ETIHAD TOWERS PROJECT

CLIENT SSPD ITP REFERENCE NO.


Specification 3 Digit
PROJECT MANAGER HILL INTERNATIONAL Originator Code
No.
Discipline
Serial No.
Rev.

CONSULTANT CANSULT LTD.


07 07100 WB 016 00
MAIN CONTRACTOR ARABIAN CONSTRUCTION COMPANY
INSPECTION & TEST PLAN – SUB STRUCTURE WATERPROOFING SYSTEM

ITP Inspection
Cla Responsible Reference Type Of Verifying And Test
Description Of Activity Frequency Acceptance Criteria Code
use Person Document Inspection Records
CA
No. AMC ACC
N
1.0 APPROVAL OF QUALITY DOCUMENTS AND DRAWINGS
Check Prequalification and
PM, EM,PQM, Spec Clause &
materials/system applicator Once for Document All documents to have a minimum approval status of “B” – Approved with comments, Approved Pre-
1.1 CM, Sub Pre-Qualification H H H
documents are submitted all areas Review Incorporate and proceed with works Qualification/ M.S
Contractor Document
and approved

Check the relevant shop PM, EM,PQM, Approved Shop


Once for Document All documents to have a minimum approval status of “B” – Approved with comments,
1.2 drawings, ITP & M.S are CM, Sub Spec Clause drg’s, ITP’s, M.S H H H
all areas Review Incorporate and proceed with works
submitted and approved Contractor Approval

2.0 MATERIAL RECEIVING INSPECTION


CM, ME,QC
Check received materials Relevant
Engr, Store All All received materials should be as per approved material submittals and Material receiving
2.1 are as per Approved material Visual Approved MIR H H W
Keeper, Sub Shipment inspection shall be carried out as per Company Material receiving inspection procedure
Materials submittals submittals
Contractor
3.0 SURFACE PREPARATION
* Blinding /profiling done as required.
Spec .&
Ensuring Concrete Post * Surface is sufficiently hardened/cured to ensure application of the waterproofing system
3.1 CM, SEC. & approved Shop
Pour Inspection All Areas Visual *Concrete surface is hardened/ ready to receive the primer as per clause#3.01.A, 3.02 & Check List/WIR H H S
QC Engr Drg Manufacter
Material manufacturers clause#2.01.A.1-6
Recommend
*surface levels are as per the approved drawings
4.0 APPLICATION OF WATERPROOFING SYSTEM

4.1 PILE HEAD TREATMENT


SEC. & QC Spec’s Clause,
Every *Grooves around steel rebars done as specification sec:- 07130 clause #3.03.H.1.B Approved WIR,
4.1.1 Piling top Fairing Grout and Engr. , Sub MS, Approved Visual H H S
Pile *Loose particles are cleaned and mastic applied as per material approval Check List
Mastic Application Contractor Shop Drg’s

LEGEND FOR INSPECTION AND TEST CODE


S = SURVEILLANCE H = HOLD POINT W = WITNESS POINT R = REVIEW DS = DOCUMENT SUBMITTAL

Page of 3 FM E01 Rev. 0


ETIHAD TOWERS PROJECT
CLIENT SSPD ITP REFERENCE NO.
Specification 3 Digit
PROJECT MANAGER HILL INTERNATIONAL Originator Code
No.
Discipline
Serial No.
Rev.

CONSULTANT CANSULT LTD.


07 07100 WB 016 00
MAIN CONTRACTOR ARABIAN CONSTRUCTION COMPANY
INSPECTION & TEST PLAN – SUB STRUCTURE WATERPROOFING SYSTEM

ITP Inspection
Cla Responsible Reference Type Of Verifying And Test
Description Of Activity Frequency Acceptance Criteria Code
use Person Document Inspection Records
CA
No. AMC ACC
N
Spec’s Clause #
* Surface is clean, dry and smooth to receive the primer as per Spec Clause #2.01.A.6.a
Check for Application of CM, SEC. & & approved Approved WIR
4.1.2 All Areas Visual * Primer applied uniformly over the surfaces covering the whole surface Spec sec:-07130 H H S
Primer QC Engr. MS,Approved Check List
clause#3.03.F.1.
Drawings
* Approved Membrane applied as specification sec:-07130 clause#3.03.d
* Corner strips at the interfaces of ver/hor surfaces applied with approved materials clause #
Check for application of CM, SEC. & Spec’s Clause #
3.03.H.1.d Approved WIR
4.1.3 4mm thk membrane & QC Engr. / Sub ,MS,approved All Areas Visual H H S
*Membrane terminated/lapped with horizontal membrane over blinding as per manufacturer Check List
Parafor M3 Contractor Shop Drg’s
recommendation (100mm at side,150mm at end) as per Material Submittal 0063/Product
Technical Data
*Membrane application completed as specified
*Mastic at the grooves cured/set Spec sec:-07130 clause # 3.03.H.1.C
Spec’s Clause #
Check for capping over the CM, SEC. & * Formwork around the peripheral of the pile installed as specification sec:-07130 clause #
& approved Approved WIR
4.1.4 pile head with approved QC Engr. / Sub All Areas Visual 3.03.H.1.e H H W
MS,Approved Check List
grout Contractor *Mixing of grout done as per the manufacturer recommendations (Material Submittal #0063)
Drawings
*Pouring of grout done and compacted properly over and around the surfaces

4.2 HORIZONTAL SURFACES AND VERTICAL SURFACE (Pile Cap & Raft)
* Surface is clean, dry and smooth to receive the primer as per clause # 3.01
* Primer applied uniformly over the surfaces covering the whole surface as per clause
#3.03.F.1
Primer,Geo-Textile Spec’s Clause # * Geotextile laid ion layers as specification sec # 07130 clause # 3.03.F.1
100g/m2,TERNAP 431 TP CM, SEC. & & approved MS, *Approved Membrane applied as specification sec:-07130 clause # 3.03.D Approved WIR
4.2.1 All Areas Visual H H W
Memberane and Geotextile QC Engr. Approved Shop * Corner strips at the interfaces of ver/hor surfaces applied with approved materials as per Check List
140g/m2 Drawings clause # 3.03.C
*Overlapping of vert/Hor membranes at interfaces applied as specification sec:-07130 clause
#3.03.E
*Termination, MEP Sleeves & Openings as per approved Shop Drawing
* Water stopper lapped and welded as recommended by the manufacturer/and as per clause
Check for installation of CM, SEC. & Spec’s Clause #
#3.03.F.2 Approved WIR
4.2.2 water stopper and injection QC Engr. / Sub ,MS,approved All Areas Visual H H W
* Injection hoses fixed at intervals/locations as specification sec:-07130clause # 3.03.H.3.a Check List
hoses Contractor Shop Drg’s
*Water stoppers are protected properly

LEGEND FOR INSPECTION AND TEST CODE


S = SURVEILLANCE H = HOLD POINT W = WITNESS POINT R = REVIEW DS = DOCUMENT SUBMITTAL

Page of 3 FM E01 Rev. 0


ETIHAD TOWERS PROJECT
CLIENT SSPD ITP REFERENCE NO.
Specification 3 Digit
PROJECT MANAGER HILL INTERNATIONAL Originator Code
No.
Discipline
Serial No.
Rev.

CONSULTANT CANSULT LTD.


07 07100 WB 016 00
MAIN CONTRACTOR ARABIAN CONSTRUCTION COMPANY
INSPECTION & TEST PLAN – SUB STRUCTURE WATERPROOFING SYSTEM

ITP Inspection
Cla Responsible Reference Type Of Verifying And Test
Description Of Activity Frequency Acceptance Criteria Code
use Person Document Inspection Records
CA
No. AMC ACC
N

CM, SEC. & Spec’s Clause # * Geotextile membrane is laid and free from wraps as per clause # 3.03.F.1
Check for protection screed/ Approved WIR
4.2.3 QC Engr. / Sub ,MS,approved All Areas Visual * Pouring done with approved grade and finished to the levels as specified H H H
Protection Board Check List
Contractor Shop Drg’s * Curing done as specified

4.3 VERTICAL SURFACES (Retaining Wall)


* Surface is clean, dry and smooth to receive the primer
* Primer applied uniformly over the surfaces covering the whole surface as per clause #
3.03.G.1
Spec’s Clause # * Geotextile laid ion layers as specification sec:-07130 clause # 3.03.F.1
Check for Application of
CM, SEC. & & approved *Approved Membrane applied as specification sec:-07130 clause # 3.03.D Approved WIR
4.3.1 Primer Geo-Textile and All Areas Visual H H S
QC Engr. MS,Approved * Corner strips at the interfaces of ver/hor surfaces applied with approved materials Check List
Membrane
Drawings * System applied around the sleeves/inserts as specified
*Overlapping of vert/Hor membranes at interfaces applied as specification sec:-07130 clause
# 3.03.E
*Termination, MEP Sleeves & Openings as per approved Shop Drawing

Check for installation of CM, SEC. & Spec’s Clause # * Water stopper lapped and welded as recommended by the manufacturer
4.3.2 water stopper and injection QC Engr. / Sub ,MS,approved All Areas Visual * Injection hoses fixed at intervals/locations as specification sec:-07130 clause # 3.03.H.3 Approved WIR H W S
hoses Contractor Shop Drg’s *Water stoppers are protected properly Check List

CM, SEC. & Spec’s Clause #


* Termination of membrane done at the levels as specified Approved WIR
4.3.3 Check for protection Board QC Engr. / Sub ,MS,approved All Areas Visual H H H
*Approved Protection board 6 mm thick applied Check List
Contractor Shop Drg’s

LEGEND FOR INSPECTION AND TEST CODE


S = SURVEILLANCE H = HOLD POINT W = WITNESS POINT R = REVIEW DS = DOCUMENT SUBMITTAL

Page of 3 FM E01 Rev. 0