COMBINED SCHEDULE FOR SUB-STRUCTURE & SUPER STRUCTURE WORKS UNDER TRAFFIC DIVERSION NO.

2-2
JANUARY FEBRUARY
Item No Construction Activity 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE WED THU FRI SAT SUN MON TUE
End of Diversion 2-1 LHS End of Diversion 2-1 RHS

1 Diversion 2-1 in Operation

Road surface rectification LHS Diversion completes RHS Diversion completes Backfiling & Hoarding

2 Diversion 2-2 Preparation works

LHS LHS/RHS
3 Diversion 2-2 in Operation

curing F/W removal/ Backfilling/ Waler beam removal Superstructure works will be started from Aug 2019

4 MB-P4 LHS

F/W Concrete Curing F/W removal/ Backfilling/ Waler beam removal Superstructure works will be started from Sep 2019

5 MB-P3 LHS

Superstructure works will be started from Jul 2019

6 MB-P5 LHS

Backfilling/ Waler beam removal Superstructure works will be started from Oct 2019

7 MB-P6 LHS

Piling works

8 MB-P3 - MB-P6 RHS Piling works