ENGINEERING- Machine manufacturer - xxx

Date : 03-01-2006 JOB - XXXXXX


S No Description
1 Qty 1
2 Raw material Ring
3 RM Weight 1.00
4 RM cost 41.00
5 Cutting Charge 8.00
6 Lathe Work 0.00
7 Surface Grinding 5.00
8 Cylindrical Grinding 0.00
9 Total 54.00
10 Rejection 3% 1.62
11 Total 55.62
12 Overhead & Profit 15% 8.34
13 Total 63.96
14 Low Volume allowance 3.20
15 Part Final 67.16