EO 70 PROGRESS MONITORING FORM

AGENCY: DILG COTABATO


REGION: XII
COVERAGE: January – December 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

Monitor the organization and Technical Assistance to the 100% of LGUs with organized January – February 2020
functionality of the RCSP organization of RCSP Teams RCSP Teams and Core Teams of
Teams and Core Teams that and Core Teams. Province of Cotabato, Antipas,
will spearhead the Arakan, Kidapawan City, Magpet,
operationalization of the Makilala, Pres. Roxas, Tulunan.
RCSP.
Cascading to other members Orientation LCEs, RCSP 100% of RCSP members of July 24-28, 2020
of the RCSP Team of the 19 Teams and Core Teams and Province of Cotabato, Antipas,
Local Task Forces after the their roles and responsibilities Arakan, Kidapawan City, Magpet,
February 12, 2020 Regional in RCSP Processes and Makilala, Pres. Roxas, Tulunan
Orientation. Protocols and deliverables oriented on RCSP Processes and
under DILG MC 2020-095. DILG MC 2020-095.
Implementation of various Submission of Priority Projects Support to the Barangay September 30, 2020
support programs of the NTF for the CY 2020 RCSP Original Development Program of the NTF-
for the cleared barangays. Target Barangays. ELCAC Project Lists of the CY
2020 RCSP 36 Original Target
Barangays.
Conduct of Preparatory Conduct of Convergence Revised Action Plans prepared/ September 14 – 15, 2020
activities prior to the conduct Planning and development of RCSP Immersion Plan developed.
of Barangay Immersion. LGUs’ RCSP Immersion Plan.
Priorities identified issues Conduct of Convergence September 22 – 23, 2020;
that need government Meetings. September 24 – 30 and
interventions based on the October 1 – 2, 2020
level of significance and
impact to the community.
Empower of LGUs and Conduct of Local Serbisyo 100% of CY 2020 Priority October 23 – December 8,
communities in the Caravan. Barangays conducted Serbisyo 2020
implementation of needed Caravans.
PPAs and activity of basic
services to the communities.
Foster convergence and Orientation Session on Local 100% PTF Members oriented on December 16, 2020
collaboration among various Peace Engagement Guidelines Local Peace Engagement
Institutions as lead agency of and Peacebuilding Approaches Guidelines and Peacebuilding
Local Peace Engagement for the Provincial Task Force of Approaches for the Provincial
Cluster – PTF Cotabato. Task Force of Cotabato.
EO 70 PROGRESS MONITORING FORM
AGENCY: TESDA Cotabato Provincial Office
REGION: XII
COVERAGE: August 2020 – January 2021

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

Reduction of Poverty Rate Conduct of skills training on August 26 – January 2021


and Enhancement of Job Organic Vegetable and 175
Opportunities as well as to Concoction.
ensure food Security and Project TALA (TESDA Alay ay 160 August 26 – January 2021
provision of empowerment in Liwanag at Asenso)
every community. Provision of Free Haircutting, November 12 – December
Manicure and Pedicure And 449 10, 2020
Soft Massage.

EO 70 PROGRESS MONITORING FORM


AGENCY: PhilHealth Regional Office
REGION: XII
COVERAGE: October 22 – December 10, 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

To ensure Philhealth 1. PhilHealth registration


coverage to all Filipinos and 2. Verification of Membership October 22 – December
as specific compliance to EO Status 642 10, 2020
70 to the *ECLIP 3. Updating of Records
beneficiaries. 4. Conduct of Orientation
EO 70 PROGRESS MONITORING FORM
AGENCY: LTO Kidapawan City District Office
REGION: XII
COVERAGE: October 22 – December 10, 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

To distribute LTO flyers to Distributed LTO flyers to road October 22 – December


road users as one way of users during the activity. 1,868 10, 2020
information dissemination.
To answer/ reply queries and Replied queries and concerns October 22 – December
concerns of public regarding of public on our mandates. 1,868 10, 2020
our mandates.
To conduct lecture and Conducted lecture and October 22 – December
awareness re: Road Safety awareness re: Road Safety 1,868 10, 2020
Advocacy. Advocacy.
To distribute facemasks and Distributes facemasks and 100 facemasks & October 22 – December
candies to persons visiting or candies. 10 packs of candies. 10, 2020
booths.
To cater recipients who will Issued certificates of
avail free Theoretical Driving completion to those qualified
Course (TDC) offered by our individuals who avail free TDC. 670 October – December 2020
office to interested qualified
individuals.
EO 70 PROGRESS MONITORING FORM
AGENCY: DOLE North Cotabato Field Office
REGION: XII
COVERAGE: May – November 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

To reduce poverty DOLE Integrated Livelihood 100% Provisions of Starter Kits to May 7 – July 8, 2020
Program 30 identified beneficiaries.
To provide juridical Registration of Workers Certificate of Registration May 26 – October 26,
personality Association. processed. 2020
Conducted orientation on DOLE
Integrated Livelihood and
Emergency Employment
To inform and capacitate the Programs (DILP), Registration of August 11 – 13, 2020
residents in the areas Info dissemination and Workers Association and Simple
identified as threatened Capacity Building. Bookkeeping to the residents of
barangays. the barangay.
Conducted orientation on DOLE
Integrated Livelihood and October 22 – November
Emergency Employment 17, 2020
Programs (DILP).
EO 70 PROGRESS MONITORING FORM
AGENCY: PSA Cotabato Provincial Statistical Office
REGION: XII
COVERAGE: October 29 – December 8, 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

All individual are provided Copy issuance of Civil Registry


with legal documentation of Documents (Birth, Marriage,
Civil Registry Documents. Death Certificates, Negative 1,364 October 29 – December 8,
Certification and Certificates of 2020
No Marriage or CENOMAR) in
security paper.

EO 70 PROGRESS MONITORING FORM


AGENCY: PENRO Cotabato
REGION: XII
COVERAGE: October 22 – December 8, 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

Narra Seedling 1,600 October 22 & 27, 2020 and


November 3, 2020
Coffee Seedlings 2,100 November 3, 10, 12, 17 &
19 2020 – December 8,
2020
Falcata Seedlings 500 November 5 & December
8, 2020
EO 70 PROGRESS MONITORING FORM
AGENCY: PENRO Cotabato
REGION: XII
COVERAGE: October 22 – December 8, 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

Ensure provision of logistics, Oral/Dental Kits 787 October 22 – December


human resource for health in 10, 2020
order to provide quality Wheelchairs, quad cane and 14 October 27 – December
health services to end local crutches 10, 2020
communist insurgency in the PWD/ Senior Medicines November 10, 2020
area.

EO 70 PROGRESS MONITORING FORM


AGENCY: DTI Cotabato Provincial Office
REGION: XII
COVERAGE: June – November 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

Establishment and launching of


Negosyo Serbisyo sa Barangay June – November 2020
To bring government close (NSB)
to the people and to increase Distribution of Livelihood 137 June – November 2020
jobs and sales in the Starter Kits
barangays and to encourage Distribution of Personal
entrepreneurship in the Computers for Public Schools 10 November 26, 2020
barangays. (PCPS) computer sets
Participation to Local Serbisyo October 27 – November
Caravan 26, 2020
EO 70 PROGRESS MONITORING FORM
AGENCY: DAR Cotabato Province
REGION: XII
COVERAGE: June – November 2020

OBJECTIVE PROGRAMS, PROJECTS TARGET/ EXPECTED DATE OF


AND ACTIVITIES (PPAs) OUTPUT IMPLEMENTATION

Basic Services (BS) Land Tenure Services CLOA Distributed August 25, 2020
Establishment of nurseries for
cacao and coffee (provision of
planting seeds for nursery, 4 nursery established
polyethylene bags, fertilizer and
garden nets)
Provision of 1 buck and 10 Livestock provided
does for each site
Provision of African Night Organic fertilizer produced
Crawler worms
Climate Resilient Farm Cacao seedlings provided
Productivity support Project
Village Level Farm-focus Tablea and ground coffee
enterprise Development processing and Processing facility
(VLFED) established.
Poverty Reduction, Agrarian Reform Community Processing equipment provided
Livelihood and Employment Connectivity Economic Support and Provision of hauling truck
(PRLEC) Services (ARCCESS)
Land Tenure Services CLOA Distributed August 8, 2020
Establishment of nurseries for
cacao and coffee (provision of
planting seeds for nursery, 2 Nursery Established
polyethylene bags, fertilizer and
garden nets)
Provision of 1 buck and 10 Livestock provided
does for each site
Provision of African Night Organic fertilizer produced
Crawler worms
Processing of Turmeric Processed turmeric produced
Construction of building for Processing facility established
processing
Land Tenure Services CLOA Distributed October 29 – December 3,
2020
Provision of Postharvest Postharvest facilities provided September 10, 2020
facilities
Planting materials Planting materials & inputs January – December 2020
provided
Land Tenure Services CLOA Distributed December 10, 2020
Provision of Postharvest Postharvest facilities provided September 10, 2020
facilities