You are on page 1of 2

No.

Area Grid Total Pile Pile Cutting Remaining Percentage


1 Production & Warehouse BA 940
2 Utility Building BB 109
3 Hydrant Building BC 107
4 Waste Building BD 0
5 Pipe Bridge BE 58
Total 1214
No. Grid Work Description
BA Excavation
Sand Bedding
Lean Concrete

You might also like