UPGRADATION OF 120-GT-14

PUNCH LIST
Test Package No : 120-GT-14 Area : South Stablizer

Issuer Discipline : Piping Issuer Name : Abdul Salam Date: 22/4/2021


PUNCH CLEARANCE STATUS
SL No. REF. DRAWING No. DESCRIPTION CATEGORY
SIG CONTRACTOR SIG ARAMCO

1 NB-646329/PS-061 Pipe support Missing B

2 BB-034819 Paint Touch Up Need to be done B

3 BB-034818 Paint Touch Up Need to be done B

4 NB-646329 Final Aligment & Bolt torquening Need to be done B

5 NB-646327 Final Aligment & Bolt torquening Need to be done B

6 Drain drain pipe connection from throtille valve missing C1

7 Drain drain pipe connection from throtille valve missing C1


Master Welding Summary sheet need to be
8 C2
submitted

Category A - To be completed before piping test.


B - To be completed after piping test.
C1 - To be completed during pre-commissioning.
C2 - To be completed during Commissioning. 1 of 1