You are on page 1of 26

Project Planning : Cost Estimate and Budget

Copyright © 2015 - 2018, Victorian Institute of Technology.


The contents contained in this document may not be reproduced in any form or by any means, without the written permission of VIT, other
than for the purpose for which it has been supplied. VIT and its logo are trademarks of Victorian Institute of Technology.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 1


Develop the Cost Estimate and Budget

• Accurately estimating the cost of a project and translating


that estimate into a realistic budget are important planning
activities for project managers.
• Preparing an accurate estimate is a matter of answering the
following question:
– How much will it cost our firm to complete this project?

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 2


Develop the Cost Estimate and Budget

• An estimate that is too high will lessen the firm’s chances of


winning the contract.
• An estimate that is too low may cause the firm to win the
contract but lose money.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 3


Develop the Cost Estimate and Budget

• Padding a cost estimate (building in contingencies) is


common practice to cover unanticipated costs or errors.
However, an overly padded estimate is not likely to win the
contract.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 4


Develop the Cost Estimate and Budget

• When developing a cost estimate it is necessary to consider


both direct and indirect costs.
– Direct costs are those tied directly to the project in question including
personnel, material, equipment, facilities, services, inflation, cost of
money (interest), and contingency funds.

continued on next slide

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 5


Develop the Cost Estimate and Budget

• When developing a cost estimate it is necessary to consider


both direct and indirect costs.
– Indirect costs consist of the firm’s overhead and are often computed
as a percentage of the overall cost estimate for a project.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 6


Develop the Cost Estimate and Budget

• Inputs for cost estimating include:


– scope statement, schedule, human resource plan, risk register, and
enterprise environmental factors.
• Cost estimation methods include:
– expert judgment, analogous estimating, parametric estimating,
bottom-up estimating, three-point estimating, reserve analysis,
vendor bid analysis, and the use of estimating software.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 7


Figure 5.6 Sample budget summary
forms.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 8


Develop the Cost Estimate and Budget

• Accurately estimating the cost of a project and translating


that estimate into a realistic budget are important planning
activities for project managers.
• Preparing an accurate estimate is a matter of answering the
following question:
– How much will it cost our firm to complete this project?

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 9


Develop the Cost Estimate and Budget

• An estimate that is too high will lessen the firm’s chances of


winning the contract.
• An estimate that is too low may cause the firm to win the
contract but lose money.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 10


Develop the Cost Estimate and Budget

• Padding a cost estimate (building in contingencies) is


common practice to cover unanticipated costs or errors.
However, an overly padded estimate is not likely to win the
contract.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 11


Develop the Cost Estimate and Budget

• When developing a cost estimate it is necessary to consider


both direct and indirect costs.
– Direct costs are those tied directly to the project in question including
personnel, material, equipment, facilities, services, inflation, cost of
money (interest), and contingency funds.

continued on next slide

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 12


Develop the Cost Estimate and Budget

• When developing a cost estimate it is necessary to consider


both direct and indirect costs.
– Indirect costs consist of the firm’s overhead and are often computed
as a percentage of the overall cost estimate for a project.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 13


Develop the Cost Estimate and Budget

• Inputs for cost estimating include:


– scope statement, schedule, human resource plan, risk register, and
enterprise environmental factors.
• Cost estimation methods include:
– expert judgment, analogous estimating, parametric estimating,
bottom-up estimating, three-point estimating, reserve analysis,
vendor bid analysis, and the use of estimating software.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 14


Types of Costs and Benefits

• Tangible costs or benefits are those costs or benefits that an


organization can easily measure in dollars
• Intangible costs or benefits are costs or benefits that are
difficult to measure in monetary terms
• Direct costs are costs that can be directly related to
producing the products and services of the project
• Indirect costs are costs that are not directly related to the
products or services of the project, but are indirectly related
to performing the project
• Sunk cost is money that has been spent in the past; when
deciding what projects to invest in or continue, you should
not include sunk costs

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 15


More Basic Principles of Cost
Management
• Learning curve theory states that when many items are
produced repetitively, the unit cost of those items decreases
in a regular pattern as more units are produced
• Reserves are dollars included in a cost estimate to mitigate
cost risk by allowing for future situations that are difficult to
predict
– Contingency reserves allow for future situations that may be partially
planned for (sometimes called known unknowns) and are included in
the project cost baseline
– Management reserves allow for future situations that are
unpredictable (sometimes called unknown unknowns

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 16


Planning Cost Management

• The project team uses expert judgment, analytical


techniques, and meetings to develop the cost management
plan
• A cost management plan includes:
– Level of accuracy and units of measure
– Organizational procedure links
– Control thresholds
– Rules of performance measurement
– Reporting formats
– Process descriptions

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 17


Estimating Costs

• Project managers must take cost estimates seriously if they


want to complete projects within budget constraints
• It’s important to know the types of cost estimates, how to
prepare cost estimates, and typical problems associated
with IT cost estimates

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 18


Table 7-2. Types of Cost Estimates

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 19


Cost Estimation Tools and Techniques

• Basic tools and techniques for cost estimates:


– Analogous or top-down estimates: use the actual cost of a previous,
similar project as the basis for estimating the cost of the current
project
– Bottom-up estimates: involve estimating individual work items or
activities and summing them to get a project total
– Parametric modeling uses project characteristics (parameters) in a
mathematical model to estimate project costs

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 20


Figure 5.6 Sample budget summary
forms.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 21


Figure 7.1 The step of estimating the work in the development of the project schedule.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 22


Figure 7.2 The foundational role that the WBS and the work estimates play in the overall
planning process.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 23


Figure 7.3 Estimates are key inputs for scheduling, budgeting, and risk management.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 24


Figure 7.4 Estimating the work overview.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 25


Figure 9.1The budget-focused planning steps.

ITSU 2006 [ Lesson 4 ] Copyright © 2018 VIT, All Rights Reserved 26

You might also like