You are on page 1of 1

EPC&C OF GAS TRAIN 5 PROJECT AT MAA REFINERY

CONTRACT NO: CA/CSPD/0116


INSTRUMENT CHECK LIST
CJX31 - INSTRUMENT JUNCTION BOX INSTALLATION
APPLICABLE QMS: PRJ-QMS 9C-03-5243

*A10050046*
*A10050046*
TAG: 337-JF-D-002-4 DESCRIPTION: INSTRUMENTATION JUNCTION BOX
SUB-SYSTEM: 0I03-007 - MULTICABLE & JUNCTION BOX 337
P&ID / DWG: 3-D-337-1-64-7381-4 USER GROUP: HEISCO

ITEM CHECK LIST RESULT


1 Location of JB as per the approved drawing
2 Check equipment is de-energized and safe.
3 Check nameplate data/certification is in accordance with project data.
4 Check enclosure is correctly tagged as per drawing.
5 Check enclosure is correctly mounted and easily accessible.
6 Check enclosure is correctly earthed.
7 Check all unused entries are plugged with approved blanks.
8 Check segregation barriers are fitted where necessary.
9 Check support frame installation
10 Incoming cable size and numbers verified
11 Outgoing cable size and numbers verified
12 Cables are properly glanded
13 Cablels termination correct and neatly done
14 All materials used as per approved specifications
N.A. Not applicable. P_ Punch item (categorized PA, PB, PC) to be recorded in the punch list register. No further work required.
No te: if there are NO ADDITIONA L REM A RKS enter NONE, initials and date. If there are remarks, reaso n to be written in "REM A RKS" sectio n and, where applicable, raised as an
exceptio n o r o utstanding issue as part o f the system hando ver/punchlist.
Remarks :

SUBCONTRACTOR CONTRACTOR COMPANY

Signature

Name
Designation
Date

CJX31, Rev.0