Comparision of Cooling Tower

Company
S.No Parameters UOM Matangi

1 Water Flow Rate M3/hr 150

2 Hot Water Temp Degree 60

3 Cold Water Temp Degree 35

4 Wet Bulb temp Degree 28

5 Type Fan less Fan less

6 Basin Size Meters 4.5x 4.5x1

7 Price

8 Cooling Tower 285000

9 Erection 18000

10 total 303000
Company
Mist

150

60

32

28

Fan less

7x7

965000

100000

1065000
Water Collecti

Toal Collection goes to New


Cooling Tower

From CSP From recovery


Boiler
From Old
evaporator

New Pump Required @ 160


M3/Hr
Water Collection and discharge Scheme

Discharge Water to be Distributed in


Recovery Boiler , Both Cooling Tower ,
Both Evaporator and Causticizing

From recovery
Boiler
Extra Condensate

New Pump Required @ 160


M3/Hr `
New Pump Required @ 200
M3/Hr
Approximate Cost

S.No Required Approximate Price Approximate Price


Matangi Mist cooling tower
1 Cooling Tower 350000 1000000

2 Pumps ( 4 Nos ) 700000 700000

3 Required Valves 300000 300000

4 Piping 350000 350000

5 Erection of Piping 100000 100000

6 Civil Cost 500000 500000

7 Electrical 500000 500000

8 Instrument 200000 200000

9 M.S. Tank 1000000 1000000

10 Total 4000000 4650000