Professional Documents
Culture Documents
www.sawayra.org
1-Problem Statement…………………………………………………………………………...2
2-Objective……………………………………………………………………………………..2
3-Abstract………………………………………………………………………………………2
A-Elective Measures…………………………………………………………………………..2
4-Flow Chart……………………………………………………………………………………2
5-Internal Design……………………………………………………………………………….3
6-Procurement………………………………………………………………………………….3
7-Brief Description of Equipment……………………………………………………………...3
A- Solar Panel………………………………………………………………………………….3
A1- Mechanical Characteristics………………………………………………………………..3
A2- Electrical Characteristics………………………………………………………………….4
B- Inverter……………………………………………………………………………………..4
C- Rechargeable Battery………………………………………………………………………4
D- Dehumidifier……………………………………………………………………………….4
8- Weather Station Data………………………………………………………………………..5
A- For Karachi…………………………………………………………………………………5
B- Solar Tracking Calculations……………………………………………………………......5
9- PV System Sizing……………………………………………………………………………5
A- Calculation as per Load Wattage…………………………………………………………...5
B- Synopsis…………………………………………………………………………………….6
10-Installation…………………………………………………………………………………..7
A- Pilot Phase………………………………………………………………………………….7
11-Excel Sheets………………………………………………………………………………….
A- Overview…………………………………………………………………………………….
B- Test Plan……………………………………………………………………………………..
C- Liters per Day Sample Sheet………………………………………………………………...
12-Test Results…………………………………………………………………………………7
A- Panel Outcome……………………………………………………………………………..7
B- Condensate Rate……………………………………………………………………………7
13-Troubleshoot………………………………………………………………………………...8
14-Excel Sheet…………………………………………………………………………………...
A- Revision of Quotation……………………………………………………………………….
B- Cost Analysis………………………………………………………………………………...
15-Conclusion…………………………………………………………………………………..8
1
1-Problem Statement:
In countries; highlighting Pakistan, lack of water leads to severe hardships and death every year due to uneasy
access to groundwater, ponds or lakes especially in desserts and barren lands.
2-Objective:
To extract water from the humid environment or atmospheric moisture by the process of condensation,
powered by renewable energy source and put to use for drinking purpose.
3-Abstract:
To devise a sustainable solution for water deprived areas, the design of Atmospheric Water Generator is based
on PV system to generate electricity. The conversion of DC power obtained from solar panels to AC power
takes place by a pure sine wave inverter built in charge controller, which later be fed into the AC powered
Dehumidifier; the device associated with refrigeration process used to generate water through moisture. For
inverter, the only important step followed here is to range it twice the load wattage if the load is dependent on
compressor so that it handles the relative surge. Moreover, backup is provided to the load by the usage of
rechargeable batteries which withstand the reduction of power production at night and during cloudy weather,
thus the charging and discharging of batteries will be examined by the charge controller. In last, dehumidifier
will be connected as a load.
A- Elective Measures:
High Relative Humidity
Peak sunshine hours
4-Flow Chart:
2
5-Internal Design:
6-Procurements:
Solar Panels
Inverter with built-in Charge Controller
Batteries
Dehumidifier
3
A2-Electrical Characteristics:
Maximum Power at STC 150W
Optimum Operating Voltage 17.8V
Optimum Operating Current (Imp) 8.427A
Open-Circuit Voltage (Voc) 22.38V
Short-Circuit Current (Isc) 9.057A
Solar Cell Efficiency (%) 17.7
Solar Module Efficiency (%) 15.06
Operating Temperature -40 to 85°C
B- Inverter:
Model: Axpert KS Off-Grid Inverter
Rated Power 1000VA / 800W
Voltage 230 V AC
Selectable Voltage Range 170-280 VAC (For Personal Computers)
90-280 V AC (For Home Appliances)
Frequency Range 50 Hz/60 Hz (Auto sensing)
Surge Power 2000VA
Efficiency (Peak) 90%
Maximum PV Array Open Circuit Voltage 50VDC
Standby Power Consumption 1 W
Maximum Solar Charge Current 50A
Maximum AC Charge Current 20 A
Maximum Charge Current 50 A
Battery Voltage 12 VDC
Floating Charge Voltage 13.5 VDC
Overcharge Protection 15.5 VDC
Humidity 5% to 95% Relative Humidity (Non-condensing)
Operating Temperature 0°C - 55°C
Storage Temperature -15°C - 60°C
C- Rechargeable Battery:
Quantity: 2
Model: 6-CNF 100, 12V Gel Battery
Nominal voltage: 12V
Capacity: 100Ah @10hr to 10.6
Weight: 29.5kg
Internal resistance; 2.86mΩ
Temperature ranges: -20°C to 45°C
Max charging current: 20Ah
Charge Voltage: 14.2V
Recover performance: recharge to 95%
D- Dehumidifier:
Model: BL-830E, Belin China
Moisture removed: 30L/Day
Test Conditions: 30°C, 80%RH
Rated Power: 330W
Max Power: 396W
4
Rated Current: 1.5A
Max Current: 1.8A
Energy Consumption/24hr: 7.92KWh
Energy Factor: 3.8L/KWh
Motor: AC Induction motor
Voltage/cycle: 220V/50Hz
Inverter sizing:
Since, Load power= 330Watt
On considering safety purpose, Inverter with 25% wattage will be used
Therefore, 330*(25/100) = 82.5Watt
Battery sizing:
Since, load having 1650Wh, battery capacity will be:
1650/ (12) = 286.45Ah
On considering 15% battery losses;
286.45/0.85= 137.5Ah losses
For improved battery life, considering 50% Depth of Discharge:
Hence, required battery capacity is137.5/0.5= 275Ah
So, on taking 12V, 100Ah battery:
5
275Ah/100Ah= 2.75
Therefore, on approximations: 3 Batteries are needed
Charge controller:
Current Ratings= Panel Power/ System voltage= 150/12 = 12.5 Amp
Hence; on keeping margin, 20Amp, 12V will be used with the inverter 800W (twice the wattage of load)
As we know that:
Axpert KS 1KVA, PWM Inverter is limited on voltage handlings, thus as per given in the brochure
solar panels will be given parallel connection.
Rechargeable battery backup system will also be given parallel connection, therefore total voltage will
remain 12V while the capacity will become twice.
100Ah+100Ah= 200Ah
Since, a solar panel featured 17.8V, 8.427A, 150W
Now, Voltage= 17.8V
Total current= 8.427* 5=42.135A
Total Power Output= 750W
Charge Controller Input:
Voltage= 17.8V
Current= 42.135A
Power= 17.8V * 42.135A= 750.003Watt
Charge Controller Output:
Voltage= 12V dc
Current= 42.135A
Power= 12V * 42.135A= 505.62Watt
Since, inverter is 90% efficient;
Therefore, 505.62Watt * (90/100) = 455.058Watt
B- Synopsis:
As per load wattage, 5*150= 750W of Solar panels is required.
Two 100Ah, 12V batteries are provided with parallel connection.
A hybrid 1KVA/800W inverter with built-in charge controller of 20Amp is categorically selected.
6
10-Installation:
Date: May24, 2017
A- Pilot Phase:
Brief Description:
5 Solar panels “150W mono crystalline” were given parallel connection to one another on the roof of “Solar
Energy Lab” at NED University of Engineering and Technology. The output of solar panels through the
“Hager MC 263A, C63, 6000, 3” circuit breaker is given to the inverter by the usage of “H&H 7mm 2 220/440
V” flexible cables.
As per prescription by Solar and Electrical Technologies (Select.pk), the provided Simtek Inverter is
categorically pure sine waved, having similar characteristics as “Axpert KS 1KVA, 12V, 50A” Inverter which
convert DC power generation to AC power and maintain maximum yield without dropping the peak of
voltage.
Two 100Ah Ritar Batteries were given parallel connection inputted to the Simtek Inverter passing by the
“Hager MC 263A, C63, 6000, 3” circuit breaker. The size of cables provided from batteries to inverter is
“H&H 7mm2 220/440 V” (similar to the wire gauge incoming from panels to the inverter).
The Earth wire of the PV system is laid underground for safety purpose.
12-Test Results:
A- Panel Outcome
June15, 2017; running the load on PV system following results was obtained:
As per weather station data: temperature 33°C, Humidity 64%, wind 29km/hr.
Concerning manufacturer ratings, the maximum voltage is 18.2V while on testing the system for first time,
18Volt was measured at 10:45am using clamp meter. The load remained in operation for tentative 1 hour and
10 minutes, which resulted in the generation of 370ml water. Indicated RH on dehumidifier was 54%.
7
13-Troubleshoots:
As per test plan, all major equipment of the subject project with the inclusion of circuit breakers, wire gauges
and accessories are being tested.
In early Feb, 2017; dehumidifier was being tested on grid power by using Power Analyzer. At the start of the
particular equipment; input voltage 236.9V, current drawn 1245mA, frequency 50Hz and real power drawn
295.1W were inspected at relative humidity 49% and temperature 24°C. When the compressor kicked off,
tentative 20 minutes later; examined parameters were 228.4V, 1371mA, 50Hz and 313.13W real power along
with the relative humidity 48-52% and temperature 24-26°C. Compressor got shut off within an hour due to
less humid air and low temperature. Noise level without compressor and with compressor was not detected.
In late Feb, 2017; tripping of compressor took place due to low humid environment than that of the set point
humidity. Later, in order to increase the level of humidity synthetically, steam was provided near to the
compressor which in turn increased the temperature beyond limit and appeared to be the false alternative.
Hence, selection of the above said equipment needs to be modified for the low temperature ranges along with
high relative humidity.
Moreover, in the mid of July 2017; during a bright sunny day, measured parameters were quite less than the
expected results as per given manufacturer ratings and operating efficiency of the panels failed to be proven.
The measured currents were 0.9-1.2A from panels individually, summing up to 4-5Amperes whereas; the
voltage 12.8V was measured close to the manufacturer ratings.
Initially batteries took tentative 12-18 hours to get charged, thus running the load on PV system batteries got
drained and frequent tripping of the system was inspected. Precisely, charge of batteries along with the depth
of discharging has not been observed yet due unfriendly digital display interface of the Simtek Inverter.
The suspected causes can be the unsupportive selection of circuit breakers, the cable sizing of batteries which
should be twice than that coming from the solar panels to the inverter or disintegration.
15-Conclusion:
Hence, after the completion of Market survey, theoretical load calculations and PV System sizing, pilot
installation of the subject project is made done in Solar Energy Lab, NED by the courtesy of Solar and
Electrical Technologies. Objective has been achieved along with the test plan which is under consideration for
accurate outcome after troubleshoots.