ONGOING PMGSY WORKS IN RESPECT OF GOHAR DIVISION HPPWD UP TO 20.10.

2020
Sr. Name of Package No Name of Scheme Sanctioned Date of Expenditure Contractor Date of Awarded Stipulated Present status of Remarks
No. Division amount (Rs In Sanction Incured up to Name Award amount Date of Work (in KMs)_
Lakh) 30.09.2020 (In lakh) Completion
as per
Agreement

1 2 3 4 5 6 7 8 9 10 11 12
1 Gohar HP-08-189 L059-Taraur to Balhari km 0/0 to 194.37 22.02.2017 85.01 Sh. Ajay 18.07.2017 134.97 17.02.2020 FC - 4.440 90 % work completed.
4/900 Sharma Remaining work is in progress.

CD - 2.500
2 Gohar HP-08- 255 C/o Gadog Nallah to Barnog road km 367.32 22.02.2017 - Sh. RP 29.11.2019 297.26 13.05.2021 0.500 KM 5 % work completed. Remaining
0/0 to 5/00 Dhiman work is in progress.

3 Gohar HP08-427 Construction of Matal to Kutachi 136.17 25.09.2017 64.96 Sh. Suresh 04.06.2018 122.56 14.12.2019 CD- 0.250 95 % work completed.
(Bithari to Kutachi) road in Km. 0/0 Kumar Remaining work is in progress.
to 2/510. Sharma GSB-2.510
G-II 2.510
G-III-
2.510
M/T-2.510

4 Gohar HP-08-466 M/T on Segli to Kathla road km. 0/0 271.57 26.03.2018 222.25 Sh. Surender 06.08.2018 252.00 16.02.2020 GSB-6.000 95 % work completed.
to 6/080. Kumar G-II - Remaining work is in progress.
Sharma 6.000

G-III -6.000
5 Gohar HP-08-467 250.09 26.03.2018 273.07 Sh. Jai Singh 19.09.2018 196.25 19.03.2020 CD - 4.000 Work Completed on 07/2020
M/T-5.800
GSB
-4.000
G-II - 4.000
6 Gohar HP08470 Seri Jalah to Mandar Tanda road (L- 236.42 20.12.2018 30.85 S.A. 25.07.2019 166 08.02.2021 GSB- 2.400 60 % work completed.
055) Stage-II km 0/0 to 3/400 (Up- Associates G-II- Remaining work is in progress.
Gradation) 2.400
G-III-2.400
M/T -2.100
7 Gohar HP08471 Dhaban Tamroh Chountra road (L- 382.46 20.12.2018 50.40 Sh. Devaki 25.07.2019 284 08.02.2021 GSB-2.800 35 % work completed.
059) km 0/0 to 5/500 (Up- Nandan G-II Remaining work is in progress.
Gradation) -2.800
Sr. Name of Package No Name of Scheme Sanctioned Date of Expenditure Contractor Date of Awarded Stipulated Present status of Remarks
No. Division amount (Rs In Sanction Incured up to Name Award amount Date of Work (in KMs)_
Lakh) 30.09.2020 (In lakh) Completion
as per
Agreement

1 2 3 4 5 6 7 8 9 10 11 12
8 Gohar HP08476 Naun to Chabli Devidarh road (L- 407.40 20.12.2018 86.15 Sh. Surender 25.07.2019 268.52 08.02.2021 CD-4.250 30% work completed.
026) km 0/0 to 5/700 Kumar GSB-4.000 Remaining work is in progress.
(Up-Gradation) Batch-I, 2018- G-II- 3.000
19(Package No HP 08-474)

9 Gohar HP08484 N.H. Dhanotu to Rohangaloo road (L- 1866.04 20.12.2018 422.58 Sh. Vijay 09.08.2019 1373.00 23.02.2021 ROFD -25.000 CD- ROFD-25.000 Kms, CD- 5 Nos,
104) km 0/0 to 32/400 Kumar 1.250 GSB & G-II in extended portion
(Up-Gradation) Sharma of road =10.00 Kms , G-III -
GSB- 4.000 Kms in full width of road.
30% work completed Remaining
10.000 work is in Progress.
G-II-
10.000
G-III
10 Gohar HP08-540 Up-Gradation of Chail to Moviseri 853.77 13.12.2019 49.91 M/S B.P. 01.06.2020 697.48 15.06.2021 -4.000
ROFD works is in Work is in progress. 10 % work
road KM 0/00 to 11/200 Under Mahajan progress done so far.
PMGSY PMGSY-II

11 Gohar HP08-520 Up-Gradation of Syanh to Dhaban 350.32 13.12.2019 - M/S S.A. 08.06.2020 297.05 21.06.2021 ROFD works is in Work is in progress. 5 % work
road KM 0/00 to 6/200 Under Associates progress done so far.
PMGSY PMGSY-II

Executive Engineer
Gohar Division(B&R)
HP,PWD Gohar