Sl # Description of Item Unit Unit Rate

1 Picking up road surface & removing debris cum 932


2 Earthwork in Excavation cum 178
3 Laying of Polythene Sheet sqm 27
4 Brickwork cum 1274
5 Formwork sqm 337
Reinforced Cement concrete (f'c=25
6 cum 11677
N/mm2)
7 M.S work (fy=414 N/mm2) mt 79324
8 Backfiling by sand (F.M=>0.8) cum 858
9 Plaster sqm 307
10 Others L.S 10%
Total Cost per meter (Taka)
Construction of RCC Footpath
Sl # Description of Item Unit Unit Rate DNCC Rate Code Quantity
1 Picking up road surface & removing debris cum 932 7 : Road 1.50
2 Earthwork in Excavation cum 178 8(a) : Road 0.33
3 Laying of Polythene Sheet sqm 27 3.7 : Building 1.00
4 Brickwork cum 1274 27.6.2 : Building 0.16
5 Formwork sqm 337 7.12.1 : Building 0.30
6 Reinforced Cement concrete (f'c=25 N/mm2) cum 11677 35(b) : Road 0.23
7 M.S work (fy=414 N/mm2) mt 79324 41(b) : Road 0.02
8 Backfiling by sand (F.M=>0.8) cum 858 9(b) : Road 0.36
9 Plaster sqm 307 15.2 : Building 1.30
10 Others L.S 10%
Total Cost per meter (Taka)
Total Taka
1,398.00
57.85
27.00
207.03
101.10
2,627.33
1,400.07
311.03
399.10
652.85
7,181.34