1

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း


DETAIL OF MEASUREMENT
Measurements Dedu
NO DESCRIPTION Qty. Contents Total of each
L B H ction

1 Earth work excavation medium soil


1 x 1 13' - 9'' 11' - 9'' 6' - 3'' 1,009.77
1009.77 Fc

2 9" Hard core (Bolder stone packing, Sand Blanding,

Watering and Ramming) 1 x 1 13' - 9'' 11' - 9'' 0' - 9'' 121.17

121.17 Fc
3 ½"Ø Mildsteel bar for short Column ½"Ø
2 x 26 13' - 9'' 715.00
2 x 22 11' - 9'' 517.00
1,232.00 823.0 Lb

4 6" TK (1:2:4) R.C.C for footing slab 1 x 1 13' - 9'' 11' - 6'' 0' - 6'' 79.06

79.06 Fc
5 9" T.K (1:3) C.M Brick walling
(L) 1 x 2 12' - 9'' 0' - 9'' 5' - 0'' 95.63
(B) 1 x 2 9' - 3'' 0' - 9'' 5' - 0'' 69.38
165.01 Fc
6 ½"TK (1:3) C.M Plastering
Flooring 1 x 1 11' - 3'' 9' - 3'' 104.06
Walling internal (L) 1 x 2 11' - 3'' 5' - 0'' 112.50
(B) 1 x 2 9' - 3'' 5' - 0'' 92.50
Walling External (L) 1 x 2 12' - 9'' 2' - 6'' 63.75
(B) 1 x 2 10' - 9'' 2' - 6'' 53.75
426.56 Fs
7 Formwork For R.C.C Cover
Under cover slab 1 x 1 12' - 9'' 10' - 9'' 137.06
Side of cover slab (L) 1 x 2 11' - 3'' 0' - 4'' 7.50
(B) 1 x 2 9' - 3'' 0' - 4'' 6.17
150.73 Fs
8 ½"Ø Mildsteel bar for Cover ½"Ø
2 x 24 12' - 0'' 576.00
2 x 20 10' - 0'' 400.00
976.00 Fr
652.0 Lb
9 (1:2:4) for Cover
1 x 1 12' - 0'' 10' - 0'' 0' - 4'' 40.00
40.00 Fc
10 Plastic Paint (3)Coat
(L) 1 x 2 12' - 9'' 2' - 10'' 72.25
2
Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း
DETAIL OF MEASUREMENT
Measurements Dedu
NO DESCRIPTION Qty. Contents Total of each
L B H ction

(B) 1 x 1 10' - 9'' 2' - 10'' 30.46


102.71 Fs
3

5.875
4

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Builder's Estimate

NO DESCRIPTION Quantity Unit Rate (Ks) Per Amount (Ks)

1 Earth work excavation medium soil 1009.77 Fc


Worker 20.20 Nos 3500 70684

2 9" Hard core (Bolder stone packing, Sand Blanding,


Watering and Ramming) 121.17 Fc
6"x9" Bolder stone 0.70 Sud 22000 15461
Sand 0.64 Sud 30000 19266
Worker 1.82 No 3500 6361
41089
3 ½"Ø Mildsteel bar for short Column 822.98 Lb
½"Ø M.S bar 822.98 Lb
½"Ø M.S bar 0.39 Ton 950000 366482
Bending Wire 7.35 Lb 1389 10206
Steel Fixer 7.35 Nos 5000 36740
Worker 7.35 Nos 3500 25718
439145
4 6" TK (1:2:4) R.C.C for footing slab 79.06 Fc
Cement 14.61 Bags 10000 146120
Sand 0.36 Sud 30000 10910
RSA 0.73 Sud 40000 29094
H.S.D 1.58 Gal 5000 7906
Mason 1.58 Nos 5000 7906
Worker 7.12 Nos 3500 24904
M-Driver 0.40 Nos 5000 1977
228817
5 9" T.K (1:3) C.M Brick walling
165.01 Fc
Brick 2227.64 Nos 100 222764
Cement 11.49 Bags 10000 114918
Sand 0.43 Sud 30000 12871
Mason 6.60 Nos 5000 33002
Worker 9.90 Nos 3500 34652
418206
6 ½"TK (1:3) C.M Plastering 426.56 Fs
Cement 5.71 Bags 10000 57129
5

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Builder's Estimate

NO DESCRIPTION Quantity Unit Rate (Ks) Per Amount (Ks)

Sand 0.21 Sud 30000 6398


Mason 4.27 Nos 5000 21328
Worker 8.53 Nos 3500 29859
114714
7 Formwork For R.C.C Cover 150.73 Fs
Jungle Wood(s) (3 time) 0.15 Ton 400000 60292
Jungle Wood(P) (3 time) 0.09 Ton 450000 41452
Nail 0.01 Lbs 1389 19
Carpenter 6.03 Nos 5000 30146
Worker 3.01 Nos 3500 10551
142461
8 ½"Ø Mildsteel bar for Cover 651.97 Lb
½" Ø M.S bar 651.97 Lb
½" Ø M.S bar 0.31 Ton 950000 290330
Bending Wire 5.82 Lb 1389 8085
Steel Fixer 5.82 Nos 5000 29106
Worker 5.82 Nos 3500 20374
347894
9 (1:2:4) for Cover 40.00 Fc
Cement 7.39 Bags 10000 73929
Sand 0.18 Sud 30000 5520
RSA 0.37 Sud 40000 14720
H.S.D 0.80 Gal 5000 4000
Mason 0.80 Nos 5000 4000
Worker 3.60 Nos 3500 12600
M-Driver 0.20 Nos 5000 1000
115769
10 Plastic Paint (3)Coat 102.71 Fs
Plastic Paint 0.51 Gal 15000 7703
Wall putty 0.36 Gal 10000 3566
Painting Roller 0.17 Nos 4000 686
4" Brush 0.10 Nos 700 72
Sand Paper(A.A 40) 0.13 Dz 1800 231
Painter(For Painting) 0.77 Nos 5000 3852
6

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Builder's Estimate

NO DESCRIPTION Quantity Unit Rate (Ks) Per Amount (Ks)

16110
Total 2,364,543
7

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း


Abstract Of Cost

NO DESCRIPTION Quantity Unit Rate (Ks) Per Amount (Ks)

1 Earth work excavation medium soil 1009.77 Fc 70.00 70684

2 9" Hard core (Bolder stone packing, Sand Blanding,


Watering and Ramming) 121 Fc 339.10 41089

3 ½"Ø Mildsteel bar for short Column 822.98 Lb 533.61 439145

4 6" TK (1:2:4) R.C.C for footing slab 79.06 Fc 2894.21 228817

5 9" T.K (1:3) C.M Brick walling 165.01 Fc 2534.43 418206

6 ½"TK (1:3) C.M Plastering 426.56 Fs 268.93 114714

7 Formwork For R.C.C Cover 137.06 Fs 1039.40 142461

8 ½"Ø Mildsteel bar for Cover 651.97 Lb 533.61 347894

9 (1:2:4) for Cover 40.00 Fc 2894.21 115769

10 Plastic Paint (3)Coat 103 Fs 156.85 16110

Total 2,364,543
8

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Bill Of Quantity

No. Particular Unit Qty Rate (Ks) Amount (Ks)

A Material Cost

1 Cement Bag 39.21 10,000 392,095

2 Sand Sud 1.83 30,000 54,965

3 R.S.A Sud 1.10 40,000 43,814

4 6"x9" Bolder stone Sud 0.70 22,000 15,461

5 H.S.D Gal 2.38 5,000 11,906

6 Brick(1stclass) Nos 2227.6 100 222,764

7 Jangle Wood(S) Ton 0.15 400,000 60,292

8 Jangle Wood(P) Ton 0.092 450,000 41,452

9 Nail Lb 0.014 1,389 19

10 ½"ØM.S bar Ton 0.69 950,000 656,811

11 Binding Wire Lbs 13.17 1,389 18,290

12 Plastic Paint Gal 0.51 15,000 7,703

13 Painting roller Nos 0.17 4,000 686

14 Wall putty Gal 0.36 10,000 3,566

15 Sand Paper(A.A-40) Dz 0.13 1800 231

16 4" Brush Nos 0.10 700 72

1,530,129

B Labour

1 Mason Nos 13.25 5,000 66,236

2 Carpenter Nos 6.03 5,000 30,146

3 Steel fixer Nos 13.17 5,000 65,846


9

Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Bill Of Quantity

No. Particular Unit Qty Rate (Ks) Amount (Ks)

4 Painter Nos 0.77 5,000 3,852

5 Worker Nos 67.34 3,500 235,704

6 M-Driver Nos 0.60 5,000 2,977

Labours Cost Ks 404,759

TOTAL 1,934,888

Materials Cost Ks 1,530,129

Transporting Charges Ks 429,655

Labour Cost Ks 404,759

Materials & Labour Cost Ks 2,364,543

Supervision Charges 10% Ks 236,454.27

Total Cost Ks 2,600,997


ေဒသေပါက္ေစ်းႏႈန္း
No. Particular Unit Qty Rate (Ks)
A Material Cost
1 Cement Bag 1.00 12,000
2 Sand Fc 1.00 250
3 R.S.A Fs ### 350
4 Brick(1stclass) Nos ### 75
5 X-met Fr ### 200
6 Jangle Wood(S) Fs 0.15 7,000
7 Jangle Wood(P) Fs ### 8,000
8 Nail Lb ### 1,250
9 Earth(Excavating carrying) Fs ### 60
10 5/8"ØM.S bar Ton 1.00 1,150,000
11 1/2"ØM.S bar Ton ### 60,000
12 Bending Wire Lbs ### 1,200
13 Hard Wood(S) Fs ### 10,000
14 1-1/2" T.K Ready made panelled D&W(Teak) Fs ### 3,500
15 30 CGI Sheet Fs ### 6,500
16 30 G, CGI Plain Sheet Fs ### 12,000
17 Roofing Nail Lbs ### 1,100
18 Roofing Washer Lbs ### 1,000
19 4"ButtHinge Nos ### 500
20 Tower Bolts(9")(Alu) Nos ### 750
21 Tower Bolts(6")(Alu) Nos ### 500
22 Hooks & Eyes Nos ### 300
23 Locking Hapes Fs ### 2,500
24 Wood Screw Gross ### 1800
25 Plastic Paint Gal 0.51 9,000
26 Ready mixed paint Gal ### 12,000
27 Painting roller Nos 0.17 1,600
28 Wall putty Gal 0.36 10,000
29 Sand Paper(A.A-40) Dz ### 2500
30 Wood Putty Lbs ### 1500
31 3" Brush Nos ### 500
32 4" Brush Nos 0.10 700
33 Bamboo(wanat) Nos ### 1,500
34 Coilyan Viss ### 3,000
35 Handle Nos ### 350
36 1-1/2"x1/4" x1'x-6" M.S M.S Flate Nos ### 1,500
37 4" Bolt & Nut Nos ### 500
38 6" Bolt & Nut Nos ### 500
B Labours
1 Mason Nos ### 5,000
2 Carpenter Nos ### 5,000
3 Steel fixer Nos ### 5,000
4 Painter Nos ### 5,000
5 M-Driver Nos 5,000
6 Worker Nos ### 3,500
Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Transportation Charges/ Loading & Unloading


No Particular Unit Qty Rate(Ks) Amount (Ks)
1 Cement
က ေတာင္ကုတ္မွသေဘာၤဆိပ္သို႕(3)မို င္
ကားျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 1.96 10,000 19,605
ခ ကားေပၚတင္ခ Ton 1.96 7,000 13,723
ဂ ကားေပၚမွခ်ခ Ton 1.96 6,000 11,763
45,091
2 Cement
က ေတာင္ကုတ္သေဘၤာဆိပ္မွငေမာက္ေခ်ာင္းအေရွ႕ဘက္ခ်င္းရြာဆိပ္ကမ္းသို ႕ေရမို င္ (10)မို င္
စက္ေလွျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 1.96 9,750 19,115
ခ စက္ေလွေပၚတင္ခ Ton 1.96 7,000 13,723
ဂ စက္ေလွေပၚမွခ်ခ Ton 1.96 6,000 11,763
44,601
3 Cement
က ခ်င္းရြာဆိပ္ကမ္းမွလု ပ္င န္းခြ င္သို႕ (2)မို င္
ေထာ္လာဂ်ီျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 1.96 10,000 19,605
ခ ေထာ္လာဂ်ီေပၚတင္ခ Ton 1.96 7,000 13,723
ဂ ေထာ္လာဂ်ီေပၚမွခ်ခ Ton 1.96 6,000 11,763
45,091

4 Brick
က ေတာင္ကုတ္မွသေဘာၤဆိပ္သို႕(3)မို င္
ကားျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) ေခါက္ 2.2 10,000 22,276
ခ ကားေပၚတင္ခ ခ်ပ္ 2227.64 6 13,366
ဂ ကားေပၚမွခ်ခ ခ်ပ္ 2227.64 6 13,366
49,008
5 Brick
က ေတာင္ကုတ္သေဘၤာဆိပ္မွငေမာက္ေခ်ာင္းအေရွ႕ဘက္ခ်င္းရြာဆိပ္ကမ္းသို ႕ေရမို င္ (10)မို င္
စက္ေလွျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) ေခါက္ 2.23 9,750 21,719
Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Transportation Charges/ Loading & Unloading


No Particular Unit Qty Rate(Ks) Amount (Ks)
ခ စက္ေလွေပၚတင္ခ ခ်ပ္ 2227.64 6 13,366
ဂ စက္ေလွေပၚမွခ်ခ ခ်ပ္ 2227.64 6 13,366
48,451
6 Brick
က ခ်င္းရြာဆိပ္ကမ္းမွလု ပ္င န္းခြ င္သို႕ (2)မို င္
ေထာ္လာဂ်ီျဖင့္ သယ္ယူပို ႔ေဆာင္ခ)ေခါက္ 2.23 10,000 22,276
ခ ေထာ္လာဂ်ီေပၚတင္ခ ခ်ပ္ 2227.64 6 13,366
ဂ ေထာ္လာဂ်ီေပၚမွခ်ခ ခ်ပ္ 2227.64 6 13,366
49,008
7 Wood
က ေတာင္ကုတ္မွသေဘာၤဆိပ္သို႕(3)မို င္
ကားျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 0.24 10,000 2,428
ခ ကားေပၚတင္ခ Ton 0.24 7,000 1,700
ဂ ကားေပၚမွခ်ခ Ton 0.24 6,000 1,457
5,585

8 Wood
က ေတာင္ကုတ္သေဘၤာဆိပ္မွငေမာက္ေခ်ာင္းအေရွ႕ဘက္ခ်င္းရြာဆိပ္ကမ္းသို ႕ေရမို င္ (10)မို င္
စက္ေလွျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 0.24 9,750 2,368
ခ စက္ေလွေပၚတင္ခ Ton 0.24 7,000 1,700
ဂ စက္ေလွေပၚမွခ်ခ Ton 0.24 6,000 1,457
5,525
9 Wood
က ခ်င္းရြာဆိပ္ကမ္းမွလု ပ္င န္းခြ င္သို႕ (2)မို င္
ေထာ္လာဂ်ီျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 0.24 10,000 2,428
ခ ေထာ္လာဂ်ီေပၚတင္ခ Ton 0.24 7,000 1,700
ဂ ေထာ္လာဂ်ီေပၚမွခ်ခ Ton 0.24 6,000 1,457
5,585
Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Transportation Charges/ Loading & Unloading


No Particular Unit Qty Rate(Ks) Amount (Ks)
10 River Shingle
က ေတာင္ကုတ္မွသေဘာၤဆိပ္သို႕(3)မို င္
ကားျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Sud 1.10 10,000 10,954
ခ ကားေပၚတင္ခ Sud 1.10 3,500 3,834
ဂ ကားေပၚမွခ်ခ Sud 1.10 3,000 3,286
18,073
11 River Shingle
က ေတာင္ကုတ္သေဘၤာဆိပ္မွငေမာက္ေခ်ာင္းအေရွ႕ဘက္ခ်င္းရြာဆိပ္ကမ္းသို ႕ေရမို င္ (10)မို င္
စက္ေလွျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Sud 1.10 9,750 10,680
ခ စက္ေလွေပၚတင္ခ Sud 1.10 3,500 3,834
ဂ စက္ေလွေပၚမွခ်ခ Sud 1.10 3,000 3,286
17,799
12 River Shingle
က ခ်င္းရြာဆိပ္ကမ္းမွလု ပ္င န္းခြ င္သို႕ (2)မို င္
ေထာ္လာဂ်ီျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Sud 1.10 10,000 10,954
ခ ေထာ္လာဂ်ီေပၚတင္ခ Sud 1.10 3,500 3,834
ဂ ေထာ္လာဂ်ီေပၚမွခ်ခ Sud 1.10 3,000 3,286
18,073
13 Sand
က ( )မွလု ပ္င န္းခြ င္သို႕(3)မို င္
ေထာ္လာဂ်ီျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Sud 1.83 10,000 18,322
ခ ေထာ္လာဂ်ီေပၚတင္ခ Sud 1.83 3,500 6,413
ဂ ေထာ္လာဂ်ီေပၚမွခ်ခ Sud 1.83 3,000 5,497
30,231
14 M.S Rod
က ေတာင္ကုတ္မွသေဘာၤဆိပ္သို႕(3)မို င္
ကားျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 0.69 10,000 6,914
ခ ကားေပၚတင္ခ Ton 0.69 7,000 4,840
Name of Work ၃၂၀၀ဆံ့ ေျမေအာက္ေရေလွာင္ကန္(၁)လံ ု း ေဆာက္လုပ္ျခင္းလု ပ္င န္း

Transportation Charges/ Loading & Unloading


No Particular Unit Qty Rate(Ks) Amount (Ks)
ဂ ကားေပၚမွခ်ခ Ton 0.69 6,000 4,148
15,902
15 M.S Rod
က ေတာင္ကုတ္သေဘၤာဆိပ္မွငေမာက္ေခ်ာင္းအေရွ႕ဘက္ခ်င္းရြာဆိပ္ကမ္းသို ႕ေရမို င္ (10)မို င္
စက္ေလွျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 0.69 9,750 6,741
ခ စက္ေလွေပၚတင္ခ Ton 0.69 7,000 4,840
ဂ စက္ေလွေပၚမွခ်ခ Ton 0.69 6,000 4,148
15,729
16 M.S Rod
က ခ်င္းရြာဆိပ္ကမ္းမွလု ပ္င န္းခြ င္သို႕ (2)မို င္
ေထာ္လာဂ်ီျဖင့္ သယ္ယူပို ႔ေဆာင္ခ) Ton 0.69 10,000 6,914
ခ ေထာ္လာဂ်ီေပၚတင္ခ Ton 0.69 7,000 4,840
ဂ ေထာ္လာဂ်ီေပၚမွခ်ခ Ton 0.69 6,000 4,148
15,902
စု စု ေပါင္း 429,655
Total
Mile 1 2 2 4 1 10
Rate 7500 13000 11000 18000 2500 52000

Total
Mile 1 2 2 4 1 10
Rate 7500 13000 11000 18000 2500 52000

Total
Mile 1 2 2 4 1 10
Rate 7500 13000 11000 18000 2500 52000

You might also like