DATE & DAY 31st july & 2nd August

REASON Eid shutdown


ELECTRICAL MAINTENANCE JOB SCHEDULE
TIME
DURATION

SL
DESCRIPTIONS OF THE JOB MANPOWER ATTENDING
SUPERVISED Job start Date
no: BY Time
Stand#5 Drive panel modification Job 31st July & 2nd
1 Nazrul,Titu, Salim, Saddam Iftekhar 6.00am
August
2 Furnace dual conbustion fan software modification & trail job. Belal,Naiem Imrul 9.00am 31-Jul-20
3 Main pulpit spare CPU trail job. Belal,Naiem Imrul 9.00am 31-Jul-20
DC motor(1,3,5,7,9,11,13,15,17,19,sh#1,sh#2) maintenance job & magger test
4 Jafor,Jay,Annaya,Akash Imraz 6.00am 31-Jul-20
DC motor(2,4,6,8,10,12,14,16,18,20,sh#3) maintenance job & magger test
5 Joglu,Kawsar, Rezaul,Khurshed Imraz 6.00am 31-Jul-20
Cooling bed AC motor connection checking, brake coil, positioning proximity
6 Rezaul,Kawsar Imraz 6.00am 31-Jul-20
checking.
Furnace charging area all sensor condition checking & tightening check
7 Raju,Ananya Birol A shift 1-Aug-20
8 Furnace exit area all sensor condition checking & tightening check Raju,Ananya Birol A shift 1-Aug-20
9 Rolling mill area all sensor condition checking & tightening check Jay,Rajesh Birol C shift 1-Aug-20
10 Cooling bed area all sensor condition checking & tightening check Noyon,Ananya Birol B shift 1-Aug-20
11 Stacker area all sensor condition checking & tightening check Noyon,Ananya Birol B shift 1-Aug-20
12 Sh-3 immobilization proximity need to do wiring Joglu,Jay Nehal 9.00am 2-Aug-20
13 Peel bar camera protection cover support install Saddam,Ananya Nehal 9.00am 2-Aug-20
14 Weighing scale section 2 all plate replace with mechanical Joglu,Jay Nehal 9.00am 2-Aug-20
Vertical pocket aditional leaser installization work. All photocell alignment
15 Saddam,Ananya Nehal 9.00am 2-Aug-20
check & supporting all nut bolt check & tightening.
16 After cold shear magnetic roll connection & trail Joglu,Jay Nehal 9.00am 2-Aug-20
17 Mill ready for trail & ghost rolling Noyon, Rajesh Nehal B shift 2-Aug-20