIPING MATERIAL REQUISITION FOR BOLT/NUTS
PIPING MATERIAL REQUISITION FOR STRAINER
LEVEL 3 PROJECT SCHEDULE FOR WORK ORDER 1,2,3
LEVEL 3 PROJECT SCHEDULE FOR WORK ORDER 1,2,3
LEVEL 4 PROJECT SCHEDULE FOR WORK ORDER 1,2,3
LEVEL 4 PROJECT SCHEDULE FOR WORK ORDER 1,2,3
GENERAL WELDING PROCEDURE
GENERAL WELDING PROCEDURE
WELDING REPAIR PROCEDURE
WELDING REPAIR PROCEDURE
ELECTRICAL SYMBOLS AND LEGEND
ELECTRICAL SYMBOLS AND LEGEND
CONSTRUCTION EXECUTION PLAN
CONSTRUCTION EXECUTION PLAN
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 4 - FIRE FIGHTING SYSTEM)
DOCUMENT LIST (EXISTING DGS MODIFICATIONS - WO 4 - FIRE FIGHTING SYSTEM)
LOSS PREVENTION & ENVIRONMENT PHILOSOPHY (Adeendum)
LOSS PREVENTION & ENVIRONMENT PHILOSOPHY (Adeendum)
PIPING PRESSURE TEST PROCEDURE
PIPING PRESSURE TEST PROCEDURE
INSPECTION AND TEST PLAN FOR VESSEL INSTALLATION
INSPECTION AND TEST PLAN FOR VESSEL INSTALLATION
INSPECTION AND TEST PLAN FOR HEAT EXCHANGER INSTALLATION
INSPECTION AND TEST PLAN FOR HEAT EXCHANGER INSTALLATION
INSPECTION AND TEST PLAN FOR FILTER INSTALLATION
INSPECTION AND TEST PLAN FOR FILTER INSTALLATION
INSPECTION AND TEST PLAN FOR SKID & PACKAGE INSTALLATION
INSPECTION AND TEST PLAN FOR SKID & PACKAGE INSTALLATION
INSPECTION AND TEST PLAN FOR PUMP INSTALLATION
INSPECTION AND TEST PLAN FOR PUMP INSTALLATION
INSPECTION AND TEST PLAN FOR COMPRESSOR INSTALLATION
INSPECTION AND TEST PLAN FOR COMPRESSOR INSTALLATION
INSPECTION AND TEST PLAN FOR BLOWER INSTALLATION
INSPECTION AND TEST PLAN FOR BLOWER INSTALLATION
Material Selection Report for Produced Water Treatment Package
Material Selection Report for Produced Water Treatment Package
MATERIAL REQUISITIONS FOR LIMIT SWITCH
PLANT GASKETS INSPECTION DATA SHEET
PLANT STUD BOLTS AND NUTS INSPECTION DATA SHEET
PLANT STRAINERS INSPECTION DATA SHEET
PLANT GASKETS REQUIRED DOCUMENT DATA SHEET
PLANT STUD BOLTS AND NUTS REQUIRED DOCUMENT DATA SHEET
PLANT STRAINERS REQUIRED DOCUMENT DATA SHEET
MATERIAL REQUISTIONS FOR SIGNAL CONVERTER
PROCUREMENT STATUS REPORT A
PROCUREMENT STATUS REPORT A
PROCUREMENT STATUS REPORT B
PROCUREMENT STATUS REPORT B
TYPICAL LOOP WIRING (BROWNFIELD)
TYPICAL LOOP WIRING (BROWNFIELD)
MATERIAL REQUISITIONS FOR CORROSION COUPON
MATERIAL REQUISITIONS FOR MIXING VALVE
INSTRUMENT TYPICAL INSTALLATION DETAIL DRAWING
INSTRUMENT TYPICAL INSTALLATION DETAIL DRAWING
MATERIAL REQUISITIONS FOR CHOKE VALVE
TYPICAL INSTRUMENT ELECTRICAL HOOK-UP DRAWINGS
TYPICAL INSTRUMENT ELECTRICAL HOOK-UP DRAWINGS
DATA SHEET FOR INSTRUMENT CABLE
DATA SHEET FOR INSTRUMENT CABLE
Shop Notification of Inspection
Shop Notification of Inspection
TYPICAL SUPPORTS FOR PIPING AND EQUIPMENT
TYPICAL SUPPORTS FOR PIPING AND EQUIPMENT
FIREPROOFING SPECIFICATION
FIREPROOFING SPECIFICATION
PROCEDURE FOR EARTHING & LIGHTNING SYSTEM INSTALLATION
PROCEDURE FOR EARTHING & LIGHTNING SYSTEM INSTALLATION
PROCEDURE FOR LIGHTING SYSTEM INSTALLATION
PROCEDURE FOR LIGHTING SYSTEM INSTALLATION
PROCEDURE FOR ELECTRICAL & INSTRUMENT EQUIPMENT INSTALLATION
PROCEDURE FOR ELECTRICAL & INSTRUMENT EQUIPMENT INSTALLATION
PROCEDURE FOR FIBER OPTICAL CABLE
PROCEDURE FOR FIBER OPTICAL CABLE
PROCEDURE FOR FIRE & GAS DETECTION SYSTEM
PROCEDURE FOR FIRE & GAS DETECTION SYSTEM
PROCEDURE FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
PROCEDURE FOR SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
METHOD STATEMENT OF UNDER & ABOVE GROUND ELECTRICAL & INSTRUMENT CABLE INSTALLATION
METHOD STATEMENT OF UNDER & ABOVE GROUND ELECTRICAL & INSTRUMENT CABLE INSTALLATION
METHOD STATEMENT OF EARTHING WORK
METHOD STATEMENT OF EARTHING WORK
METHOD STATEMENT OF CATHODIC PROTECTION SYSTEM INSTALLATION WORK
METHOD STATEMENT OF CATHODIC PROTECTION SYSTEM INSTALLATION WORK
METHOD STATEMENT OF ELECTRICAL EQUIPMENT INSTALLATION WORK
METHOD STATEMENT OF ELECTRICAL EQUIPMENT INSTALLATION WORK
METHOD STATEMENT OF CABLE RACEWAY INSTALLATION WORK
METHOD STATEMENT OF CABLE RACEWAY INSTALLATION WORK
METHOD STATEMENT OF CABLING & WIRING WORK
METHOD STATEMENT OF CABLING & WIRING WORK
METHOD STATEMENT OF LIGHTING INSTALLATION WORK
METHOD STATEMENT OF LIGHTING INSTALLATION WORK
METHOD STATEMENT OF INSTRUMENT INSTALLATION WORK
METHOD STATEMENT OF INSTRUMENT INSTALLATION WORK
METHOD STATEMENT OF IMPULSE TUBING WORK
METHOD STATEMENT OF IMPULSE TUBING WORK
METHOD STATEMENT OF FIRE & GAS DETECTION INSTALLATION WORK
METHOD STATEMENT OF FIRE & GAS DETECTION INSTALLATION WORK
PROCEDURE FOR INSULATION INSTALLATION
PROCEDURE FOR INSULATION INSTALLATION
PROCEDURE FOR HYDROSTATIC TEST
PROCEDURE FOR HYDROSTATIC TEST
PROCEDURE FOR PRE-COMMISSIONING
PROCEDURE FOR PRE-COMMISSIONING
METHOD STATEMENT FOR STEEL PIPE INSTALLATION
METHOD STATEMENT FOR STEEL PIPE INSTALLATION
METHOD STATEMENT FOR STEEL STRUCTURE ERECTION
METHOD STATEMENT FOR STEEL STRUCTURE ERECTION
METHOD STATEMENT FOR DESALTER / DEHYDRATOR - ZUBAIR MISHRIF
METHOD STATEMENT FOR DESALTER / DEHYDRATOR - ZUBAIR MISHRIF
METHOD STATEMENT FOR DESALTER / DEHYDRATOR - HAMMAR MISHRIF
METHOD STATEMENT FOR DESALTER / DEHYDRATOR - HAMMAR MISHRIF
METHOD STATEMENT FOR WATER TANK ERECTION - ZUBAIR MISHRIF
METHOD STATEMENT FOR WATER TANK ERECTION - ZUBAIR MISHRIF
METHOD STATEMENT FOR WATER TANK ERECTION - HAMMAR MISHRIF
METHOD STATEMENT FOR WATER TANK ERECTION - HAMMAR MISHRIF
METHOD STATEMENT FOR HYDROSTATIC TEST OF NORTH SATELLITE
METHOD STATEMENT FOR HYDROSTATIC TEST OF NORTH SATELLITE
METHOD STATEMENT FOR HYDROSTATIC TEST OF LOWER MIDDLE SATELLITE
METHOD STATEMENT FOR HYDROSTATIC TEST OF LOWER MIDDLE SATELLITE
METHOD STATEMENT FOR HYDROSTATIC TEST OF SOUTH SATELLITE
METHOD STATEMENT FOR HYDROSTATIC TEST OF SOUTH SATELLITE
METHOD STATEMENT FOR TIE-IN - ZUBAIR MISHRIF
METHOD STATEMENT FOR TIE-IN - ZUBAIR MISHRIF
METHOD STATEMENT FOR TIE-IN - HAMMAR MISHRIF
METHOD STATEMENT FOR TIE-IN - HAMMAR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF TIE-IN - ZUBAIR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF TIE-IN - ZUBAIR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF TIE-IN - HAMMAR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF TIE-IN - HAMMAR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - ZUBAIR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - ZUBAIR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - HAMMAR MISHRIF
METHOD STATEMENT FOR HYDROTEST OF GUARD FILTER - HAMMAR MISHRIF
METHOD STATEMENT FOR PGI EQUIPMENT - HAMMAR MISHRIF
METHOD STATEMENT FOR PGI EQUIPMENT - HAMMAR MISHRIF
METHOD STATEMENT FOR PGI EQUIPMENT - ZUBAIR MISHRIF
METHOD STATEMENT FOR PGI EQUIPMENT - ZUBAIR MISHRIF
CONTROL AND USE OF PLANTS AND EQUIPMENT PROCEDURE
CONTROL AND USE OF PLANTS AND EQUIPMENT PROCEDURE
COMPRESSED GAS CYLINDER STORAGE, TRANSPORTATION AND USE PROCEDURE
COMPRESSED GAS CYLINDER STORAGE, TRANSPORTATION AND USE PROCEDURE
HAND AND POWER TOOLS PROCEDURE
HAND AND POWER TOOLS PROCEDURE
HAZARD COMMUNICATION (COSHH) PROCEDURE
HAZARD COMMUNICATION (COSHH) PROCEDURE
HEARING CONSERVATION PROCEDURE
HEARING CONSERVATION PROCEDURE
HEAT-COLD STRESS PROCEDURE
HEAT-COLD STRESS PROCEDURE
HOUSEKEEPING PROCEDURE
HOUSEKEEPING PROCEDURE
MANUAL HANDLING PROCEDURE
MANUAL HANDLING PROCEDURE
MATERIAL SAFETY DATA AND HAZARD ASSESSMENT PROCEDURE
MATERIAL SAFETY DATA AND HAZARD ASSESSMENT PROCEDURE
TEMPORARY ELECTRICS PROCEDURE
TEMPORARY ELECTRICS PROCEDURE
TOOLBOX TALKS PROCEDURE
TOOLBOX TALKS PROCEDURE
WARNING SIGNS AND BARRIERS PROCEDURE
WARNING SIGNS AND BARRIERS PROCEDURE
WORKING AT HEIGHT PROCEDURE
WORKING AT HEIGHT PROCEDURE
MATERIAL REQUISITIONS FOR LOCAL CONTROLLER
MATERIAL REQUISITIONS FOR LOCAL CONTROL PANEL
MATERIAL REQUISITIONS FOR SIGHT GLASS
MATERIAL REQUISION FOR FIRE EXTINGUISHER
BITUMEN EMULSION PROTECTIVE COATING DATA SHEET
BITUMEN EMULSION PROTECTIVE COATING DATA SHEET
CONTROL OF MEASURING EQUIPMENT
CONTROL OF MEASURING EQUIPMENT
CURING COMPOUND DATA SHEET
CURING COMPOUND DATA SHEET
FOSROC NITOSEAL PU 40 POLYURETHANE SEALANT DATA SHEET
FOSROC NITOSEAL PU 40 POLYURETHANE SEALANT DATA SHEET
GROUTING FOR THE PEDESTAL AND ANCHOR BOLTS DATA SHEET
GROUTING FOR THE PEDESTAL AND ANCHOR BOLTS DATA SHEET
INSPECTION AND TESTING PROCEDURE
INSPECTION AND TESTING PROCEDURE
INSPECTION AND TEST PLAN FOR BLINDING CONCRETE
INSPECTION AND TEST PLAN FOR BLINDING CONCRETE
INSPECTION AND TEST PLAN FOR EARTHWORKS FOR UNDERGROUND SERVICE
INSPECTION AND TEST PLAN FOR EARTHWORKS FOR UNDERGROUND SERVICE
INSPECTION AND TEST PLAN FOR ROADS CONSTRUCTION
INSPECTION AND TEST PLAN FOR ROADS CONSTRUCTION
MATERIAL CONTROL AT SITE PROCEDURE
MATERIAL CONTROL AT SITE PROCEDURE
PAINTING AND TOUCH UP PROCEDURE
PAINTING AND TOUCH UP PROCEDURE
PROCEDURE FOR COORDINATION AT CONSTRUCTION SITES
PROCEDURE FOR COORDINATION AT CONSTRUCTION SITES
PROCEDURE FOR STORAGE, HANDLING AND ISSUANCE OF WELDING CONSUMABLES
PROCEDURE FOR STORAGE, HANDLING AND ISSUANCE OF WELDING CONSUMABLES
PROTECTIVE EPOXY RESIN COATING DATA SHEET
PROTECTIVE EPOXY RESIN COATING DATA SHEET
READ BOAD-SBR CHEMICAL ADDITIVES FOR CEMENT
READ BOAD-SBR CHEMICAL ADDITIVES FOR CEMENT
RECEIVING & INSPECTION MATERALS - I&TP
RECEIVING & INSPECTION MATERALS - I&TP
SITE QUERY AND DEVIATION REQUEST
SITE QUERY AND DEVIATION REQUEST
SUBCONTRACTORS CONTROL PROCEDURE
SUBCONTRACTORS CONTROL PROCEDURE
VISUAL INSPECTION
VISUAL INSPECTION
AERIAL WORK PLATFORMS PROCEDURE
AERIAL WORK PLATFORMS PROCEDURE
CAMP MANAGEMENT PLAN
CAMP MANAGEMENT PLAN
ELECTRICAL SAFETY PROCEDURE
ELECTRICAL SAFETY PROCEDURE
ENERGY ISOLATION PROCESS PROCEDURE
ENERGY ISOLATION PROCESS PROCEDURE
ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN
ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN
FOOD SAFETY AND CATERING PROCEDURE
FOOD SAFETY AND CATERING PROCEDURE
HSE STATISTICS REPORTING PROCEDURE
HSE STATISTICS REPORTING PROCEDURE
MANAGEMENT OF CHANGE (MOC) PROCEDURE
MANAGEMENT OF CHANGE (MOC) PROCEDURE
NIGHT WORKS PROCEDURE
NIGHT WORKS PROCEDURE
PNEUMATIC TESTING PROCEDURE
PNEUMATIC TESTING PROCEDURE
RADIOGRAPHY PLAN
RADIOGRAPHY PLAN
SIMULTANEOUS OPERATIONS (SIMOPS) PROCEDURE
SIMULTANEOUS OPERATIONS (SIMOPS) PROCEDURE
SPILL RESPONSE PROCEDURE
SPILL RESPONSE PROCEDURE
METHOD STATEMENT FOR PIPING SHOP FABRICATION
METHOD STATEMENT FOR PIPING SHOP FABRICATION
PAINTING – DATA SHEET FOR ZINC PRIMER (ORGANIC)
PAINTING – DATA SHEET FOR ZINC PRIMER (ORGANIC)
PAINTING – DATA SHEET FOR EPOXY PHENOLIC
PAINTING – DATA SHEET FOR EPOXY PHENOLIC
PAINTING – DATA SHEET FOR POLYURETHANE TOPCOAT
PAINTING – DATA SHEET FOR POLYURETHANE TOPCOAT
GENERAL MAGNETIC PARTICLE TESTING PROCEDURE For Al-bilal
GENERAL MAGNETIC PARTICLE TESTING PROCEDURE For Al-bilal
PAINTING – DATA SHEET FOR EPOXY MODIFIED
PAINTING – DATA SHEET FOR EPOXY MODIFIED
GENERAL LIQUID PENETRANT TESTING PROCEDURE For Al-bilal
GENERAL LIQUID PENETRANT TESTING PROCEDURE For Al-bilal
PAINTING – DATA SHEET FOR EPOXY UNDERCOAT
PAINTING – DATA SHEET FOR EPOXY UNDERCOAT
PAINTING – DATA SHEET FOR EPOXY PRIMER
PAINTING – DATA SHEET FOR EPOXY PRIMER
PAINTING – DATA SHEET FOR ZINC PRIMER (INORGANIC)
PAINTING – DATA SHEET FOR ZINC PRIMER (INORGANIC)
GENERAL RADIOGRAPHIC TESTING PROCEDURE For Al-bilal
GENERAL RADIOGRAPHIC TESTING PROCEDURE For Al-bilal
PAINTING – DATA SHEET FOR SILICONE
PAINTING – DATA SHEET FOR SILICONE
PAINTING – DATA SHEET FOR WATER TREATED TANK (EXTERNAL)
PAINTING – DATA SHEET FOR WATER TREATED TANK (EXTERNAL)
GENERAL ULTRASONIC TESTING PROCEDURE For Al-bilal
GENERAL ULTRASONIC TESTING PROCEDURE For Al-bilal
WELDING VISUAL INSPECTION PROCEDURE For Al-bilal
WELDING VISUAL INSPECTION PROCEDURE For Al-bilal
MATERIAL REQUISITIONS FOR SELF REGULATING VALVE
MINOR FOUNDATION & STRUCTURAL DETAILS FOR MISCELLANEOUS ITEMS
MINOR FOUNDATION & STRUCTURAL DETAILS FOR MISCELLANEOUS ITEMS
CALCULATION REPORT FOR MISCELLANEOUS ITEMS
CALCULATION REPORT FOR MISCELLANEOUS ITEMS
NDT PROCEDURE
NDT PROCEDURE
INSPECTION AND TEST PLAN FOR NDT
INSPECTION AND TEST PLAN FOR NDT
Journey Management Procedure
Journey Management Procedure
HAMMAR MISHRIF - HYDROTEST PACKAGE FOR LP Flaring System (SS 2006;PKG-001)
HAMMAR MISHRIF - HYDROTEST PACKAGE FOR LP Flaring System (SS 2006;PKG-001)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-03 ;PKG No.002)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-03 ;PKG No.002)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS-2001/CO-01; PKG No. 003)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS-2001/CO-01; PKG No. 003)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-04;PKG No.004)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CO-04;PKG No.004)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CO-06;PKG No. 005)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CO-06;PKG No. 005)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-01;PKG No. 006)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-01;PKG No. 006)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-03; PKG No. 007)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/PW-03; PKG No. 007)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-05;PKG No. 008)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-05;PKG No. 008)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-06 ;PKG No.009)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-06 ;PKG No.009)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CD-08 ;PKG No.010)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CD-08 ;PKG No.010)
HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-02 ;PKG No.011)
HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-02 ;PKG No.011)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-07 ;PKG No.012)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-07 ;PKG No.012)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-01;PKG No.013)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-01;PKG No.013)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-04;PKG No. 014)
HYDROTEST PACKAGE FOR Dehydrator Unit (SS 2001/CD-04;PKG No. 014)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-02;PKG No.015)
HYDROTEST PACKAGE FOR Desalter Unit (SS 2002/CD-02;PKG No.015)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-010 ;PKG No.016)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-010 ;PKG No.016)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/IW-01;PKG No.017)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/IW-01;PKG No.017)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-08;PKG No.018)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-08;PKG No.018)
HYDROTEST PACKAGE FOR Instrument Air System (SS 3002/IA-01;PKG No.019)
HYDROTEST PACKAGE FOR Instrument Air System (SS 3002/IA-01;PKG No.019)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-07;PKG No.020)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-07;PKG No.020)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-09 ;PKG No.021)
HYDROTEST PACKAGE FOR Oil Transfer Pump (SS 2003/CO-09 ;PKG No.021)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-02;PKG No.022)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-02;PKG No.022)
HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-01 ;PKG No.023)
HYDROTEST PACKAGE FOR Wash Water Pump/Economizert (SS 3001/RW-01 ;PKG No.023)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-03;PKG No.024)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/CD-03;PKG No.024)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-01;PKG No.025)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-01;PKG No.025)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-02;PKG No.026)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-02;PKG No.026)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-03;PKG No.027)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/DH-03;PKG No.027)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/SL-01;PKG No.028)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/SL-01;PKG No.028)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/UN-01;PKG No.029)
HYDROTEST PACKAGE FOR Closed Drain System (SS 2007/UN-01;PKG No.029)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-01;PKG No.030)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-01;PKG No.030)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-02;PKG No.031)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-02;PKG No.031)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-03;PKG No.032)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-03;PKG No.032)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-04;PKG No.033)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-04;PKG No.033)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-05;PKG No.034)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-05;PKG No.034)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-06;PKG No.035)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-06;PKG No.035)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-07;PKG No.036)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-07;PKG No.036)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-08;PKG No.037)
HYDROTEST PACKAGE FOR Chemical Injection System (SS 2009/CH-08;PKG No.037)
HYDROTEST PACKAGE FOR Wash Water Pump/Economizer(SS 3001/IW-02;PKG No.038)
HYDROTEST PACKAGE FOR Wash Water Pump/Economizer(SS 3001/IW-02;PKG No.038)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-04;PKG No.039)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-04;PKG No.039)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-05;PKG No.040)
HYDROTEST PACKAGE FOR Recycle Water Pumps/Economizer (SS 2008/PW-05;PKG No.040)
BUTT AND/OR FILLET WELD- PIPE TO PIPE, PIPE TO PUP AND PIPE TO FITTINGS PIPING WELDING (WPS NO: AD-SS-02 Rev.0
BUTT AND/OR FILLET WELD- PIPE TO PIPE, PIPE TO PUP AND PIPE TO FITTINGS PIPING WELDING (WPS NO: AD-SS-02 Rev.0
HYDROTEST PACKAGE FOR Treated Water Tank (Tank No.002510015550TA001)
HYDROTEST PACKAGE FOR Treated Water Tank (Tank No.002510015550TA001)
HYDROTEST PACKAGE FOR Treated Water Tank (Tank No..002512015550TA001)
HYDROTEST PACKAGE FOR Treated Water Tank (Tank No..002512015550TA001)
PUNCH LIST FOR WO#1
PUNCH LIST FOR WO#1
PUNCH LIST FOR WO#2
PUNCH LIST FOR WO#2
PUNCH LIST FOR WO#3
PUNCH LIST FOR WO#3
PUNCH LIST FOR WO#4
PUNCH LIST FOR WO#4
CHEMICAL LOADING PROCEDURE - anti-scaling
CHEMICAL LOADING PROCEDURE - anti-scaling
CHEMICAL LOADING PROCEDURE - Corrosion Inhibitor
CHEMICAL LOADING PROCEDURE - Corrosion Inhibitor
CHEMICAL LOADING PROCEDURE - Demulsfier
CHEMICAL LOADING PROCEDURE - Demulsfier
CHEMICAL LOADING PROCEDURE - DIESEL
CHEMICAL LOADING PROCEDURE - DIESEL
COMMISSIONING PERMIT TO WORK (PTW) PROCEDURE
COMMISSIONING PERMIT TO WORK (PTW) PROCEDURE
COMMISSIONING PROCEDURE
COMMISSIONING PROCEDURE
COMMISSIONING TEAM ORGANIZATION CHART
COMMISSIONING TEAM ORGANIZATION CHART
COMMISSIONING TOOLS & EQUIPMENTS LIST
COMMISSIONING TOOLS & EQUIPMENTS LIST
GENERAL LEAK TESTING & INERTING PROCEDURE
GENERAL LEAK TESTING & INERTING PROCEDURE
HANDOVER CERTIFICATES READY FOR COMMISSIONING AND READY FOR STARTUP
HANDOVER CERTIFICATES READY FOR COMMISSIONING AND READY FOR STARTUP
ISOLATION POINTS MANAGEMENT
ISOLATION POINTS MANAGEMENT
OPERATIONAL TEST LIST
OPERATIONAL TEST LIST
OTP (Operational Test Procedure) of Corrosion Inhibitor Injection Unit.
OTP (Operational Test Procedure) of Corrosion Inhibitor Injection Unit.
OTP (Operational Test Procedure) of Dehydrator Package.
OTP (Operational Test Procedure) of Dehydrator Package.
OTP (Operational Test Procedure) of Desalter Package.
OTP (Operational Test Procedure) of Desalter Package.
OTP (Operational Test Procedure) of Emulsifier Inhibitor Injection Unit.
OTP (Operational Test Procedure) of Emulsifier Inhibitor Injection Unit.
OTP (Operational Test Procedure) of Oil Pump.
OTP (Operational Test Procedure) of Oil Pump.
OTP (Operational Test Procedure) of Pack-up IA Compressor
OTP (Operational Test Procedure) of Pack-up IA Compressor
OTP (Operational Test Procedure) of Recycled Water Pump Motor
OTP (Operational Test Procedure) of Recycled Water Pump Motor
OTP (Operational Test Procedure) of Scale Inhibitor Injection Unit
OTP (Operational Test Procedure) of Scale Inhibitor Injection Unit
OTP (Operational Test Procedure) of Wash Water Pump Motor
OTP (Operational Test Procedure) of Wash Water Pump Motor
OTP (Operational Test Procedure) of Produced Water Treatment Package
OTP (Operational Test Procedure) of Produced Water Treatment Package
OTP (Operational Test Procedure) of Produced Water Treatment Drain Pit Pumps
OTP (Operational Test Procedure) of Produced Water Treatment Drain Pit Pumps
PRE-COMMISSIONING PROCEDURE (CHECK LISTS & STATIC TEST SHEETS)
PRE-COMMISSIONING PROCEDURE (CHECK LISTS & STATIC TEST SHEETS)
PRE-COMMISSIONING TEMPORARY TOOLS & EQUIPMENT LIST
PRE-COMMISSIONING TEMPORARY TOOLS & EQUIPMENT LIST
PROCEDURE OF COMMISSIONING WITNESS BY COMPANY
PROCEDURE OF COMMISSIONING WITNESS BY COMPANY
PUNCH LIST MANAGEMENT PROCEDURE
PUNCH LIST MANAGEMENT PROCEDURE
SITE PRE-COMMISSIONING WITNESS BY COMMISSIONING
SITE PRE-COMMISSIONING WITNESS BY COMMISSIONING
STARTUP ISOLATING LIST
STARTUP ISOLATING LIST
STARTUP SEQUENCE
STARTUP SEQUENCE
SUBSYSTEM IDENTIFICATION LIST
SUBSYSTEM IDENTIFICATION LIST
SWITCHING PROCEDURE FOR ENERGISATION OF EMERGENCY SWITCHBOARDS
SWITCHING PROCEDURE FOR ENERGISATION OF EMERGENCY SWITCHBOARDS
TRAINING PLAN FOR OPERATION
TRAINING PLAN FOR OPERATION
SAND BLAST AND PAINTING PROCEDURE AT SITE
SAND BLAST AND PAINTING PROCEDURE AT SITE
PAINTING METHOD OF STATEMENT FOR TREATED WATER TANK
PAINTING METHOD OF STATEMENT FOR TREATED WATER TANK
FLUSHING PROCEDURE
FLUSHING PROCEDURE
TYPICAL DRAWINGS FOR UNDERGROUND PIPING
TYPICAL DRAWINGS FOR UNDERGROUND PIPING
TOPOGRAPHIC SURVEY REPORT
TOPOGRAPHIC SURVEY REPORT
METHOD STATEMENT of UNDERGROUND PIPE INSTALLATION
METHOD STATEMENT of UNDERGROUND PIPE INSTALLATION
WELDING PROCEDURE SPECIFICATION FOR EMC(EM-CS-04)
WELDING PROCEDURE SPECIFICATION FOR EMC(EM-CS-04)
Field Inspection And Test Procedure/Plan (Itp)
Field Inspection And Test Procedure/Plan (Itp)
SITE NOTIFICATION OF INSPECTION PROCEDURE
SITE NOTIFICATION OF INSPECTION PROCEDURE
INSPECTION AND TEST PROCEDURE FOR WATER STORAGE TANK
INSPECTION AND TEST PROCEDURE FOR WATER STORAGE TANK
WELDING BOOK OF SITE WPS/PQR,s
WELDING BOOK OF SITE WPS/PQR,s
INSPECTION AND TEST PLAN FOR STORAGE TANK
INSPECTION AND TEST PLAN FOR STORAGE TANK
Visual Inspection Procedure for Structure Welds
Visual Inspection Procedure for Structure Welds
INSPECTION AND TEST PLAN FOR SITE ERECTION OF BRIDGE CRANE
INSPECTION AND TEST PLAN FOR SITE ERECTION OF BRIDGE CRANE
INSPECTION AND TEST PLAN FOR GATCH PAVING
INSPECTION AND TEST PLAN FOR GATCH PAVING
METHOD STATEMENT FOR 6.6 kV MAIN CABLE ROUTING WORK
METHOD STATEMENT FOR 6.6 kV MAIN CABLE ROUTING WORK
METHOD STATEMENT FOR HYDROSTATIC TEST
METHOD STATEMENT FOR HYDROSTATIC TEST
INSPECTION DATA SHEET (IDS) FOR DIAPHRAGM PUMP
REQUIRED DOCUMENT DATA SHEET (RDDS) FOR DIAPHRAGM PUMP
DATA SHEET FOR FIRE PROOFING MATERIAL
DATA SHEET FOR FIRE PROOFING MATERIAL
METHOD OF STATEMENT FOR DISMANTLING EXISTING ACCESS PLATFORM AT UPPER MIDDLE SATELLITE
METHOD OF STATEMENT FOR DISMANTLING EXISTING ACCESS PLATFORM AT UPPER MIDDLE SATELLITE
START-UP PROCEDURE (DRY TO WET)
START-UP PROCEDURE (DRY TO WET)
Surveillance
Eni Document ID Validity Status Type
00250600DADQ0035M EX-CO A
00250600DADQ0033M EX-CO A
00250600DADQ0034M EX-CO A
00250600DADQ0032M EX-CO I
00250600DAST0054M EX-CO I
00250600DASG0049M EX-CO I
00250600DASG0053M EX-CO I
00250600DADB0060M EX-CO I
00250600DAST0052M EX-CO I
00250600DAST0055M EX-CO I
00250600DADQ0030M EX-DE A
00250600DADQ0030M EX-CO I
00250600DADQ0058M EX-CO I
00250600DADQ0056M EX-CO I
00250600DADQ0057M EX-CO I
00250600DASS5001M EX-CO I
00250600DASG0042M EX-CO A
00250600DASG0051M EX-CO I
00250600DASG0045M EX-CO I
00250600DASG0046M EX-CO I
00250600DASG0043M EX-CO I
00250600DASG0041M EX-CO I
00250600DASG0044M EX-CO I
00250600DASG0050M EX-CO I
00250600DASG0048M EX-CO I
00250600DASG0047M EX-CO I
00250600DADQ0039M EX-CO I
00250600DADQ0038M EX-CO I
00250600DAGC0061M EX-CO A
00250600DADQ0040M EX-CO I
00250600DADQ0037M EX-CO I
00250600DADQ0059M EX-CO I
00250600DADQ0036M EX-CO I
00250600DARS5011M EX-DE I
00250600DARS5011M EX-CO I
00250600DARS5012M EX-DE I
00250600DARS5012M EX-CO I
00250600DEGB0036M EX-CO A
00250600DEST0089M EX-CO I
00250600DEST0025M EX-DE I
00250600DEST0025M EX-CO A
00250600DEST0091M EX-CO A
00250600DEST0088M EX-CO A
00250603DESF5358M EX-CO A
00250600DEGB0038M EX-CO A
00250600DEGC0061M EX-CO A
00250600DEST0007M EX-DE A
00250600DEST0007M EX-CO A
00250600DEGB0040M EX-CO A
00250600DEGB0039M EX-CO A
00250600DEGC0063M EX-CO A
00250600DEGC0059M EX-CO A
00250600DEGC0062M EX-CO A
00250600DEST0028M EX-DE A
00250600DEST0028M EX-CO A
00250600DEST0090M EX-CO A
00250600DEGB0037M EX-CO A
00250600DEGC0060M EX-CO A
00250600DEST0087M EX-CO A
00250600DEGB0035M EX-CO A
00250600DEGC0058M EX-CO A
00250600DEST0086M EX-CO A
00250600DEGB0034M EX-CO A
00250600DEGB0083M EX-CO A
00250600DEGC0057M EX-CO A
00250600DEGC0084M EX-CO A
00250600DEST0008M EX-DE A
00250600DEST0008M EX-CO A
00250600DESF5353M EX-CO A
00250603DEEP5350M EX-CO A
00250603DESF5357M EX-CO A
00250600DESF5355M EX-CO A
00250600DESF5356M EX-CO A
00250600DESF5352M EX-CO A
00250600DESF5354M EX-CO A
00250600DESF5351M EX-CO A
00250600DEST0006M EX-DE A
00250600DEST0006M EX-CO A
00250600DEGB0047M EX-CO A
00250600DEGC0048M EX-CO A
00250600DGPG0001M EX-DE A
00250600DGPG0001M EX-CO A
00250600DGPT0007M EX-DE A
00250600DGPT0007M EX-CO I
00250600DGPL0014M EX-DE I
00250600DGPL0014M EX-CO I
00250600DGPL0013M EX-DE I
00250600DGPL0013M EX-CO I
00250600DHPF0008M EX-DE I
00250600DHPF0008M EX-CO I
00250600DHRV1001M EX-DE I
00250600DHRV1001M EX-CO I
00250600DGRG0032M EX-DE I
00250600DGRG0032M EX-CO I
00250600DGED0002M EX-DE I
00250600DGED0002M EX-CO I
00250600DGED0003M EX-DE I
00250600DGED0003M EX-CO I
00250600DGED0004M EX-DE I
00250600DGED0004M EX-CO I
00250600DGPP0019M EX-DE I
00250600DGPP0019M EX-CO I
00250600DGRG0031M EX-DE I
00250600DGRG0031M EX-CO I
00250600DGPG0012M EX-DE I
00250600DGPG0012M EX-CO I
00250600DGST0010M EX-DE I
00250600DGST0010M EX-CO A
00250600DGED0005M EX-DE A
00250600DGED0005M EX-CO I
00250600DGSG0001M EX-CO I
00250600DFPV3007M EX-DE I
00250600DFPV3007M EX-CO I
00250600DFPV3008M EX-DE I
00250600DFPV3008M EX-CO I
00250600DFPA0026M EX-DE I
00250600DFPA0026M EX-CO I
00250600DFPG3002M EX-DE A
00250600DFPG3002M EX-CO A
00250600DFRS3003M EX-DE I
00250600DFRS3003M EX-CO I
00250600DFPG3005M EX-DE I
00250600DFPG3005M EX-CO I
00250600DFPV3010M EX-DE I
00250600DFPV3010M EX-CO I
00250600DFPV3009M EX-DE I
00250600DFPV3009M EX-CO I
00250600DFRZ3006M EX-DE I
00250600DFRZ3006M EX-CO I
00250600DFPV3011M EX-DE I
00250600DFPV3011M EX-CO I
00250600DFPG3004M EX-DE I
00250600DFPG3004M EX-CO I
00250600DFPA3001M EX-DE I
00250600DFPA3001M EX-CO I
00250600DFPV3012M EX-DE I
00250600DFPV3012M EX-CO I
00250600DFPV3019M EX-DE I
00250600DFPV3019M EX-CO I
00250600DFPV3013M EX-DE I
00250600DFPV3013M EX-CO I
00250600DFPV3017M EX-DE I
00250600DFPV3017M EX-CO I
00250600DFPV3021M EX-DE I
00250600DFPV3021M EX-CO I
00250600DFPV3015M EX-DE I
00250600DFPV3015M EX-CO I
00250600DFPV3014M EX-DE I
00250600DFPV3014M EX-CO I
00250600DFPV3018M EX-DE I
00250600DFPV3018M EX-CO I
00250600DFPV3020M EX-DE I
00250600DFPV3020M EX-CO I
00250600DFPV3016M EX-DE I
00250600DFPV3016M EX-CO I
00250600DFPV3022M EX-DE I
00250600DFPV3022M EX-CO I
00250600DFPU0034M EX-DE I
00250600DFPU0034M EX-CO I
00250600DFPU0035M EX-DE I
00250600DFPU0035M EX-CO I
00250600DFST0023M EX-DE I
00250600DFST0023M EX-CO I
00250600DFPU0014M EX-CO I
00250600DIGC0070M EX-CO I
00250600DIGB0067M EX-CO A
00250600DISH0043M EX-CO I
00250600DISG0037M EX-CO A
00250600DIST0050M EX-CO A
00250600DIST0061M EX-DE A
00250600DIST0061M EX-CO I
00250600DIST0044M EX-CO A
00250600DIST0049M EX-CO A
00250600DIGC0069M EX-CO A
00250600DIGB0066M EX-CO I
00250600DISF0027M EX-CO A
00250600DISF0026M EX-CO A
00250600DISG0191M EX-CO A
00250600DISG0039M EX-CO A
00250600DIST0038M EX-CO A
00250600DIST0040M EX-CO A
00250600DIGC0072M EX-CO I
00250600DIGB0068M EX-CO A
00250600DIGC0071M EX-CO A
00250600DIGB0009M EX-CO A
00250600DIST0042M EX-CO A
00250600DIST0062M EX-DE A
00250600DIST0062M EX-CO A
00250600DIGB0002M EX-CO I
00250611DIEJ5229M EX-CO A
00250600DIGC0015M EX-CO A
00250600DIGB0006M EX-CO A
00250603DIEJ5409M EX-CO A
00250600DIGC0017M EX-CO I
00250600DIGB0008M EX-CO A
00250600DIGC0016M EX-CO A
00250600DIGB0007M EX-CO A
00250600DIGC0014M EX-CO A
00250600DIGB0005M EX-CO A
00250600DIGC0011M EX-CO A
00250600DISF5006M EX-DE A
00250600DISF5006M EX-CO A
00250600DISG0052M EX-CO A
00250600DISG0051M EX-CO A
00250600DISG0089M EX-CO A
00250600DISG0056M EX-CO A
00250600DIGB0090M EX-CO A
00250600DISG0053M EX-CO A
00250600DISG0055M EX-CO A
00250600DISG0054M EX-CO A
00250600DIGC0094M EX-CO A
00250600DIGB0091M EX-CO A
00250600DIGC0093M EX-CO A
00250600DMSG0003M EX-CO A
00250600DMGB0005M EX-CO A
00250600DMGC0001M EX-CO A
00250600DMGC0004M EX-CO A
00250600DMST0032M EX-CO A
00250600DXRV0001M EX-CO A
00250600DVSG0004M EX-CO A
00250600DVGB0005M EX-CO A
00250600DVST0010M EX-CO A
00250600DVGC0003M EX-CO A
00250600DVGB0002M EX-CO A
00250600DVST0006M EX-CO A
00250600DVGC0007M EX-CO A
00250600DVGB0009M EX-CO A
00250600DVGC0008M EX-CO A
00250600DVST0011M EX-CO A
00250600DTST0008M EX-CO A
00250600DTSG0006M EX-CO A
00250600DTGB0052M EX-CO A
00250600DTGB0054M EX-CO A
00250600DTGB0033M EX-CO A
00250600DTGB0051M EX-CO A
00250600DTSG0007M EX-CO A
00250600DTGC0053M EX-CO A
00250600DTSG0003M EX-CO A
00250600DTSG0002M EX-CO A
00250600DTSG0004M EX-CO A
00250600DTGB0055M EX-CO A
00250600DTGB0047M EX-CO A
00250600DTGC0048M EX-CO A
00250600DTGB0032M EX-CO A
00250600DTGC0031M EX-CO A
00250600DTGB0049M EX-CO A
00250600DTGC0050M EX-CO A
00250600DTSG0005M EX-CO A
00250600DTSG0001M EX-CO A
00250600DTQR5016M EX-DE A
00250600DTQR5016M EX-CO A
00250600DPRB0100M EX-CO A
00250600DPFM0005M EX-DE A
00250600DPFM0005M EX-CO A
00250600DBQR2002M EX-DE A
00250600DBQR2002M EX-CO A
00250600DBQR2001M EX-DE A
00250600DBQR2001M EX-CO A
00250600DBQR2005M EX-DE A
00250600DBQR2005M EX-CO A
00250600DBQR2003M EX-DE A
00250600DBQR2003M EX-CO A
00250600DBQA0024M EX-DE A
00250600DBQA0024M EX-CO A
00250600DBQA0021M EX-DE A
00250600DBQA0021M EX-CO A
00250600DBQR2004M EX-DE A
00250600DBQR2004M EX-CO I
00250600DBQR2012M EX-DE I
00250600DBQR2012M EX-CO I
00250600DBQR2019M EX-DE I
00250600DBQR2019M EX-CO I
00250600DBQR2006M EX-DE I
00250600DBQR2006M EX-CO I
00250600DBQR2010M EX-DE I
00250600DBQR2010M EX-CO I
00250600DBQN2020M EX-DE I
00250600DBQN2020M EX-CO I
00250600DBQR2008M EX-DE I
00250600DBQR2008M EX-CO I
00250600DBQR2018M EX-DE I
00250600DBQR2018M EX-CO I
00250600DBQR2009M EX-DE I
00250600DBQR2009M EX-CO I
00250600DBQR2014M EX-DE I
00250600DBQR2014M EX-CO I
00250600DBQR2016M EX-DE I
00250600DBQR2016M EX-CO I
00250600DBQR2007M EX-DE I
00250600DBQR2007M EX-CO I
00250600DGPT1007M EX-DE I
00250600DGPT1007M EX-CO I
00250600DGPP1006M EX-DE I
00250600DGPP1006M EX-CO I
00250600BGSG0011M EX-CO I
00250600DIDR5062M EX-DE I
00250600DIDR5062M EX-CO I
00250600DIDR5063M EX-DE I
00250600DIDR5063M EX-CO I
00250600DBQR2022M EX-DE A
00250600DBQR2022M EX-CO A
00250600DBPS4004M EX-DE A
00250600DBPS4004M EX-CO A
00250600DF PV4005M EX-DE A
00250600DF PV4005M EX-CO A
00250600DBQB4006M EX-DE A
00250600DBQB4006M EX-CO A
00250600DBQB4007M EX-DE A
00250600DBQB4007M EX-CO A
00250600DBQB4008M EX-DE I
00250600DBQB4008M EX-CO I
00250600DBQB4009M EX-DE I
00250600DBQB4009M EX-CO I
00250600DBQB4010M EX-DE I
00250600DBQB4010M EX-CO I
00250600DBQB4011M EX-DE I
00250600DBQB4011M EX-CO I
00250600DBQB4012M EX-DE I
00250600DBQB4012M EX-CO I
00250600DBQB4013M EX-DE I
00250600DBQB4013M EX-CO I
00250600DBQB4014M EX-DE I
00250600DBQB4014M EX-CO I
00250600DBQB4015M EX-DE I
00250600DBQB4015M EX-CO I
00250600DBQB4017M EX-DE A
00250600DBQB4017M EX-CO A
00250600DBQB4018M EX-DE I
00250600DBQB4018M EX-CO I
00250600DBQB4019M EX-DE A
00250600DBQB4019M EX-CO A
00250600DBQB4020M EX-DE A
00250600DBQB4020M EX-CO A
00250600DBQB4021M EX-DE A
00250600DBQB4021M EX-CO A
00250600DBQB4022M EX-DE A
00250600DBQB4022M EX-CO A
00250600DBQB4023M EX-DE A
00250600DBQB4023M EX-CO A
00250600DBQB4024M EX-DE A
00250600DBQB4024M EX-CO A
00250600DBQB4025M EX-DE A
00250600DBQB4025M EX-CO A
00250600DBQB4026M EX-DE A
00250600DBQB4026M EX-CO A
00250600DBQB4027M EX-DE A
00250600DBQB4027M EX-CO A
00250600DBQB4028M EX-DE A
00250600DBQB4028M EX-CO A
00250600DBQB4029M EX-DE A
00250600DBQB4029M EX-CO A
00250600DBQB4030M EX-DE A
00250600DBQB4030M EX-CO A
00250600DBQB4031M EX-DE A
00250600DBQB4031M EX-CO A
00250600DBQB4032M EX-DE A
00250600DBQB4032M EX-CO A
00250600DBQB4033M EX-DE A
00250600DBQB4033M EX-CO A
00250600DBQB4034M EX-DE A
00250600DBQB4034M EX-CO A
00250600DBQB4035M EX-DE A
00250600DBQB4035M EX-CO A
00250600DBQB4036M EX-DE A
00250600DBQB4036M EX-CO A
00250600DBQB4037M EX-DE A
00250600DBQB4037M EX-CO A
00250600DBQB4038M EX-DE A
00250600DBQB4038M EX-CO A
00250600DBQB4039M EX-DE A
00250600DBQB4039M EX-CO A
00250600DBQB4040M EX-DE A
00250600DBQB4040M EX-CO A
00250600DBQB4041M EX-DE A
00250600DBQB4041M EX-CO A
00250600DBQB4042M EX-DE A
00250600DBQB4042M EX-CO A
00250600DBQB4043M EX-DE A
00250600DBQB4043M EX-CO A
00250600DBQB4044M EX-DE A
00250600DBQB4044M EX-CO A
00250600DBQB4045M EX-DE A
00250600DBQB4045M EX-CO A
00250600DBQB4046M EX-DE A
00250600DBQB4046M EX-CO A
00250600DBQB4047M EX-DE I
00250600DBQB4047M EX-CO I
00250600DBQB4048M EX-DE I
00250600DBQB4048M EX-CO I
00250600DBQB4049M EX-DE A
00250600DBQB4049M EX-CO A
00250600DBPV4050M EX-DE A
00250600DBPV4050M EX-CO A
00250600DBPS4051M EX-DE A
00250600DBPS4051M EX-CO A
00250600DBPC4053M EX-DE A
00250600DBPC4053M EX-CO A
00250600DBPC4054M EX-DE A
00250600DBPC4054M EX-CO A
00250600DBPC4055M EX-DE A
00250600DBPC4055M EX-CO A
00250600DBPF4056M EX-DE A
00250600DBPF4056M EX-CO A
00250600DBPC4057M EX-DE A
00250600DBPC4057M EX-CO A
00250600DBPC4058M EX-DE A
00250600DBPC4058M EX-CO A
00250600DBPC4059M EX-DE A
00250600DBPC4059M EX-CO A
00250600DBPV4060M EX-DE A
00250600DBPV4060M EX-CO A
00250600DBPC4061M EX-DE A
00250600DBPC4061M EX-CO A
00250600DBPC4062M EX-DE A
00250600DBPC4062M EX-CO A
00250600DBPC4063M EX-DE A
00250600DBPC4063M EX-CO A
00250600DBPV4064M EX-DE A
00250600DBPV4064M EX-CO A
00250600DBPV4065M EX-DE A
00250600DBPV4065M EX-CO A
00250600DBPC4066M EX-DE A
00250600DBPC4066M EX-CO A
00250600DBPC4067M EX-DE A
00250600DBPC4067M EX-CO A
00250600DBPC4068M EX-DE A
00250600DBPC4068M EX-CO A
00250600DBPS4069M EX-DE A
00250600DBPS4069M EX-CO A
00250600DBPC4070M EX-DE A
00250600DBPC4070M EX-CO A
00250600DBPC4071M EX-DE A
00250600DBPC4071M EX-CO A
00250600DBPC4072M EX-DE A
00250600DBPC4072M EX-CO A
00250600DBPC4073M EX-DE A
00250600DBPC4073M EX-CO I
00250600DFPA4075M EX-DE A
00250600DFPA4075M EX-CO A
00250600DFPA4076M EX-DE A
00250600DFPA4076M EX-CO A
00250600DFMO4077M EX-DE A
00250600DFMO4077M EX-CO A
00250600DFMS4078M EX-DE A
00250600DFMS4078M EX-CO A
00250600DFEA4079M EX-DE A
00250600DFEA4079M EX-CO A
00250600DFRS4080M EX-DE A
00250600DFRS4080M EX-CO A
00250600DESF5366M EX-CO A
00250600DISF5007M EX-CO A
00250600DISF5008M EX-CO A
00250600DISF5009M EX-CO A
00250600DISF5010M EX-CO A
00250600DISF5011M EX-CO A
00250600DISF5012M EX-CO A
00250600DISF5013M EX-CO A
00250600DISF5014M EX-CO A
00250600DISF5015M EX-CO A
00250600DISF5016M EX-CO A
00250600DISF5017M EX-CO A
00250600DISF5018M EX-CO A
00250600DISF5019M EX-CO A
00250600DISF5020M EX-CO A
00250600DISF5021M EX-CO A
00250600DISF5023M EX-CO A
00250600DISF5025M EX-CO A
00250600DISF5027M EX-CO A
00250600DISF5029M EX-CO A
00250600DTSF5001M EX-CO A
00250600DTSF5002M EX-CO A
00250600DTSF5004M EX-CO A
00250600DTSF5005M EX-CO A
00250600DTSF5006M EX-CO A
00250600DTSF5007M EX-CO A
00250600DTSF5009M EX-CO A
00250600DTSF5010M EX-CO A
00250600DTSF5011M EX-CO A
00250600DTSF5012M EX-CO A
00250600DTSF5050M EX-CO A
00250600DTSF5008M EX-CO A
00250600DTSF5014M EX-CO A
00250600DGPL0016M EX-DE A
00250600DGPL0016M EX-CO A
00250600DGPL0015M EX-DE A
00250600DGPL0015M EX-CO A
00250600DBQB2023M EX-DE A
00250600DBQB2023M EX-CO A
00250600DBQB2024M EX-DE A
00250600DBQB2024M EX-CO A
00250600DEFU0142M EX-DE A
00250600DEFU0142M EX-CO A
00250600DJPC0009M EX-DE A
00250600DJPC0009M EX-CO A
00250600DGED0006M EX-DE A
00250600DGED0006M EX-CO A
00250600DFRB0040M EX-DE A
00250600DFRB0040M EX-CO A
00250600DBQB2008M EX-DE A
00250600DBQB2008M EX-CO A
00250600DBQB4081M EX-DE A
00250600DBQB4081M EX-CO A
00250600DBQB4082M EX-DE A
00250600DBQB4082M EX-CO A
00250600DBQB4083M EX-DE A
00250600DBQB4083M EX-CO A
00250600DBQB4084M EX-DE A
00250600DBQB4084M EX-CO A
00250600DBQB4085M EX-DE A
00250600DBQB4085M EX-CO A
00250600DBQB4086M EX-DE A
00250600DBQB4086M EX-CO A
00250600DBQB4087M EX-DE A
00250600DBQB4087M EX-CO A
00250600DXRV0002M EX-DE A
00250600DXRV0002M EX-CO A
00250600DISF5071M EX-CO A
00250600DTGB5070M EX-CO A
00250600DTGB5069M EX-CO A
00250600DTGB5071M EX-CO A
00250600DTGC5073M EX-CO A
00250600DTGC5072M EX-CO A
00250600DTGC5074M EX-CO A
00250600DISF5031M EX-CO A
00250600DHRV1001M EX-DE A
00250600DHRV1001M EX-CO A
00250600DHRV1002M EX-DE A
00250600DHRV1002M EX-CO A
00250601DIEI0092M EX-DE A
00250601DIEI0092M EX-CO A
00250600DISF5072M EX-CO A
00250600DISF5073M EX-CO A
00250600DIDQ5074M EX-DE A
00250600DIDQ5074M EX-CO A
00250600DISF5075M EX-CO A
00250600DIDQ5076M EX-DE A
00250600DIDQ5076M EX-CO A
00250600DIGA5077M EX-DE A
00250600DIGA5077M EX-CO A
00250600DBQR2023M EX-DE I
00250600DBQR2023M EX-CO I
00250600DTDQ5075M EX-DE A
00250600DTDQ5075M EX-CO A
00250600DFST0041M EX-DE I
00250600DFST0041M EX-CO I
00250600DBPC4081M EX-DE I
00250600DBPC4081M EX-CO I
00250600DEPC4082M EX-DE I
00250600DEPC4082M EX-CO I
00250600DBPC4083M EX-DE I
00250600DBPC4083M EX-CO I
00250600DEPC4084M EX-DE I
00250600DEPC4084M EX-CO I
00250600DBPC4085M EX-DE I
00250600DBPC4085M EX-CO I
00250600DBPC4087M EX-DE I
00250600DBPC4087M EX-CO I
00250600DEPC4602M EX-DE I
00250600DEPC4602M EX-CO I
00250600DEPC4600M EX-DE I
00250600DEPC4600M EX-CO I
00250600DEPC4601M EX-DE I
00250600DEPC4601M EX-CO I
00250600DBPC4083M EX-DE I
00250600DBPC4083M EX-CO I
00250600DEPC4603M EX-DE I
00250600DEPC4603M EX-CO I
00250600DEPC4605M EX-DE I
00250600DEPC4605M EX-CO I
00250600DEPC4606M EX-DE I
00250600DEPC4606M EX-CO I
00250600DEPC4607M EX-DE I
00250600DEPC4607M EX-CO I
00250600DEPC4608M EX-DE I
00250600DEPC4608M EX-CO I
00250600DEPC4609M EX-DE I
00250600DEPC4609M EX-CO I
00250600DBPC4086M EX-DE I
00250600DBPC4086M EX-CO I
00250600DBPC4400M EX-DE I
00250600DBPC4400M EX-CO I
00250600DBPC4401M EX-DE I
00250600DBPC4401M EX-CO I
00250600DTPC4202M EX-DE I
00250600DTPC4202M EX-CO I
00250901DAPC4101M EX-DE I
00250901DAPC4101M EX-CO I
00251001DJPC4402M EX-DE I
00251001DJPC4402M EX-CO I
00251201DJPC4403M EX-DE I
00251201DJPC4403M EX-CO I
00251001DJPC4404M EX-DE I
00251001DJPC4404M EX-CO I
00251201DJPC4405M EX-DE I
00251201DJPC4405M EX-CO I
00250600DTPC EX-DE I
00250600DTPC EX-CO I
00250600DTPC4501M EX-DE I
00250600DTPC4501M EX-CO I
00250600DTPC4502M EX-DE I
00250600DTPC4502M EX-CO I
00250600DTPC4503M EX-DE I
00250600DTPC4503M EX-CO I
00250600DTPC4504M EX-DE I
00250600DTPC4504M EX-CO I
00250600DTPC4505M EX-DE I
00250600DTPC4505M EX-CO I
00250600DTPC4506M EX-DE I
00250600DTPC4506M EX-CO I
00250600DJPC4406M EX-DE I
00250600DJPC4406M EX-CO I
00250600DJPC4407M EX-DE I
00250600DJPC4407M EX-CO I
00250600DJPC4408M EX-DE I
00250600DJPC4408M EX-CO I
00250600DJPC4409M EX-DE I
00250600DJPC4409M EX-CO I
00250600DFPV3023M EX-DE I
00250600DFPV3023M EX-CO I
00250600DFPV3024M EX-DE I
00250600DFPV3024M EX-CO I
00250600DFPV3025M EX-DE I
00250600DFPV3025M EX-CO I
00250600DFPV3026M EX-DE I
00250600DFPV3026M EX-CO I
00250600DFPV3027M EX-DE I
00250600DFPV3027M EX-CO I
00250600DFPV3028M EX-DE I
00250600DFPV3028M EX-CO I
00250600DFPV3029M EX-DE I
00250600DFPV3029M EX-CO I
00250600DFPV3030M EX-DE I
00250600DFPV3030M EX-CO I
00250600DFPV3031M EX-DE I
00250600DFPV3031M EX-CO I
00250600DFPV3032M EX-DE I
00250600DFPV3032M EX-CO I
00250600DFPV3033M EX-DE I
00250600DFPV3033M EX-CO I
00250600DFPV3034M EX-DE I
00250600DFPV3034M EX-CO I
00250600DFPV3035M EX-DE I
00250600DFPV3035M EX-CO I
00250600DISF5078M EX-CO I
00250600DISF5079M EX-CO I
00250600DISF5076M EX-CO I
00250600DVSF7900M EX-CO I
00250600DBQR4088M EX-DE I
00250600DBQR4088M EX-CO I
00250600DBQR4089M EX-DE I
00250600DBQR4089M EX-CO I
00250600DBQR4090M EX-DE I
00250600DBQR4090M EX-CO I
00250600DBQR4091M EX-DE I
00250600DBQR4091M EX-CO I
00250600DBQR4092M EX-DE I
00250600DBQR4092M EX-CO I
00250600DBQB4093M EX-DE I
00250600DBQB4093M EX-CO I
00250600DBQB4094M EX-DE I
00250600DBQB4094M EX-CO I
00250600DBQB4095M EX-DE I
00250600DBQB4095M EX-CO I
00250600DBQB4096M EX-DE I
00250600DBQB4096M EX-CO I
00250600DBQR4097M EX-DE I
00250600DBQR4097M EX-CO I
00250600DBQR4098M EX-DE I
00250600DBQR4098M EX-CO I
00250600DBQR4099M EX-DE I
00250600DBQR4099M EX-CO I
00250600DBQR4800M EX-DE I
00250600DBQR4800M EX-CO I
00250600DBQR4801M EX-DE I
00250600DBQR4801M EX-CO I
00250600DBQR4802M EX-DE I
00250600DBQR4802M EX-CO I
00250600DBQR4803M EX-DE I
00250600DBQR4803M EX-CO I
00250600DBQR4804M EX-DE I
00250600DBQR4804M EX-CO I
00250600DBQR4805M EX-DE I
00250600DBQR4805M EX-CO I
00250600DBQR4806M EX-DE I
00250600DBQR4806M EX-CO I
00250600DFPV3036M EX-DE I
00250600DFPV3036M EX-CO I
00250600DFPV3037M EX-DE I
00250600DFPV3037M EX-CO I
00250600DFPV3038M EX-DE I
00250600DFPV3038M EX-CO I
00250600DFPV3039M EX-DE I
00250600DFPV3039M EX-CO I
00250600DFPV3040M EX-DE I
00250600DFPV3040M EX-CO I
00250600DFPV3041M EX-DE I
00250600DFPV3041M EX-CO I
00250600DFPV3042M EX-DE I
00250600DFPV3042M EX-CO I
00250600DFPV3043M EX-DE I
00250600DFPV3043M EX-CO I
00250600DFPV3044M EX-DE I
00250600DFPV3044M EX-CO I
00250600DFPV3045M EX-DE I
00250600DFPV3045M EX-CO I
00250600DFPV3046M EX-DE I
00250600DFPV3046M EX-CO I
00250600DFPV3047M EX-DE I
00250600DFPV3047M EX-CO I
00250600DFPV3048M EX-DE I
00250600DFPV3048M EX-CO I
00250600DTPC1001M EX-DE I
00250600DTPC1001M EX-CO I
00250600DBQR3049M EX-DE I
00250600DBQR3049M EX-CO I
00250600DBQR3050M EX-DE I
00250600DBQR3050M EX-CO I
00250600DBQR3051M EX-DE I
00250600DBQR3051M EX-CO I
00250600DBPV3052M EX-DE I
00250600DBPV3052M EX-CO I
00250600DBQR3053M EX-DE I
00250600DBQR3053M EX-CO I
00250600DBPV3054M EX-DE I
00250600DBPV3054M EX-CO I
00250600DBQR3055M EX-DE I
00250600DBQR3055M EX-CO I
00250600DBQR3056M EX-DE I
00250600DBQR3056M EX-CO I
00250600DBQR3057M EX-DE I
00250600DBQR3057M EX-CO I
00250600DBPV3058M EX-DE I
00250600DBPV3058M EX-CO I
00250600DBQR3059M EX-DE I
00250600DBQR3059M EX-CO I
00250600DBQR3060M EX-DE I
00250600DBQR3060M EX-CO I
00250600DBPV3061M EX-DE I
00250600DBPV3061M EX-CO I
00250600DBPV3062M EX-DE I
00250600DBPV3062M EX-CO I
00250600DISF5081M EX-CO I
00250600DADB9801M EX-DE I
00250600DADB9801M EX-CO I
00250600DACC9802M EX-DE I
00250600DACC9802M EX-CO I
00250600DBPV3063M EX-DE I
00250600DBPV3063M EX-CO I
00250600DBSS3064M EX-DE I
00250600DBSS3064M EX-CO I
00250600DFPV3065M EX-DE I
00250600DFPV3065M EX-CO I
00251200DBQR8000M EX-DE I
00251200DBQR8000M EX-CO I
00250600DBQR8001M EX-DE I
00250600DBQR8001M EX-CO I
00250600DBQR8002M EX-DE I
00250600DBQR8002M EX-CO I
00250600DBQR8003M EX-DE I
00250600DBQR8003M EX-CO I
00250600DBQR8004M EX-DE I
00250600DBQR8004M EX-CO I
00250600DBQR8005M EX-DE I
00250600DBQR8005M EX-CO I
00250600DBQR8006M EX-DE I
00250600DBQR8006M EX-CO I
00250600DBQR8007M EX-DE I
00250600DBQR8007M EX-CO I
00250600DBQR8008M EX-DE I
00250600DBQR8008M EX-CO I
00250600DBQR8009M EX-DE I
00250600DBQR8009M EX-CO I
00250600DBQR8010M EX-DE I
00250600DBQR8010M EX-CO I
00250600DBQR8011M EX-DE I
00250600DBQR8011M EX-CO I
00250600DBQR8012M EX-DE I
00250600DBQR8012M EX-CO I
00250600DBQR8013M EX-DE I
00250600DBQR8013M EX-CO I
00250600DBQR8014M EX-DE I
00250600DBQR8014M EX-CO I
00250600DBQR8015M EX-DE I
00250600DBQR8015M EX-CO I
00250600DBQR8016M EX-DE I
00250600DBQR8016M EX-CO I
00250600DBQR8017M EX-DE I
00250600DBQR8017M EX-CO I
00250600DBQR8018M EX-DE I
00250600DBQR8018M EX-CO I
00250600DBQR8019M EX-DE I
00250600DBQR8019M EX-CO I
00250600DBQR8020M EX-DE I
00250600DBQR8020M EX-CO I
00250600DBQR8021M EX-DE I
00250600DBQR8021M EX-CO I
00250600DBQR8022M EX-DE I
00250600DBQR8022M EX-CO I
00250600DBQR8023M EX-DE I
00250600DBQR8023M EX-CO I
00250600DBQR8024M EX-DE I
00250600DBQR8024M EX-CO I
00250600DBQR8025M EX-DE I
00250600DBQR8025M EX-CO I
00250600DBQR8026M EX-DE I
00250600DBQR8026M EX-CO I
00250600DBQR8027M EX-DE I
00250600DBQR8027M EX-CO I
00250600DBQR8028M EX-DE I
00250600DBQR8028M EX-CO I
00250600DBQR8029M EX-DE I
00250600DBQR8029M EX-CO I
00250600DBQR8030M EX-DE I
00250600DBQR8030M EX-CO I
00250600DBQR8031M EX-DE I
00250600DBQR8031M EX-CO I
00250600DBQR8032M EX-DE I
00250600DBQR8032M EX-CO I
00250600DBQR8033M EX-DE I
00250600DBQR8033M EX-CO I
00250600DBQR8034M EX-DE I
00250600DBQR8034M EX-CO I
00250600DBQR8035M EX-DE I
00250600DBQR8035M EX-CO I
00250600DBQR8036M EX-DE I
00250600DBQR8036M EX-CO I
00250600DBQR8037M EX-DE I
00250600DBQR8037M EX-CO I
00250600DBQR8038M EX-DE I
00250600DBQR8038M EX-CO I
00250600DBQR8039M EX-DE I
00250600DBQR8039M EX-CO I
00250600DBQR8040M EX-DE I
00250600DBQR8040M EX-CO I
00250600DBQR8041M EX-DE I
00250600DBQR8041M EX-CO I
00250600DBQR8042M EX-DE I
00250600DBQR8042M EX-CO I
00250600DWPP9000M EX-DE I
00250600DWPP9000M EX-CO I
00250600DWPP9001M EX-DE I
00250600DWPP9001M EX-CO I
00250600DWPP9002M EX-DE I
00250600DWPP9002M EX-CO I
00250600DWPP9003M EX-DE I
00250600DWPP9003M EX-CO I
00250600DWQR9004M EX-DE I
00250600DWQR9004M EX-CO I
00250600DWQR9005M EX-DE I
00250600DWQR9005M EX-CO I
00250600DWQR9006M EX-DE I
00250600DWQR9006M EX-CO I
00250600DWQR9007M EX-DE I
00250600DWQR9007M EX-CO I
00250600DWQR9009M EX-DE I
00250600DWQR9009M EX-CO I
00250600DWQR9010M EX-DE I
00250600DWQR9010M EX-CO I
00250600DWPP9011M EX-DE I
00250600DWPP9011M EX-CO I
00250600DWEA9012M EX-DE I
00250600DWEA9012M EX-CO I
00250600DWQR9013M EX-DE I
00250600DWQR9013M EX-CO I
00250600DWQE9014M EX-DE I
00250600DWQE9014M EX-CO I
00250600DWQR9015M EX-DE I
00250600DWQR9015M EX-CO I
00250600DWPC9016M EX-DE I
00250600DWPC9016M EX-CO I
00250600DWQR9017M EX-DE I
00250600DWQR9017M EX-CO I
00250600DWQR9018M EX-DE I
00250600DWQR9018M EX-CO I
00250600DWQR9019M EX-DE I
00250600DWQR9019M EX-CO I
00250600DWQR9020M EX-DE I
00250600DWQR9020M EX-CO I
00250600DWQR9021M EX-DE I
00250600DWQR9021M EX-CO I
00250600DWQR9023M EX-DE I
00250600DWQR9023M EX-CO I
00250600DWQR9024M EX-DE I
00250600DWQR9024M EX-CO I
00250600DWQR9025M EX-DE I
00250600DWQR9025M EX-CO I
00250600DWQR9026M EX-DE I
00250600DWQR9026M EX-CO I
00250600DWQR9027M EX-DE I
00250600DWQR9027M EX-CO I
00250600DWQR9028M EX-DE I
00250600DWQR9028M EX-CO I
00250600DWQR9029M EX-DE I
00250600DWQR9029M EX-CO I
00250600DWEA9030M EX-DE I
00250600DWEA9030M EX-CO I
00250600DWQR9031M EX-DE I
00250600DWQR9031M EX-CO I
00250600DWPG9032M EX-DE I
00250600DWPG9032M EX-CO I
00250600DWQR9033M EX-DE I
00250600DWQR9033M EX-CO I
00250600DWPC9034M EX-DE I
00250600DWPC9034M EX-CO I
00250600DWPC9035M EX-DE I
00250600DWPC9035M EX-CO I
00250600DWPC9036M EX-DE I
00250600DWPC9036M EX-CO I
00250600DWQR9037M EX-DE I
00250600DWQR9037M EX-CO I
00250600DWQR9038M EX-DE I
00250600DWQR9038M EX-CO I
00250600DJPV4416M EX-DE I
00250600DJPV4416M EX-CO I
00250600DJPC4418M EX-DE I
00250600DJPC4418M EX-CO I
00250600CWQR9040M EX-DE I
00250600CWQR9040M EX-CO I
00250600DADQ0061M EX-DE I
00250600DADQ0061M EX-CO I
00250600DARS4003M EX-DE I
00250600DARS4003M EX-CO I
00250600DBPC4200M EX-DE I
00250600DBPC4200M EX-CO I
00250600DBPV4421M EX-DE I
00250600DBPV4421M EX-CO I
00250600DBQB2021M EX-DE I
00250600DBQB2021M EX-CO I
00250600DBQB2022M EX-DE I
00250600DBQB2022M EX-CO I
00250600DBQB2025M EX-DE I
00250600DBQB2025M EX-CO I
00250600DBQB4072M EX-DE I
00250600DBQB4072M EX-CO I
00250600DBQB4088M EX-DE I
00250600DBQB4088M EX-CO I
00250600DBQR2017M EX-DE I
00250600DBQR2017M EX-CO I
00250600DBQR3063M EX-DE I
00250600DBQR3063M EX-CO I
00250600DBQR3064M EX-DE I
00250600DBQR3064M EX-CO I
00250600DEPC4610M EX-DE I
00250600DEPC4610M EX-CO I
00250600DTPC4500M EX-DE I
00250600DTPC4500M EX-CO I
00250600CMGB0017M EX-CO I
00250600CMGC0018M EX-CO I
00250600DBGB7000M EX-DE I
00250600DBGB7000M EX-CO I
00250600DJPC6000M EX-DE I
00250600DJPC6000M EX-CO I
00250600DWPG9039M EX-DE I
00250600DWPG9039M EX-CO I
First A - Planned First A - Replanned First F -
Discipline Name Date Date Planned Date
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Logistic
Logistic
Logistic
Logistic
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Machinery
Machinery
Machinery
Machinery
Machinery
Corrosion and materials selection
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Mechanical Equipment
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Process
Process
Process
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Electrical
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Electrical
Electrical
Construction and erection/installation
Construction and erection/installation
Interdisciplinary and Miscellaneous
Interdisciplinary and Miscellaneous
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Corrosion and materials selection
Corrosion and materials selection
Instrumentation, Control and Automation
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Instrumentation, Control and Automation
Logistic
Logistic
Logistic
Logistic
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Quality Assurance and Control
Quality Assurance and Control
Plant layout and Piping
Plant layout and Piping
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Quality Assurance and Control
Quality Assurance and Control
Electrical
Electrical
Quality Assurance and Control
Quality Assurance and Control
Electrical
Electrical
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Plant layout and Piping
Plant layout and Piping
Civil and Architectural
Civil and Architectural
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Plant layout and Piping
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Instrumentation, Control and Automation
Instrumentation, Control and Automation
Instrumentation, Control and Automation
HSE (Health Safety & Environment)
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Plant layout and Piping
Plant layout and Piping
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Instrumentation, Control and Automation
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
HSE (Health Safety & Environment)
HSE (Health Safety & Environment)
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
Civil and Architectural
Civil and Architectural
Civil and Architectural
Civil and Architectural
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Quality Assurance and Control
Electrical
Electrical
Plant layout and Piping
Plant layout and Piping
Machinery
Machinery
Quality Assurance and Control
Quality Assurance and Control
Machinery
Machinery
Precommissioning,commissioning and test run
Precommissioning,commissioning and test run
First I - weight
Planned Date value (%) Remark VoWD code