You are on page 1of 9

3rd party inspection

Rumailah combined cycle


730MW power plant project
ALdeqaa

Daily QAQC and NDT inspection activity report


Weather Sunny Temp. 16C Wind speed 5.3 km/h
Humidity 51%
Report No. D.R167Rumaila Date 21/12/2019 Shift time Day shift
Facility CS Power plant Location Block No.1 & 2 Project Code ASME 31.1
HRSG area

1. Daily Welding production summary:


1. Type of welding Number of welder for each w Welding production today
,type
2. SMAW welding 5 welders 26 m (ring welding)
3. SAW Welding 2 welders 11 (horizontal welding )
4. GMAW Welding 2 welders 0 m (ring welding)
5. SMAW welding Steel Structure 5 welders 18m
6. SMAW welding expansion duct chimney 2 welders 0m

2. Welding Electrodes heaters


Main heater 250 Holding 3 hr. QTY 2 Location Work shop Situation Working
temp. time probably
Portable 100 Holding Continues QTY 16 Location 6 Work shop Situation Working
heater time probably
10 steel structure

3. Painting:
location Work progress Comments
CW pipe Checking and monitoring of Sand Blasting activity for CW pipes /
according to procedure
CW pipe Checking and monitoring of Painting for CW pipes according to A paint use roller is
procedure
not recommended
Painting Notes and comments:
*The humidity of the atmosphere should be a maximum of 80%.

P. 1 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

4. NDT inspection activity


Inspection Activities Description Comments
1. VT inspection for the base metal situation and thickness for CW pipes plats /
2. Checking of the rolling activity and roundness for CW pipes /
3. Checking of cutting bevel for CW pipes /
4. Checking the fabrication and the gap of the CW pipe /
5. VT Inspection the tack welding of the CW pipe /
6. VT inspection for all welding activity (SAW,SMAW,GTAW) In ALL project /
7. VT inspection for welding of steel structure /

8. VT inspection for welding of SIDE CASING HRSG #2 /

9. VT inspection for welding of TOP CASING HRSG #1 /

10. VT inspection for hangers panel of boilers welded at workshop of HRSG /


Unit 4

Welding Notes and comments:


*No comment
*cannot check the high level of steel structure welding (waiting for crane 20 ton kindly see memo no.7 date
13/11/2019)
5. Mechanical Inspections:-
NO Activities Description Comments
1 Mechanical Inspection for CCP Structure according to DWGs /
2 Mechanical Inspection for HRSG# 2 according to DWGs /
3 Mechanical Inspection for HRSG# 1 according to DWGs /
4 Mechanical Inspection for HRSG #4 Structure according to DWGs /
5 Mechanical Inspection for MAIN POWER BUILDING Structure according to DWGs /
6 Mechanical Inspection for industrial west water Building Structure according to DWGs /

P. 2 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

6 . Radiographic test
Line no. Number of RT shoots Result Notes
C.W.PIPE diameter 1820 mm 8 6 ACCEPTED and 2 Repair
REJECTED

7. Dye penetrant test


Line no. Total inches Result Notes
No activity today

8. Ultrasonic test
Line no. Total inches Result Notes
No activity today

9. Welders Qualification :-
Position no. Total Result Position
No activity today

10. Other Testes

11. Crane and transport for today and tomorrow


Type of crane Qty Area Note
20 ton crane 1 Block 1 Steel structure Urgently Required for tomorrow (see memo no.7 date
with basket 13/11/2019) for Closed

12. Staff
Name Position Hours Area and shift
Ahmed Basem ASNT L2 QAQC / team leader inspection Engineer 10 Day shift
Suhail Najm ASNT L2 welding inspector Engineer 10 Day shift
Ali waheeb ASNT L2 welding inspector Engineer 10 Day shift
Mustafa jumma ASNT L2 welding inspector Engineer 10 A vacation
Mazin Haleem CWI ASNT L2 Mechanical inspector Engineer 10 Mechanical inspect.

P. 3 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

3. Pictures for today NDT activity:

Mech. Inspection:- Final Tension Bolt for CCP Structure

P. 4 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

Mech. Inspection:- Final Tension Bolt for CCP

P. 5 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

VT inspection for welding of Colums And Beams HRSG #4

P. 6 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

Painting inspection the first layer and Surface roughness for C.W.PIPE
diameter 2240mm

P. 7 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

VT inspection / Welding and Heating electrodes C.W.PIPE

P. 8 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2
3rd party inspection
Rumailah combined cycle
730MW power plant project
ALdeqaa

Mech. Inspection:- Bolt tack weld & covered plate inspection for HRSG#1

Engr.Ahmed Basim
QAQC /3rd party inspector
21/12/2019

P. 9 of 9

ALDEQAA Co, Baghdad ST70DIST 835 07706227680 www.aldeqaa.com haider@aldeqaa.com


Standard Technic co, /Erbil st40
07501692541 www.st--company.co info@st-company.co
Barzanchi Building-Floor No,2

You might also like