You are on page 1of 2

Iraq Zubair North New DGS Project

ATTENDANCE SHEET FOR T.B.M.


Date: ___________________________ Conducted By: ____________________________

Place:___________________________

Discussion points: ( Lifting & Rigging Activity Safety Precactions)


.• Check your PPE, Area barricade, Signage & communication means.
• Forecast the weather & inspect the ground condition.
• Inspect all crane and lifting accessories with TPI certificate
• Sign the TBM sheet and provide all items as per work permit requirement
• Keep crane access routes clear, safe distance, and prohibit unauthorized entry.
• No lift can proceed without an approved Lifting Plan
• If you hear or see any crane warning alarms then report this to your supervisor immediately
• Do not ask the crane driver directly to lift something.
• Know the weight of the load to be lifted, Don’t forget to include the weight of lifting
accessories
• Avoid simultaneous operations unless it has approval by Samsung HSE Manager
• Never carry an un permitted and un planned work.

) ‫ (رفع وتزوير االحتياطات آخر السالمة‬: ‫نقاط النقاش‬


. ‫ األشارات التحذيرية و وسائل األتصال‬, ‫ حواجز المنطقة‬, ‫أفحص معدات الوقاية الشخصية‬
. ‫التأكد من حالة الطقس وتفقد حالة األرض‬
. ‫التأكد من شهادات الكرين و كل وسائل الرفع‬
‫ أبقي‬. ‫وقع ورقة حضور أجتماع السالمة وأرفق كل متطلبات تصريح العمل‬
. ‫الممرات واضحة وعلى مسافة امنة وامنع كل شخص غير مصرح به للدخول ال تبدء الرفع بدون تصريح عمل‬
‫في حالة الطوارئ أو الجرس التحذيري أخبر المشرف الموجود في‬
‫ال تطلب من مشغل الكرين أن يرفع اي حمل مباشرة‬ . ً ‫الموقع حاال‬
‫أعرف وزن الحمل المقرر رفعه ال‬ .
‫ تجنب األعمال المتتزامنة ( في وقت واحد ) أال بتصريح من مدير سالمة سامسونج‬. ‫تنسى أضافة وزن وساءل الحمل‬
‫ال تبدء بأي عمل خالي من التخطيط وتصريح العمل‬ .

No Name Nationatility Company Position Signature

Trained By: ______________________


10

Trained By: ______________________