Professional Documents
Culture Documents
ORGANIZATION
RICO AUTO INDUSTRIES LIMITED
GURGAON, HARYANA
INDIA
PROJECT
Rejection Control of the component Crank Case Left
Raghvendra Singh
ACKNOWLEDGEMENT
I would like to take this opportunity to thank my project guide, Mr. Rajiv Yadav, AGM, Production,
who agreed to be my project guide despite of so much work pressure. He was very patient and
understanding. He always pushed me to learn new things. I would like to thank Mr. Amit Tiwari,
Manager, Quality Assurance, without whose guidance it would have been impossible to complete
the project. He shared a great interest and enthusiasm towards the project and was a constant
motivating factor. He always had something for me to do, even on the last day of the training. I
would also like to thank Mr. S. Kaul, Manager, Production who told me so much about die casting.
He was always very helpful and cooperative. A special word of thanks to Mr. Kunal, Graduate
Engineer Trainee, who was like a friend and with whom besides having technical discussions, I
discussed all the trivial details for which I could not have approached anybody else in the industry. I
would also like to thank Mr. Sandeep Anand, General Manager, Improvement whom I approached
towards the end of my project. His guidance was invaluable. He taught me so many things which I
would not have been able to learn otherwise. Finally, I would like to thank all the operators and
engineers to whom I talked to during my project and whose suggestions went a long way in the
successful completion of the project.
2
TABLE OF CONTENTS
List of figures v
List of tables vi
Abbreviations used vii
3
4.3 Pareto Analysis 24
4.4 Understanding the process flow 25
4.5 Die casting – process and its principles 26
4.6 Identification of the 4M conditions 28
4.7 Process Monitoring 30
4.8 Theoretical analysis 37
4.9 Observations 41
4.10 Conclusion and Suggestions 42
APPENDIX I 47
4
LIST OF FIGURES
Figure 1.1 Plant Layout 6
Figure 3.1 Process Flow HPDC division 10
Figure 3.2 Process Flow Paint shop 12
Figure 3.3 Process Flow – Die division 18
Figure 4.1 Crank Case
19
Figure 4.2 Pareto chart analysis of the rejection data 25
Figure 4.3 Process Flow – CCL 25
Figure 4.4 3M conditions chart-Part 1 29
Figure 4.5 3M conditions chart-Part 2 30
Figure 5.1 Career graph at RICO
5
LIST OF TABLES
Table 1.1 Ferrous Products 4
Table 1.2 Aluminium Products 4
Table 2.1 Training schedule 9
Table 3.1 Sampling Plan 15
Table 4.1 Production data 20
Table 4.2 Rejection data for the months of March, April and May 2005 20
Table 4.3 Rejection data Die-wise for the month of March 2005 21
Table 4.4 Rejection data Die-wise for the month of April 2005 21
Table 4.5 Rejection data Die-wise for the month of May 2005 22
Table 4.6 Overall Die-wise rejection data 22
Table 4.7 Percentage rejection Die-wise for the month of March 2005 22
Table 4.8 Percentage rejection Die-wise for the month of April 2005 23
Table 4.9 Percentage rejection Die-wise for the month of May 2005 23
Table 4.10 Overall rejection percentages Die-wise 23
Table 4.11 Percentage contribution of each defect to the total rejections 24
Table 4.12 Velocity profile 27
Table 4.13 Process Sheet – CCL 31
Table 4.14 Process Monitoring Sheet for the component CCL, cast on 1050T machine 32
Table 4.15 Process Monitoring Sheet for the component CCL, cast on 1050T machine 33
Table 4.16 Process monitoring data : Date 6 July, 2005 ; Shift A ; Machine 1050T ;
Die number 11 35
Table 4.17 Process monitoring data : Date 7 July, 2005 ; Shift A ; Machine 1050T ;
Die number 11 36
Table 4.18 Velocity profile 41
6
ABBREVIATIONS USED
CAD Computer Aided Design
CAE Computer Aided Engineering
CAM Computer Aided Manufacturing
CII Confederation of Indian Industries
CNC Computer Numeric Control
CRAM Casting Rejection After Machining
EDM Electro Discharge Machining
EHS Environment Health and Safety
ETP Effluent Treatment Plant
HDS Hot Die Steel
HHML Hero Honda Motors Limited
HMSI Honda Motors and Scooters India Limited
HPDC High Pressure Die Casting
JV Joint Venture
LDO Low Density Oil
OEE Overall Evaluation of Efficiency
OEM Original Equipment Manufacturers
OHSAS Occupational Health and Safety Assessment Series
PLC Programmable Logic Control
RAIL Rico Auto Industries Limited
R.O. Reverse Osmosis
RPM Revolutions Per Minute
SAP Systems Application Product
SPM Special Purpose Machine
STP Sewage Treatment Plant
TC Turning Center
TCL Tata Cummins Limited
TDS Total Dissolved Solute
TPM Total Productive Maintenance
7
VMC Vertical Machining Center
1977 : Rico commences operations at Ludhiana with ferrous foundry and machining.
1984 : Rico diversifies into aluminium HPDC and machining at Dharuhera.
1990 : Rico enters international market as OEM supplier.
1992 : Rico installs automatic High pressure moulding line ferrous foundry and machining at
gurgaon plant.
1994 : Rico achieves ISO 9000 certification.
1996 : Rico enters into JV with FCC company of Japan.
1998 : Rico gurgaon plant is certified QS 9000.
1999 : Rico dharuhera plant is certified QS 9000.
8
2000 : Rico starts aluminium HPDC at gurgaon.
2001 : Rico enters IT enabled field, Rico softech formed.
Rico opens wholly owned subsidiary in USA.
Rico gurgaon plant is certified ISO/TS16949.
Rico starts Outsourced international Contact centre.
2002 : Rico dharuhera plant certified ISO/TS16949.
All Rico facilities certified ISO-14001.
All Rico facilities certified OHSAS-18001.
1.4 Location
REGISTERED OFFICE & PLANT I : 69 KM Stone, Delhi-Jaipur Highway, Dharuhera -122106
District Rewari, Haryana (India).
1.5 Inputs
1.5.1 Raw materials
The raw materials required are cast iron and aluminium (for castings), other elements for making
alloys such as silicon, copper, manganese, zinc etc, tools and inserts (for cutting, drilling and other
machining operations), moulding sand for ferrous castings, Resin Coated sand (for making cores to
be used in the ferrous shop), bearing, nuts, bolts, sprockets and other material for clutch and panel
assemblies. Sometimes alloy is purchased directly from the vendor (instead of making it on the shop
floor).
1.6 Customers
RICO supplies auto components to major OEMs (Original Equipment Manufacturers) in both India
and abroad. RICO has come a long way since the setting up of its Dharuhera plant in 1984. At that
time it supplied goods only to Hero Honda. Now, RICO has a long list of customers and the list is
growing by the day.
Domestic Customers : Hero Honda, Honda, Tata Cummins, Maruti Suzuki, General Motors India.
Global Customers : Ford, GM, Jaguar, Land Rover, Eaton, Volvo, Cummins, Caterpillar.
Among the domestic customers, a large percentage of goods still goes to Hero Honda. An unofficial
estimate says that about 60% of the domestic supplies go to Hero Honda. RICO Dharuhera plant
manufactures components only for Hero Honda. The two companies being situated adjacent to each
other, components are not even packed before dispatching, but are transported in trolleys. The
figure of 60% is still a long way off from what it was in 1990 (98%). It is planned to further reduce
it to 30% by the year 2010.
1.7 Products
10
The Products manufactured can broadly be divided into two categories : Ferrous products and
Aluminium products. The major products in both these categories are being mentioned below, along
with their annual production and customers.
1.9 IT Applications
11
The entire company is connected via a Local Area Network (LAN). Internet access is provided only
to officials at a higher hierarchical level. This has been done to prevent misuse of the internet by the
employees for personal purposes. Recently, the software SAP (Systems Application Product) has
been successfully implemented in the entire industry. It is a management software which makes
data storage, transfer, sharing and accessibility easier. Tasks such as placement of demand for raw
materials to the purchase section, maintaining records for production data & rejection data,
consumer demands to be met, existing stocks in the stores are carried out through SAP. The
implementation was done through a one year project ending in March, 2005. A 20 member team
was made for the purpose which consisted of people from all the divisions of the organization.
Engineering softwares used by the industry are Pro-E, Unigraphics, AutoCAD, CATIA, SolidEdge
(2D & 3D drawings), Varicut (CAM profile inspection) and Magma (die casting simulation). These
softwares are basically used by the R&D and the die design divisions. Other divisions work mainly
on Microsoft Office packages such as MS Word, MS Excel, MS Outlook, MS Powerpoint. The
operating system used is Microsoft Windows.
Iron scrap (slag) being non hazardous is dumped into the ground as landfill. All harmful chemicals
such Copper scrap, aluminium scrap, lime, Sodium Meta BiSulphide (SMBS), alum, sulphuric acid,
alchrome etc are treated in the ETP before disposing them off. Alchrome, which is used in the paint
shop, contains copper in hexavalent form and it is converted to tetravalent form which is less
reactive and hence less hazardous.
As the ferrous foundry uses induction furnaces, it causes no environmental pollution. Aluminium
foundry uses furnace oil as fuel for melting of aluminium. Gases such as CO and SO2 are released to
the atmosphere. But their amounts are regularly monitored and they are maintained within
permissive limits.
Measures for health of workers include Proactive monitoring of noise, dust and heat in the working
conditions. Environmental Health and Safety Management Programmes (EHSMP) are held
regularly to monitor the health of the workers.
13
CHAPTER 2 TRAINING SCHEDULE
14
S.No DEPARTMENT REPORTING OFFICER DATE
HPDC – Production/Quality
1. Mr. S.K. Bisht 16 May,05-20 May,05
Assurance/Maintenance/Development
Foundry - Production/Quality
2. Mr. Sanjay Arora 21 May,05-25 May,05
Assurance/Maintenance/Development
Machine shop – Production/Quality
3. Mr. R.K. Mighlani 26 May,05-31 May,05
Assurance/Maintenance/Development
4. Dies and Moulds Mr. R.K. Aggarwal 1 June,05-4 June,05
The various divisions of RICO Gurgaon plant were visited as per the schedule given in the table 2.1.
This chapter presents a brief account of the observations made, technical details, description and
new knowledge gained at the HPDC division.
15
The HPDC division deals with pressure die casting of aluminium products. Aluminium (either in its
pure form or as an alloy) is bought from Hindalco (and other vendors). The process flow is
described by figure 3.1.
3.1.1 Melting
There are six furnaces in the HPDC division (+one under installation). Out of these, 3 are
continuous or shaft furnaces and 3 are batch or tilting furnaces. The capacity of the batch furnaces is
1 ton, 1.5 ton and 2 tons respectively. The holding capacity of the shaft furnaces are 2 and 3 tons.
The fuels used in these furnaces are furnace oil and Low Density Oil. Four different types of alloys
are made in these furnaces, namely ADC-12, ADC-14, LM-24 and ADC-12 special. They vary in
their percentage composition of different elements such as silicon, copper, iron, manganese, zinc.
Silicon is added to increase the flow of molten metal and reduce shrinkage. Copper is added for
better machinability. Cover flux is added to make the slag float at the surface. Degasser is added to
remove dissolved hydrogen. Degasser basically consists of chlorine or nitrogen which react with
hydrogen to form HCl and NH3 respectively which do not dissolve in molten aluminium. Cleaning
and maintenance of these furnaces is done once in 15 days.
16
made of Hot Die Steel or Copper Beryllium. The die temperature is maintained at 250 degrees
Celsius. The plunger velocity has three stages
1. Slow - 0.2 m/s
2. Fast – 1.4-2.4 m/s
3. Intensification – At this stage a high pressure is applied to spread the metal evenly and so
that it reaches the intricate corners of the die.
The life of the die is around 80000 shots while that of the plunger is around 20000 shots. After the
metal has solidifies the moving part of the die retreats and the casting comes along with it. The
casting is pushed by the ejector pins and it is then removed by the operator using tongs. The
operator breaks the gates manually and then sends the casting for machining.
3.1.3 Machining
After casting, fettling is done which involves removal of flash and extra unwanted metal from the
casting. Filing is then done to smoothen the edges. Then the component is sent for machining. The
HPDC division has an in house capacity for machining of cast components. There are a number of
CNCs and SPMs for machining purpose. These machines are either VMC or TC. Certain machining
lines are fully automated and work is going on to automate certain other lines.
3.1.4 Assembly
Some components may need to be assembled before dispatching them like clutch assembly and the
panel assembly. Assembly lines are situated at the place of manufacture of these components itself.
Loading (on to the conveyor belt) Predegreasing and degreasing (for removal of dirt
and other particles) Water Rinse I & II (to neutralize the component and remove
adhering chemicals) Chromatising (for better bonding of paint with the component)
Water Rinse III Rinsing in DM water (for neutralizing the component) dry oven
(at 100 degrees for 12 minutes to remove water) Primer bath base coat Clear coat
(for shine) baking oven (at 180 degrees for 30 minutes to dry the paint) unloading.
17
Figure 3.2 Process Flow Paint shop
18
poured over this mix (passing over a conveyor belt) and the sand is passed through a “mixer” for
mixing. The whole process is fully automated and various parameters are controlled automatically.
c) Sand mould : The mixed sand from the mixer is transformed to the sand mould machine (DISA)
which applies a pressure of 15 Kg/cm2 to make the sand moulds. The machine operates at a fixed
cycle time. These sand moulds are passed onto a moving belt and the melted material is poured in
them by a pressure funnel (which has heater arrangements to keep the molten materials at a fixed
temperature). The molten metal is kept in pouring furnaces connected to funnel. The temperature
for pouring ranges from 1380-1450 °C depending upon the component to be made. The venting for
the removal of gases is accounted in the pattern itself. The conveyor belt carries 45 moulds at a
time. By the time one mould (with casting inside it) reaches the end of the conveyor, the casting
gets solidified.
d) Casting line : These castings are then moved onto a vibrator on which the sand mould breaks.
This casting and sand mixture then passes through a rotating drum (DIDION) inner regions having
holes to remove the sand from the casting. Sand which can’t be removed through these holes is
removed manually at the end of the drum. Castings then pass through shot blasting operation which
is done to remove the fine sand particles sticking on to the casting which could not be removed in
the casting vibrator. Inspection is done after the sand blasting operation to check for casting
rejections. The OK components are passed on for breaking the runners and the risers.
e) Fettling : Some portions of the components can’t be cleaned by shot blasting. So, grinding
operation is done for these portions. Also, parting line is removed if required by grinding. Then, the
components are checked for defects like, shrinkage, blow holes, core defects etc.
f) Core shop and the pattern shop : The foundry shop has an in house facility for core making. The
resin coated sand is replicated to make core for the cavities of various components and is heated so
that all the moisture in the sand is lost, making the core sand to reach the required strength. Another
method for core formation is , by adding resin to the core sand and applying the prescribed air
pressure. Also, the final gating and pouring basin for the patterns are made here attaching wooden
pieces to the finished pattern obtained from dies and moulds division.
3.2.2 Quality department
Most of the castings are sent to the machining division for machining. Only a few products are
dispatched to the customers as cast. No dimensional inspection is done for the components which
are sent for machining. Only visual inspection suffices. The quality section collects data from
machining division on the numbers of CRAM’s per shift. The quality section has a metallurgical lab
for inspection purpose. Tests are conducted for checking the material composition (spectrometer),
19
hardness (Rockwell and brinell hardness tester), various parameters for sand such as permeability,
porosity, wet tensile strength, shear strength, moisture content etc. The results of material testing in
terms of percentage composition are displayed on the shop floor to let the workers know of it and so
that they can decide if they have to make any changes.
b) Process Inspection : In the drawings from the customer, dimensions are always large in number
and checking of all dimensions is not at all feasible. So, either the critical dimensions are specified
by the customer or the quality department itself decides the critical dimensions. Process sheet
contains all the critical dimensions which need to be checked for every component by the operator
or by the quality inspector (as per checking frequency).
21
Specification Limit), the department tries to control the tolerance zone within UCL (Upper Control
Limit) and LCL (Lower Control Limit) to ensure that the process is under control and that the
process is capable of meeting the required specifications.. The data for a particular critical
dimension is taken (5 consecutive readings) for 125 readings in a month. The process capability is
then calculated from that data by plotting X bar and R charts.
22
g) Training : The department has to ensure that its workers have the ability to correct the
breakdowns to its best. Their work should be up to the levels of satisfaction. So there are training
programs (in-house and outside) so that the efficiency of the manpower is higher.
23
Fitting of water cooling pipes, die insert into the mould base, cores into the slides, minor machining
operations such as drilling are the tasks that are done at the assembly division. The fixed and the
moving half also tested to see that they match with each other perfectly. The process is called
spotting.
The process flow for die manufacturing can be represented as in the following figure.
24
various components. I pursued a project titled “Rejection Control of the component Crank Case Left
(CCL)”. The component CCL is manufactured for HMSI. The component is sent “as cast” i.e. no
machining is done after casting. The product is critical for both RICO (in terms of profit) and HMSI
(for proper functioning of its scooters and motorcycles). The component manufactured is on two
machines – 800T and 1050T in all the three shifts.
25
be obtained die wise. Therefore, the rejection percentages could not be compared for the two
machines on which the component is manufactured. Table 4.1 gives the production data die wise for
the months of March, April and May.
Table 4.2 Rejection data for the months of March, April and May 2005
March April May
Warm up 1304 1230 1309
Non filling 2664 2752 2117
Crack 213 134 217
Catching 56 108 81
Gate broken 40 42 137
Soldering 10 0 41
Bend 0 44 23
Pin broken 0 6 0
Extra metal 0 0 80
Table 4.2 gives the rejection data along with the major kinds of defects occurring in the component.
Tables 4.3-4.5 show the rejection data die wise, indicating the frequency of occurrence of each
defect for each die. This could be used to see whether a particular die was having any particular
defect more frequently than the other dies. However, no such trends were observed.
Table 4.3 Rejection data Die-wise for the month of March 2005
Die Non Gate
Warm up Crack Catching Others Total
number filling broken
4 119 207 10 4 15 355
10
6 176 357 14 19 9 585
(soldering)
7 333 768 142 8 6 1257
9 392 753 2 19 8 1174
11 284 579 45 6 2 917
26
Table 4.4 Rejection data Die-wise for the month of April 2005
Die Non Gate
Warm up Crack Catching Others Total
number filling broken
4 48 119 0 20 0 0 187
6 (pin
6 142 301 26 14 12 507
broken)
7 67 160 0 0 0 0 227
9 417 939 26 9 12 44 (bend) 1447
11 255 628 38 59 6 0 986
13 49 130 24 0 0 0 203
14 252 475 20 6 12 0 765
Table 4.5 Rejection data Die-wise for the month of May 2005
Die Non Gate
Warm up Crack Catching Others Total
number filling broken
4 156 294 6 0 22 0 478
7 404 693 84 10 58 56 1585
9 383 654 83 34 29 55 1238
11 331 614 44 37 22 26 1074
14 35 92 0 0 6 7 140
27
Table 4.7 Percentage rejection Die-wise for the month of March 2005
Die number Production Rejection Percentage rejection
4 4333 355 8.19
6 6834 585 8.56
7 13027 1257 9.65
9 15801 1174 7.43
11 8788 914 10.40
Table 4.8 Percentage rejection Die-wise for the month of April 2005
Die number Production Rejection Percentage rejection
4 1850 187 10.11
6 5414 507 9.36
7 2777 227 8.17
9 15387 1447 9.40
11 8581 986 11.49
13 1561 203 13.00
14 8957 765 8.54
Table 4.9 Percentage rejection Die-wise for the month of May 2005
Die number Production Rejection Percentage rejection
4 6138 478 7.79
7 12585 1585 12.59
9 13486 1238 9.18
11 12153 1074 8.84
14 1173 140 11.93
28
b) for all the dies.
The Pareto chart analysis showed clearly that Non-filling was the major defect which was
accounting 60% of the total rejections. Warm up can not really be counted as a defect as it is
unavoidable and can be reduced by reducing the number of stoppages of the machine.
29
Pareto Analysis
120
100
Cumulative percentage
Percentage Rejection
80
Percentage
60
Cumulative percentage
40
20
0
l
ng u p ack ing ken eta end ring k en
if lli rm r
C a tc
h o B e o
o n a br ra m old br
W C e t S Pi n
N at Ex
G
Defects
After casting of the component, the operator puts it in a trolley (without breaking the runners and
the gates). The trolley is then taken to the fettling area. Here first the removal of runners and gates
takes place and then fettling is done in 3-4 stages in which flashes, burrs, parting line spots are
removed by filing. Holes are opened and the edges are smoothened. The component is then
inspected before being carried in trolleys to the packaging area. Inspection is done to ensure that
any “suspected leaking” pieces are removed. Human subjectivity is involved in this as there is no
sure shot way of checking whether a component is leaking or not. It is impossible to seal the
component (for leak testing) without machining it. So small levels of non-filling are acceptable
30
provided they don’t lead to the leaking of the component. The component is machined after it
reaches HMSI and is then subjected to leak testing.
j) High Speed length – This is the length for which the plunger moves at high speed. It includes the
distance covered in accelerating from slow speed to high speed. For example, in the velocity profile
given in table 4.12 the high speed length is 805-665 = 140 mm.
k) Biscuit – It is a cylindrical piece of metal which remains between the plunger and the diffuser. Its
diameter is obviously the same as the diameter of the plunger and its thickness varies from shot to
shot and is called biscuit thickness.
l) Intensification position – It is the plunger position from which the intensification stroke begins.
32
m) Die lubrication time – It is the time for which lubrication of the die takes place in machines in
which lubrication takes place automatically.
n) Plunger forward limit stroke (halt position) – The plunger moves forward a small distance at the
time of die opening. The distance between the initial position of the plunger and this final position
is called the plunger forward limit stroke and this final position is called the halt position.
33
Figure 4.4 3M conditions chart-Part 1
34
Figure 4.4 3M conditions chart-Part 2
35
Table 4.13 Process Sheet – CCL
Whether
SNo Parameter Dimension 1050T
monitored
1. Die height mm 805 No
Dry shot stroke
2. mm 659±10 No
(initial position)
Plunger forward limit stroke
3. mm 710±10 No
(halt position)
4. Plunger diameter mm 90 No
Ejection type
5. (C-plate, bumper rod, ejector - E/rod No
rod)
6. Fix block cooling Yes/No Yes Yes
7. Moving block cooling Yes/No Yes Yes
8. Die timer sec 12±3 Yes
9. Die lubrication time sec 1.5±0.5 Yes
10. Ejection delay time sec 2.5±1.0 Yes
11. Biscuit size mm 25±5 Yes
12. Low speed m/s 0.2±0.05 Yes
13. High speed m/s 3±0.5 Yes
14. High speed length mm 170±10 Yes
15. INTF. position mm NA Yes
16. Pressure up time % 80±20 Yes
17. Cast pressure kg/cm2 650~850 Yes
18. Accumulator pressure kg/cm2 90~135 Yes
19. Metal temperature °C 660~690 Yes
For the purpose of process monitoring, process monitoring sheet was made which contained the
parameters to be monitored along with their specifications. Some other parameters from the 4M
conditions chart were not monitored, either because it was not possible to monitor them under the
given constraints and conditions, or the probability of their deviating from their specification zone
was extremely low. The process monitoring sheet along with the monitoring data is given in tables
4.14 and 4.15. Initially it was decided to concentrate on the 1050T machine as the machine was new
and it was easier to understand its controls.
36
Table 4.14 Process Monitoring Sheet for the component CCL, cast on 1050T machine
OK OK OK
SN 5/7 6/7 7/7
Parameter Specification / / /
o Shift A Shift A Shift A
NG NG NG
Material (Metal)
1. ADC-12 OK OK OK
Composition
Metal temperature
2. 660-690 °C 692 OK NM NM
(holding furnace)
No metal
should be
3. Metal sensor condition NG NG NG
sticking on
them
4. Plunger temperature 60-80 °C NM NM NM
±0.05
5. Low speed 0.2 m/s 0.25 OK 0.25 OK 0.25 OK
6. High speed 3±0.5 m/s 2.50 OK 2.50 OK 2.30 NG
±10
7. High speed length 170 mm 140 NG 140 OK 145 NG
8. Cast pressure 650-850 kg/cm2 700 OK 700 OK 720 OK
±20
9. Pressure up time 80 % NG NG NG
2
10. Accumulator pressure 90-135 kg/cm 121 OK 121 OK 123 OK
11. Biscuit size 25±5 mm 50 NG 47 NG 53 NG
12. Intensification position NA - - - - - -
13. Solidification time 16±3 sec 14 OK 15 OK 14 OK
14. Ejection delay time 2.5±1.0 sec 2.5 OK 2.5 OK 2.0 OK
±0.5
15. Die lubrication time 2.5 sec NA NA NA NA NA NA
Locking force
16. 7150 KN OK OK OK
delivered
No flashes
17. Air vents condition should stick on OK OK OK
them
They should
18. Overflows come out with OK OK OK
the casting
Fixed block
19. NM NM NM
temperature
Moving block
20. NM NM NM
temperature
21. Diffuser temperature NM NM NM
Sprue bush
22. NM NM NM
temperature
NG Not Good
NM Not Monitored
37
Table 4.15 Process Monitoring Sheet for the component CCL, cast on 1050T machine
OK OK OK
SN 9/7 11/7
Parameter Specification / / /
o Shift A Shift A
NG NG NG
Material (Metal)
1. ADC-12 OK OK
Composition
Metal temperature
2. 660-690 °C 610 NG NM
(holding furnace)
No metal
should be
3. Metal sensor condition NG NG
sticking on
them
4. Plunger temperature 60-80 °C NM NM
±0.05
5. Low speed 0.2 m/s 0.25 OK 0.25 OK
6. High speed 3±0.5 m/s 2.30 NG 2.50 OK
±10
7. High speed length 170 mm 145 NG 145 OK
8. Cast pressure 650-850 kg/cm2 720 OK 750 OK
±20
9. Pressure up time 80 % NG NG
2
10. Accumulator pressure 90-135 kg/cm 119 OK 121 OK
11. Biscuit size 25±5 mm 57 NG 45 NG
12. Intensification position NA - - - -
13. Solidification time 16±3 sec 14 OK 13 OK
14. Ejection delay time 2.5±1.0 sec 1.0 NG 1.0 NG
15. Die lubrication time 2.5±0.5 sec NA NA NA NA
Locking force
16. 7150 KN OK OK
delivered
No flashes
17. Air vents condition should stick on OK OK
them
They should
18. Overflows come out with OK OK
the casting
Fixed block
19. NM NM
temperature
Moving block
20. NM NM
temperature
21. Diffuser temperature NM NM
Sprue bush
22. NM NM
temperature
23. Dry shot stroke 659±10 mm 880 NG 880 NG
24. Plunger halt position 710±10 mm 900 NG 900 NG
NG Not Good
38
NM Not Monitored
The die temperature could not be monitored as the temperature probe was not available with the
company. There was a laser device which was used for measurement of temperature but it was not
accurate and gave deviations of upto 30-40 °C.
The next step was to actually stand in front of the machine and each shot as it comes out. Check
whether the piece is OK or reject. Then take down the shot parameters from the computer control
unit of the machine. This had to be done for atleast 1 hour at a stretch. This needed you to be able to
judge on your own whether a component was OK or reject. As explained earlier, this involved some
amount of human subjectivity as their were no hard and fast rules guiding it. So first lot of time was
spent with the quality inspector to try to develop that sense of judgment and to understand what
level of non filling was acceptable. Die coat (lubricant) marks on the casting could easily be
mistaken for non filling. It was essential to be able to differentiate between the two. Some of the
process monitoring data is being given in tables 4.16 and 4.17.
39
Table 4.16 Process monitoring data : Date 6 July, 2005 ; Shift A ; Machine 1050T ;
Die number 11
Time Press
Biscui Max.
Shot Cavit till Inject ure Plung Locki Gate
t metal Cycle
numb y fill end ion build er ng veloci Status
thick press time
er time cavity time up speed force ty
ness ure
fill time
mm bar sec sec sec sec sec m/s KN m/s
273 59 750 91.5 0.161 3.409 3.715 0.003 2.48 7307 - OK
274 55 741 91.5 0.149 3.423 3.775 0.003 2.48 7326 55.4 OK
275 56 746 94.5 0.151 3.41 4.298 0.002 2.49 7341 55.6 OK
276 44 746 101.4 0.165 3.452 3.596 0.065 2.48 7334 55.4 *
277 60 737 100.4 0.168 3.408 3.836 0.003 2.5 7311 55.9 OK
278 59 739 93.5 0.31 3.392 3.65 0.02 2.47 7328 55 OK
279 58 737 94.5 0.158 3.42 3.981 0.003 2.5 7348 55.7 OK
280 58 739 93.5 0.154 3.426 3.857 0.002 2.5 7360 55.8 OK
281 56 741 95.5 0.148 3.429 3.614 0.003 2.5 7265 55.8 OK
282 57 741 100.4 0.162 3.421 4.034 0.003 2.49 7267 55.6 OK
283 50 753 157.2 0.141 3.42 3.603 0.023 2.5 7207 55.8 OK
284 45 750 92.6 0.171 3.476 3.592 0.041 2.5 7220 55.7 NG
285 47 747 92.5 0.145 3.447 3.618 0.048 2.48 7228 55.4 *
286 50 747 97.4 0.139 3.417 3.594 0.049 2.5 7214 55.7 NG
287 46 767 94.6 0.138 3.427 3.541 0.032 2.46 7237 54.8 NG
288 55 750 101.4 0.145 3.413 3.581 0.004 2.47 7227 55 OK
289 49 750 98.4 0.145 3.412 3.51 0.012 2.47 7219 55.6 *
290 52 744 92.5 0.143 3.414 3.522 0.015 2.48 7250 55.3 *
291 52 747 92.5 0.145 3.425 3.659 0.011 2.45 7254 54.7 *
292 47 551 96.6 0.14 3.429 3.559 0.023 2.48 7219 55.4 *
293 53 757 95.5 0.289 3.408 3.574 0.024 2.42 7234 54 OK
294 49 748 95.5 0.138 3.435 3.594 0.047 2.51 7222 56.1 *
295 53 751 235.7 0.146 3.409 3.66 0.004 2.49 7136 55.7 *
297 57 753 93.5 0.151 3.421 3.689 0.003 2.49 7155 55.6 *
298 69 415 576.1 0.299 3.626 3.636 0.005 0.97 7037 21.6 NG
299 60 376 86.6 0.261 3.653 3.66 0.006 0.97 7094 21.6 NG
300 54 737 90.3 0.146 3.413 3.699 0.005 2.48 7142 55.3 *
301 50 755 94.5 0.14 3.416 3.534 0.032 2.5 7140 55.8 *
302 50 751 90.5 0.14 3.434 3.679 0.023 2.49 7163 55.6 *
303 44 754 90.5 0.141 3.427 3.553 0.039 2.48 7182 55.4 NG
304 39 770 175 0.147 3.468 3.604 0.065 2.47 7132 55.1 NG
305 56 742 86.5 0.165 3.416 3.85 0.006 2.47 7146 55.2 OK
306 54 750 88.6 0.292 3.405 3.607 0.024 2.44 7181 54.5 NG
Mean 53 721 117.3 0.171 3.436 3.681 0.02 2.39 7225 53.28
Stand
ard
6 91 87.6 0.052 0.055 0.168 0.019 0.37 79.29 8.323
Devia
tion
* though the casting was acceptable but their were significant levels of non filling in the
component
40
Table 4.17 Process monitoring data : Date 7 July, 2005 ; Shift A ; Machine 1050T ; Die number 11
Time Press
Biscui Max.
Shot Cavit till Inject ure Plung Locki Gate
t metal Cycle
numb y fill end ion build er ng veloci Status
thick press time
er time cavity time up speed force ty
ness ure
fill time
mm bar sec sec sec sec sec m/s KN m/s
764 57 764 95.5 0.145 3.422 3.8 0.002 2.29 7228 51 OK
765 48 762 95.5 0.116 3.424 3.662 0.004 2.3 7223 51.3 OK
766 46 763 93.5 0.114 3.431 3.678 0.004 2.29 7244 51.2 OK
767 50 757 92.5 0.125 3.423 3.838 0.002 2.3 7249 51.2 OK
768 48 758 95.6 0.119 3.43 3.665 0.004 2.28 7248 50.9 OK
769 53 768 94.5 0.135 3.425 3.677 0.003 2.27 7271 50.7 OK
770 44 768 242.6 0.113 3.426 3.524 0.008 2.29 7155 51.1 NG
771 53 757 93.5 0.138 3.401 3.634 0.004 2.28 7183 50.8 OK
772 49 767 96.6 0.122 3.429 3.657 0.004 2.28 7185 50.9 *
773 49 761 96.5 0.122 3.427 3.661 0.004 2.27 7207 50.6 OK
774 51 772 91.5 0.131 3.429 3.618 0.005 2.25 7226 50.3 OK
775 49 758 96.5 0.118 3.429 3.62 0.004 2.27 7246 50.6 OK
776 47 773 114.4 0.257 3.395 3.581 0.022 2.22 7228 49.6 NG
777 49 767 108.5 0.119 3.429 3.612 0.003 2.28 7251 50.9 OK
778 51 772 90.5 0.128 3.422 3.936 0.003 2.3 7261 51.4 OK
779 52 756 94.5 0.131 3.427 4.037 0.002 2.3 7276 51.3 OK
780 56 766 95.5 0.141 3.426 3.791 0.002 2.28 7289 51 OK
781 48 771 94.5 0.119 3.428 3.598 0.005 2.28 7291 50.8 OK
782 53 763 105.5 0.138 3.407 3.653 0.005 2.28 7281 50.9 *
783 52 756 94.5 0.128 3.424 3.711 0.003 2.29 7281 51.1 OK
784 52 756 108.3 0.128 3.41 3.587 0.003 2.29 7273 51.1 *
785 47 764 94.6 0.116 3.429 3.648 0.005 2.29 7281 51.1 *
786 47 763 96.5 0.119 3.426 3.709 0.005 2.28 7276 50.9 *
787 48 759 100.4 0.119 3.432 3.602 0.005 2.29 7297 51.1 *
788 50 770 98.4 0.121 3.427 3.66 0.003 2.29 7302 51.1 OK
Mean 50 764 103.2 0.13 3.423 3.686 0.005 2.28 7250 50.92
Stand
ard
3 5.47 29.01 0.027 0.009 0.113 0.004 0.02 37.61 0.363
Devia
tion
* though the casting was acceptable but their were significant levels of non filling in the
component
41
4.8.1 Machine parameters
4.8.1.1 CASTING COMPONENTS
plunger diameter 90.0 mm
active sleeve length 880 mm
biscuit thickness programmed 25 mm
end of pourhole 125 mm
4.8.1.2 CASTING DATA
designation of casting 2
number of castings 1
designation of alloy ADC-12
density solid metal 2.70 g/cc
density factor : RhoM liquid 0.95
projected area – total 1175 cm2
gate area 285 mm2
vent area 27 mm2
total casting weight 4830 gms
weight after gate 2840 gms
weight of overflows 210 gms
casting weight 2630 gms
π * D2 * (L – l4) / 4 = V4
π * 92 * (880 – l4) / (4 * 10) = 1305.09
l4 = 674.85 mm
14. Weight after gate – Cast iron ring weight = W5
W5 = W1 – w
W5 = 2840 – 70
W5 = 2770 gms
15. Volume of metal after gate (V5) = W5 / d
= 2770 / 2.70
= 1025.53 cc
16. Filling stroke = l5
π * D2 * l5 = V5
π * 92 * l5 = 1025.53
44
l5 = 161.2 mm
4.8.3 Estimation of high speed position, intensification position and gate velocity
I High speed injection position
Sleeve cross section area = π * D2 / 4
= π * 92 / 4
= 63.62 cm2
85
0.25
180
0.25
250
0.25
665
0.25
700
2.50
805
2.50
815
0.60
820
0.40
4.9 Observations
1. During the monitoring of the process, it was observed that biscuit size and cycle were critical for
obtaining a good casting. Whenever the biscuit size fell below 50 mm, the casting obtained was
invariably found to have non filling. Similarly, when the cycle time exceeded 110 seconds the
casting obtained was not good which is quite expected as the die gets cooled down. Also, although
the specification for biscuit size was 25±5 mm, it was always around 50 mm
2. There was a difference between the biscuit size as indicated by the machine and the actual biscuit
size as measured by the vernier calipers. The actual biscuit size was found to be 18 mm less than
that indicated by the machine. Nobody in the company was aware of this, and after they were told
about this nobody could explain as to why this was happening.
3. The process sheet for 1050T machine has arbitrarily been made on the basis of the process sheet
for 800T machine. The 1050T machine has different machine parameters than the 800T machine.
4. The velocity profile showed that the high speed length has been set to 140 mm whereas
calculations suggested that it should be around 165 mm. This could be a big reason behind the
46
occurrence of defects as a lower high speed length means longer cavity fill time which could lead to
cooling of the metal inside the die. The cavity fill time was coming out to be around 120
milliseconds. For a casting of this weight, the suggested cavity fill time is 80-90 milliseconds.
5. The variation in the biscuit size on 1050T machine was found to be higher than the other
machines operating in the industry. Whereas the standard deviation for other machines was around
1.5 mm, for the 1050 T machine it was around 3mm. This shows lack of process control. Part of the
reason for this could be the poor condition of the sensors attached to the ladle which draws metal
from the holding furnace and lack of temperature control of the holding furnace.
47
CHAPTER 5 TRAINING EXPERIENCE
5.1.3 Award-Reward
The company has instituted the following awards for the motivation of the workers
i) Long service award – It is given to the worker who has worked for the company for 5 or more
years.
ii) Best Worker award – This award is given on recommendation of the supervisors and the
engineers of each division.
iii) Best suggestion award
48
Deputy General Manager General Manager
Figure 5.1 Career Graph at RICO
5.1.5 VRS history/plans
The company has no VRS history and it does not plan to introduce the scheme in the near future.
5.1.6 Innovations
The company has taken a number initiatives to increase the productivity of the organization. Efforts
have been made and are being made to remove all unproductive activities to as much extent as
possible. Major steps taken in this direction are introduction of TPM, Kaizen and six sigma.
5.1.6.1 TPM
TPM stands for Total Productive Maintenance. TPM is a Japanese concept and it originated from
the Japan Institute of Plant Maintenance (JIPM). In India, the CII has opened a TPM club of India,
in collaboration with JIPM, for spreading the TPM culture among Indian industries. TPM aims at
removing all unproductive activities prevalent in the industry. According to TPM, all activities
should be aimed at increasing the productivity. All activities should be for the benefit of the
company. The concept can be summarized by the following definition.
Total : Involvement of all people horizontally and Vertically.
Productive : All activities are focused towards increasing the productivity.
Maintenance : To develop a habit of maintaining all the 4M’s.
TPM is equipment focused. dustry is measured by its OEE. OEE is defined as
OEE = Availability rating * Performance rating * Quality rating
85% OEE is considered to be good in process industries. In engineering industries, especially
machine shop, it can be as high as 95%. There are 8 pillar activities of TPM.
1. Autonomous maintenance (AM)
2. Plant Maintenance (PM)
3. Quality Maintenance (QM)
4. Focused Improvement (KK)
5. Education and Training (E&T)
6. Safety, Health and Environment (SHE)
7. Office TPM (OTPM)
8. Development Management (DM)
49
The foundry and the machine shop have already achieved high OEE’s. The company aims to
achieve the TPM status by December, 2006.
5.1.6.2 Kaizen
Kaizens are low cost, small improvements made to any production activity in the industry such as
casting, machining, material management. They can be initiated by anyone from the operator to the
plant manager. Improvements are made by doing a “Why-Why” analysis of the existing problem.
Repeated questioning is done until the root cause of the problem is found or reached at. Then a
counter measure is taken which counters the root cause of the problem. Employees are rewarded for
initiation and successful execution of Kaizens. A Kaizen workshop has also been made for this
purpose. Kaizens contribute greatly towards increasing the productivity .
Magma software : Magma is used in the die design division to simulate the filling up of metal inside
the die and the die and the metal temperatures. It gives an estimate of what happens inside the die
once metal has been poured in the shot sleeve and the plunger starts to move. The reliability of the
software is high and it saves a lot of time and effort.
50
Diamond cutting tools : Diamond tools (inserts) are used for operations requiring a high
dimensional tolerance. They can cost upto Rs. 50000. Requirement of high precision product by the
customer and long insert life justify the use of such costly tooling.
42000 rpm machine : CNC machines with rpm as high as 42000 are used for machining purposes in
CAM division. Such a high rpm is needed for machining of HDS which is used for making die
inserts. It is a very hard material and besides requirement of very high tolerance necessitate and
justify the use of such heavy equipment.
Wire cut EDM : The principle of operation of wire cut EDM is same as EDM. The electrode used
in this case is a fine copper wire. Current is made to pass through the wire and it is given a certain
velocity at the required position with the help of motor and pulleys. Material is removed by virtue
of spark produced between the wire and the component.
51
APPENDIX I
52