Work Execution Status Report for Ranchi District

Name of the Town: Ranchi & Bundu

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Cost of Work: Rs. 100.72 Cr. LOA date: 09.05.2017

Monthwise Breakup of
Total Work Balance Balance work
Sl. No Activity Unit
Scope Executed Work
June,20 Aug,20
1 33/11kV PSS (2X5 MVA) Nos 2 2 0

2 Additional PTR (5 MVA) Nos 1 1

3 Additional PTR (10 MVA) Nos 4 4

4 Aug. of PSS (5 MVA to 10 MVA) Nos 6 6

5 PSS R &M Nos 2 2

6 33kV New Line Kms 13.935 13.935

7 33kV UG Cable Kms 5.95 5.95

8 33kV Line Re-conductoring Kms 45.98 45.98 0

9 11kV New Line Kms 20.65 20.65 0.0 0.0

10 11kV UG Cable Kms 0.78 0.78 0

11 11kV Line Re-conductoring Kms 65.014 65.014

12 11/0.433kV New DTR Nos 139 139

13 11/0.433kV Aug DTR Nos 19 19

14 R & M of DSS Nos 8 8

15 LT Line through AB Cable Kms 158.161 158.161

16 Metering Nos 11660 11660 0

17 Solar Panel Nos 110 108 2 2


Note: Old Bus Stand PSS delayed due to delay in land handing-over (Jul'18), repetitive RoW & labour contractor
issue.
Reconductoring of 33 kV line delayed due to unavailability of shutdpwn in Bero & Tatisilwai Feeder.
Additional scope of replacement of 6301 Nos, meters included in Ranchi Town in the Month of May,19
Work Execution Status Report for Khunti District
Name of District: Khunti
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)
Cost of Work: Rs. 17.59 Cr. LOA date: 09.05.2017

Sl. Total Work Balance Target Completion


Activity Unit
No Scope Executed Work Month

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 Additional PTR (10 MVA) Nos 1 1

3 PSS R &M Nos 1 1

4 33kV New Line Kms 3.79 3.79

5 33kV UG Cable Kms 0 0

5 33kV Line Re-conductoring Kms 20.5 20.5

6 11kV New Line Kms 1.3 1.3 COMPLETED


7 11kV UG Cable Kms 0.12 0.12

8 11kV Line Re-conductoring Kms 9.26 9.26

9 11/0.433kV New DTR Nos 15 15

10 11/0.433kV Aug DTR Nos 89 89

11 LT Line through AB Cable Kms 41.61 41.61

12 Metering Nos 470 470

13 Solar Panel Nos 10 10


Work Execution Status Report for Gumla District
Name of the Town: Gumla
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)
Cost of Work: Rs. 26.57 Cr. LOA date: 09.05.2017

Monthwise Breakup of
Sl. Work Balace Balance work
Activity Unit Total Scope
No Executed Work
June,20 July,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 Aug. of PSS (5 MVA to 10 MVA) Nos 2 2

3 33kV New Line Kms 0.06 0.06

4 33kV UG Cable Kms 0.55 0.55

5 33kV Line Re-conductoring Kms 3.622 3.62

6 11kV New Line Kms 27.91 27.91

7 11kV UG Cable Kms 4.2 4.20

8 11kV Line Re-conductoring Kms 15.381 15.381

9 11/0.433kV New DTR Nos 113 113

10 R & M of DSS Nos 60 60

11 LT Line through AB Cable Kms 66.931 66.931

12 Metering Nos 485 485


Work Execution Status Report for Lohardaga District

Name of the Town: Lohardaga

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Cost of Work: Rs. 19.11 Cr. LOA date: 09.05.2017

Monthwise
Breakup of
Sl. Total Work
Activity Unit Balance Work Balance work
No Scope Executed
June,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 33kV New Line Kms 8.187 8.187

3 33kV UG Cable Kms 0.13636364 0.1363636364

4 11kV New Line Kms 25.546 25.546

5 11/0.433kV New DTR Nos 52 52

6 LT Line through AB Cable Kms 91.44 91.44

7 Metering Nos 494 494

8 Solar Panel Nos 10 10


Work Execution Status Report for Simdega District

Name of the Town: Simdega

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)

Cost of Work: Rs. 5.89 Cr. LOA date: 09.05.2017

Monthwise Breakup of
Sl. Work Balance Balance work
Activity Unit Total Scope
No Executed Work
June,20 July,20

1 PSS R &M Nos 1 1

2 11kV New Line Kms 15.95 15.95

3 11kV Line Re-conductoring Kms 13.934 13.934

4 11/0.433kV New DTR Nos 25 25

5 LT Line through AB Cable Kms 24.876 24.876

6 Metering Nos 395 395

7 Solar Panel Nos 5 5


Work Execution Status Report for Latehar District

Name of the Town: Latehar


Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)
Cost of Work: Rs. 17.09 Cr. LOA date: 09.05.2017
Monthwise
Sl. Work Balance Breakup of
Activity Unit Total Scope Balance work
No Executed Work
June,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 Additional PTR (10 MVA) Nos 1 1

3 PSS R &M Nos 1 1

4 33kV New Line Kms 3.1 3.1

5 33kV UG Cable Kms 0.165 0.165

6 11kV New Line Kms 13.06 13.06

7 11kV UG Cable Kms 0.437 0.437

8 11kV Line Re-conductoring Kms 12.436 12.436

9 11/0.433kV New DTR Nos 50 50

10 11/0.433kV Aug DTR Nos 19 19

11 R & M of DSS Nos 23 23 0 0

12 LT Line through AB Cable Kms 73.4 73.4

13 Metering Nos 755 755

14 Solar Panel Nos 10 10


Work Execution Status Report for Palamu District
Name of the Town: Daltenganj, Hussainabad & Bishrampur
Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)
Cost of Work: Rs. 34.65 Cr. LOA date: 09.05.2017

Monthwise
Sl. Work Balance Breakup of
Activity Unit Total Scope Balance work
No Executed Work
June,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 Additional PTR (10 MVA) Nos 1 1

3 Aug. of PSS (5 MVA to 10 MVA) Nos 4 4

4 PSS R &M Nos 3 3 0

5 33kV New Line Kms 24.307 23.107 1.2 1.2

6 33kV UG Cable Kms 0.5 0.5

7 33kV Line Re-conductoring Kms 10.9 10.9 0 0

8 11kV New Line Kms 29.868 28.630 1.238 1.238

9 11kV UG Cable Kms 1.89 1.89

10 11kV Line Re-conductoring Kms 43.922 42.822 1.1 1.1

11 11/0.433kV New DTR Nos 111 111

12 11/0.433kV Aug DTR Nos 67 67

13 R & M of DSS Nos 80 80

14 LT Line through AB Cable Kms 219.267 219.267

15 Metering Nos 3712 3712 0 0

16 Solar Panel Nos 12 12


Work Execution Status Report for Garhwa District

Name of the Town: Garhwa & Majhiaon

Name of the Agency: M/s Ashoka Buildcon Limited. (M/s ABL)


Cost of Work: Rs. 17.35 Cr. LOA date: 09.05.2017
Monthwise
Breakup of
Sl. Work Balance
Activity Unit Total Scope Balance work
No Executed Work
June,20

1 33/11kV PSS (2X5 MVA) Nos 2 2

2 Aug. of PSS (5 MVA to 10 MVA) Nos 2 2

3 PSS R &M Nos 1 1

4 33kV New Line Kms 20.2 20.200 0.000 0.000

5 33kV UG Cable Kms 0.277 0.277 0.000 0.000

6 11kV New Line Kms 17.409 17.409 0.000 0.000

7 11kV UG Cable Kms 0.8 0.800

8 11kV Line Re-conductoring Kms 9.72 9.72

9 11/0.433kV New DTR Nos 15 15

10 11/0.433kV Aug DTR Nos 11 11

11 R & M of DSS Nos 33 33

12 LT Line through AB Cable Kms 71.87 71.87 0.0 0.000

13 Metering Nos 956 956 0 0.000

14 Solar Panel Nos 20 20


Work Execution Status Report for Bokaro District

Name of The Towns: Chas & Phusro

Name of the Agency: M/s OFFSHORE INFRASTRUCTURES LIMITED,

Cost of Work: Rs. 29.0 Cr. LOA date: 28.06.2017

Sl. Work Balance


Activity Unit Total Scope Target Completion
No Executed Work

1 Additional PTR (5 MVA) Nos 2 2

2 33kV New Line CKms 13.57 13.57

3 33kV UG Cable CKms 1.185 1.185

4 11kV New Line CKms 15.64 15.64

5 11kV Line Re-conductoring CKms 16.8 16.8

COMPLETED
6 11/0.433kV New DTR Nos 103 103

7 11/0.433kV Aug DTR Nos 66 66

8 R & M of DSS Nos 35 35

9 LT Line through AB Cable Kms 76.431 76.431

10 Metering Nos 6240 6240

11 Solar Panel Nos 5 5


Work Execution Status Report for Giridih District
Name of the Town: Giridih
Name of the Agency: M/s Offshore Infrastructure Limited.
Cost of Work: Rs. 41.92 Cr. LOA date: 28.06.2017

Sl. Work
No
Activity Unit Total Scope Balance Work Target Completion
Executed

1 33/11kV PSS (2X5 MVA) Nos 2 2

2 Additional PTR (10 MVA) Nos 1 1

3 PSS R &M Nos 2 2

4 33kV New Line CKms 16.81 16.81

5 33kV UG Cable CKms 10.36 10.36

6 11kV New Line CKms 13.26 13.26

7 11kV UG Cable CKms 3.09 3.09


COMPLETED
8 11kV Line Re-conductoring CKms 1.078 1.078

9 11/0.433kV New DTR Nos 86 86

10 11/0.433kV Aug DTR Nos 22 22

11 R & M of DSS Nos 42 42

12 LT Line through AB Cable Kms 79.88 79.88

13 Metering Nos 2500 2500

14 Solar Panel Nos 17 17


Work Execution Status Report for Koderma District
Name of the Towns: Koderma & Jhumritilaya
Name of the Agency: M/s Offshore Infrastructure Limited.
Cost of Work: Rs. 30.34 Cr. LOA date: 28.06.2017

Monthwise
Sl. Work Balance Breakup of
Activity Unit Total Scope Balance work
No Executed Work
June,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 Additional PTR (10 MVA) Nos 1 1

3 Aug. of PSS (5MVA to 10MVA) Nos 1 1

4 PSS R &M Nos 3 3

5 33kV New Line CKms 14.5 14.5

6 33kV UG Cable CKms 0.412 0.412

7 11kV New Line CKms 11.82 11.82

8 11kV UG Cable Kms 0.38 0.38

9 11/0.433kV New DTR Nos 39 39

10 11/0.433kV Aug DTR Nos 17 17

11 LT Line through AB Cable Kms 144.51 144.51

12 Metering Nos 2500 2500

13 Solar Panel Nos 20 18 2 2


Work Execution Status Report for Hazaribagh District

Name of the Town: Hazaribagh

Name of the Agency: M/s SRI GOPIKRISHNA INFRA PVT LTD

Cost of Work: Rs. 27.89 Cr. LOA date: 28.06.2017

Monthwise Breakup of
Sl. Total Work Balance Balance work
Activity Unit
No Scope Executed Work
June,20 July,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 33kV New Line CKms 9.653 9.653

3 33kV UG Cable CKms 0.8515 0.8515

4 33kV Line Re-conductoring CKms 4.713 3.646 1.067 1.067

5 11kV New Line CKms 8.951 8.951

6 11kV UG Cable CKms 0.5818 0.5818

7 11/0.433kV New DTR Nos 63 63

8 11/0.433kV Aug DTR Nos 8 8

9 LT Line through AB Cable Kms 80.1594 80.1594

10 Metering Nos 1660 1660

11 Solar Panel Nos 30 30


Work Execution Status Report for Chatra District
Name of the Town: Chatra

Name of the Agency: M/s SRI GOPIKRISHNA INFRA PVT LTD

Cost of Work: Rs.9.9 Cr. LOA date: 28.06.2017

Monthwise Breakup of
Sl. Work Balance Balance work
Activity Unit Total Scope
No Executed Work

June,20 July,20

1 33/11kV PSS (2X5 MVA) Nos 1 1

2 33kV New Line CKms 0.337 0.337

3 11kV New Line CKms 2.955 2.955

4 11kV Line Re-conductoring CKms 12.194 12.194

5 11/0.433kV New DTR Nos 20 20

6 LT Line through AB Cable Kms 37.9983 37.9983

7 Metering Nos 1000 1000

8 Solar Panel Nos 10 10


Work Execution Status Report for Ramgarh District

Name of the Town: Ramgarh

Name of the Agency: M/s SRI GOPIKRISHNA INFRA PVT LTD

Cost of Work: Rs. 14.99 Cr. LOA date: 28.06.2017

Sl. Work Balance


Activity Unit Total Scope Target Completion
No Executed Work

1 Aug. of PSS (5 MVA to 10 MVA) Nos 2 2

2 PSS bay extension work Nos 1 1

3 33kV New Line CKms 14.4716459 14.4716459

4 33kV UG Cable CKms 0.751363636 0.751363636

5 33kV Line Re-conductoring CKms 0.173770492 0.173770492

COMPLETED.
6 11kV New Line CKms 15.1843 15.1843

7 11kV UG Cable CKms 1.857272727 1.857272727

8 11/0.433kV New DTR Nos 46 46

9 LT Line through AB Cable Kms 40.8326 40.8326

10 Metering Nos 1907 1907

11 Solar Panel Nos 5 5


Work Execution Status Report for Deoghar District

Name of the Town: Deoghar & Madhupur

Name of the Agency: M/s NCC Limited.

Cost of Work: Rs. 48.53 Cr. LOA date: 28.06.2017

Monthwise
Breakup of
Work Balance Balance work
Sl. No Activity Unit Total Scope
Executed Work
June,20

1 33/11kV PSS (2X5 MVA) Nos 4 4

2 33kV New Line CKms 10.377 10.377

3 33kV UG Cable CKms 10.66 10.660 0.00 0.00

4 11kV New Line CKms 44.775 44.775

5 11kV UG Cable CKms 48.039 48.039

6 11/0.433kV New DTR Nos 75 75

7 11/0.433kV Aug DTR Nos 48 48

8 LT Line through AB Cable CKms 117.403 117.403

9 Metering Nos 500 500 0 0

10 Solar Panel Nos 15 15

Page 15 of 28
Work Execution Status Report for Godda District
Name of the Town: Godda
Name of the Agency: M/s NCC Limited.
Cost of Work: Rs. 16.55 Cr. LOA date: 28.06.2017
Monthwise
Breakup of
Work Balance Balance work
Sl. No Activity Unit Total Scope
Executed Work
June,20

1 33kV UG Cable CKms 3.88 3.88

2 11kV New Line CKms 3.546 3.546

3 11kV UG Cable CKms 2.983 2.983

4 11/0.433kV New DTR Nos 38 38

5 11/0.433kV Aug DTR Nos 48 48

6 R & M of DSS Nos 86 86

7 LT Line through AB Cable Kms 37.117 37.117

8 Solar Panel Nos 5 5


Work Execution Status Report for Dhanbad District
Name of the town: Dhanbad & Chirkunda
Name of the Agency: M/s SRI GOPIKRISHNA INFRA PVT LTD
Cost of Work: Rs. 73.44 Cr. LOA date: 07.03.2019

Monthwise Breakup of Balance work


Total Work Balance
Sl. No Activity Unit
Scope Executed Work
June,20 July, 20 Aug, 20 Sep,20

1 33/11kV PSS (2X5 MVA) Nos 3 1 2 2

2 Aug. of PSS (5 MVA to 10 MVA) Nos 2 2 0

3 33kV New Line CKms 3 2.638 0.362 0.362

4 33kV UG Cable CKms 3 0.2 2.8 1 1.8

5 11kV New Line CKms 19.42 11.475 7.945 0.2 4.145 3.6

6 11kV UG Cable CKms 7 2.6 4.4 1.42 1.98 1

7 11kV Line Re-conductoring CKms 22.3 13.5 8.8 4.8 4

8 11/0.433kV New DTR Nos 265 214 51 30 21

9 11/0.433kV Aug DTR Nos 47 47 0

10 R & M of DSS Nos 34 34 0

11 LT Line through AB Cable Kms 288.00 207.4 80.60 35 45.6

12 Metering Nos 4223 937 3286 370 1000 1316 600

13 Solar Panel Nos 5 0 5 2 3 0


Work Execution Status Report for East Singhbhum District
Name of the Agency: M/s Offshore Infrastructures
Name of the Towns: Jamshedpur, Chakulia & Jugsalai
Cost of Work: Rs. 28.62 Cr. LOA date: 05.07.2019

Monthwise Breakup of Balance work


Total Work Balance
Sl. No Activity Unit
Scope Executed Work
June'20 July, 20 Aug, 20 Sep,20

1 Additional PTR (5 MVA) Nos 1 1 0

2 Additional PTR (10 MVA) Nos 1 1 0

3 Aug. of PSS (5 MVA to 10 MVA) Nos 3 3 0

5 11kV New Line CKms 1.312 0 1.312 1.312

6 11kV UG Cable CKms 1.232 1.232 0

7 11kV Line Re-conductoring CKms 38.781 18.9 19.881 4.471 15.41

8 11/0.433kV New DTR Nos 113 89 24 12 12

9 R & M of DSS Nos 58 24 34 34

10 LT Line through AB Cable Kms 125.33 68.29 57.04 33.74 23.68

11 Metering Nos 2736 1687 1049 124 925

12 Solar Panel Nos 11 11 0


Work Execution Status Report for East Singhbhum District
Name of the Agency: M/s Gupta Transformer Products

Name of the Towns: Mango


Cost of Work: Rs. 10.38 Cr. LOA date: 07.03.2019

Monthwise Breakup of Balance work


Total Work Balance
Sl. No Activity Unit
Scope Executed Work
June'20 July, 20 Aug, 20 Sep,20

1 Additional PTR (10 MVA) Nos 1 1 0

2 Aug. of PSS (5 MVA to 10 MVA) Nos 1 1 0

3 11/0.433kV New DTR Nos 42 33 9 9

4 R & M of DSS Nos 18 6 12 12

5 LT Line through AB Cable Kms 45 30.4 14.600 14.6

6 Metering Nos 4934 4330 604 604


Work Execution Status Report for West Singhbhum District
Name of the Towns: Chaibasa & Chakradharpur
Name of the Agency: M/s Suncity Enterprise
Cost of Work: Rs. 31.43 Cr. LOA date: 07.03.2019
Monthwise Breakup of Balance
Total Work Balance work
Sl. No Activity Unit
Scope Executed Work
June, 20 July, 20 Aug, 20

1 33/11kV PSS (2X5 MVA) Nos 2 0 2 2

2 33kV New Line CKms 15.607 5.55 10.057 3.41 6.647

3 33kV UG Cable CKms 4.849 3.721 1.128 1.128

4 11kV New Line CKms 9.532 4.38 5.152 4.28 0.872

5 11kV UG Cable CKms 3.091 3.091 0

6 11kV Line Re-conductoring CKms 0 0 0.0

7 11/0.433kV New DTR Nos 52 51 1 1

8 R & M of DSS Nos 33 33 0

9 LT Line through AB Cable Kms 75.00 75.00 0.000

10 Metering Nos 870 580 290 63 227


Work Execution Status Report for Saraikela District

Name of the Towns: Adityapur


Name of the Agency: M/s Gupta Transformer Products
Cost of Work: Rs. 16.89 Cr. LOA date: 07.03.2019

Monthwise Breakup of Balance work


Sl. Total Work Balance
Activity Unit
No Scope Executed Work
June'20 July, 20 Aug, 20 Sep,20

1 Additional PTR (10 MVA) Nos 1 1 0

2 Aug. of PSS (5 MVA to 10 MVA) Nos 1 1 0

3 11kV Line Re-conductoring CKms 3.2 3.2 0

4 11/0.433kV New DTR Nos 43 35 8 1 7

5 R & M of DSS Nos 17 0 17 17

6 LT Line through AB Cable Kms 78.20 62.30 15.90 15.9

7 Solar Panel Nos 0 0 0


Work Execution Status Report for Saraikela District

Name of the Towns: Saraikela

Name of the Agency: M/s Suncity Enterprise

Cost of Work: Rs. 29.23 Cr. LOA date: 07.03.2019


Monthwise Breakup of
Sl. Total Work Balance Balance work
Activity Unit
No Scope Executed Work
July, 20 Aug, 20 Sep, 20

1 Additional PTR (5 MVA) Nos 1 0 1 1

2 33kV UG Cable CKms 0.229 0.229 0

3 11kV New Line CKms 1 0.39 0.61 0.052 0.558

4 11/0.433kV New DTR Nos 19 17 2 2

5 R & M of DSS Nos 7 3 4 4

6 LT Line through AB Cable Kms 14.1 12.3 1.800 1.8

7 Metering Nos 300 201 99 99


Work Execution Status Report for Dumka District
Name of the Towns: Dumka & Basukinath
Name of the Agency: M/s Offshore Infrastructures Ltd.
Cost of Work: Rs. 10.77 Cr. LOA date: 05.07.2019
Monthwise Breakup of Balance
Work Balance work
Sl. No Activity Unit Total Scope
Executed Work
July, 20 Aug, 20 Sep, 20

1 11kV New Line CKms 14.06 12.75 1.31 0.8 0.51

2 11kV UG Cable CKms 0.92 0 0.92 0.12 0.8

3 11/0.433kV New DTR Nos 30 28 2 2 0

4 11/0.433kV Aug DTR Nos 1 1 0 0

5 R & M of DSS Nos 18 8 10 2 8

6 LT Line through AB Cable Kms 42.43 38.56 3.870 0 3.87

7 Metering Nos 959 819 140 21 119


11 Solar Panel Nos 5 5 0
Work Execution Status Report for Jamtara District
Name of the Towns: Jamtara & Mihijam
Name of the Agency: M/s Offshore Infrastructures Ltd.
Cost of Work: Rs. 14.45 Cr. LOA date: 05.07.2019
Monthwise Breakup of
Total Work Balance Balance work
Sl. No Activity Unit
Scope Executed Work
July, 20 Aug, 20 Sep, 20

1 Additional PTR (10 MVA) Nos 1 1 0

2 11kV New Line CKms 6.43 5.52 0.91 0.51 0.4

3 11kV UG Cable CKms 0.79 0 0.79 0.79

4 11kV Line Re-conductoring CKms 1.1 1.1 0

5 11/0.433kV New DTR Nos 23 20 3 3

6 11/0.433kV Aug DTR Nos 29 24 5 5

7 R & M of DSS Nos 34 16 18 2 16

8 LT Line through AB Cable Kms 55.942 54.75 1.192 0.8 0.39

9 Metering Nos 992 856 136 136

10 Solar Panel Nos 5 5 0


Work Execution Status Report for Sahibganj District
Name of the towns: Sahibganj & Rajmahal
Name of the Agency: M/s Jakson Limited
Cost of Work: Rs. 32.85 Cr. LOA date: 07.03.2019

Monthwise Breakup of Balance work


Total Work Balance
Sl. No Activity Unit
Scope Executed Work
June,20 July, 20 Aug,20 Sep,20

1 33/11kV PSS (2X5 MVA) Nos 3 3 0

2 33kV New Line CKms 8.86 7.82 1.040 0.54 0.5

3 11kV New Line CKms 22 3 19 15.84 3.16

4 11kV UG Cable CKms 9.1 9.1 0

5 11kV Line Re-conductoring CKms 5.3 4.4 0.9 0.9

6 11/0.433kV New DTR Nos 48 46 2 2

7 11/0.433kV Aug DTR Nos 22 22 0

8 R & M of DSS Nos 16 10 6 3 3

9 LT Line through AB Cable Kms 56.63 56.63 0.00

10 Metering Nos 3281 3018 263 224 39

11 Solar Panel Nos 0 0 0


Work Execution Status Report for Pakur District
Name of the town: Pakur
Name of the Agency: M/s Jakson Limited
Cost of Work: Rs. 10.54 Cr. LOA date: 07.03.2019

Monthwise Breakup of Balance work


Sl. Total Work Balance
Activity Unit
No Scope Executed Work
June,20 July, 20 Aug,20 Sep,20

1 PSS R &M Nos 1 1 0


2 33kV Line Re-conductoring CKms 7.9 7.9 0

3 11kV New Line CKms 7 1.40 5.6 5.6

5 11kV UG Cable CKms 0.526 0 0.526 0.526

4 11kV Line Re-conductoring CKms 2.5 0 2.5 0 2.5

5 11/0.433kV New DTR Nos 15 12 3 1 1 1

6 11/0.433kV Aug DTR Nos 10 10 0

7 R & M of DSS Nos 11 8 3 3

8 LT Line through AB Cable Kms 28.62 25.32 3.3 1.3 2

9 Metering Nos 2683 1204 1479 179 400 400 500

10 Solar Panel Nos 0 0 0


Work Execution Status Report for Jharkhand as on 16.05.19

Sl. No Activity Unit #REF! #REF! #REF! #REF!

1 33/11kV PSS (2X5 MVA) Nos #REF! #REF! #REF! Err:509

2 Additional PTR (10 MVA) Nos #REF! #REF! #REF! Err:509

3 Aug. of PSS (5 MVA to 10 MVA) Nos #REF! #REF! #REF! Err:509

4 PSS R &M Nos #REF! #REF! #REF! Err:509

5 33kV New Line Kms #REF! #REF! #REF! Err:509

6 33kV UG Cable Kms #REF! #REF! #REF! Err:509

7 33kV Line Re-conductoring Kms #REF! #REF! #REF! Err:509

8 11kV New Line Kms #REF! #REF! #REF! Err:509

9 11kV UG Cable Kms #REF! #REF! #REF! Err:509

10 11kV Line Re-conductoring Kms #REF! #REF! #REF! Err:509

11 11/0.433kV New DTR Nos #REF! #REF! #REF! Err:509

12 LT Line through AB Cable Kms #REF! #REF! #REF! Err:509

13 Metering Nos #REF! #REF! #REF! Err:509

14 Solar Panel Nos #REF! #REF! #REF! Err:509


Work Execution Status Report for Jharkhand State

Work Balance
Sl. No Activity Unit Total Scope Charged
Executed Work

1 33/11kV PSS (2X5 MVA) Nos 26 22 4 18

2 Additional PTR (5 MVA) Nos 5 4 1 3

3 Additional PTR (10 MVA) Nos 13 13 0 10

4 Aug. of PSS (5 MVA to 10 MVA) Nos 24 24 0 24

5 PSS R &M Nos 16 16 0 16

6 33kV New Line Kms 180.765 168.106 12.659 129.285

7 33kV UG Cable Kms 43.756 39.828 3.928 34.252

8 33kV Line Re-conductoring Kms 93.789 92.722 1.067 92.722

9 11kV New Line Kms 348.578 305.501 43.077 271.487

10 11kV UG Cable Kms 87.817 81.181 6.636 74.327

11 11kV Line Re-conductoring Kms 272.920 239.739 33.181 239.739

12 11/0.433kV New DTR Nos 1640 1535 105 1453

13 11/0.433kV Aug DTR Nos 523 518 5 518

14 R & M of DSS Nos 613 509 104 509

15 LT Line through AB Cable Kms 2171.198 1992.896 178.302 1888.893

16 Metering Nos 56212 48866 7346 48866

17 Solar Panel Nos 310 301 9 251