You are on page 1of 8

Name of Work-Clearance of Slush from drain & barrel, clearance of jungle and

Oiling and Greasing of Barrel on Gomti Nagar protection bundh behind


janeshwar mishra park

Abstract of Cost

Sl. No. Name of Items Unit Quantity Rate Amount. (Rs.)


1 Oiling and Greasing of gates whole system
at barrel with material, labour, T & P etc
required as per site condition complete . Nos 2 2452.55 4905.10

2 Thick jungle clearance with thorney bushes


on bundh and drain river side without M² 5850.00 6.00 35100.00
uprooting
3 Clearance Slush from Nala Bed and barrel
with its proper disposal inluding cost of all
labour and T&P etc. complete required as cum 1101.17 122.65 135058.50
per side condition.

Total Rs. 175063.60


Add- G.S.T. @ 12 % 21007.63
Add- Labour Cess @ 1 % 1750.64
Net Total Rs. 197821.87
Say Rs. 1.98

JE A E IV
LDSC
LUCKNOW
.
Name of Work-Clearance of Slush from drain & barrel, clearance of jungle and
Oiling and Greasing of Barrel on Gomti Nagar protection bundh behind janeshwar
mishra park

Bill of Quantity /Detail of measurement


Sl.
No. Item of works No. L B D/H Qty
Oiling and Greasing of gates whole system at
1 barrel with material, labour, T & P etc required
as per site condition complete . 2 2
Total quantity in nos 2
Thick jungle clearance with thorney bushes
2 on guide bundh and drain without uprooting

LS 1 30.00 25.00 750.00


1 25.00 35.00 875.00
1 30.00 30.00 900.00
RS 1 25.00 35.00 875.00
1 25.00 30.00 750.00
1 35.00 28.00 980.00
drain rider side 1 28.00 15.00 420.00
1 25.00 12.00 300.00
Total quantity in sqm 5850.00
Digging Slush from Nala Bed and its proper
3 disposal inluding cost of all labour and T&P
etc. complete.

barrel 1 53.00 3.45 0.95 173.71


1 53.00 3.45 0.95 173.71
drain rider side 1 30.00 7.50 1.20 270.00
1 30.00 7.50 1.35 303.75
1 20.00 7.50 1.20 180.00
Total quantity in cum 1101.17

JE A E IV
LDSC
LUCKNOW
Analysis of Rates Year 2018 - 19

Item of work

1 Oiling and greasing of Barrels per Nos


Cost of grease 3kg @ Rs 350/Kg Rs. 1050.00
Cost of 1 Lt. Mobil Oil @ Rs 310/Lt. Rs. 310.00
Cost of 5 Lt. Diesel @ Rs. 64.31/Lt. Rs. 321.55
Rs. Approved as per estimet no. 39/EE/2017-18
Labour charges for 1Nos barrel.
2 Nos Beldars @ Rs 274 ie Rs 584.00 (As per IDSOR Chap -1, item no. 6 Rs. 548.00
Add 10 % contractor Profit on Rs (1050+310+321.55+548.00) is Rs. 2229.55 Rs. 223.00
Total.Rs. 2452.55 /Nos

2 JUNGLE CLEARANCE/M²
(i) Thick jungle clearance with thorney bushes
on bundh without uprooting (As per
I.D.S.O.R Chap no.iV item no. 1c(iV) Rs. 500.00
(ii) 20% Extra on Rs. 500.00 due to work in Lko
corporation limit area Rs. 100.00
Total.Rs. 600.00 /M³
Total Rate per sqm 6.00
3 Digging Slush from Nala Bed and its proper disposal inluding cost of all labour
and T&P etc. complete.
(i) Earth work in Clearence of drain initial
rate including all lead and lift with partial Rs. 59.10 per M³
dressing.
(as per I.D.S.O.R. chapter
V/Item
(ii) Extra forNo. 18) and taking out slush not
digging
flowing. (as per I.D.S.O.R.
chapter V/item no. 15) Rs. 43.10

102.20
(iii) Add 20% extra due to work in Lucknow on Rs 120.20
City corporation limited. Rs. 20.44
(59.10+43.10) = 102.20
Total Rs. 224.84
Say Rs. 122.65 per M³

JE A E IV
LDSC
LUCKNOW
Lucknow Division, Sharda canal, Lucknow

Name of Work-Clearance of Slush from drain & barrel, clearance of jungle and
Oiling and Greasing of Barrel on Gomti Nagar protection bundh behind janeshwar
mishra park

Bill of Quantity
Rates
Sl. No. Name of Items Unit Quantity In figures In words
1 Oiling and Greasing of gates whole system
at barrel with material, labour, T & P etc
Nos 2
required as per site condition complete .

2 Thick jungle clearance with thorney bushes


on bundh and drain river side without M² 5850.00
uprooting
3 Clearance Slush from Nala Bed and barrel
with its proper disposal inluding cost of all
labour and T&P etc. complete required as cum 1101.17
per side condition.
Name of Work-Clearance of Slush from drain & barrel, clearance of
jungle and Oiling and Greasing of Barrel on Gomti Nagar protection
bundh behind janeshwar mishra park

Mts record against aggrement no 08/A E IV/2019-20 in favour of


cont M /S Maa shree construction
Site--Barrel on Gomti Nagar protection bundh behind
janeshwar mishra park
Sl.
No. Item of works No. L B D/H Qty
Record ofThick jungle for clearance with thorney bushes on guide bundh and drain
1 without uprooting
LS 1 30.00 15.75 472.50
1 30.00 28.40 852.00
1 28.00 29.30 820.40
RS 1 30.00 28.50 855.00
1 30.00 28.10 843.00
1 30.00 29.50 885.00
drain river side 1 30.00 10.50 315.00
1 15.00 11.00 165.00
1 28.00 12.60 352.80
1 18.00 9.80 176.40
Total quantity in sqm 5737.10
Record of existing section
bforeDigging Slush from Nala Existing x
2 sectinal
Bed
L B H /D area
barrel 52.60 3.44 2.65 9.12
52.60 3.44 2.58 8.88
drain 28.00 (8.90+9.75)/2 1.60 14.92
30.00 (7.00+7.30)/2 1.20 8.58
14.00 (6.90+7.40)/2 0.85 6.08

Mts taken by me

Mts record against aggrement no 08/A E IV/2019-20 in


favour of cont M /S Maa shree construction
Oiling and Greasing of gates
whole system at barrel with
1 material, labour, T & P etc
required as per site condition
complete . 1+1 2
totalqty in nos 2

Record of executed
sectionafter Digging Slush Exicuted x
2 sectinal
from Nala Bed
L B H /D area
barrel 52.60 3.44 3.75 12.90
52.60 3.44 3.75 12.90
drain 28.00 (8.40+9.75)/2 2.82 25.59
30.00 (6.80+7.40)/2 2.50 17.75
14.00 (6.42+7.58)/2 2.00 14.00

Existing Exicute
x dx
sectinal sectinal Net x sec
Calculation of quantity area area area length qty
9.12 12.90 3.78 52.60 199.04
8.88 12.90 4.02 52.60 211.7
14.92 25.59 10.67 28.00 298.76
8.58 17.75 9.17 30.00 275.1
6.08 14.00 7.92 14.00 110.88
total qty 1095.48

Mts taken by me