Definition: Clearing and loading broken rock and other excavated materials, as in tunnels
or shafts.
ElectroMech has developed a unique and cost effective bulk material handling system for
extraction and disposal of overburden generated during construction of tunnels. This system
can very efficiently remove overburden generated during construction of deep shafts as well
as the overburden generated during the tunneling operation itself.
Briefly the system consists of:
After every blast/drilling operation carried out to extend the shaft/tunnel, the
overburden generated needs to be removed immediately in order to proceed further.
Once the affected area is approachable, the empty bucket is lowered to the appropriate
elevation.
The bucket is then filled with the generated overburden, either by payloaders or
manually depending on the space available below for movement of men and
machines.
The laden bucket is then automatically hoisted to a pre-determined height above the
surface using the winch and the hoisting arrangement.
The laden bucket is then automatically traversed longitudinally to a pre-determined
distance using the trolley.
The laden bucket is then lowered at the dumping station.
The door locks are now released and the bucket further lowered using the winch,
emptying the overburden into dump trucks standing below.
After the bucket is empty, the bucket is hoisted, the doors locked and are then
automatically traversed to the centreline of the shaft and the whole cycle is repeated
once more.
The whole system is custom built.
OTHER EXAMPLE OF MUCKING SYSTEMS TO CARRY MATERIALS AWAY FROM
THE DRILLING SITE.
1. Conveyor belts