SAT MASTER

Honeywell Process Solutions – Project & Automation Solutions, India

3.1 System Cabinet


Cabinet Name: ___________________________
Reference: V-2171-001-A-12x
By:
Date:

Sr. Verification Punch Point


Detail Test Items
No. OK / NOT OK Reference
Verification of cabinet Name Plate, Gland plate &
Document Holder. The plinths are free from dents
1
and scratches. Cabinet installed properly on base
frame and nut/bolts are tighten.
Verification of placement of components (controllers,
2
I/O modules, PSUs etc.) as per drawing.
Verification of SE, IE & ISE bus bars (As Applicable)
for securely connected to a local earth point as per
3 Grounding scheme. SE, IE & ISE resistance should
be less than 1 Ω.
Verification of system cable laying, dressing &
4
termination.
Verification of Power cable laying, dressing &
5
termination.
Installation of Door switches and its functional checks
6
(As Applicable)
Installation of Fan assemblies & Functional check of
7
fans (As Applicable)
8 Verification of smooth door operation.
Network connections and identification (As
9
Applicable)
Power on Check & PSU Voltage Verification.
10 As per V-2171-001-A-800 (Installation and Erection
Procedure (Site Planning Guide))
Verification of all internal component are functioning
11
properly.
12 Verification of Cabinet alarms (As Applicable)

13 Verification of OHD Setting at 35 Deg.C

Purpose: Overall acceptance of this test by the CA / Signature:


Purchaser. Purchaser /CA

Project: HMD South Satellite Revamping Doc Title: SAT Procedure (English)
Project – Algeria

D R A Revision:
Revision date:
1 Doc No.:
Dec 03, 2018 Page:
V-2171-001-A-504
20 of 62