ID : 51Q-BU-0002

KNPC CFP – MAB2 PROJECT


Protected Membrane Roofing Roof
Water Proofing Checklist
Tag Description: Tag No:
P.O No: Area(Unit): Turnover System No.:
Subcontractor : Section(Train): Sub–System No.:
Work Package: Report. No : Drawing Ref.:
ITP Ref No / Rev. No RFI No.:

Inspection Result
Description of Activities Remarks
Accept Reject N/A

1 Cleaning top of Concrete slab  

2 Vents, drains curbs other projections  

3 Survey slopes  

4 Light weight concrete thickness  

5 Light weight concrete setting  

6 Sand cement screed thickness  

7 Screed Surface Preparation  


Primer_________________ according to
8  
manufacturer's recommendation
Waterproofing membrane______ application
9  
as per manufacturer's recommendation
Termination of membrane top of parapet &
10  
drain
11 Overlap as specified  

12 Leak Test 48 hours of water  

13 Thermal insulation  

14 Filter fabric  

15 Tiles  
16 Metal flashing  
17 Sealant  
18 Cleaning  