You are on page 1of 11

Progress for Sahibganj Cricle as on 12.06.

2020
(Towns – Sahibganj, Rajmahal & Pakur)

Name of the Agency: M/s Jakson Pvt. Ltd.

Cost of Work: Rs. 43.39 Cr. LOA date: 07.03.2019 Target Completion Month: December, 20

Total Cummulative
Sl. No Activity Unit Required Progress upto Work done in Cumulative Progress in Charged Remarks
Quantity June'20 till date June'20 till date
May'20

1. The entire process of handing over of left over


materials available at IL&FS store has been completed
on 24.02.2020.
33/11kV PSS (2X5 MVA) 2. The PSS land were handed over to agency on
Sahibganj Town – 05.12.2019. The delay is on account of hindrance
1 Barabhitana & Lohanda Nos 3 created by sub-contractor of previous agency.
Rajmahal Town – 3. Present Status of PSS:
Mangalhat
a) Civil & Electrical Work WIP at Barabhitana PSS.
b) 1no.5MVA PTR erected at Barabhitana PSS.
c) Civil & Electrical Work WIP at Lohanda PSS.
d) Civil & Electrical Work WIP at Rajmahal PSS.

1. The entire process of handing over of left over


materials available at IL&FS store has been
PSS R & M at Pakur Town completed on 24.02.2020.
2 (Pakur & Nos 2 1 1 2. Civil work completed at Ballavpur PSS.
Ballavpur PSS) 3. 4nos. 11kV Isolator erection completed at Pakur
PSS.
4. Manpower at Ballavpur PSS & Pakur PSS - NIL
Progress for Sahibganj Cricle as on 12.06.2020
(Towns – Sahibganj, Rajmahal & Pakur)

Name of the Agency: M/s Jakson Pvt. Ltd.

Cost of Work: Rs. 43.39 Cr. LOA date: 07.03.2019 Target Completion Month: December, 20

Total Cummulative
Sl. No Activity Unit Required Work done in Cumulative Progress in Charged Remarks
Progress upto
Quantity May'20 June'20 till date June'20 till date

1) The entire process of handing over of left over


materials available at IL&FS store has been
3 33kV New Line Kms 11.84 5.5 5.5 2.3 completed on 24.02.2020.
2) Manpower at Site - NIL

4 33kV Line Re- Kms 7.9 7.9 7.9 7.9 SCOPE COMPLETED.
conductoring

1) The entire process of handing over of left over


materials available at IL&FS store has been
5 11kV New Line Kms 47.71 completed on 24.02.2020.
2) Pole Erection WIP at Rajmahal Town.
3) Manpower at Sahibganj & Pakur Town - NIL
Progress for Sahibganj Cricle as on 12.06.2020
(Towns – Sahibganj, Rajmahal & Pakur)

Name of the Agency: M/s Jakson Pvt. Ltd.

Cost of Work: Rs. 43.39 Cr. LOA date: 07.03.2019 Target Completion Month: December, 20

Total Cummulative
Sl. No Activity Unit Required Work done in Cumulative Progress in Charged Remarks
Progress upto June'20 till date June'20 till date
Quantity May'20

1) The entire process of handing over of left over


materials available at IL&FS store has been
completed on 24.02.2020.
2) Rajmahal Town: Town feeder 2 - Railway crossing
(Location: Near Begumpura) - 30mtrs
Online application submitted on August, 2018. Joint
Inspection done & based on observations from Railway
department revised drawing was submitted at DRM,
6 11kV UG Cable Kms 14.368 7.79 0.1 7.89 1.4 Malda Office in 2nd week of December, 2018.

3) Rajmahal Town: Objection from NHAI regarding at


Eleven locations regarding excavation of NHAI road for
Inter connection of UG Cable in Town -2 Feeder
(Approx. 15.5 mtrs) .
4) Pole Erection & Termination WIP at Rajmahal Town.
5) Manpower at Sahibganj & Pakur Town – NIL

1) The entire process of handing over of left over


7 11kV Line Re- Kms 20.94 2.6 2.6 2.6 materials available at IL&FS store has been
conductoring completed on 24.02.2020.
2) Manpower at Site - NIL
Progress for Sahibganj Cricle as on 12.06.2020
(Towns – Sahibganj, Rajmahal & Pakur)

Name of the Agency: M/s Jakson Pvt. Ltd.

Cost of Work: Rs. 43.39 Cr. LOA date: 07.03.2019 Target Completion Month: December, 20

Total Cummulative
Sl. No Activity Unit Required Progress upto Work done in Cumulative Progress in Charged Remarks
Quantity June'20 till date June'20 till date
May'20

1) The entire process of handing over of left over


materials available at IL&FS store has been
8 11/0.433kV New DTR Nos 55 36 1 37 32 completed on 24.02.2020.
2) DTR erection WIP at Rajmahal Town.
5) Manpower at Sahibganj & Pakur Town – NIL

1) The entire process of handing over of left over


materials available at IL&FS store has been
completed on 24.02.2020.
9 11/0.433kV Aug DTR Nos 32 30 30 30 2) Scope Completed at Rajmahal & Pakur Towns.
3) Manpower at Sahibganj Town – NIL

1) The entire process of handing over of left over


materials available at IL&FS store has been
10 R & M of DSS Nos 85 8 8 8 completed on 24.02.2020.
5) Manpower at Site – NIL
Progress for Sahibganj Cricle as on 12.06.2020
(Towns – Sahibganj, Rajmahal & Pakur)

Name of the Agency: M/s Jakson Pvt. Ltd.

Cost of Work: Rs. 43.39 Cr. LOA date: 07.03.2019 Target Completion Month: December, 20

Total Cummulative
Sl. No Activity Unit Required Progress upto Work done in Cumulative Progress in Charged Remarks
Quantity June'20 till date June'20 till date
May'20

1) The entire process of handing over of left over


materials available at IL&FS store has been
completed on 24.02.2020.
11 LT Line through AB Cable Kms 90.4 38.8 3.5 42.3 27.7 2) Cable Stringing WIP at Sahibganj & Rajmahal
Town.
3) Manpower at Pakur Town – NIL

1) The entire process of handing over of left over


materials available at IL&FS store has been
12 Metering Nos 4000 569 293 862 862 completed on 24.02.2020.
2) Meter Erection WIP at Sahibganj Town.
3) Manpower at & Rajmahal & Pakur Town – NIL

13 Solar Panel Nos 30 1) Unavailability of Material at site.


Material Status for Sahibganj Cricle as on 12.06.2020
BOQ as per Survey submitted to GM Circle Office on 11.05.2020
Total Requirement as Balance Material to be
SL. No Item Description per Freezing Unit Material at Site Procured
1 200kVA DTR 67 No 58 9
2 100kVA, 11/0.4 kV, Station Trafo 3 No 1 2

3 DP structure for 11/0.4 KV Station Transformer comprising 3 Set   3


of H-Beam
4 M S Nuts & Bolts of different size 8.68 MT 3.09 5.59
5 Fabrication Item-Lines & DTR 154.70 MT 65.37 73.19
6 12 kV, 1250 A VCB 28 No 23 5
7 11kVCurrent transformer 28 Set 23 5
8 12kV, 600A, Isolator 35 Set 15 20
9 12 kV PT - 3 nos 1 ph 8 set 6 2
10 33 kV, 630 A, AB Switch 5 Set   5
11 11 kV, 630 A, AB Switch 61 Sets   61
12 11 kV, 200 A, AB Switch 51 Sets 50 1
13 11KV HG Fuse 175 Set 143 32
14 9kV, 10kA, LA 118 Set 26 74

15 33 kV CRP-feeder with Static Tri-Vector Energy Meter 7 No 6 1


Material Status for Sahibganj Cricle as on 12.06.2020
BOQ as per Survey submitted to GM Circle Office on 11.05.2020
Total Requirement as Balance Material to be
SL. No Item Description per Freezing Unit Material at Site Procured
33kv-CRP-Power transformer with Static Tri-Vector Energy
16 Meter 7 No 6 1

17 11kV CRP- Feeder Breaker 22 No. 12 10

18 30V, 100 AH Battery 4 Set   4

19 30V, 40 A, Battery Charger 4 set   4


20 LT ACDB 3 No   3
21 30V DCDB 3 Set   3
LTDB-Station transformer - Yard lighting timer unit, tri-
22 3 Set   3
vector electronic energy meter
23 LTDB-100kVA DTR 57 No 48 9
24 LTDB-200kVA DTR 112 No 95 7
25 LTDB-500kVA DTR 3 No   1
26 AB-DB mounted on pole 2256 No 1834 228
27 LTCT cum Metering box-100kVA DTR 57 Set 53 4
28 LTCT cum Metering box-200kVA DTR 115 Set 106 9
29 LTCT cum Metering box-500kVA DTR 3 Set   1

30 Aluminium Wire for Binding 0.4867 MT   0.4867


Material Status for Sahibganj Cricle as on 12.06.2020
BOQ as per Survey submitted to GM Circle Office on 11.05.2020
Total Requirement as Balance Material to be
SL. No Item Description per Freezing Unit Material at Site Procured
31 Aluminium Tape 0.0472 MT   0.0472

32 P G clamp connectors -Panther 342 No. 108 234

33 P.G. Clamp connectors-Wolf 258 No. 88 61

34 P.G. Clamp connectors-Dog 1383 No. 599 518


35 AB-Service rings 2256 No.   2256
36 Connector of different type 486 No.   486

37 Connector Dog to AB Switch 834 No.   834

38 AB-LT connector 3258 No.   1546


39 AB-Suspension clamp asssembly 2893 No. 992 93
40 Panther 6.6 km 2.5 4.104
41 Wolf 61.5185 km 32.0 19.7605
42 Dog 226.783 km 32.0 50.483
43 LTAB cable 94.92 km 62.0 15.721
44 75 x 8 mm GI flat for ground mat 12 MT 2 10

45 65 x 6 mm Galvanized GI flat for earth mat 9.5 MT 1 8.5


Material Status for Sahibganj Cricle as on 12.06.2020
BOQ as per Survey submitted to GM Circle Office on 11.05.2020
Total Requirement as Balance Material to be
SL. No Item Description per Freezing Unit Material at Site Procured
46 50 x 6 mm Galvanized GI flat (risers) 1.8 MT 0.04 1.76

47 25 x 3 mm Galvanized GI flat (risers) 2.35 MT 0.1 2.25

48 G.I wire no-6 SWG 1.99212 MT 0.31 1.54712

49 Deep bore Earthing 6 Set   6


50 Spike earthing-20mm solid rod 2260 Set 1000 481
51 Revamping of DSS earthing-Pipe,50x6 Flat,25x3 GS flat 84 Set   84

52 33 KV Disc Insulator 753 Set 79 510

53 11kV Pin Insulator 4878 Set 1222 1495


54 11kV UG Cable 28.73 Km 16.9 8.825
55 1x35 sqmm Cable 33.84 km 11.3 16.363
56 1x150 sqmm Cable 2.605 km 1.6 0.795
57 1x300 sqmm Cable 5.13 km 0.99 2.576
58 2 x 6 sqmm Cable 160 km   160
59 2 Core 2.5 sqmm 6.3 km 0.76 2.537

60 4 Core 2.5 sqmm 7.3 km 1.2 3.099


Material Status for Sahibganj Cricle as on 12.06.2020
BOQ as per Survey submitted to GM Circle Office on 11.05.2020

Total Requirement as Balance Material to be


SL. No Item Description per Freezing Unit Material at Site Procured

61 10 Core 2.5 sqmm 6.1 km 1.94 3.365

62 2 x16 sqmm cable 1.05 km 0.05 1.005

63 3 Phase 4 wire Electronic Meter W.C with meter box 4 Nos   4

64 33 KV Feeder Metering (CT/PT Metering Unit) 8 Set 6 2

65 11 KV Feeder Metering (CT/PT Metering Unit) 17 Set 14 3

66 1 ph, 5-30A, Meter with meter box and wooden board 4000 Set 3395 385

67 Internal Electrification works 3 Set   3

68 External Electrification in switch yard area 5 Set   5

69 Rubber mat along length of pannel 50 No   50

70 11kV Danger Board 1519 0 447 74

71 LT Danger Board 1086 0 955 131


Material Status for Sahibganj Cricle as on 12.06.2020
BOQ as per Survey submitted to GM Circle Office on 11.05.2020
Total Requirement as Balance Material to be
SL. No Item Description per Freezing Unit Material at Site Procured
72 4 sand bucket with angle chuggi type sand 5 No   5

73 CO2 type 4.5Kg capacity for control room 8 No   8

74 150mm GI pipe 1200 Meter 320 280

75 Tube well with pump 3 set   3


Al paint
76 1968 Ltr 1240 728
77 Red oxide Paint 1923 Ltr 1240 683
78 13m Long Rail Pole 60kg/m 1983 No 770 1213
79 Stone Base Plate 3183 No 1123 2060
80 Stay set (HT-33kV) 303 Set 166 137

81 Stay set (11kV/LT) 3129 Set 2466 663

82 11kV Termination kit 194 Set 18 176


83 11kV Jointing kit 30 Set 18 12
84 Solar panels 30 Set   30
85 Support str-Solar panel 30 Set   30

You might also like