Zamil schedule for HVAC- commissioning

Major Equipment

Total Pre-Commissioning Testing time Approximately : 7 Days

Pre-commissioning :Electrical & controls

 Internal testing (Visual inspection ) without power to Panels like (DS,MSP,AHU Motor )
 Pre-commissioning check list power checklist ,control panels

 Pre-commissioning :Mechanical
 Charging of refrigerant line for ACCU
 Internal testing (Visual inspection ) AHU, Actuator with damper ,pre-filter ,Bag filter ,temporary
skids & support ,Lubrication check , Belts
 Pre-commissioning check list of unit
Without DDC control Manual run Equipment

Total Commissioning Testing time Approximately : 7 Days

Commissioning Startup

 Power receiving MCC to DS


 Startup solo run for motors without load (vibration test , bearing heat test )
 Startup run for motors with load
 AHU Run without cooling
 AHU Run with cooling

Minor Equipment Testing time Approximately: 2 Days


Exhaust fan, EDH
Pre-commissioning & commissioning startup

DDC Testing time Approximately: 6 Days

 DDC Startup : one to one check loop test


 DDC Program sequence of operation

TAB : Testing Adjusting Balancing :10 Days


 Air flow ,sound test

Approximately 30 Days schedule